Project Charter
Project Name:
Kitchen Remodel
Project Manager:
Whitney Andersen
Todays Date:
10/06/2015
Project Sponsor:
Betty Crocker
Purpose / Objective of the Project
(Provide a description of why we doing the project, project objectives and benefits)
Sabrina Racca has been the winner of Betty Crockers annual kitchen makeover. This project will be
photographed for House & Home and HGTV Magazines. This project should be completed in less
than 2 months from todays date. Each individual contractor needs to be on time so the following
contractor can complete their work when planned. The budget for this project is $15,000.
Items in Scope (List all items that are to be included in the project)
New cupboards
New appliances
New sink
New countertops
New flooring
Items not in Scope (List all items that are not being addressed during the project)
Backsplash
Kitchen Table or Stools
Doors & Handles
Lighting & Fixtures
Other Decorations
Complete the following for all deliverables expected. Note the dates and estimated times are negotiated.
Deliverable / Milestone
Floor plan/layout created
Demolish
Paint Walls
Floor
Cupboards
Countertop & Sink
New Appliances
Person/Team Responsible
Dexigner
Ace Junk Removal
Signature Design Painting
Zeus Flooring
The Home Depot
Lowes
Maytag
Estimated End Date
10/10/2015
10/20/2015
10/27/2015
11/05/2015
11/15/2015
11/23/2015
11/25/2015
Assumptions (Complete the following for any assumptions required to satisfy the scope of the project)
1
White Cabinets
2
Granite Countertops
3
Gray Walls
Project Charter v1.0
Document Last Updated: <date>
<Project Name>
Project Charter
4
5
6
7
Wooden Floors
Stainless Steel Appliances
Budget: $15,000
To be finished in under 2 months from todays date
Project Manager Approval
10/07/2015
Name Typed
Whitney Andersen
Signed
e-signed
Sponsor Approval
10/06/2015
Name Typed
Betty Crocker
Signed
e-signed
Project Charter v1.0