S.
No
SKIDTAGS
RESPONSIBILITY
PUNCH LIST DESCRIPTION
ME-424
Actual PD volume is 10L but P&ID shows 20L. P&ID shall be revised.
ME-411
Horizontal reference dimention (X-direction) for TP-004/005 not provided in GA drawing.
ME-435
Blanketing line 2'' X 3/4'' line ball valve 3/4'' not provided and the same line not shown in
P&ID.
ME-423
ME-424
ME-435
Discharge 2'' X 3/4'' line ball valve 3/4'' not provided and the same line not shown in P&ID.
ME-423
Horizontal distance from center to center deviation found.Actual-3400 but As per GAD
require-3420. GA drawing shall be updted.
ALL 7 SKIDS
ME-423
TP 001 does not have spectacle blind as per P&ID. But in actual Spectacle blind available.
P&ID shall be updated.
ME-464
Actual Size fasteners to be provided.
Pulsation Dampener details to be provided in P&ID
ME-423
All the hanging tags does not have prefix 4S
10
ME-435
FT tag no to be change- Actual is -4S-FT-1178 but is should be FI-1178
11
ALL 7 SKIDS
12
ME-411
LG Tag is not provided
13
ME-445
LG tag no to be change- Actual is -4S-LG-0176 but is should be LG-0176
14
ME-424
Prefix 4S not availble in all Hanging tags
15
ME-411
ME-464
ME-463
Temporary nut bolts to replaced with original
16
ME-463
Tie-in point tag TP-002 to be provided
17
ME-424
Tie-in point tag TP-005 to be provided
18
ME-423
ME-424
TT tag no to be change- Actual is -4S-TE-0151 but is should be - 4S-TT-0151
Hanging tags for Level Transmitter found wrong
( LIT in the place of LT)
19
ME-411
TT tag no to be change- Actual is -4S-TT-0101 but is should be TT-0101
20
ME-445
Balance material certificates for Washer and fasteners
Test certificates balance for following items.
21
ALL 7 SKIDS
1. PSV
2. Mixer
3. Pump Motor
22
ALL 7 SKIDS
Earthing connection and continuity check balance
23
ALL 7 SKIDS
All open end to be properly closed.
24
ALL 7 SKIDS
All pipe supports & support clamp and cable Tray support to be checked for tightness.
25
ALL 7 SKIDS
Bolts shall be tightened properly wherever applicable.
26
ME-424
ME-423
Calibration pot Picking & passivation to be carried out
27
ALL 7 SKIDS
Clamps painting to be carried out wherever applicable
28
ME-423
Drain line found bend for level transmitter LT-0153
29
ME-411
ME-464
ME-463
Drip Tray angle support not installed
30
ALL 7 SKIDS
Final washing & cleaning shall be carried out for skid before shipment.
31
ALL 7 SKIDS
Grating clamp to be tightened propely.
32
ME-464
ME-463
Hand rail closing bar to be provided
33
ME-411
Handrail bar fouling with handrail port.
34
ALL 7 SKIDS
35
ME-464
ME-463
Pickling & passivation touch up to be carried out for tank and Piping.
36
ME-445
Piping Pickling and passivation touch up to be carried out.
Paint touch to be completed whereever applicable.
37
ME-424
Pump drain tubing line to be provided.
38
ALL 7 SKIDS
Rust preventive oil shall be applied in rusted flange surfaces.
39
ALL 7 SKIDS
Rusted valves handles to be painted
40
ALL 7 SKIDS
Skid Direction to be marked.
41
ME-423
ME-424
42
ALL 7 SKIDS
Strainer drain spectacle blind is in NO condition instead of NC condition
Support with clamps to installed wherever applicale
43
ME-423
ME-424
44
ALL 7 SKIDS
45
ME-411
46
ALL 7 SKIDS
47
ME-463
Cable tray supports to be provided
48
ME-423
ME-424
Calibration tube not visible from Pump stroke adjustment
49
ME-424
Sunshade for LT and TT not availble. Clarify required or not?
Tag welds available in Hand rail post to be removed.
Tank Man way, Gasket, Spilt pin with fasteners to be provided.
Cable tray fouling below the suction drip tray. Cable tray to be rerouted.
Cable tray groomet to be provided in balance areas
50
ME-411
ME-435
ME-445
51
ALL 7 SKIDS
52
ME-411
ME-435
ME-445
Motor Gear Pump :1) Painting report to be provided for reviewed.
53
ME-464
ME-463
Piping and Tank Pickling & passivation report to be provided for review.
54
ALL 7 SKIDS
55
ME-423
Mixer installation balance
Pump Name plate not installed.
Following Reports review balance from KNM and TAIF.
1. Material certificates and inspection reports for Base frame , Tank and Piping.
2. Paiting reports.
3. Galvanizing reports
4. Pickling and passivation reports.
Insulation material inspection has to be carried out
Level Gauge : 1) Certificates Model number not matching with datasheet.
2) LG range to be provided in Certificates.
3) Flange size not mentioned in Certificates.
56
ALL 7 SKIDS
57
ME-423
ME-424
TPI Review of Base frame, Tank and piping certificates
58
ME-423
ME-424
TPI Review of LG, LT, PG, PD, FI, FT, TT, Pump, RO certificates.
59
ME-464
ME-463
TPI Review of PD, PSV, PG, Motor for Dosing pump, Mier , Motor for Mixer and
Calibration Pot certificates balance.
60
ME-423
Performance report and painting for pumps not received.
61
ME-435
ME-445
Motor for Mixer :1) Type Test Certificates not provided with certificate
ME-435
ME-445
Pump :1) As Pump test certificates plunger diameter shown 30mm but data sheet showing as 35mm.
2) Sectional Drawing all items material is not traceable.
3) Clear / visible material certificates are require.
ME-464
ME-463
Pump :1) Motor RPM as data sheet 1450 but actual as per Pump certificates 1400.As per motor data
sheet 1500 rpm.
2) Sectional Drawing all items material is not traceable.
3) Clear / visible material certificates are require.
64
ME-411
Pump :1) Sectional Drawing all items material is not traceable.
2) Clear / visible material certificates are require.
65
ME-411
ME-435
ME-445
Temperature Transmiter :1) Certificates Model number not matching with data sheet and PO(R21 as per PO and Data
sheet)
62
63
CATEGORY
STATUS
ACTION BY
CLOSURE DATE
CLOSED
4th feb 2016
CLOSED
4th feb 2016
CLOSED
4th feb 2016
CLOSED
4th feb 2016
CLOSED
4th feb 2016
CLOSED
4th feb 2016
CLOSED
4th feb 2016
OPEN
OPEN
9th Feb 2016
8th Feb 2016
8th Feb 2016
8th Feb 2016
8th Feb 2016
9th Feb 2016
10th feb 2016
9th Feb 2016
9th Feb 2016
9th Feb 2016
9th Feb 2016
7th feb 2016
OPEN
OPEN
OPEN
7th feb 2016
7th feb 2016
8th Feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
8th Feb 2016
8th Feb 2016
8th Feb 2016
CLOSED
8th Feb 2016
8th Feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
OPEN
7th feb 2016
7th feb 2016
7th feb 2016
7th feb 2016
CLOSED
LOOSE SUPPLY
9th Feb 2016
8th Feb 2016
REMARKS
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Noted & Incorporated.
As built documents submitted on 04Feb-16.
Bolts delivery date on 15th Feb
2016. To be expedited
Partially closed
Some tags still missing
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
Partially closed
Some tags still missing
Bolts delivery date on 15th Feb
2016. To be expedited
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
RFQ raised on 6th Feb 2016
DURING PACKING
NOT REQUIRED
Will be delivered on 8th feb 2016