Construction of Student Centre: Change Request No.34 (Build Out Pod&Ofss Offices)

CONSTRUCTION of STUDENT CENTRE CR#34, Build Out shell Space for POD and OFFS Offices (IFC21 Partially, Only Rooms 25150 and 23100) Total 132 01OCT11 31JAN12 05OCT11A 13FEB12 4 0 -13 CHANGE REQUEST No.34(BUILD OUT POD&OFSS OFFICES) Milestone No. 12 CR340010 Schedule Completion
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
328 views4 pages

Construction of Student Centre: Change Request No.34 (Build Out Pod&Ofss Offices)

CONSTRUCTION of STUDENT CENTRE CR#34, Build Out shell Space for POD and OFFS Offices (IFC21 Partially, Only Rooms 25150 and 23100) Total 132 01OCT11 31JAN12 05OCT11A 13FEB12 4 0 -13 CHANGE REQUEST No.34(BUILD OUT POD&OFSS OFFICES) Milestone No. 12 CR340010 Schedule Completion
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

CONSTRUCTION OF STUDENT CENTRE CR#34, Build Out shell Space for POD & OFFS Offices (IFC21 Partially,

Only Rooms 25150 and 23100)


Activity ID Activity Description Orig Dur Planned Start Planned Finish Progress Start Progress Finish % Planned Comp % Actual Comp Total Float

Client: QATAR FOUNDATION Consultant: KEO INTERNATIONAL CONSULTANT Contractor: TADMUR CONTRACTING

OCT

2011 NOV

DEC

JAN

2012 FEB MAR

APR M

CONSTRUCTION OF STUDENT CENTRE


Total 132 01OCT11 31JAN12 05OCT11A 13FEB12 4 0 -13

CHANGE REQUEST No.34(BUILD OUT POD&OFSS OFFICES)


Mile Stone
General
CR340770 CR340000 Access to Offices Area(OFSS) Instruction to Proceed, Cost& time approval 0 0 01OCT11 01OCT11 09OCT11A 14OCT11 100 100 100 0 -13 Access to Offices Area(OFSS) Instruction to Proceed, Cost& time approval

Milestone No. 12
CR340010 Schedule Completion 0 31JAN12 13FEB12 0 0 -13 Schedule Completion

Engineering
Civil / Architectural
CR340020 CR340030 Arch/ civil Shop Dwg Prep'n & Subtt'l Arch/ civil Shop Dwg Rev'w & Appv'l 21 21 01OCT11 15OCT11 21OCT11 04NOV11 14OCT11 28OCT11 03NOV11 17NOV11 62 0 0 0 -12 -12 Arch/ civil Shop Dwg Prep'n & Subtt'l Arch/ civil Shop Dwg Rev'w & Appv'l

Mechanical & Electrical


CR340040 CR340050 CR340060 CR340070 Electrical Shop Dwg Prep'n & Subtt'l Mech Shop Dwg Prep'n & Subtt'l Electrical Shop Dwg Rev'w & Appv'l Mech. Shop Dwg Rev'w & Appv'l 21 21 21 21 03OCT11 03OCT11 17OCT11 17OCT11 23OCT11 23OCT11 06NOV11 06NOV11 16OCT11 16OCT11 30OCT11 30OCT11 05NOV11 05NOV11 19NOV11 19NOV11 52 52 0 0 0 0 0 0 -13 -13 -13 -13 Electrical Shop Dwg Prep'n & Subtt'l Mech Shop Dwg Prep'n & Subtt'l Electrical Shop Dwg Rev'w & Appv'l Mech. Shop Dwg Rev'w & Appv'l

Procurement, Fabrication & Delivery to site


General
CR340080 CR340090 subcontrators Instruction to proceed Contracts Agreement/ Amendment 2 14 01OCT11 03OCT11 02OCT11 16OCT11 06OCT11A 11OCT11A 15OCT11 28OCT11 100 79 20 5 -13 -12 subcontrators Instruction to proceed Contracts Agreement/ Amendment

Start Date Finish Date Must Finish Date Data Date Primavera Systems, Inc.

01OCT11 3402 13FEB12 Detailed Progress Status 31JAN12 Detailed 14OCT11

Sheet 1 of 4 Date 06OCT11 Rev.02 Revision Checked Approved

Progress Status Report_ Planned vs Actual

Activity ID CR340100

Activity Description Material Order/ LPO & LC

Orig Dur 14

Planned Start 14OCT11

Planned Finish 27OCT11

Progress Start 26OCT11

Progress Finish 08NOV11

% Planned Comp 0

% Actual Comp 0

Total Float

S
-12

OCT

2011 NOV

DEC

JAN

2012 FEB MAR

APR M

Material Order/ LPO & LC

Civil / Architectural
CR340110 CR340120 CR340130 CR340140 CR340150 CR340160 CR340170 CR340180 Delivery of Stone Cladding Delivery of Hardware Delivery of Carpet Delivery of AV Equipments Delivery of BUTZBACH NOVOSPRINT Doors Fabrication & Delivery of Wooden Doors Fabrication &Delivery of Glass Partitions/ Doors Fabrication &Delivery Steel doors 60 60 45 55 60 30 45 45 20OCT11 26OCT11 28OCT11 28OCT11 28OCT11 05NOV11 05NOV11 05NOV11 18DEC11 24DEC11 11DEC11 21DEC11 26DEC11 04DEC11 19DEC11 19DEC11 01NOV11 08NOV11 09NOV11 09NOV11 09NOV11 18NOV11 18NOV11 18NOV11 30DEC11 06JAN12 23DEC11 02JAN12 07JAN12 17DEC11 01JAN12 01JAN12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -5 24 -9 -12 9 -6 -6 Delivery of Stone Cladding Delivery of Hardware Delivery of Carpet Delivery of AV Equipments Delivery of BUTZBACH NOVOSPRINT Fabrication & Delivery of Wooden Doors Fabrication &Delivery of Glass Partitions Fabrication &Delivery Steel doors

Mechanical & Electrical


CR340190 CR340200 CR340210 CR340220 CR340240 CR340230 CR340320 CR340250 CR340260 CR340270 CR340280 CR340290 CR340330 CR340300 CR340310 Delivery of Ducting, insulation & fitting Delivery of VAV, Plenum Box ( Alternative) Delivery of DB's, wiring accessories Delivery of Fire Dedection,Fire alarm &Sprinkler Delivery of Grill & diffusers Delivery of XLPE/SWA/PVC wires & cables Delivery of Light fitting Delivery of Copper,Galvanized steel pipe&fitting Delivery of Exhaust Fan Delivery of VAV Heater ( Alternative) Delivery of emergency Battery pack system Delivery of Security System , Structure Cabling Delivery of BMS system delivery Delivery of Sump Pump Delivery of Air Compressor System 30 45 60 60 60 30 60 30 52 55 60 60 60 75 75 10OCT11 13OCT11 13OCT11 13OCT11 15OCT11 15OCT11 18OCT11 16OCT11 17OCT11 17OCT11 17OCT11 17OCT11 19OCT11 17OCT11 17OCT11 08NOV11 26NOV11 11DEC11 11DEC11 13DEC11 13NOV11 16DEC11 14NOV11 07DEC11 10DEC11 15DEC11 15DEC11 17DEC11 30DEC11 30DEC11 20OCT11 23OCT11 23OCT11 23OCT11 27OCT11 28OCT11 28OCT11 29OCT11 29OCT11 29OCT11 29OCT11 29OCT11 29OCT11 29OCT11 29OCT11 18NOV11 06DEC11 21DEC11 21DEC11 25DEC11 26NOV11 26DEC11 27NOV11 19DEC11 22DEC11 27DEC11 27DEC11 27DEC11 11JAN12 11JAN12 13 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -7 -4 -9 3 -1 -13 -2 -13 -12 -10 -3 -3 -3 -12 -12 Delivery of Ducting, insulation & fitting Delivery of VAV, Plenum Box ( Alternative) Delivery of DB's, wiring accessories Delivery of Fire Dedection,Fire alarm &Sprin Delivery of Grill & diffusers Delivery of XLPE/SWA/PVC wires & cables Delivery of Light fitting Delivery of Copper,Galvanized steel pipe&fitting Delivery of Exhaust Fan Delivery of VAV Heater ( Alternative) Delivery of emergency Battery pack system Delivery of Security System , Structure Ca Delivery of BMS system delivery Delivery of Sump Pump Delivery of Air Compressor System

Construction & Installation


Build out shell Space 25150 to POD Print Shop
CR340340 CR340350 Demolition Works Block Works 8 9 09OCT11 15OCT11 17OCT11 24OCT11 05OCT11A 10OCT11A 30OCT11 06NOV11 63 0 5 10 -5 -11 Demolition Works Block Works

Sheet 2 of 4

Activity ID CR340360 CR340370 CR340380 CR340390 CR340400 CR340410 CR340420 CR340430 CR340440 CR340460 CR340520 CR340470 CR340450 CR340480 CR340490 CR340500 CR340510 CR340540 CR340530

Activity Description MEP-1st Fix ( walls) Plaster Works MEP-1st Fix(Conduit,Trunking,Piping,Ducting,wirn Floor Trunking & Conduit Steel Bulkhead Screed Primer & 1st coat paint Ceiling Suspension System MEP 2nd Fix ( dropers, VAV) Glass Windows External Stone Cladding Ceiling Gypsum & Metal Tiles Glass Partitions MEP & Audio Visual -Final Fix Doors ( Metal, Wood & Glass Doors Installation of Air Compressor system Epoxy Paint Painting Final Coat Carpet Tiles

Orig Dur 7 10 32 5 10 6 14 21 18 10 21 10 7 16 10 16 12 5 3

Planned Start 22OCT11 26OCT11 06NOV11 07NOV11 07NOV11 13NOV11 20NOV11 27NOV11 04DEC11 06DEC11 19DEC11 20DEC11 25DEC11 25DEC11 27DEC11 31DEC11 05JAN12 16JAN12 21JAN12

Planned Finish 29OCT11 06NOV11 12DEC11 12NOV11 17NOV11 19NOV11 05DEC11 20DEC11 24DEC11 17DEC11 11JAN12 31DEC11 01JAN12 11JAN12 07JAN12 17JAN12 18JAN12 21JAN12 23JAN12

Progress Start 03NOV11 08NOV11 19NOV11 20NOV11 20NOV11 26NOV11 03DEC11 10DEC11 17DEC11 19DEC11 31DEC11 02JAN12 07JAN12 07JAN12 08JAN12 12JAN12 18JAN12 29JAN12 02FEB12

Progress Finish 10NOV11 19NOV11 25DEC11 24NOV11 30NOV11 01DEC11 18DEC11 02JAN12 05JAN12 29DEC11 23JAN12 12JAN12 14JAN12 24JAN12 18JAN12 30JAN12 31JAN12 02FEB12 05FEB12

% Planned Comp 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

% Actual Comp 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total Float

S
-11 -11 -11 -9 -8 -9 -9 -11 -11 -9 0 -11 5 -11 -10 -11 -11 -11 -11

OCT

2011 NOV

DEC

JAN

2012 FEB MAR

APR M

MEP-1st Fix ( walls) Plaster Works MEP-1st Fix(Conduit,Trunking,Piping,Ducti Floor Trunking & Conduit Steel Bulkhead Screed Primer & 1st coat paint Ceiling Suspension System MEP 2nd Fix ( dropers, VAV) Glass Windows External Stone Cladding Ceiling Gypsum & Metal Tiles Glass Partitions MEP & Audio Visual -Final Fix Doors ( Metal, Wood & Glass Doors Installation of Air Compressor system Epoxy Paint Painting Final Coat Carpet Tiles

Build out shell Space 23100 to OFSS Offices


CR340780 CR340550 CR340560 CR340570 CR340580 CR340590 CR340600 CR340610 CR340620 CR340630 Temporary fencing, barriers & site Protection Block Works MEP-1st Fix ( walls) Plaster Works Floor Trunking & Conduit MEP-1st Fix(Conduit,Trunking,Piping,Ducting,wirn Screed Primer & 1st coat paint Gypsum ceiling suspension & Bulkhead MEP 2nd Fix ( dropers, VAV) 5 12 6 9 5 28 6 14 21 18 04OCT11 10OCT11 24OCT11 27OCT11 07NOV11 06NOV11 13NOV11 20NOV11 24NOV11 03DEC11 09OCT11 23OCT11 30OCT11 06NOV11 12NOV11 07DEC11 19NOV11 05DEC11 18DEC11 22DEC11 11OCT11A 13OCT11A 05NOV11 08NOV11 19NOV11 19NOV11 24NOV11 01DEC11 07DEC11 15DEC11 20OCT11 03NOV11 10NOV11 17NOV11 23NOV11 20DEC11 30NOV11 17DEC11 31DEC11 04JAN12 100 33 0 0 0 0 0 0 0 0 30 5 0 0 0 0 0 0 0 0 -9 -10 -10 -10 -9 -11 -9 -9 -11 -11 Temporary fencing, barriers & site Protection Block Works MEP-1st Fix ( walls) Plaster Works Floor Trunking & Conduit MEP-1st Fix(Conduit,Trunking,Piping,Ducting Screed Primer & 1st coat paint Gypsum ceiling suspension & Bulkhead MEP 2nd Fix ( dropers, VAV)

Sheet 3 of 4

Activity ID CR340640 CR340650 CR340660 CR340670 CR340680 CR340700 CR340690 Glass Partitions

Activity Description

Orig Dur 12 12 10 10 10 6 6

Planned Start 14DEC11 17DEC11 25DEC11 27DEC11 03JAN12 11JAN12 17JAN12

Planned Finish 27DEC11 29DEC11 04JAN12 07JAN12 14JAN12 17JAN12 23JAN12

Progress Start 27DEC11 29DEC11 07JAN12 08JAN12 16JAN12 24JAN12 30JAN12

Progress Finish 09JAN12 11JAN12 17JAN12 18JAN12 26JAN12 30JAN12 05FEB12

% Planned Comp 0 0 0 0 0 0 0

% Actual Comp 0 0 0 0 0 0 0

Total Float

S
-11 -11 -11 -2 -11 -11 -11

OCT

2011 NOV

DEC

JAN

2012 FEB MAR

APR M

Glass Partitions Gypsum,plaster board Ceiling Joint Fillers , Stucco & first coat pa Glass Doors MEP & Audio Visual -Final Fix Painting Final Coat Carpet Tiles

Gypsum,plaster board Ceiling Joint Fillers , Stucco & first coat painting Glass Doors MEP & Audio Visual -Final Fix Painting Final Coat Carpet Tiles

+ Testing, Commissioning & Handing Over


12 18JAN12 31JAN12 31JAN12 13FEB12 0 0 -11