1 of 4
FAILURE ANALYSIS
Date of the failure:
FA Number:
Date of Analysis:
Type of Failure:
Cost of Failure:
Classification:
Process
Internal/ External
Repetitive: Yes/ No
System
Product
Department & Section:
Equipment:
Component:
Trigger:
KPI Index:
Defect or Problem:
Batches / Materials
Batches
Qty (kg)
Material
Issuer:
Shift:
Start of the interruption:
hh:mm:ss
Total interruption time:
minutes
End of the interruption:
hh:mm:ss
Description of the failure:
Observation of the failure:
Symptom removal:
Particpants
Annexure 01 - Why-Why Analysis Template
Annexure 02 - Fish Bone diagram
3 of 4
Annexure 01 - Why - Why Analysis
Note: Based on Failure, the tree can be expanded
How Problem was created?
Why did this happen?
Why did this happen?
Why did this happen?
Why did this happen?
4 of 4
ANALYSIS OF THE PROBLEM (Annexure 02)
CAUSE AND EFFECT DIAGRAM
MEASUREME
NT
MANPOWER
MACHINE
METHOD
MATERIAL
ENVIRONMEN
T
2 of 4
Action Plan
S.No. Action
CA
PA
Accountable
Deadline
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Documents to be reviewed
Review Required Document
(Yes or No)
No.
S.No. Document
1
2
3
4
5
6
7
8
Who will
review
When to
review
Quality Manual
General Management Procedure
PFMEA
Control Plan
Routine procedure
Work Instruction
Job Aid
Record Format
Effectiveness verification
Evaluation criteria :
Deadline:
Accountable:
Observation:
Obs.: The last action of the action plan should always be how the verification of the effectiveness of the analysis
Effective analysis?
Participants
ACCOUNTABLE FOR THE ANALYSIS:
Yes
No
2 of 4
Action Plan
How
Close date
If revision required, what to be revised
Verification of the
action
Prism upload
(Done/ Not done)
fectiveness verification
ification of the effectiveness of the analysis is going to be carried out
Evaluation date:
MANAGER:
DATE:
2 of 4