First Article Inspection Guidelines

A supplier must submit a First Article Inspection (FAI) report in the following situations: 1) The first time a part is provided to the customer. 2) When a design change occurs. 3) When there is a change in manufacturing source, process, inspection method, location, tooling, or materials. 4) If the part has not been provided to the customer in over 2 years. The FAI must use production tooling and methods and include all design specifications. A material and process certificate must also be included. The FAI report must be submitted with the parts it represents and all characteristics must meet the design requirements unless approved otherwise by the customer.

Uploaded by

Joe Allen
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
319 views3 pages

First Article Inspection Guidelines

A supplier must submit a First Article Inspection (FAI) report in the following situations: 1) The first time a part is provided to the customer. 2) When a design change occurs. 3) When there is a change in manufacturing source, process, inspection method, location, tooling, or materials. 4) If the part has not been provided to the customer in over 2 years. The FAI must use production tooling and methods and include all design specifications. A material and process certificate must also be included. The FAI report must be submitted with the parts it represents and all characteristics must meet the design requirements unless approved otherwise by the customer.

Uploaded by

Joe Allen
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

FIRSTARTICLEINSPECTIONREQUIREMENTS

QualityCode200(QAF7660)FIRSTARTICLEINSPECTION(FAI)

TheSuppliershallsubmitaFirstArticleInspection(FAI)whenanyofthefollowingoccur: Thefirsttimematerialisprovided(fullFAI) Achangeindesign(partialFAIforaffectedfeatures/characteristics) Achangeinmanufacturingsource(s),process(es),inspectionmethod(s),locationof manufacture, tooling, materials,NC programming,naturalormanmadeevent(forcemajeure)(fullFAI). Thefirsttimematerialisprovidedinover2years(fullFAI) First Article material shall be produced using production tooling, processing and methods and must include all design data specifiedbythePO,[Link] certificatewhereapplicablemustbeprovidedwiththeFAIreport. [Link] dataunlesspreviousapprovalhasbeengivenbyAVOXSystems. OR: [Link].

AllcharacteristicsmustbecompliantwiththedesigndataunlesspreviousapprovalhasbeengivenbyAVOXSystems.

ThefollowingformismaybeusedbythesupplierforFirstArticleInspection.

Rev.10407

FIRSTARTICLEINSPECTIONREQUIREMENTS
Form3:FIRSTARTICLE/PIECEINSPECTIONREPORT
Part Number Supplier / Dept. Rev. Part Name PO/MO FAI Report Serial Number/Cavity #/Lot/Batch#:

PAGE_1_OF__

The signature indicates that characteristics are accounted for meet drawing requirements or are documented for disposition.
Prepared By: Comments: Characteristic Accountability Char No Reference Location Characteristic Designator Requirement Results Inspection / Test Results Measurement Equipment Variant (if ) Approved By: Date MVR

Rev.10407

FIRSTARTICLEINSPECTIONREQUIREMENTS
Form3: FIRSTARTICLE/PIECEINSPECTIONREPORT(CONTINUATIONSHEET)
Part Number Prepared By: Rev. Part Name Date FAI Report MVR

PAGE____OF___

Approved By:

The signature indicates that characteristics are accounted for meet drawing requirements or are documented for disposition
Comments: Characteristic Accountability Char No Reference Location Characteristic Designator Requirement Results Inspection / Test Results Measurement Equipment Variant (if )