‘Company Logo
Company Name
GENERAL METHOD STATEMENT
FOR
FOUNDATIONS
Document Number: MS0605 rev.0
BLCP, 2x700 MW Coal Fired Power Plant,
Map Ta Phut, Thailand
On Shore Civil WorksITEM
10.
Method Statement
Title: General Foundation
LIST OF CONTENTS
Purpose
Scope
Definitions
Responsibilities
Safety
4.1 Machinery and Equipment
4.2 Personal Protective Equipment
43° Safety Arrangement during the Foundation Work
Working Method
6.1 Preparing Work
6.2 Survey and Setting out
63 Excavation
64 Dewatering
6.5 Piles (where applicable)
6.6 Blinding Concrete
6.7 Foundation
67.1 Rebar
6.7.2 Formwork
673 — Concrete
68 Embedded Items
6.9 Repair and Items
6.10 Repair and Touch-up
G11 Pedestal
Allowance and Tolerance
References
Appendices
A Activity Organization Chart
B Emergency Action Plan
Sketches and Drawings
D Foundation Location Plan
Foundation Construction Sequences
Foundation Schedule
Exhibits
Manufactures repaired product data sheets to be added
‘™MS0605Method Statement
Title: General Foundation
‘Mso60sMethod Statement
v
General-Foundation
Appendix rgency Action plan Flow Chart
(™c)
Mitsubishi Corporation
(INC)
Thai Nishimatsu Construction Co., Ltd.
Thai Maruken Co., Ltd.
Sino-Thai Engineering
Construction Public Co., Ltd.
(STECON)
Mso60sMethod Statement
Title: General-Foundation
Appendix B: Emergency Action plan Flow Chart
Organization Chat of Thai Maruken Co., Ltd.
Mr. Sophon Jakmanon
Project Manager
Mr. Worathad Mingmanee
Site Manager
Mr. Wanchai Saknanurak
Supervisor
1* Team 2" Team 3 Team
Crane Operator Crane Operator ‘Crane Operator
Welder / Worker || Welder/Worker || Welder / Worker
Mso6osMethod Statement
Title: General-Foundation
Appendix B: Emergency Action plan Flow Chart
Mitsubishi Corporation
Mr. Masashi Okushita
Project Manager
09-9687250
‘Mr, Seksan D.
Site Manager
01-7012624
Mr. Haan C, Mr. T. Koyama
Building Construction manager Civil Construction Manager
01-6194588 09-9687291
Mr. Shiooka Mr. Thawatchai C. Mr. Yotson T.
Senior Engineer Senior Engineer Senior Engineer
01-3433669 09-8415384 06-8191462
Italian -Thai Development Sino Thai Engineering &
Public Company Limited Construction Public
038-683631-2 Company Limited
MrKraiwudh L. MrPitan
Project Engineer Project Manager
01-9827245 01-6832463
I I
Mr-VasantT. Mr. Apiwat N
Project Engineer Construction Manager
01-9196114 01-9826796
Mr. Surapon. Mr. Vasan S| Mr. Sunun A.
Safety Safety Safety
06-3326281 05-085-2508 01-3654095
$
Incident
Mso60s10
2.0
3.0
40
Method Statement
Title: General-Foundations
Purpose
The purpose of this general method statement is to describe the construction
procedures for the isolated pile cap and pad foundations. Large raft foundations will
be covered in specific foundation method statements and are not included in this
document,
Scope
The works will incorporate the procedures necessary to execute the following items:-
Preparing of Work
Survey And Setting Out
Excavation
Dewatering
Pile (If Applicable)
Blinding Concrete
Foundation — Rebar- Formwork — Concrete
Embedded Items
Backiill
Pedestal
Definitions
Client = BLCP Power Limited (BLCP)
Contractor = MITSUBISHI CORPORATION (MC)
Responsible in the supervision of the sub-contractor who will perform the
construction work and all related activities as outlined in this procedure
‘Sub-Contractor = THAI NISHIMATSU CONSTRUCTION CO., LTD. (TNC)
Responsible in the execution of the construction work as well as the tests
required in accordance to this procedure
‘Sub-Subcontractor = Italian ~ Thai Development Public Co., Ltd. (ITD)
Responsible in the execution of Foundation Work
Sub-Subcontract = Sino-Thai Engineering & Construction Public Company
Limited. (STECON) Responsible in the execution of Foundation Work
Responsibilities
Construction Manager and Senior Engineer = responsible in ensuring the implement
of construction procedure and method statement, the Quality Control of
work, Supervise the work and reporting the progress of work to Site
Manager,
1MS00605-Page 1/7Method Statement
Title: General-Foundations
Safety / Environmental Officer = responsible in ensuring that all activities are carried
out safety patrol at the site, Establishing the site safety plan, Conducting
continuous safety inspection and stop any work deemed unsafe and a risk to
personal, Taking action to rectified the unsafe condition and report to
project manager and preparing the notes of safety meeting.
QA / QC Engineer = responsible to monitor the execution and performance of the
works in relation to this method statement, approved drawings and material
specifications; detect and report non-conformance; ensure that all non-
conformance products or activities identified are reported; propose the
corrective and preventive action where possible and appropriate and record
the completion the Non Conformance by Report format,
Site Engineer & Foreman_ = responsible in all activities on site are carried out in
accordance with the schedule and the construction drawing and take care
all worker to be work with their responsibilities and make a decision when
some non conformance occurring their report to senior engineer
5 Safety
Refer to the site safety policy for general safety controls. One of the main aspects of this
procedure is Safety and Health Control. This is to control occurrence of injuries as well
as damage to equipment and properties during the entire construction period. In order to
ensure a safe working environment during the entire construction period, the following
safety measures will be implemented:
5.1 Machinery and Equipment:
- Prior to using any machinery’s/equipment at site, it shall be inspected and
cettified by qualified person.
- Periodic Preventive Maintenance shall be made on all equipment and
machineries.
= All operators and drivers are to be equipped with valid driver’s/operator’s
license or permit from concemed goverment agency.
- Only authorized drivers or operators will be allowed to operate machineries or
equipment.
- Only authorized signalman shall be assigned together with the operator or
driver.
- All lifting equipment as well as its accessories such as sling wire, nylon sling,
shackles, chain blocks crane hook and latch shall be inspected periodically,
5.2 Personal Protective Equipment:
- Personal Protective Equipment (PPE) shall be issued to alll workers such as
safety shoes, hardhat, working gloves, earplug, safety goggles (if required) and
safety belt and or safety harness for workers who will be assigned in elevated
places 2.0meter and above.
Ms00605-Page 2/7Method Statement
Title: General-Foundations
- Wearing of the basic PPE shall be enforced fully.
5.3 Safety Arrangement during the Foundation Worl
- Emergency Action Plan ~ refer to Appendix-B
Note:
All new recruits shail undergo proper orientation and safety induction before they are
deployed at site for work,
6.0 Work Procedure
6.1 Preparation of Works:
* Foundation works will not commence until confirmation that all pre-construction
planning and safety checks are completed,
© The supervisor shall be familiar with the latest construction drawings and method
statements.
* Plant and equipment requirements will be assessed on a case-by-case basis for each
foundation location and agreed with the TNC Construction Manager prior to starting
the works
6.2 Survey and Setting out
* Before work starts TNC survey department will establish baselines and benchmarks
from which co-ordinates and elevations will be taken to set out the foundation works.
6.3 Excavation
+ Excavations will generally be executed in open cut to the size, slope and elevation
shown on the construction drawings and/or design calculations.
© Survey will verify set out and check edge slope and bottom founding level of
excavation.
* Excavation will be camied out with excavator and the excavated material loaded
directly into dump truck and transported to temporary stockpile area,
* A small bucket or manual digging will be used when excavating between piles.
* The final bottom founding level under each foundation will be inspected by QC and
‘tamped or compacted as per design requirements before pouring blinding concrete,
* For a description of all related work activities refer to MS0SO1-General method
statement for open-cut excavations.
64 Dewatering
* From the site soil report the relative groundwater level is approx, -2.5m below
existing ground level
MS00605-Page 3/7Method Statement
Title: Gencral-Foundations
© During excavation and after reaching the required excavation level a dewatering
system will be installed as required and any water discharged to the vicinity drainage
pits
‘+ For a description of all related work activities refer to MS0S06-General method
statement for dewatering excavations.
65 Piles (where applicable)
Following final excavation the piles will be cut down to design pile cut off level.
Removed sections will be lifted out and taken to designated disposal area.
Afier cleaning, the pile head treatment will be done to connect pile to foundation.
For a description of all related work activities refer to MS0405-Method statement for
ile cut-off.
6.6 Blinding Concrete
* Bottom of the excavation should be dry and tamped or compacted to a uniform level
before pouring the 50mm thick lean concrete blinding layer.
* For a description of all related work activities refer to MS0601-General method
statement for conerete.
627 Foundation
‘* After QC inspection of the prepared founding level and lean concrete base layer then
construction of the foundation will follow.
6.7.1 Rebar
© Rebars will be cut and bent on site in line with the agreed construction sequence.
¢ Installation of rebar will begin as soon as blinding concrete has hardened enough for
trafficking (normally 12 hours)
A mobile truck crane and/or manual workers will be used for rebar installation,
Rebar placement sequence will follow the latest rebar construction shop drawings.
Suitable concrete spacers will be used to achieve the desired covers and additional
rebar spacers will be installed to maintain support of top steel and any cast-in items.
* All pedestal column starter bars and cast-in anchor bolts will be accurately located
and securely fixed in the correct position.
© Location, spacing, verticality and cover shall be checked during the installation
process and QC will make a final inspection prior to calling up concrete.
© For a full description of all work activities refer to MS0602-General Method
Statement for Rebar.
6.7.2 Formwork
+ The formwork system to be adopted for each foundation type and size will be as
specified in approved calculations prepared by the Temporary Works Design
MS00605-Page 4/7Method Statement
Title: Gencral-Foundations
Engineer. The different types of formwork for site installation purposes are
summarized in Table 27722in Appendix 2777272?
* Plywood sheathing with timber and steel props will be used for formwork and manual
labour will be used for lifting and placing according to survey-lines of the foundation
outline.
© Approved form release agent is applied prior to lifting-in and erection of the clean
forms.
¢ Forms are connected tightly together and braced to the excavation profile or waling in
the case of sheet pile wall.
* For a full description of all work activities refer to MS0603-General Method
Statement for Formwork.
6.7.3 Concrete
* 1 no concrete pump will be available (with back-up pump) for placing concrete at a
rate of around 35-40m3/hr. In some cases pouring concrete will be done by bucket
and 25T mobile crane at a rate of 10-1Shr.
A minimum of 4nos of 50mm vibrators shall be used for compaction,
Unless agreed otherwise the foundations will be poured at one time in layers, starting
from the centre and spreading out to each side. CHECK IF CORRECT!
Keep concrete alive without performing any cold joints.
Manual tools and float are used to finish the top surface.
For a full description of all work activities refer to MS0601-General Method
Statement for Concrete.
6.8 Embedded Items
* All embedded items and cast-in anchor bolts shall be placed to the specified
installation tolerances shown on the construction drawings,
© Special care will be taken to place and maintain embedded materials to the proper
setting location to prevent movement during the progress of the work and to tamp
concrete thoroughly around them,
* For a fill description of all work activities refer to MS0901- General Method
Statement for embedded items,
6.9 Repair and Touch-up,
* After striking of forms a QC inspection will be conducted to decide whether any
repairs to the concrete surfaces are necessary.
© Fora full description of concrete repair procedures and materials to be used refer to
MS0604- General Method Statement for Concrete repair and touch-up.
6.10 Backfilling
MS00605-Page 5/7Method Statement
Title: General-Foundations
Backiilling operations will be exccuted in two (2) stages using suitable excavated
sand material,
The first stage fill will be placed up to the top of foundation level and will commence
as soon as formwork has been removed and QC inspection of foundation is approved.
NOTE: If this method is adopted then curing of the foundation will be done
using?????curingcompound dete .
Backfilling will be done in loose layers not more than 250mm in thicknes
Suitable vibrator plate/rollers and/or water will be used to achieve the compaction
requirements for each layer field density test will be performed to check the soil
compaction 095% maximum dry density,
Any embedded cableway conduits and earthing/grounding wires, drainage pipes and
trenches etc. should be installed simultaneously with the backfilling layers.
After completion of the concrete pedestal then the second stage fill will be carried out
up to grade level below proposed finished ground level
For a full description of all work activities refer to MS0S0S- General Method
Statement for backfilling of excavations.
6.11 Pedestal
Formwork will be made using plywood form panels in sizes to suit manual
installation and dismantling.
All construction joints will be properly prepared at location indicated on the
construction shop drawings.
For general construction details and work procedures refer to General Method
Statements for Rebar, formwork and conerete.
7.0 Tolerances
As final design drawings and/or Main Contractors instructions.
8.0 References
Specification: Client's Technical Specification for Civil Works, Section 6 ~ Material
and Workmanships Sub-section 6.4 “Concrete Work”.
Safety provisions: Refer to Site Safety Plan.
Related Method Statements:
© MS0601; General Method Statement of Concrete
© MS0602; General Method Statement of Reinforcement
© MS0603; General Method Statement of Formwork
© M0604; General Method Statement of Conerete Repair and Touch up
Drawings: Refer to latest “For Construction” drawing list,
MS00605-Page 6/7Method Statement
Title: Gencral-Foundations
9.0 Appendices
Appendix A: Activity Organization Chart
Appendix B: Emergency Action Plan
Appendix C: 1. Foundation Location Plan
2, Foundation Schedule
3. Foundation Construction Sequences
10.0 Exhibits
MS00605-Page 7/7Method Statement
Title: Foundations
Appendix A: Activity Organization Chart
Mitsubishi Corporation
(MC)
Thai Nishimatsu Construction Co., Ltd.
(TNC)
Italian-Thai Development Public Sino-Thai Engineering & Construction
Company limited Public Company Limited
aTD) (STECON)
Chimney and CW Intake Canal Foundation Work
Msosos