75% found this document useful (4 votes)
1K views3 pages

Critical Path Method Guide

The Critical Path Method (CPM) is a technique for scheduling a set of project activities. It identifies the critical path of interdependent activities that must go according to plan in order to complete the project on schedule. CPM determines the float, or slack time, of each activity to identify which can be delayed without pushing out the project's deadline. It also calculates early and late start and finish dates to determine the earliest and latest times each activity can begin and end.

Uploaded by

clewis00771897
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
75% found this document useful (4 votes)
1K views3 pages

Critical Path Method Guide

The Critical Path Method (CPM) is a technique for scheduling a set of project activities. It identifies the critical path of interdependent activities that must go according to plan in order to complete the project on schedule. CPM determines the float, or slack time, of each activity to identify which can be delayed without pushing out the project's deadline. It also calculates early and late start and finish dates to determine the earliest and latest times each activity can begin and end.

Uploaded by

clewis00771897
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

The Critical Path Method (CPM)

The Critical Path Method (CPM) can help you keep your projects on track.
Critical path schedules...
Help you identify the activities that must be completed on time in order to complete the whole project on
time.
Show you which tasks can be delayed and for how long without impacting the overall project schedule.
Calculate the minimum amount of time it will take to complete the project.
Tell you the earliest and latest dates each activity can start on in order to maintain the schedule.
The CPM has four key elements...
Critical Path Analysis
Float Determination
Early Start & Early Finish Calculation
Late Start & Late Finish Calculation
Critical Path Analysis
The critical path is the sequence of activities with the longest duration. A delay in any of these activities will
result in a delay for the whole project. Below are some critical path examples to help you understand the key
elements...
Using the Critical Path Method
(CPM)
The duration of each activity is listed above each node in the diagram. For each path, add the duration of each
node to determine it's total duration. The critical path is the one with the longest duration.
There are three paths through this project...
Use Critical Path Analysis to find
Your Critical Path
Float Determination
Once you've identified the critical path for the project, you can determine the float for each activity. Float is the
amount of time an activity can slip before it causes your project to be delayed. Float is sometimes referred to as
slack.
Figuring out the float using the Critical Path Method is fairly easy. You will start with the activities on the
critical path. Each of those activities has a float of zero. If any of those activities slips, the project will be
delayed.
Then you take the next longest path. Subtract it's duration from the duration of the critical path. That's the float
for each of the activities on that path.
You will continue doing the same for each subsequent longest path until each activities float has been
determined. If an activity is on two paths, it's float will be based on the longer path that it belongs to.
Determining Float
Using the critical path diagram from the previous section, Activities 2, 3, and 4 are on the critical path so they
have a float of zero.
The next longest path is Activities 1, 3, and 4. Since Activities 3 and 4 are also on the critical path, their float
will remain as zero. For any remaining activities, in this case Activity 1, the float will be the duration of the
critical path minus the duration of this path. 14 - 12 = 2. So Activity 1 has a float of 2.
The next longest path is Activities 2 and 5. Activity 2 is on the critical path so it will have a float of zero.
Activity 5 has a float of 14 - 9, which is 5. So as long as Activity 5 doesn't slip more than 5 days, it won't cause
a delay to the project.
Early Start & Early Finish Calculation
The Critical Path Method includes a techniques called the Forward Pass which is used to determine the earliest
date an activity can start and the earliest date it can finish. These dates are valid as long as all prior activities in
that path started on their earliest start date and didn't slip.
Starting with the critical path, the Early Start (ES) of the first activity is one. The Early Finish (EF) of an
activity is its ES plus its duration minus one. Using our earlier example, Activity 2 is the first activity on the
critical path: ES = 1, EF = 1 + 5 -1 = 5.
Critical Path Schedules
You then move to the next activity in the path, in this case Activity 3. Its ES is the previous activity's EF + 1.
Activity 3 ES = 5 + 1 = 6. Its EF is calculated the same as before: EF = 6 + 7 - 1 = 12.
If an activity has more than one predecessor, to calculate its ES you will use the activity with the latest EF.
Late Start & Late Finish Calculation
The Backward Pass is a Critical Path Method techique you can use to determine the latest date an activity can
start and the latest date it can finish before it delays the project.
You'll start once again with the critical path, but this time you'l begin from the last activity in the path. The Late
Finish (LF) for the last activity in every path is the same as the last activity's EF in the critical path. The Late
Start (LS) is the LF - duration + 1.
In our example, Activity 4 is the last activity on the critical path. Its LF is the same as its EF, which is 14. To
calculate the LS, subtract its duration from its LF and add one. LS = 14 - 2 + 1 = 13.
You then move on to the next activity in the path. Its LF is determined by subtracting one from the previous
activity's LS. In our example, the next Activity in the critical path is Activity 3. Its LF is equal to Activity 4 LS
- 1. Activity 3 LF = 13 -1 = 12. It's LS is calculated the same as before by subtracting its duration from the LF
and adding one. Activity 3 LS = 12 - 7 + 1 = 6.
You will continue in this manner moving along each path filling in LF and LS for activities that don't have it
already filled in.

You might also like