Bridge Inspection Basic Procedures and Practices
Bridge Inspection Basic Procedures and Practices
Prepared by:
Bureau of Bridges and Structures
Division of Highways
Agency:
Illinois Department of Transportation
Place of Publication:
Springfield Illinois
2011
ii
Table of Contents
SECTION - I. INTRODUCTION ....................................................................................................... 1
GENERAL. ................................................................................................................................... 1
BRIDGE CONDITION REPORTS. ................................................................................................ 1
Purpose. .................................................................................................................................... 1
Submittal Requirements. ........................................................................................................... 2
Bureau of Bridges & Structures (BB&S) Concurrence................................................................ 2
SECTION - II. BRIDGE INSPECTION............................................................................................. 4
GENERAL. ................................................................................................................................... 4
BRIDGE INSPECTION REFERENCES. ....................................................................................... 4
FIELD INSPECTION PROCESS................................................................................................... 4
Preparation. ............................................................................................................................... 5
Field Inspection. ........................................................................................................................ 5
Documentation. ......................................................................................................................... 8
DELAMINATION SURVEYS. ...................................................................................................... 10
ADDITIONAL TESTING METHODS. .......................................................................................... 11
SECTION - III. BRIDGE ANALYSIS & SCOPE OF WORK SELECTION....................................... 13
GENERAL. ................................................................................................................................. 13
SCOPE OF WORK DEFINITIONS. ............................................................................................. 13
BRIDGE ANALYSIS PROCESS. ................................................................................................ 13
GEOMETRIC & HYDRAULIC CAPACITY EVALUATION. .......................................................... 14
General. .................................................................................................................................. 14
Roadway Geometry. ................................................................................................................ 14
Bridge Clearances. .................................................................................................................. 14
Hydraulic Capacity. .................................................................................................................. 14
Geometric & Hydraulic Capacity Evaluation Assessment. ....................................................... 15
DECK EVALUATION. ................................................................................................................. 15
General. .................................................................................................................................. 15
Deck Joints. ............................................................................................................................. 15
Bridge Railings. ....................................................................................................................... 16
Wearing Surface Condition. ..................................................................................................... 16
Deck Condition. ....................................................................................................................... 16
Deck Repair/Replacement Assessment. .................................................................................. 16
Deck Repair Methods. ............................................................................................................. 17
Deck Repair Overlay Selection. ............................................................................................... 18
B-SMART Criteria. ................................................................................................................... 19
SUPERSTRUCTURE EVALUATION (other than deck) .............................................................. 20
General. .................................................................................................................................. 20
Condition. ................................................................................................................................ 20
Load Capacity. ........................................................................................................................ 20
Coring of Reinforced Concrete Superstructures....................................................................... 21
Bearings. ................................................................................................................................. 21
Special Considerations. ........................................................................................................... 22
Superstructure Widening. ........................................................................................................ 22
Superstructure Evaluation Assessment. .................................................................................. 22
iii
iv
Key to Acronyms:
AASHTO
ASD
ASTM
BB&S
BCR
BD&E
B-SMART
CO
Concrete Overlay
FHWA
FWS
GGBFS
HRM
HMA
IDOT
ISIS
LFD
LRFD
PONTIS
SPC
SPZ
3P
3R
SECTION - I. INTRODUCTION
GENERAL.
This document provides guidance for preparing Bridge Condition Reports for the improvement of
roadway structures. It covers the wide range of information necessary to complete reports for
various types of bridge projects. The guideline reviews background information, field inspection &
testing (in brief), general analysis procedures and report preparation. Example bridge condition
report formats have been provided in the appendices. This document was developed primarily with
multi-girder supported bridges with cast in place concrete decks in mind. However, the general
process provided can be applied to both simpler and more complicated structures.
The information provided in this revised Bridge Condition Report Procedures & Practices
supersedes the guidance published in the previous document dated February, 2007.
All existing structures > 20 ft. in length back-back abutment and cast in place multiple cell concrete
box culverts meeting the above criteria require a Bridge Condition Report.
Coordination requirements for structures with the scope of work Bridge to Remain in Place that
are located within a 3R type highway project are found in Section IV, ABBREVIATED BRIDGE
COORDINATION of this document.
Scope of work definitions for bridge projects are provided in Section-III of this document.
For structures to be Gapped Temporarily within a 3R type highway project, a memorandum may
be submitted briefly describing the Districts intent to complete work on these structures in a
separate project. This approach should only be used in rare instances and the reason for gapping
the structure provided in the memorandum. A Bridge Condition Report is still required in this case
at a later date.
Structures located within SMART and 3P projects do not require the submittal of a Bridge Condition
Report. However, if the structure is being resurfaced as part of the project, coordination will be
made with the BB&S to approve the resurfacing method, bridge rating and general scope of work.
See Section IV, ABBREVIATED BRIDGE COORDINATION of this document for details.
Structures planned for maintenance type work do not require coordination with BB&S unless
specifically requested by the District. However, if the structure is being resurfaced, coordination will
be made with the BB&S to approve the resurfacing method and bridge rating. See Section IV
ABBREVIATED BRIDGE COORDINATION of this document for details.
Bureau of Bridges & Structures (BB&S) Concurrence.
The Bridge Condition Report allows the BB&S to review the proposed scope of work for a structure
and provide concurrence based on its current condition, relevant design criteria and other
applicable issues. Upon completion of their review, the BB&S will document concurrence or nonconcurrence with the following geometric and structural factors as applicable:
type of superstructure
type and age of deck and of deck overlays
joint types longitudinal and transverse
bearing types
substructure types and borings
details requiring special inspection
fatigue prone details
fracture critical details
pins and hangers in the main load carrying elements
previous repair or maintenance work
previous inspection reports
2. Prepare sketch plans of the top and bottom of the deck, abutments, piers and other structural
elements as necessary to allow proper documentation of the location and description of significant
distress features using the following guidelines:
plans should be roughly to scale and of a convenient size for field use
plans should include basic dimensions and a reference line from a point that can be easily
located and measured from in the field and identified in the report
areas of distress located on the sketches should have a linear or area dimension placed on it
as appropriate
areas of distress should be detailed in a distinctive manner and a key provided to distinguish
between the different deterioration types
3. Prepare a list of equipment needed to complete the inspection. Include how you will access
each element of the bridge to be inspected and if it will require coordination for special equipment
and traffic control.
Field Inspection.
The inspection will generally include all elements of the bridge. The following list describes
elements found on a typical bridge and issues to consider during their inspection. Photographs of
distressed areas, areas of concern and areas depicting the general overall condition of the structure
should be taken during the inspection. This list is not all inclusive and is only intended as a guide.
Bearings:
Inspect the bearings. Some problem areas to look for and document are:
areas with heavy rusting or section loss
excessive movement, lack of movement or excessive tilting of the bearing
damaged or missing bolts
deterioration of the concrete at the base of the bearing
bulging or tearing of elastomer
Abutments:
Inspect the abutments and wing walls. Some problem areas to look for and document are:
areas of cracking and leaching
spalled and delaminated areas
exposed reinforcement (concrete sounding recommended in this area)
section loss in reinforcement
movement or rotation of the abutments
scour or erosion around the abutments
presence of excessive or unexplained moisture at or behind the abutments
Piers:
Inspect the piers. Some problem areas to look for and document are:
areas of cracking and leaching
spalled and delaminated areas
exposed reinforcement (concrete sounding recommended in this area)
section loss in reinforcement
movement or rotation of the piers
scour or erosion around the piers
Other Items:
Additional items that should be identified & documented as appropriate:
presence and extent of scour or erosion at the site
presence, types and condition of utilities on or near the structure
condition of the slope protection system
Documentation.
Proper documentation of the inspection results is critical to producing a good BCR. Without proper
documentation, it will be difficult to conduct a thorough analysis of the structure to determine the
appropriate scope of work. It will also be difficult for the BB&S to quickly review the report once it is
submitted for approval. Poor documentation often leads to wasted time for District, Consultant and
BB&S personnel in retrieving information that should have been documented as part of the initial
inspection and report preparation process. General guidance on providing adequate
documentation of important aspects of the inspection is provided in the following paragraphs.
Photographs:
Adequate photographs of the structure need to be taken to convey its current condition and
corroborate the recommended scope of work in the report. Photographs provided in the report
must be color and of high quality to be useful. Photographs of distressed areas, areas of concern
and areas depicting the general overall condition of elements of the structure should be taken
during the inspection.
The example report formats located in Appendix A and B of this document provide a sample listing
of photographs required.
plans should be drawn roughly to scale and made to fit in the report
plans should include basic dimensions and reference points that can be easily identified in
the report
areas of distress should have a linear or area dimension placed on it as appropriate
areas of distress should be detailed in a distinctive manner and a key provided to distinguish
between different deterioration types
Plot estimated full and partial-depth patch areas on the bottom and top of deck surveys. Avoid
being too conservative since the actual full-depth areas are generally larger than the distress areas
visible during the inspection.
The bottom of deck survey is the more important of the two surveys as it allows the report preparer
to estimate the amount of full depth patching required for the deck.
If a delamination survey is used, the areas of delamination found in the survey are plotted to scale
on the top of deck survey sketch and squared off for easy measurement of delaminated areas.
These areas will frequently overlap other distressed areas plotted and provide a more
comprehensive assessment of the deck condition.
Substructure Surveys:
Provide detailed substructure surveys. These surveys are critical in estimating the condition of the
substructure and whether or not it is economical to reuse. The survey plans provide documentation
of the location and type of distress in the substructure and should be detailed similar to the top and
bottom of deck surveys. The surveys will be used later to develop detailed repair plans, if
applicable.
Measurements at Areas of Concern:
Section Loss. If significant section loss is detected on main load carrying elements the following
measurements should be taken, if appropriate:
Concrete Crack. If significant concrete cracks are detected in structural members the following
measurements should be taken:
length of crack
DELAMINATION SURVEYS.
The decision to use a delamination survey is dependent on several factors. Delamination surveys
are not always appropriate due to the cost to prepare this data verses the potential benefit of having
the additional information. This is often true for small deck areas, structures with little or no
apparent deterioration, those that are functionally obsolete and must therefore be replaced
regardless or are obviously beyond repair. On the other hand, for structures that exhibit a level of
deterioration where it is unclear if the deck is beyond economical repair, completing a delamination
survey is appropriate.
If it is estimated a deck will require deck repair, a delamination survey is recommended to verify the
scope of work selected and aid in determining the estimated deck repair quantities.
The following methods are used to conduct delamination surveys:
Method 1-(ASTM D 4580) Measuring Delaminations in Concrete Bridge Decks by Sounding
Method 2 (AASHTO TP36)* Evaluating Asphalt-Covered Concrete Bridge Decks Using Pulsed
Radar
*This test method has been discontinued by AASHTO
Method 3-(ASTM D 4788) Detecting Delaminations in Bridge Decks Using Infrared Thermography
Method 1 may be used for exposed concrete bridge decks and bridge decks with a concrete
overlay. However, for decks with a concrete overlay, this method will detect debonding of the
overlay and delamination of the underlying concrete. This method cannot distinguish between
debonding and delamination. Method 1 is very accurate for exposed concrete bridge decks, but the
sounding process can be slow and traffic noises may restrict its use. The chain drag is the most
commonly used procedure for conducting this test.
The results of a sounding survey (Delamtect, chain drag, or hammer) can be affected by cold
temperatures and/or wet conditions. This type of survey should be performed when the air
temperatures remain above 320 F for a sufficient length of time to assure a dry and frost free deck.
The use of a delamination survey on precast-prestressed concrete box beam superstructures is not
recommended.
Method 2 is primarily intended for concrete bridge decks with a hot mix asphalt overlay. This
method may also be used for exposed concrete bridge decks and bridge decks with a concrete
10
Use Method 1, 2 or 3 for exposed concrete decks and decks with a concrete overlay.
Use Method 2 and/or 3 for decks with a hot mix asphalt overlay.
For more information concerning Methods 2 and 3, the publication Evaluation of Bridge Deck
Delamination Investigation Methods by Henrique L. M. dos Reis and Matthew D. Baright (Project
IC-H1, 95/96 and Report No. ITRC FR 95/96-1) is available from the Bureau of Materials and
Physical Research. The report recommended that a combination of Methods 2 and 3 be used for
the most accurate inspection of a bridge deck.
Since some delamination surveys may interpret the debonding of wearing surfaces as
delaminations, the surveys must be closely coordinated with both the top and bottom of deck
inspections to aid in estimating areas of deck delaminations.
If the deck condition remains unclear after the delamination survey and top and bottom of deck
survey coordination, further tests such as spot overlay removal and deck cores can be taken.
Additional diagnostic tests such as the half-cell survey and chloride content tests may also be made
to aid in determining whether or not deck repair is appropriate.
12
13
General information on how to conduct each of these evaluations is provided in the following pages.
The evaluations are presented in the general order they should be reviewed for a typical structure;
however, the order may be revised if deemed appropriate by the engineer.
Roadway Geometry
Bridge Clearances
Hydraulic Capacity
Roadway Geometry.
The geometry for the roadway through the bridge and for roadways under/over the structure should
be evaluated for conformance to Department policy and needs. It must be determined if any
changes will be made to the horizontal and vertical roadway alignments and widths within the scope
of current or future projects that will affect the existing structure.
Bridge Clearances.
The deck clear width between rails/curbs along with the horizontal and vertical clearance beneath
the structure must be reviewed, as applicable, for conformance to Department policy. Minimum
clearances for bridges to remain in place are found in the BD&E Manual in Chapters 49 and 50 (3R
Guidelines) depending on the clearance type and roadway classification. Review the sections
labeled Criteria for Bridges to Remain in Place to check existing structures. Clearances for
improved bridges can be found in these same chapters along with Chapter 39 (Structure
Planning/Geometrics).
Hydraulic Capacity.
For bridges over streams, the hydraulic capacity should be reviewed when appropriate. A review of
any hydraulic capacity analysis results and records of flooding should be made, if available.
Changes since initial construction in the channel location or hydraulic opening through the structure
should be noted. Changes in drainage conditions affecting the bridge should also be noted.
14
Where the existing vertical alignment is to be maintained and there is no history of serious hydraulic
deficiencies at the location, then the existing bridge waterway opening may usually be retained.
For the following cases, development of a formal Hydraulic Report is required:
bridge replacement.
superstructure replacement.
bridge widening requiring additional substructure to be added.
reductions to the hydraulic opening through the structure.
Detailed guidance on Hydraulic Report production is available in the IDOT Drainage Manual.
Geometric & Hydraulic Capacity Evaluation Assessment.
Once the information for the Geometric, Hydraulic and Capacity Evaluation has been collected it
must be evaluated. If the structure meets the minimum clearance requirements, is hydraulically
acceptable and no significant changes to the roadway geometry are anticipated, then it satisfies
criteria for this evaluation to remain in place.
If the structure is found not to meet minimum clearance, hydraulic or geometric requirements then
further investigation is required. The area not meeting policy must have a waiver of the policy
granted if the structure is to remain in place. If a waiver of the policy is not granted by the
approving authority, or desired by the District, then the element in question must be modified or
replaced to meet policy. In cases where complete replacement of the structure is justified as
necessary and economical after completion of the Geometric, Hydraulic and Capacity Evaluation
then only a cursory review of the structure condition related evaluations need to be made if the
existing structure is to be removed.
DECK EVALUATION.
General.
The deck evaluation consists of a review of the bridge elements that are related to the decks
condition. These elements are the deck joints, bridge railing, wearing surface (if applicable) and
structural deck element condition.
Deck Joints.
All transverse and longitudinal joints should be reviewed to determine their condition. If the joints
are found to be significantly deteriorated, they should be considered for repair or replacement.
Methods and details for replacement joint types are found in the BB&S Structural Services Manual
for decks remaining in place and the BB&S Bridge Manual for decks being replaced.
When practical, deck joints should be considered for elimination. This reduces the potential for
deck drainage passing through failed joints and causing deterioration of the structural elements
located below. Guidance on deck joint elimination is as follows:
15
16
Decks Requiring
Widening(1,2):
25%
15%
26-35%
16-25%
> 35%
> 25%
Recommendation:
Deck repair cost effective(3)
Deck repair cost effective only in well
documented cases(4)
Deck replacement appropriate
Notes to Table:
(1) Deck area calculated using length x face-face parapet width.
(2) This column pertains to deck widening which requires additional beam/s only.
(3) For decks containing sidewalks and raised medians with significant amounts of
repair/replacement work required, separate cost analysis estimates should be completed to
justify deck repair versus deck replacement.
(4) In this case deck repair may be considered appropriate when a detailed cost analysis and/or
well documented exterior constraints indicate deck repair is more advantageous.
All deck repair projects must be evaluated with the length of time until construction being
considered.
The maintenance history and age of the deck must also be considered when evaluating a deck for
repair or replacement. Concrete decks in need of repair that contain large areas of patching from
prior repair cycles are less desirable to retain. This is due to the tendency of the area around
previously repaired areas to deteriorate more rapidly than the original deck.
Decks that have had thin concrete overlays previously placed on them will also need to be
evaluated for repair. In order to be cost effective, a thin concrete overlay must last approximately
18 years, otherwise, deck replacement is often more economical. Decks that are in poor or
questionable condition to last this length of time should not be considered for an additional overlay
in most circumstances.
Deck Repair Methods.
There are multiple methods available to complete deck repairs on a bridge. Each method differs
somewhat from the others in deck slab repairs, deck surface preparation and replacement wearing
surface composition. The specific requirements for these methods are described in detail in the
Departments Standard Specifications and Special Provisions.
Any deck repair method that results in the temporary elimination of bond between the concrete and
the upper mat of negative moment reinforcing steel on continuous or rigid frame concrete structures
(such as continuous T-beam and slab bridge superstructures) where this reinforcement acts as part
of the primary superstructure support system must provide for the staging of repairs in those areas
to maintain structural integrity. If the recommended repair method results in dead load in excess of
the existing conditions, approval shall be obtained from the Bureau of Bridges and Structures.
17
Overlay
Type
Desired Overlay
Lifespan <
12years(3)
ADT < 10,000
- HMA w/coal tar
membrane
- HMA w/sheet
membrane
Desired Overlay
Lifespan <
12years(3)
ADT 10,000
- Fly Ash GGBFS
CO
- Microsilica CO
- HRM CO
- Latex CO(1)
-Thin Polymer Over.
Desired Overlay
Lifespan 12years
ADT < 3,000
Desired Overlay
Lifespan 12years
ADT 3,000
(2)
(2)
Stopping
Condition
Within 300
of Deck
Short
Construction
Duration
Required
- HMA w/sheet
membrane
- HMA w/coal tar
membrane
-Thin Polymer
Over.(2)
- HMA w/sheet
membrane
- HMA w/coal tar
membrane
Notes to Table:
- The following acronyms were used in the table above:
GGBFS = Ground Granulated Blast Furnace Slag
HMA = Hot Mix Asphalt
HRM = High Reactive Metakaolin
CO = Concrete Overlay
(1) - For Latex CO projects the maximum slope allowed is 3% and the maximum thickness is 3.5.
(2) - Thin Polymer Overlays are generally recommended on decks with small areas and low patching
quantities or when necessitated by the need to minimize additional dead load or the need to minimize
height adjustments at the expansion devices.
(3) - For projects with an estimated lifespan 5 years, an HMA without a waterproofing membrane may be
considered.
The overlay types shown are recommendations for the criteria provided. Other overlay types may
be used in these situations when justified by the engineer.
18
Full and partial depth deck repair subject to the limits outlined in the Qualification Criteria
paragraph.
Expansion joint repair/replacement.
Bearing reconditioning/replacement.
Deck drain replacement, extension or plugging.
Bridge rail repair/retrofit (replacement not allowed).
Minor abutment backwall repairs (formed concrete repair 5 in.).
Other substructure repairs are excluded from this program unless approved by the Bureau of
Bridges and Structures on an individual basis.
Qualification Criteria. The following criteria must be met to qualify for the B-SMART Program:
A delamination survey of the deck is not required. A visual top and bottom of deck survey is
adequate for documentation. This survey will be satisfied by a PONTIS inspection.
There are no restrictions on these projects regarding roadway type, age of structure or ADT. They
also need not be used in conjunction with Pavement SMART projects.
B-SMART projects will not be approved for funding beyond the first three years in the Departments
Multiyear Program due to the potential for structural condition state changes. The deck survey
must be taken within one year of the proposed letting date. Structures that fail the above
restrictions will not be approved and will revert to standard procedures for deck repair.
Projects that qualify for the B-SMART Program should be submitted for review and approval using
the Abbreviated Bridge Condition Report Format in this document.
19
significant section loss of a member/reinforcement that will affect the load capacity.
general deteriorated condition of an element that indicates possible reduced capacity.
damaged areas due to impacts or other causes that may affect the load capacity.
If elements of the superstructure are thought to have sufficient damage to significantly affect the
load capacity, a capacity check must be made. The design loading requirements are described in
the next sub-section.
Load Capacity.
The load capacity of the superstructure must be evaluated for conformance to Department policy.
Review the superstructure elements live load capacity based on the design specifications used to
design the structure:
ASD and LFD Designs (HS-20 live load). Evaluate these structures based on the proposed scope
of work as described below.
Bridge Rehabilitation, Bridge Deck Repair & Bridge to Remain in Place Projects: If the
superstructure has a live load inventory rating equal to or greater than HS-20 for the proposed
loading condition, no further investigation is required. If this live load rating is less than HS-20,
the main load carrying elements of the superstructure must be investigated to determine if they
are capable of carrying the live load specified in the BDE Manuals 3R Guidelines (Chapters 49 &
50) for the type of roadway classification being considered. These loads are found under the 3R
sections labeled Criteria for Bridges to Remain in Place. If the member does not meet these
criteria in its current condition it must be strengthened or replaced to meet the required capacity.
Bridge Reconstruction Projects: All superstructure replacement projects will be designed using
HL-93 live load and the LRFD Bridge Design Specifications.
LRFD Designs (HL-93 live load): If the superstructure has a live load inventory rating factor for the
proposed loading condition equal to or greater than 1.0 using LRFR, no further investigation is
required. If the live load rating factor is less than 1.0, the main load carrying elements of the
superstructure must be investigated to determine if they are capable of carrying the design loading
without exceeding 65% of the strength of any member. If the member does not meet these criteria
in its current condition it must be strengthened or replaced to meet the required capacity.
20
Note: LRFR rating factors may be obtained from the BB&S if necessary.
If additional dead load is to be added to the superstructure, the capacity of the main load carrying
elements must be reviewed for compliance with the live load criteria discussed in the previous
paragraphs for either case described.
In some cases the use of a reduced FWS allowance may be considered to permit reuse of existing
structure elements. Contact the BB&S for approval when considering this approach.
Coring of Reinforced Concrete Superstructures.
Projects involving the staged removal of reinforced concrete slab bridges and box culverts will have
top slab concrete cores taken to verify the condition of the concrete for use under stage traffic. Use
the following guidance in taking cores:
A Bridge Core Data Form (IDOT BB&S Form: BBS 2720) will be used to record the results and
provide a detailed description and photograph of the core. If the cores indicate the concrete is in an
advanced state of deterioration (i.e. heavily fragmented or returned to an aggregate like material)
immediately notify the Bureau of Bridges and Structures for evaluation and possible load posting.
The coring results will be used in the analysis and scope of work selection process as well as
included in Attachment M of the Bridge Condition Report.
Bearings.
The general condition and type of bearings present on the structure must be reviewed. All bearings
should be repaired/reset or replaced that show evidence of excessive deterioration, damage or
tilting. Additional guidance on bearings is as follows:
At Transverse Expansion Joint Locations.
On Bridge Reconstruction and Bridge Rehabilitation (deck replacement and super/substructure
widening) projects all steel high profile rocker and roller bearings will be replaced with elastomeric
bearings, if practical.
On Bridge Rehabilitation (other than deck replacement and super/substructure widening) or Bridge
Deck Repair projects these bearings should be replaced with elastomeric bearings if in poor
condition or if desired by the District and funding is available.
At Non-Transverse Joint Locations. If the bearings are in good overall condition they may be
reused, if practical.
In Structure Widening Cases Where Additional Beam Lines Are Required. If additional beam lines
are added to a structure the expansion bearings must be matched in type transversely across the
structure.
21
Special Considerations.
The superstructure should be reviewed and analyzed for the following details if applicable.
Steel Beams & Girders: Existing steel beams or girders scheduled for a new deck shall be made
composite their full length when practical regardless if composite action is necessary for strength.
Fatigue Evaluation of Existing Welded Cover-plates: On Bridge Reconstruction and Bridge
Rehabilitation (deck replacement and super/substructure widening) projects the remaining fatigue
life of all structural steel girders with Category E or E details must be evaluated in accordance with
Section [Link] Retrofit of Existing Welded Coverplates of the IDOT BB&S Bridge Manual. The
results of this analysis will be documented in the BCR. Reports produced by Consultant firms will
provide this analysis as part of the report preparation process. Reports produced by District
personnel will have this analysis completed by the BB&S Staff upon request.
Pin & Hanger Connections: On Bridge Reconstruction and Bridge Rehabilitation (deck replacement
and super/substructure widening) projects steel girders with pin and hanger connections should be
evaluated for elimination of this detail by making them continuous whenever practical and
economical. Bridge condition reports produced by Consultant firms will provide this analysis as part
of the report preparation process. Reports produced by District personnel will have this analysis
completed by the BB&S Staff upon request.
Paint System: The condition of the paint system should be assessed and the cost to repaint the
structure calculated if applicable. See the All Bridge Designers Memorandum 02.1 for details.
Superstructure Widening.
On superstructures being considered for widening, the following guidelines should be reviewed
when determining the scope of work:
The widened section should have similar structural characteristics to the existing section.
Evaluate the condition of the existing deck if it is being considered for reuse in the widening. It
is desirable for the existing and new sections of the deck to have the potential for similar
maintenance and life expectancies. The higher the percentage the new deck is of the total deck
area the more important this correlation becomes. Existing decks with significantly different
maintenance or life expectancies than the proposed addition should be considered for
replacement. If the existing deck is reused the joint between the new and existing deck sections
should be placed within the center half of the slab span when practical.
Evaluate any effects the widening will have on vertical clearances beneath the structure.
If the superstructure is found not to meet minimum requirements discussed in this section then
further investigation is required. Girders not meeting minimum strength requirements should be
strengthened or replaced. Items in the special considerations category should be assessed and
any work required identified. Changes to the bearings required to meet policy should also be noted.
SUBSTRUCTURE EVALUATION
General.
This evaluation usually consists of a review of the substructure condition, load capacity and a scour
assessment as applicable.
Condition.
The main load carrying elements of the substructure are evaluated to determine if they are
structurally sound and in sufficient condition to remain in place or require repair or replacement.
Areas that require repair are identified and an estimated length or area requiring repair is made.
These main load carrying elements often consist of substructure caps, columns, stems, footings
and piling. Some areas of importance to consider during this review are:
significant section loss or damage to a member that affects the load capacity.
general deteriorated condition of an element that indicates possible reduced capacity.
If elements of the substructure are thought to be have sufficient damage to significantly affect the
load capacity then a capacity check must be made.
Load Capacity.
Changes to substructure and foundation loading condition will be evaluated as follows:
Abbreviated Analysis:
The load capacity of existing substructure and foundation elements may be assumed to be
adequate for reuse without a detailed structural analysis when:
The substructure elements are in good condition (NBIS Condition Rating of 6 or greater) and
show no significant structural distress under existing live load.
The proposed service dead load is not greater than 115% of the original design service dead
load at the top of the substructure element (top of bearing seat).
There is no significant reconfiguration of loads (i.e. changes to bearing locations or
substructure fixities).
23
24
Cs
Cb
He
Pe
Pl
Sm
Existing Pile
Capacity
Source
Low Capacity
Formula Bias
Hammer
Efficiency
Correction
Pile Effect on
Hammer
Efficiency
Pile Length
Formula
Conservatism
Borings
Indicate Main
Mode of
Support
Example: Existing plans pile data indicate timber piles, estimated to be 62 ft. long, with a design
capacity of 24 tons. The pile driving records indicate that a MKT 11B3, a Closed End Air-Steam
hammer, was used and on average the piles were driven 57 ft. with a final bearing of 30 tons.
The allowable resistance available Ra, can be determined by the following formula: Ra = Existing
Capacity x (1+Cs+Cb+He+Pe+Pl+Sm). The Exist Cap = 30 tons from driving records, Cs = 0.0 since
we have driving records, Cb = 0.06 since the Exist Cap is below 40 tons, He = 0.08 due to the use of
an Air-Steam Hammer, Pe = 0.0 because timber piles were used, Pl = 0.0 based on a driven length <
60 ft., and Sm = 0.0 since no borings are available. The factored resistance available RF is
determined by multiplying by the factor of safety which is assumed to be 3.0 and the resistance factor
which is taken as 0.5.
Ra = 30 tons x (1+0+0.06+0.08+0+0+0) = 30 tons x 1.14 = 34.2 tons, 14% < 50% so OK.
RF = Ra x (Safety Factor) x (Resistance Factor) = 34.2 x 3 x 0.5 x 2 kips/ton = 102.6 kips
The new factored strength group pile loading must not exceed the factored resistance available of
102.6 kips.
Spread Footing Foundations: Existing spread footings often have greater geotechnical capacity
than indicated on the original plans when various factors are present. The table shown below and
the example provide a method to calculate the potential increased capacity for existing structures.
Settlement need not be checked when using this table.
25
Ra
No Borings
Available
(2 ksf)
Mixed
soils with
N >15
(4 ksf)
Clay soils
with Qu > 3.0
(6 ksf)
Very Dense
Granular
with N > 50
(8 ksf)
Hard Clay
Till with
Qu > 4.5
(10 ksf)
Sandstone
or Shale
(15 ksf)
Limestone
or
Dolomite
(30 ksf)
Example: Obtain the footing plan dimensions and base elevation from the existing plans. Calculate
the existing and proposed footing loading to obtain the maximum applied service bearing pressure
(Qmax) and resultant eccentricity. If the proposed Qmax is more than 50% above the existing
loading, the footing cannot be reused. If founded on soil, calculate the proposed equivalent uniform
bearing pressure (QEUBP). Using new or existing boring data, locate the footing base elevation and
evaluate the soils/rock within a depth of 1.5 times the footing width to determine the allowable
service bearing capacity Ra from the above table.
The proposed applied bearing pressure (Qmax for rock or QEUBP for soil) must be less than the
allowable service bearing capacity Ra and the proposed resultant eccentricity must be within the
middle third (for soil) or middle half (for rock) of the footing for the existing foundation to be
considered adequate.
For both piles and spread footings lateral loads to piles or sliding need not be checked unless the
structure is in seismic categories C or D (AASHTO LFD) or seismic zones 3 or 4 (AASHTO LRFD).
The allowable resistance available may be converted to factored resistance by multiplying by 1.5
(3.0 Factor of Safety times 0.5 resistance factor). The foundation element may be reused providing
the following conditions exist:
1. The Illinois Modified Group-1 load combination is below the actual calculated resistance
available from the existing foundation as described above.
2. The hydraulic analysis and soil conditions indicate no substantial scour.
3. Deterioration has not compromised the structural integrity of the piles or footing.
4. Inspections indicate no past foundation settlement.
5. There is sufficient redundancy (more than 4 piles per foundation element).
6. The increase in pile capacity or service bearing loading does not exceed 50%.
In-kind substructure widening with additional foundation capacity being added typically does not
require a detailed analysis at this time except as described above. However, when the original
structural design concept is changed, such as replacing a series of simple spans with a continuous
span structure, changing superstructure to substructure fixity or significant changes in bearing
location and elevation are made the capacity of the substructure unit must be evaluated. In these
cases the Abbreviated Analysis does not apply and a Detailed Analysis will be required.
In some cases the use of a reduced FWS allowance may be considered to permit reuse of existing
structure elements. Contact the BB&S for approval when considering this approach.
Semi-Integral Abutments.
Existing structures with transverse expansion joints at the abutments that are being considered for
Bridge Reconstruction or Bridge Rehabilitation (deck replacement and super/substructure widening)
should be considered for modification to semi-integral abutments if applicable. The limitations for
use of this type of abutment are found in Section [Link].1 of the IDOT Bridge Manual. The
26
Scour Review.
A review of the substructure for scour related problems should be made on structures over streams.
Areas of particular concern to identify are exposed footings and piling. The potential for future
damage due to this problem should also be assessed.
If scour damage is identified or thought to be likely then repairs/countermeasures should be
identified for bridges not being replaced.
Substructure Widening.
On substructures being considered for widening the following general guidelines should be
reviewed when determining the scope of work:
For bridge widening projects, the pier cap may be widened and cantilevered off the existing stem
where structurally practical and sufficient foundation capacity exists.
Piers with an expansion fixity condition to the superstructure that require additional foundation
capacity may often be widened with a single row of piles in a pile bent. Situations that may
preclude this treatment are locations were the loads to be carried are large and require multiple
rows of piles to support them or grade separation structures were this approach may not be
aesthetically desirable. In these situations widening the pier in kind may be necessary.
Piers with a fixed fixity condition to the superstructure that require additional foundation capacity
may potentially be widened by either of the two methods mentioned above. However, a check of
the pier capacity for the revised longitudinal and transverse forces applied must also be made in
addition to vertical load capacity review. If insufficient longitudinal or transverse capacity is found
then widening in kind may be necessary.
When selecting a method of substructure widening consideration must be given to maintaining the
structural integrity of those elements to be reused especially in regard to the method of attachment
of the new section of substructure to the existing sections.
Substructure Evaluation Assessment.
Once the information for the Substructure Evaluation has been collected, it must be evaluated. If
the substructure meets the capacity requirements for the proposed loading in its current or modified
condition then it satisfies criteria for this evaluation to remain in place.
If the structure is found not to meet requirements discussed in this section then further investigation
may be required. Substructures not meeting minimum strength requirements should be
strengthened, have capacity added, or be replaced.
27
An abbreviated seismic evaluation will be completed for these structures consisting of the following:
1. Substructure Seat Widths will be reviewed and modified if necessary to meet current policy as
outlined in the IDOT Bridge Manual (BM), T3.15.4.2-1.
2. Liquefaction potential will be reviewed using the existing borings. If existing borings are not
available or inadequate contact the BB&S for guidance.
3. Bearings will be reviewed and:
High profile rocker or roller expansion bearings will be replaced with elastomeric bearings if
practical.
High profile fixed bearings will be modified ,if necessary, for a applied lateral force of 20
percent of total dead load as stated in Appendix A-2 (FHWA), and allowable capacity as
stated in the BM, T.3.7.3-1 & 2. Contact the BB&S for fixed bearing retrofit options.
4. Projects in this category require no detailed analysis of the substructure or foundation for seismic
loads unless specifically requested by the BB&S.
29
START
Determine:
Bridge Type
Bridge Importance Category
SPC Category
Project Scope of Work
NO
YES
NO
YES
Seismic
Evaluation
Not Required
Abbreviated
Seismic Evaluation
Required
30
In category SPC-B or C
Scope of Work is:
o Bridge Reconstruction for all
importance categories
o Bridge Rehabilitation (Substructure
widening) for all importance categories
YES
Detailed
Seismic Evaluation
Required
MISCELLANEOUS CHECKS
Deck Drains.
On bridges were the existing deck is proposed to remain in place, a review of the deck drains
should be made if applicable. Many older decks have drains that do not meet current policy and
cause damage to the bridge. The following general criteria should be used when reviewing free fall
deck drains to remain in place:
Drains located within 10 of substructure units should be plugged if practical.
Decks that contain large numbers of small drains spaced at less than 8 centers should have
every other drain of this type plugged if practical.
Drains to remain in place that do not extend below the low beam elevation of the nearest
beam a minimum of 3 should be extended to a point at least 6 below the low beam.
Existing closed drainage systems should be inspected for clogging and damage. Repairs or
modifications to these systems should be planned as needed.
Waterborne Debris.
Debris buildup at structures over streams can cause a reduction in flow through the structure and
an increased likelihood of scour. Any current or past debris collection problems at the structure
should be noted and a description provided.
Slopewall & Stream Protection.
The slope and stream protection systems on structures and embankments proposed to remain in
place should be reviewed for adequacy. The following general criteria should be used when
reviewing slopewalls & stream protection systems to remain in place:
Slopewall and stream protection systems should be reviewed for damage, deterioration or
undermining. If they are found to have significant damage they should be repaired or
replaced.
When it is determined the slope protection system needs replaced it is preferred to use riprap
at stream crossings and concrete slopewalls at grade separation structures. If the stream
velocity or site conditions preclude the use of riprap then rock blankets, slope mattress or
other protective system may be considered.
The slope protection system should be checked for conformance to the width dimension
policies past the edge of deck located in the Bridge Manual Section [Link].3.
Structures falling in the scope of work categories of Bridge to Remain in Place, Bridge Deck
Repair and Bridge Rehabilitation (other than deck replacement and super/substructure
31
widening) may be considered for reuse if found to be in good condition with only the need for
minor repairs and after a structural evaluation has been made.
Structures requiring additions in load, Bridge Reconstruction or Bridge Rehabilitation (deck
replacement and super/substructure widening) should in general not be considered for reuse.
Lane widths of 14 or greater are optimal as they do not require a wide load detour.
Lane widths of 12 or greater are desirable from a safety aspect.
A lane width of 10 is generally considered the minimum allowable.
Superstructure Considerations.
The following superstructure considerations should be reviewed for stage construction projects:
Substructure Considerations.
The following substructure considerations should be reviewed for stage construction projects:
Overall stability of the remaining section of a substructure unit supporting traffic must be
reviewed if a significant structural element of the unit is removed.
One or two column piers may not be compatible with stage construction on replacement
projects. A structural evaluation will have to be made to determine staging feasibility on a
case by case basis.
32
Profile Changes.
The considerations listed below should be reviewed for stage construction projects involving
significant profile changes. Projects with large profile changes should not be stage constructed
whenever practical.
The feasibility/cost of retaining the soil due to the proposed cut/fill situation must be
reviewed.
The stability of substructure units near proposed cut/fill situations must be investigated.
ECONOMIC EVALUATION
General.
Once the evaluations of the various geometric, hydraulic, physical and structural aspects of the
structure are finished, an economic evaluation should be completed. The economic evaluation will
estimate the initial construction cost for the various scope of work alternatives being considered for the
project. The estimates will reflect the findings of the other evaluations completed regarding need for
repair, rehabilitation and reconstruction of any structure elements being considered for reuse. To be
considered for reuse an element must be in good or economically repairable condition with adequate
structural capacity. The element must also have sufficient remaining service life after the project is
complete to last as long as the other major elements of the structure without requiring an unreasonable
amount of maintenance. Aesthetic appearance may also be considered when warranted.
In the absence of other overriding factors, a rule of thumb to determine when existing structure
elements are economical for reuse is as shown below:
Cast in Place Concrete Decks:
Major Components:
33
The first three items on this list have already been covered in this section during the discussion of
the following evaluations:
The remaining factor, Exterior Constraints, consists of issues which impact a project but are not
directly related to the physical condition, geometrics/hydraulics and repair/replacement cost
relationships. Typical exterior constraints are:
When Exterior Constraints influence the scope of work decision on a structure they must be
thoroughly analyzed and well documented in the Bridge Condition Report.
Once all the categories of evaluation have been completed, the results are reviewed in whole and
the most appropriate scope of work is selected for the structure.
34
CRITERIA:
Bridge deck overlays to be completed as B-SMART projects (1).
Bridge Rehabilitation
Notes:
(1) All deck overlay projects not meeting this criterion except Day Labor Force and Contract
Maintenance Projects require the submittal of a full BCR. See Section V of this document for the
appropriate format. Day Labor Force and Contract Maintenance deck overlay projects do not
require the submittal of a BCR or Abbreviated BCR. However, a memorandum describing the
proposed work type, surface removal thickness, overlay type and overlay thickness must be sent to
the BB&S for approval prior to completing the work.
(2) When the minor repairs listed above as part of Bridge Rehabilitation are to be completed by
Day Labor forces, District Maintenance forces or as part of Contract Maintenance projects this work
does not require submittal of a BCR or Abbreviated BCR to approve the work.
35
36
REPORT PREPARATION.
Bridge Condition Reports must be detailed and thorough. Many scope of work decisions require
some structural analysis. If the report is being prepared by a Consultant Firm, then the Consultant
is responsible for completing this analysis. If the report is being prepared by the District then the
BB&S should be contacted to complete the required structural analysis. All cost estimates, surveys
and attachments must be completed by those responsible for preparing the report.
Bridge condition reports for deck repair projects should not be submitted for approval with
scheduled construction dates greater than two calendar years from the date submitted.
REPORT FORMAT.
The information required in the Bridge Condition Report has been provided in an example report
format. The format describes in detail the information required to complete high quality reports that
can be quickly processed and approved. Each report prepared should follow the format provided.
Incomplete reports will be returned to the District for correction and resubmittal.
See Appendix B, of this document for the Bridge Condition Report Format.
37
Beams: Provide a brief description of the condition of the beams. Include the locations and extent
of any significant deterioration/damage which may affect the structural capacity of the bridge.
Substructure: Provide a brief description of the condition of the substructure. Include the
area/length that is estimated currently requires repairs such as formed concrete repair or crack
sealing. Describe any scour problems identified.
(Other): Provide a description of the condition of any other area being proposed for work. Include
the locations and extent of any significant deterioration/damage.
ATTACHMENTS:
Attachment A. IDOT Master Structure Report
Provide a copy of the Master Structure Report.
39
REGION:
DISTRICT:
ROUTE:
COUNTY:
JOB NUMBER:
STRUCTURE NUMBER:
LOCATION:
(Comment: This cover sheet provides general information necessary to process the report.
Provide the information indicated.)
PREPERED BY:
DATE INSPECTED:
PROPOSED LETTING DATE:
40
Table of Contents
Item:
Page:
41
I.
Structure Number:
County:
Route Carried:
Feature Crossed:
Section:
Station:
Roadway Classification:
Design/Posted Speed:
ADT (current/design):
ADTT (current/design):
DHV:
Inventory Rating (HS or HL):
Operating Rating (HS or HL):
Sufficiency Rating:
II.
42
Substructure:
Abutments: Provide a description of the condition of the abutments, wingwalls and backwalls.
Include the area/length that is estimated currently requires repairs such as formed concrete repair
or crack sealing. If the abutments are thought to have moved or rotated this should be described
and the distance from the face of the backwall to the top and bottom of the two fascia beam ends
should be measured and provided. Describe any scour problems identified.
Piers: Provide a description of the condition of the piers. Include the area/length that is estimated
currently requires repairs such as formed concrete repair or crack sealing. If the piers are thought
to have moved or rotated this should be described. Describe any scour problems identified.
Scour/Slope Protection: Provide a description of the type and condition of the scour/slope
protection. Include any estimated areas and locations that require repair.
43
Picture taken looking up-station through the structure from approximately 30 feet downstation of bridge.
45
Picture taken looking down-station through the structure from approximately 30 feet upstation of bridge.
Picture taken from the structure looking upstream (route) showing the existing ground
features.
Picture taken from the structure looking downstream (route) showing the existing
ground features.
Picture taken through the structure looking upstream (route) showing the bridge.
Picture taken through the structure looking downstream (route) showing the bridge.
Picture(s) of the corners of the structure showing the condition of the wingwalls and
embankment.
Picture(s) of the expansion joints in the superstructure.
Picture(s) of the type and condition of the bridge rail.
Picture(s) depicting the general condition of the underside of each span of the
superstructure.
Picture(s) depicting areas of deterioration/damage on the underside of the
superstructure.
Pictures of each abutment depicting its type and condition to include the bearings and
backwall.
Pictures of each pier depicting its type and condition.
Picture(s) showing any evidence of scour or streambed movement if applicable.
Attachment I.
Provide a summary of the hydraulic analysis listing any concerns/issues and a copy of the
approved waterway information table if available along with the streambed elevation at the
structure.
Attachment J. Proposed Plan & Profile (if available)
Provide a copy of the proposed plan and profile sheet if available.
Attachment K. Existing and Proposed Roadway Cross Sections (if available)
Provide a copy of the existing and proposed (if available) roadway cross section adjacent to
the structure.
Attachment L. Abbreviated Existing Plans
Provide an 11x17 copy of the General Plan & Elevation and Superstructure Cross Section
Sheets only (provide any as built plan sheets if applicable).
Attachment M. Additional Test Results (if applicable)
Provide a copy of any additional testing results taken (if applicable), i.e. Slab Coring
Reports and structure borings.
46
Test 2 (AASHTO T 24) Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
The primary use of deck coring is to determine the depth of delaminations, and to differentiate
between delaminations and debonding when an overlay is present. This information is helpful when
conducting delamination surveys according to Methods 1 and 3. The deck core also provides a
visual inspection of the quality of the deck. The number of cores is based on engineering judgment.
47
Test 6 (Method A) (AASHTO T 260) Sampling and Testing for Chloride Ion in Concrete and
Concrete Raw Materials
This test determines total chloride content of concrete. This includes chloride content that is soluble
and will contribute to corrosion, plus chloride content that is chemically bound to the concrete and
may not contribute to corrosion. Chemically bound chlorides are found in the aggregate, and this is
called benign chloride content. If benign chlorides exist in the aggregate, the corrosion threshold
is 0.8 kg/cu m (1.4 lb./cu yd) plus the amount of benign chloride content in the aggregate. In Illinois,
chloride content in bridge decks will generally exceed the corrosion threshold limit. For a
meaningful evaluation, the greater of 10 locations per bridge deck or 10 locations per 465 m2
(5,000 sq. ft.) is recommended. The usefulness of this test comes from the comparison to tests
performed on other bridge decks. The test results and the subsequent performance of bridge deck
repairs can provide some guidance on the most effective rehabilitation method. Rehabilitation
methods may include overlays, sealers, corrosion inhibitors, and cathodic protection. In addition,
the chloride test results obtained from several bridge decks will provide information for estimating
repair quantities on future bridge deck projects. The disadvantage of the test is the fewer number
of test results which can be obtained in a day, as compared to Test 5. However, the presence of
epoxy-coated or galvanized reinforcement does not restrict the use of the test as compared to Test
5.
Test 6 (Method B) (AASHTO T 332) Determining Chloride Ions in Concrete and Concrete
Materials by Specific Ion Probe
AASHTO T 332 is another test for determining total chloride content of concrete. The test results
correlate well with the AASHTO T 260 test method. The advantage of the AASHTO T 332 test over
AASHTO T 260 is that more tests can be performed in a day. In addition, the AASHTO T 332
testing can be conducted in the field.
48
49