EXCAVATOR OPERATOR DAILY & WEEKLY INSPECTIONS
All boxes to be ticked when completing this form
NAME:. FLEET No:.. ENGINE HOURS:..
Week Commencing:.. DEPOT / SITE
ADDRESS:..
DAILY PRE-USE CHECKS M T W T F S S WEEKLY CHECKS WEEKLY SAFETY INSPECTIONS
Engine Oil Level A. Battery & Water Level The excavator has been Thoroughly Examined as required by LOLER.
Fuel Level/Leaks B. Windscreen Reservoir The operator must also inspect the excavator before use on a new site
Coolant Level C. Lub Machine and every week thereafter as required by PUWER.
Hydraulic Oil Level D.Transmission Levels Please report results below.
Hydraulic System Leaks E. Drain Fuel Sediment Bowl
Grease Attachments F. Drain Fuel Tank of Water Equipment with Machine (tick box)
Grease Base Machine G. Check Fan Belt Size (if applicable) Good Working Order
Inspect Seat Belts H. Check A/C Belt Buckets
Inspect for Cracks I. Check Track Tension Vandal Guards
Check Operation of all Switches J. Check for Loose Track Plates Quick Hitch
Check Operation of Console K. Slew Motor Oil Level Lifting Eye
Inspect Bucket/Attachment L. Tyre Condition
Check Operation of SLI M. Bucket & Dipper Arm Pins
Window Damage RESULTS OF ASLI INSPECTION (where fitted)
Cab Condition Boom Radius SWL Correct Operation
Check of Vandal Damage
Tyre Pressures
Further checks to meet the needs of manufacturer's instruction as per machine manual.
ALL DEFECTS MUST BE REPORTED. Those affecting safe operation must be repaired immediately CAB Certificates Tick Box
Description Description Thorough Examination Certificate 6/12 Monthly
ASLI Manual
Operator's Manual
Data Logger
Repairs Completed or Comments
Reported to: Date: Reported to: Date:
Operator's Comments: Were any Defects found? YES / NO
Operator's Signature:.. Date:.. Fitter's Signature: .. Date: