PAYMENT
PROCEDURE
MANUAL
5 February 2014 Revision 2.2
The Payment Procedures manual is intended to assist the contractors, Consultants, PMCs, & MCs to
apply for payments.
Document Title
Document Control Information
Payment Procedures Manual
Version
2.2
Date Created
5 February 2014
Author
Multiple Authors
Reviewed by
Mahmoud El-Zaher
Procedure written
by
Signed off by
Waleed Abou-Khadra (PB)
Procedures Development
Workshop Moderator
Sign off Date
Moataz Yousif (PWA)
Location
Revision
0.1
0.2
0.3
1.0
2.0
Payment Process Working
Group
EBSD DMS Document management System
Document Revisions Information
Description/Amendment
By
First Draft
Second Draft
Amendments Recommended by Martin Truman
Final Version
The Checklists required by EBSD have been simplified.
Some of the supporting documents by the EBSD will not
be required by the Finance & Administrative Department
2.1
2.2
27 February 2013
Implemented comments by Legal Department
Mahmoud El-Zaher
Multiple Authors
Date
Mahmoud El-Zaher
Mahmoud El-Zaher
Sep 2012
Dec 2012
Feb 2013
Feb 2013
12 Sep 2013
Mahmoud El-Zaher
Suhail Pervez
23 Sep 2013
5 Feb 2014
Document Circulation
For Implementation
For Information
PWA Affairs / Departments
PMCs
Presidents Office
PMCs & MCs
Consultants (Design, Supervision, Secondment)
GEC
Contractors / Suppliers
Revision 2.2
5 February 2014
Page 1 of 181
Revision 2.2
5 February 2014
Page 2 of 181
Revision 2.2
5 February 2014
Page 3 of 181
Revision 2.2
5 February 2014
Page 4 of 181
Revision 2.2
5 February 2014
Page 5 of 181
TABLE OF CONTENTS
Preamble
This procedures manual shall be followed in accordance with the general and particular
conditions of contract for consultants/contractors/supply contracts. In case of any
discrepancy, the terms of the general and particular conditions of each contract shall prevail.
Table of Contents
Table of Contents .................................................................................................................................... 7
SECTION 1 ............................................................................................................................................. 13
DESCRIPTION OF CONTRACTOR PAYMENT PROCESS ........................................................................... 14
1.
DEFINITIONS .............................................................................................................................. 15
1.1
2.
Definitions ............................................................................................................................. 15
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES .................................................. 17
2.1
Subject: ................................................................................................................................. 17
2.2
Purpose: ................................................................................................................................ 17
2.3
Scope: .................................................................................................................................... 17
3.
PROCEDURE .............................................................................................................................. 17
3.1
Application for Payment ....................................................................................................... 17
3.1.1
Consultant Review Process ........................................................................................... 17
3.1.2
The Engineer Review Process ....................................................................................... 18
3.1.3
Engineering Business Support Department (EBSD) Review Process ............................ 19
3.1.4
PWA Representative Department Review Process ....................................................... 19
3.1.5
PWA Finance & Administrative Review Process ........................................................... 19
3.2
Error Corrections and Reverse Process ................................................................................. 19
4.
TRACKING OF PAYMENT ........................................................................................................... 19
5.
COUNTERSIGNATURES AND COUNTER INITIALLING OF DOCUMENTS ..................................... 20
6.
PROCESS MAP FOR CONTRACTOR PAYMENT ............................................................................... 21
7.
PAYMENT CHECKLISTS FOR CONTRACTOR PAYMENT .................................................................. 23
Advance/First RP for Contractor ................................................................................................... 24
Interim RP For Contractor ............................................................................................................. 25
Penultimate RP For Contractor ..................................................................................................... 26
Final RP For Contractor ................................................................................................................. 27
Revision 2.2
5 February 2014
Page 6 of 181
SECTION 2 ............................................................................................................................................. 28
DESCRIPTION OF CONSULTANT (DESIGN & SUPERVISION) PAYMENT PROCESS .................................. 29
1.
DEFINITIONS AND ACRONYMS.................................................................................................. 30
1.1.
2.
Definitions ............................................................................................................................. 30
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES .................................................. 32
2.1
Subject: ................................................................................................................................. 32
2.2
Purpose: ................................................................................................................................ 32
2.3
Scope: .................................................................................................................................... 32
2.4
Parties: .................................................................................................................................. 32
2.5
Application for Payment ....................................................................................................... 33
2.5.1
2.6
The Consultant application for payment shall comprise the following: ....................... 33
Payment Application Review ................................................................................................ 33
2.6.1
The Engineer Review Process ....................................................................................... 33
2.6.2
PWA Representative Review Process ........................................................................... 34
2.6.3
The EBSD Review Process ............................................................................................. 34
2.6.4
Department Manager Review Process ......................................................................... 34
2.6.5
PWA Finance & Administratibe Department Review Process ...................................... 34
2.7
Key Performance Indicator (KPI) Payment Application ........................................................ 34
2.8
Countersignatures and Counter Initialing of Documents ..................................................... 35
2.9
Error Corrections and Reverse Process ................................................................................. 35
3.
PROCEDURE .............................................................................................................................. 35
4.
PROCESS MAP FOR CONSULTANT (DESIGN & SUPERVISION) PAYMENT ..................................... 36
5.
PAYMENT CHECKLISTS FOR CONSULTANT (DESIGN & SUPERVISION) PAYMENT ......................... 38
First RP For Consultant .................................................................................................................. 39
Interim RP for Consultant ............................................................................................................. 40
Final RP for Consultant.................................................................................................................. 41
SECTION 3 ............................................................................................................................................. 42
DESCRIPTION OF CONSULTANT (PMC & SEC) PAYMENT PROCESS ...................................................... 43
1.
DEFINITIONS AND ACRONYMS.................................................................................................. 44
1.1
2.
Definitions ............................................................................................................................. 44
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES .................................................. 46
2.1
Subject: ................................................................................................................................. 46
2.2
Purpose: ................................................................................................................................ 46
2.3
Scope: .................................................................................................................................... 46
Revision 2.2
5 February 2014
Page 7 of 181
2.4
Parties: .................................................................................................................................. 46
2.5
Application for Payment ....................................................................................................... 47
2.5.1
The PMC application for payment shall comprise the following: ................................. 47
2.5.2
Payment Application Summary Sheet .......................................................................... 47
2.5.3
Payment Milestone Support Sheet ............................................................................... 47
2.6
Payment Application Review ................................................................................................ 48
2.6.1
PWA Representative Review Process ........................................................................... 48
2.6.2
The EBSD Review Process ............................................................................................. 48
2.6.3
The Department Manager Approval Process................................................................ 48
2.6.4
PWA Finance & Administrative Department Review Process ....................................... 49
2.7
Key Performance Indicator (KPI) Payment Application ........................................................ 49
2.8
Error Corrections and Reverse Process ................................................................................. 49
3.
PROCEDURE .............................................................................................................................. 49
4.
PROCESS MAP FOR CONSULTANT (PMC & SEC) PAYMENT .......................................................... 50
5.
PAYMENT CHECKLISTS FOR CONSULTANT (PMC & SEC) PAYMENT ............................................. 52
First RP for PMC & Secondment .................................................................................................. 53
Interim RP for PMC & Secondment .............................................................................................. 54
Final RP for PMC & Secondment................................................................................................... 55
SECTION 4 ............................................................................................................................................. 56
DESCRIPTION OF SUPPLIER (WORKORDER & SUPPLY) PAYMENT PROCESS ......................................... 57
DEFINITIONS...................................................................................................................................... 58
1.1
2.
Definitions ............................................................................................................................. 58
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES .................................................. 60
2.1
Subject: ................................................................................................................................. 60
2.2
Purpose: ................................................................................................................................ 60
2.3
Scope: .................................................................................................................................... 60
3.
PROCEDURE .............................................................................................................................. 60
3.1
Application for Payment ....................................................................................................... 60
3.1.1
The Engineer Review Process ....................................................................................... 60
3.1.2
Engineering Business Support Department (EBSD) Review Process ............................ 61
3.1.3
PWA Finance & Administrative Review Process ........................................................... 61
3.2
Error Corrections and Reverse Process ................................................................................. 61
4.
TRACKING OF PAYMENT ........................................................................................................... 61
5.
COUNTERSIGNATURES AND COUNTER INITIALLING OF DOCUMENTS ..................................... 61
Revision 2.2
5 February 2014
Page 8 of 181
6.
PROCESS MAP FOR SUPPLIER PAYMENT ...................................................................................... 62
7.
PAYMENT CHECKLISTS FOR SUPPLIER........................................................................................... 64
RP for Work Order & Supply ......................................................................................................... 65
GUIDELINES ....................................................................................................................................... 66
1.
PAYMENTS FOR CONTRACT ITEMS - REMEASUREBALE ............................................................ 67
1.
VALUATION OF WORKS - REMEASUREMENT ITEMS................................................................. 68
1.0
Purpose of the Report ........................................................................................................... 68
2.0
Documents required ............................................................................................................. 68
3.0
Payment format .................................................................................................................... 68
2.
PAYMENTS FOR CONTRACT ITEMS LUMPSUM ...................................................................... 74
2.
VALUATION OF WORKS LUMP SUM ITEMS ........................................................................... 75
2.1 Purpose of this Procedure .......................................................................................................... 75
3.
2.2
Provisional Sums / Contingencies ......................................................................................... 75
2.3
Prime Cost Items ................................................................................................................... 75
2.4
Payment to Nominated Sub-Contractors (NSC) .................................................................... 75
2.5
Payment for Variation Works ............................................................................................... 76
2.6
Materials on /off Site ............................................................................................................ 76
PAYMENT & MEASUREMENT FOR DRAINAGE CONTRACTS ......................................................... 78
3.1
Introduction .......................................................................................................................... 79
3.2
Purpose ................................................................................................................................. 79
3.3
Guidance Measurement/Calculation Sheets ........................................................................ 79
4.
PAYMENT AND MEASUREMENT FOR ROAD CONTRACTS............................................................. 85
5.
PAYMENTS FOR LUMP SUM CONTRACT ITEMS IN BUILDING PROJECTS ...................................... 88
6.
7.
8.
5.1
Purpose of the Report ........................................................................................................... 89
5.2
Procedure for Payment Recommendations.......................................................................... 89
PAYMENT FOR CONSULTANT DEDUCTED FROM THE CONTRACTOR ........................................... 99
6.1
Subject: ............................................................................................................................... 100
6.2
Method of Payment: ........................................................................................................... 100
PAYMENT FOR CONTRACTOR DEDUCTED FROM THE CONSULTANT ......................................... 101
7.1
Subject: ............................................................................................................................... 102
7.2
Method of Payment: ........................................................................................................... 102
DESCRIPTION OF RECOVERY (RE-PAYMENT) THE ADVANCE PAYMENT ..................................... 103
8.1
Amount of Advance Payment: ............................................................................................ 104
8.2
Recovery (Re-payment) the Advance Payment: ................................................................. 104
Revision 2.2
5 February 2014
Page 9 of 181
9.
INCOME TAX REQUIREMENTS .................................................................................................... 105
APPENDICES ........................................................................................................................................ 107
APPENDIX A
TEMPLATES / FORMS APPLIED TO ALL PAYEES ...................................................... 108
Appendix A1 Transmittal Form for RP Tracking ....................................................................... 109
Appendix A2
RP Contractors & Consultants ........................................................................... 111
Appendix A3
RP PMC & GEC ................................................................................................... 114
Appendix A4
Covering Letter to Finance & Administrative Dept............................................ 117
Appendix A5
Bank Account Details ......................................................................................... 119
Appendix A6
Letter-Invoice Details......................................................................................... 121
Appendix A7 Daily Attendance Record .................................................................................... 123
Appendix A8 Monthly Attendance Record .............................................................................. 125
Appendix A9 Completion Certificate PSA ................................................................................ 127
Appendix A10 Maintenance Certificate ................................................................................... 129
Appendix A11 Statement of Final Account .............................................................................. 131
Appendix A12 Performance Certificate ................................................................................... 133
Appendix A13 Taking-over Certificate ..................................................................................... 135
APPENDICES B
TEMPLATES / FORMS APPLIED TO CONTRACTORS ............................................ 137
Appendix B1
Summary for Value of Work .............................................................................. 138
Appendix B2
Breakdown for Value of Work ........................................................................... 140
Appendix B3
Breakdown for Preliminary Items ...................................................................... 142
Appendix B4
Previous Payment Certificates ........................................................................... 144
Appendix B5
Summary of Contract Variation Orders ............................................................. 146
Appendix B6
Retention Summary ........................................................................................... 148
Appendix B7
Advance Payment Summary .............................................................................. 150
Appendix B8
Materials on Site Summary................................................................................ 152
Appendix B9
Summary of Penalties ........................................................................................ 154
Appendix B10 Summary of Penalties Under Adjustments ...................................................... 156
Appendix B11 Completion Certificate Construction ................................................................ 158
APPENDICES C
TEMPLATES / FORMS APPLIED TO PMC & SECONDMENT .................................. 160
Appendix C1 Authorization to Mobilize ................................................................................... 161
Appendix C2
Calculations for Public Holidays ......................................................................... 163
APPENDICES D
TEMPLATES / FORMS APPLIED TO WORK ORDER & SUPPLY .............................. 165
Appendix D1
Completion Certificate WO ............................................................................... 166
APPENDICES E
Revision 2.2
FINANCE & AMINISTRATION DEPARTMENT CHECKLIST ..................................... 168
5 February 2014
Page 10 of 181
Appendix E .................................................................................................................................. 169
Advance RP PMC/Secondment Check List .................................................................................. 170
First RP PMC/Secondment Check List ......................................................................................... 171
Interim RP PMC/Secondment Check List .................................................................................... 172
Final RP PMC/Secondment Check List ........................................................................................ 173
Advance RP Consultant Checklist ................................................................................................ 174
First RP Consultant Checklist....................................................................................................... 175
Interim RP Consultant Check List ................................................................................................ 176
Final RP Consultant Check List .................................................................................................... 177
Advance RP Contractor Check List .............................................................................................. 178
First RP Contractor Check List ..................................................................................................... 179
Interim RP Contractor Check List ................................................................................................ 180
Pre-ultimate RP Contractor Check List ........................................................................................ 181
Final RP Contractor Check List .................................................................................................... 182
Revision 2.2
5 February 2014
Page 11 of 181
PUBLIC WORKS AUTHORITY
SECTION 1
PAYMENT PROCEDURE FOR
CONTRACTOR
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 12 of 181
PUBLIC WORKS AUTHORITY
DESCRIPTION OF CONTRACTOR
PAYMENT PROCESS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 13 of 181
DESCRIPTION OF
CONTRACTOR PAYMENT PROCESS
1. DEFINITIONS
1.1 Definitions
For the purpose of this document, the following definitions shall be used:
PWA Representative shall mean the delegated representative by the Public Works Authority
(PWA). The representative will vary for each programme as per the blow table.
The Engineer shall have the same meaning as provided in the General Conditions of. The
Engineer will vary as delegated for each programme as per the below table.
The Design/Supervision Consultant hereafter called the Consultant. The Consultant will
vary for each programme as per the below table.
Authority shall mean the Public Works Authority (Ashghal) of the state of Qatar.
Engineering Business Support Department shall mean that department within the Authority
so titled.
Department of General Financial Affairs of the Ministry of Finance shall have the same
definition as provided in the Agreement General Conditions of Engagement.
Electronic System shall mean the software which will be used for each programme, as
agreed with the Authority, to manage and track the Payment Applications.
Period End Date shall mean the last working day of the calendar month for which the
Contractor is applying to.
Revision 2.2
5 February 2014
Page 14 of 181
Item
Programme
Programme Management
Consultant (PMC) /
Management Contractor
PWA Representative
The Engineer
The Consultant
PMC
General Engineering Consultant
(GEC)
Local Roads & Drainage
Parsons Brinckerhoff
Manager of Roads Projects
Department and/or
delegated Area Engineer
Expressway
KBR
Manager of Expressway
Department
PMC
Supervision Consultant (SC)
Building Projects
Mace/Ec_Harris
Director of Building Affairs
PWA Representative/
PMC
Design Construction Supervision
Consultant (DCSC)
IDRIS
CH2MHill
Director of Infrastructure
Affairs
PMC
Supervision Consultant (SC)
Highways Asset
Management
Amey
Director of Assets Affairs
Drainage Asset
Management
MWH
Director of Assets Affairs
Al Sharq Crossing
Fluor
B. Yacob Al Kazem
PWA Representative
PWA Representative
PMC
The Consultant
The Consultant
General Engineering Consultant
(GEC)
Table 1: Parties Involved in the Process
Revision 2.2
5 February 2014
Page 15 of 181
2. SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES
2.1.
Subject:
The subject matter of this procedure is the methodology in accordance with which the
Contractors applications for payment shall be administered by the parties.
2.2.
Purpose:
To provide a specific, detailed and transparent process to facilitate timely certification and
authorisation of the Contractors applications for payment.
2.3.
Scope:
This procedure shall be applicable to all Contractors applications for payment.
2.4.
Parties:
The parties required to administer this procedure are:
A. The Contractor: Delegated representative
B. The Engineer: Delegated representative;
C. Authority:
a) Engineering Business Support Department (EBSD) representative;
b) Finance & Administrative Department representative with delegated.
The Parties shall have, and hold, full delegated powers from their respective departments to
review and endorse the PMC Payment Applications.
The Authority (being Finance & Administrative and Engineering Business Support
Departments) and the Engineer shall accept in full without recourse to further and / or additional
review the endorsements of the Payment Application carried out on their behalf by their
delegated representatives.
3.
PROCEDURE
Payments shall be administered by 11 steps process as illustrated in 1.2. Process Map for
Contractor Payment
3.1
Application for Payment
The Contractor shall submit the application for payment in compliance with the Contract. The
Contractor shall issue application for draft payment by the end of the third week of each month.
The cut-off date of each Payment Application shall be the last working day of the third week of
each calendar month. This Pencil Copy review will be prior to the preparation and submission
of the formal Payment Application by the Contractor. The Consultant and the Contractor shall
review the current project status and Payment Application and agree on the proper amounts
due for payment to the Contractor in accordance with the Contract document requirements.
The Contractor shall submit a hardcopy as well as a softcopy through the Electronic System. A
copy of the Contractors submission shall be uploaded into the Electronic System.
The Contractor shall submit the Formal Payment Application to the Consultant within the first
week of each calendar month.
The date of receipt by the Engineer is the date from which the payment due date is calculated.
3.1.1. Consultant Review Process
After the Period End Date and within the first week thereafter, the Contractor shall submit their
formal payment application to the Consultant. The Contractor shall submit their payment
Revision 2.2
5 February 2014
Page 16 of 181
application through the Electronic System as well as hardcopy including the PWA standards
checklist as appropriate for each type of payment.
Upon receipt of the Contractors application, the Consultant shall within three (3) working
days review the Contractors application against the agreed pencil copy uploaded into the
Electronic System. The Consultant shall raise and sign the Payment Certificate as appropriate
for each type of Payment Application (i.e. First, Advance, Interim or Final).
The Consultant shall forward to the Engineer the Payment Document through the Electronic
System and hardcopy including the following as a minimum and also any further requirements
as noted in the PWA Payment Control Check list.
Copy of Contractors Commercial Registration;
Copy of Contractors Municipality Commercial Permit;
Copy of Ministry of Interiors Authorized Personnel Signature and Stamp ID Card;
Original Letters of Bank Account Information;
Copy of Workmen, Plant & Equipment Insurance Policy;
Copy of Contractors All Risk Insurance Policy;
Original Advance Payment Bond;
Copy of Performance Bond;
Copy of Award Letter; and
Copy of Contract Agreement with Bill of Quantities Summary Sheet
The above documents to be checked by the Consultant for validity, expiry dates and are to be
supplied in a clear copy, stamped and signed as true copies. All documents with an expiry date
must have at least two months validity. Updated documents to be promptly submitted to the
Engineer when issued by the Contractor. Documents which have expired or are about to expire
will delay payment.
Note: Consultant to check and advise the Contractor/Engineer that the payment details were
correct if entered by the Contractor into the Electronic System;
For each of the contractual documents, payments should be fully checked by the
Consultant to ensure that the exact drafting is used as per the Contract. Any deviation
will not be accepted by the Authority and the Engineer and any other required
checking.
Note: The Advance Payment shall be repaid through percentage deductions in Payment
Certificates:
Deductions shall commence in the first Payment Certificate (excluding the advance
payment);
Deduction shall be made as defined within the Contract Documents;
3.1.2. The Engineer Review Process
Upon receipt of the Consultant recommendation, the Engineer shall within five (5) working
days review the Consultant recommendation, approve, sign and forward the Contractors
payment certificate to the EBSD for final approval. The Engineer shall forward to the EBSD the
Payment Document through the Electronic System and (2) two hardcopies including the
following as a minimum:
1. Original Contractors Payment Documents stamped by both Consultant and the
Engineer;
Revision 2.2
5 February 2014
Page 17 of 181
2.
Signed and stamped Payment Certificate by both Consultant and the Engineer;
3. Check and validate PWA Standard Checklist submitted by the Contractor and verified
by the Consultant as appropriate for each type of payment; and
4. The Engineer recommendation.
Within the review process, The Engineer shall check and make sure that the Electronic System
entries are correct and up to date.
3.1.3. Engineering Business Support Department (EBSD) Review Process
Upon receipt of the Contractors payment from the Engineer, EBSD shall within three (3)
working days review, sign and forward the Payment Document and the signed Payment
Certificate to the concerned PWA Representative/Area Engineer through the Engineer.
3.1.4. PWA Representative Department Review Process
PWA Representative/Area Engineer shall sign and forward the Payment Certificate and
Payment Document to the Secretary of the Manager of PWA Department. The Payment
Document and Payment Certificate signed by the Manager of PWA Department will be
forwarded to the PWA Finance & Administrative Department for authorisation. The duration of
this process shall not be more than four (4) working days.
The above is applicable to Local Roads & Drainage Programme. For the other programmes the
Contractor Payment documents shall be forwarded directly to the appropriate PWA
Representative as detailed in
3.1.5. PWA Finance & Administrative Review Process
Within three (3) working days from the receipt of signed document, the PWA Finance &
Administrative Department shall authorise and issue the payment to the Ministry of Finance.
3.2
Error Corrections and Reverse Process
In case of any error found during the above review processes, the party who found the error
shall return the payment documents to the concerned party for correction along with the check
list. Once corrected, the Payment Documents shall be processed in the same order of the
above steps. The errors and corrective actions shall be clearly recorded in the payment tracking
sheet in order to be prevented in the future. The date the Engineer received the corrected
application is the date from which the payment due date is calculated.
4.
TRACKING OF PAYMENT
Upon the payment collection, The Contractor shall update the appropriate fields in the
Electronic System and notify the Consultant. By turn the Consultant shall notify the Engineer
and submit an updated payment tracker, which include all the assigned projects.
The Consultant will advise the Engineer when Contractor has received payment and upon
which date actual payment was received.
Revision 2.2
5 February 2014
Page 18 of 181
5.
COUNTERSIGNATURES AND COUNTER INITIALLING OF DOCUMENTS
Countersignature of the Payment Certificate by the Consultant, the Engineer and the Authority
is acceptable for holiday cover or leave of absence subject to the required delegated authority.
Counter initialling of any document by the Consultant, the Engineer and the Authority is
acceptable for holiday cover or leave of absence subject to the required delegated authority.
No alteration or change to the template of the Payment Certificate shall be permitted without
express approval of the Authority with reasons given for any proposed alteration or change.
Revision 2.2
5 February 2014
Page 19 of 181
PUBLIC WORKS AUTHORITY
6. PROCESS MAP FOR
CONTRACTOR PAYMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 20 of 181
Project Type:
PWA-led Project
Title
PMC-led Project
PAYMENT PROCESS
Payment For:
Contract Type:
Consultant
Contractor
Supplier
Design & Supervision
Construction
PWA1/Client2
PMC/MC3
PMC
Secondment
Workorder & Supply
In-house supervision
Operation & Maintinance
Consultant4
Contractor
(Engineers representative)
(Principle)
Other Stakeholders
Request for
Payment
Initiate Payment
Requisition process
- Review and Discuss with
contractor (if needed)
3
-Accept
Yes
GEC submits the Request for
payment
0
Accepted?
0
GEC submits the Request for
payment independently
0
No
EBSD
- Review & Approve
No
PWA rep. (PM)
Review
Review
Accepted?
1
0
Yes
No
PWA PWA Stakeholder might be the
President, Affairs, O&M Department
2
Client: Only applied for the building affairs
3
PMC: Program Management Consultant
MC: Management Contractor
4
The consultant title might be GEC (General
Engineering Consultant), SC (Supervision
Consultant), DCSC (Design Construction
Supervision Consultant
Note: in case of PWA-led projects without
PMC/MC, just skip the PMC/MC related
activities
Accepted?
Yes
days
No. of Working Days
Finance & Adm.Dpt.
Head of
of Section
Head
Section
- Process the payment
- Update the System
Review and Approve the
payment requisition
1
Advance payment
Penultimate Payment
Final payment
Interim Payment
Ministry of Finance
Dpt. Manager
Phase
Approve
Revision 2.2
Document Flow
- Processing the Payment
Calendar Day
5 February 2014
45
Level 2 process
(External Process
Page 21 of 181
PUBLIC WORKS AUTHORITY
7. PAYMENT CHECKLISTS FOR
CONTRACTOR AND TEMPLATES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 22 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
ADVANCE/FIRST RP FOR CONTRACTOR
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Contractor
2.
Original RP stamped by the Consultant*
3.
B.O.Q & Summary sheets Stamped by Consultant & Contractor* Refer to
Appendices B1 to B10
4.
Consultant Original Recommendation Letter*
5.
Copy of the Contract Agreement Refer to Appendix B11
6.
Copy of award Letter, Notice of Agreement or Notice to Proceed.
7.
Copy of Performance Bond or any Extension Refer to Appendix A5
8.
Original Advance Bond or any Extension Refer to Appendix A6
9.
Original Retention Bond or any Extension Refer to Appendix A7
10.
Copy of Valid Commercial Registration
11.
I. D. Copy of the authorized signatory
12.
Bank Account Information Letter Stamped by the Bank Refer to Appendix
A8
13.
Copy of Insurance Certificates
14.
Reason for Delay
15.
Transfer of Fund
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
*not required in case of the in-house supervision.
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 23 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
INTERIM RP FOR CONTRACTOR
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Contractor
2.
Original RP stamped by the Consultant*
3.
B.O.Q & Summary sheets Stamped by Consultant & Contractor*
4.
Consultant Original Recommendation Letter*
5.
Copy of delivery notes & Invoices for materials delivered to the site
6.
Vesting Certificate for materials not yet delivered to site
7.
Measurement Summary Sheets in the case of re-measurement contracts
8.
In case the payment for Sub contractor, Kharama, Consultant etc,
supporting document for this payment must be attached
9.
In case of penalties Detailed breakdown must be attached
10.
Copy of Vo in case of extension or costs
11.
In case of Fluctuations to be added or deducted to payment certificate,
calculation to be attached
12.
Copy of Valid Commercial Registration
13.
Minimum Amount for Interim Payment stated in the Contract
Note:
1. If the amount of the invoice submitted by the contractor is more than the actual amount to
be paid in accordance to the Contract; and the contractor has refused to amend his invoice;
the consultant may proceed with a recommendation for payment to the Contractor based on
the actual value of works completed on site and/or materials revised BOQ & Summary to
be paid as specified in Contract.
2. If the contractor fails to submit a monthly statement, the consultant must proceed with a
recommendation for payment to the contractor based on the actual value of works
completed on site and/or materials to be paid as specified in the Contract.
COMMENTS
*not required in case of the in-house supervision.
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 24 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
PENULTIMATE RP FOR CONTRACTOR
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Contractor
2.
Original RP stamped by the Consultant*
3.
B.O.Q & Summary sheets Stamped by Consultant & Contractor*
4.
Consultant Original Recommendation Letter*
5.
Copy of Valid Commercial Registration
6.
In case the payment for Sub contractor, Kharama, Consultant etc, supporting document
for this payment must be attached
7.
In case of penalties Detailed breakdown must be attached
8.
Schedule of Variations, claims, EOT and day works executed
9.
Schedule of Provisional sums how they have been expended under the Contract as VO.
10.
Measurement Summaries Sheets in case of re-measurement contracts
11.
Original Completion Certificate (PCC) Refer to Appendix B12
12.
Letter of Undertaking - Taking Over Certificate Refer to Appendix A17
13.
Original Municipality Clearance Roads & Drainage Contracts Only
14.
Transmittal sheets related to O & M Manuals inc. warranties & guaranties
15.
In case of Fluctuations to be added or deducted to payment certificate, calculation to be
attached
16.
Release of first half of the Retention Money with Penultimate Payment
Note:
If the Contractor is not a National Company then the half of the retention money payable in
accordance with sub-clause 60(3) Condition of Contract shall only be released against an
equivalent bank guarantee valid until the end of the Period of Maintenance.
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
*not required in case of the in-house supervision.
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 25 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
FINAL RP FOR CONTRACTOR
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Contractor
2.
Original RP stamped by the Consultant*
3.
B.O.Q & Summary sheets Stamped by Consultant & Contractor*
4.
Consultant Original Recommendation Letter*
5.
Copy of Valid Commercial Registration
6.
In case the payment for Sub contractor, Kharama, Consultant etc, supporting
document for this payment must be attached
7.
In case of penalties Detailed breakdown must be attached
8.
Schedule of Variations, claims, EOT and prolongation cost
9.
Schedule of Provisional sums how they have been expended under the Contract as
VO
10.
In case the Bank account changed, the Contractor must submit No Objection Letter
from previous bank
11.
Original Maintenance Certificate Refer to Appendix A14
12.
Original Final Account Statement Refer to Appendix A15
13.
Copy of Valid Income Tax I.D.
14.
Committee Approval Letter (Metrology Specification) Roads Contracts Only
15.
Original Store Clearance
16.
Original DCU Clearance
17.
I. D. Copy of the authorized signatory
18.
Copy of completion certificate confirmation all outstanding works, identified defects
have been closed out and all O & M Manuals Provided
19.
In case of Fluctuations to be added or deducted to payment certificate, calculation to
be attached
COMMENTS:
1.
Payment To Be Returned For Corrections, etc, as detailed below:
*not required in case of the in-house supervision.
Checked by:.
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 26 of 181
PUBLIC WORKS AUTHORITY
SECTION 2
PAYMENT PROCEDURE FOR
CONSULTANT
(DESIGN & SUPERVISION)
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 27 of 181
PUBLIC WORKS AUTHORITY
DESCRIPTION OF CONSULTANT
(DESIGN & SUPERVISION)
PAYMENT PROCESS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 28 of 181
DESCRIPTION OF CONSULTANT
(DESIGN & SUPERVISION) PAYMENT PROCESS
1.
1.1
DEFINITIONS AND ACRONYMS
Definitions
For the purpose of this document, the following definitions shall be used:
PWA Representative shall mean the delegated representative by the Public Works Authority
(PWA). The representative will vary for each programme as per the blow table.
The Engineer shall have the same meaning as provided in the General Conditions. The
Engineer will vary as delegated for each programme as per the below table.
The Design/Supervision Consultant hereafter called the Consultant. The Consultant will
vary for each programme as per the below table.
Authority shall mean the Public Works Authority (Ashghal) of the state of Qatar.
Engineering Business Support Department shall mean that department within the Authority
so titled.
Department of General Financial Affairs of the Ministry of Finance shall have the same
definition as provided in the Agreement General Conditions of Engagement.
Revision 2.2
5 February 2014
Page 29 of 181
Item
Programme
Programme Management
Consultant
(PMC)/Management
Contractor (MC)
Local Roads & Drainage
Parsons Brinckerhoff
Manager of Roads Projects
Department or delegated
Area Engineer
PMC
General Engineering Consultant
(GEC)
Expressway
KBR
Manager of Expressway
Department
PMC
Supervision Consultant (SC)
Building Projects
Mace/Ec_Harris
Director of Building Affairs
PWA
Representative/
PMC
Design Construction Supervision
Consultant (DCSC)
IDRIS
CH2MHill
Director of Infrastructure
Affairs
PMC
Supervision Consultant (SC)
Highways Asset
Management
Amey
Director of Assets Affairs
PWA
Representative
The Consultant
Drainage Asset
Management
MWH
Director of Assets Affairs
PWA
Representative
The Consultant
Al Sharq Crossing
Fluor
B. Yacob Al Kazem
PWA Representative
The Engineer
The Consultant
PMC
General Engineering Consultant
(GEC)
Table 1: Parties Involved in the Process
Revision 2.2
5 February 2014
Page 30 of 181
2.
2.1
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES
Subject:
The subject matter of this procedure is the methodology in accordance with which the
Consultants applications for payment shall be administered by the parties.
2.2
Purpose:
To provide a specific, detailed and transparent process to facilitate timely certification and
authorisation of the Consultants applications for payment.
2.3
Scope:
This procedure shall be applicable to all Consultants applications for payment.
This document represents the Consultant Payment Procedures based on the Authority General
Conditions of Engagement 1984 & 2010 Edition. These procedures should be adapted, after
discussion with PWA Representative as appropriate for each programme, to reflect the different
conditions of contract.
2.4
Parties:
The parties required to administer this procedure are:
A.
The Consultant: Delegated representative;
B.
The Engineer: Delegated representative;
C.
Relevant Departments within the Public Works Authority (PWA):
a)
PWA Representative to endorse the Consultant Payment Application;
b)
Engineering Business Support Department (EBSD) representative
c)
Finance & Administrative Department representative.
The Parties shall have, and hold, full delegated powers from their respective departments to
review and endorse the Consultant Payment Applications.
The Authority (being Area Engineer, Department Manager, Finance & Administrative and
Engineering Business Support Departments) shall accept in full without recourse to further and
/ or additional review the endorsements of the Payment Application carried out on their behalf
by their delegated representatives.
Revision 2.2
5 February 2014
Page 31 of 181
2.5
Application for Payment
The 28 day certification and authorisation period in General Conditions of Engagement (GCoE)
Sub-clause 4.2.2 B commences upon formal date of receipt by the PWA of the correct Payment
Application from the Consultant.
The Consultant shall submit the application for payment in compliance with the Agreement.
For the sake of clarification:
application for payment refers to the process of payment application, invoicing and
reimbursement
Payment Application refers to the document, proforma contained in the Check lists,
issued by the Consultant to the Engineer for review and endorsement. This document:
The Consultant shall submit the Payment Application within the first week of each calendar
month to the Engineer. The Cut-off date of each Payment Application is the last working day of
each calendar month. The Engineer shall use the forms in the check list & Templates. The date
of receipt by the Engineer is the date from which the payment due date is calculated.
2.5.1 The Consultant application for payment shall comprise the following:
1. Cover letter, refer to the proforma in appendices covering letter to Finance & Administrative
Department.
2. Fly sheets to separate each Payment Item Support Sheet and supporting documents;
3. Payment Application Summary Sheet, refer to proforma in the check lists & Templates.
2.6
Payment Application Review
The Consultant shall submit the Payment Application to the attention of the Engineer.
2.6.1 The Engineer Review Process
Upon receipt of the Consultant Payment Application, the Engineer shall within five (5) working
days review, prepare, approve, sign the Payment Certificate and forward the Consultants
payment document to the PWA Representative for final approval. The Engineer shall forward to
the PWA Representative two (2) hardcopies including the following as a minimum:
1. Original Consultants Payment Documents stamped by both Consultant and Engineer;
2. Signed and stamped Payment Certificate by the Engineer; and
3. Engineer recommendation.
Within the review process, The Engineer shall check and make sure that system entries are
correct and up to date.
In coordination with the PWA Representative and EBSD, the Engineer shall check the
availability of funds to process the Consultants payment. If no funds are available, the
Engineer shall prepare a Budget Transfer Request for the approval of the PWA Representative.
The approved Budget Transfer Request shall be attached to the Payment Documents for the
authorization of the PWA Finance & Administrative Department.
Revision 2.2
5 February 2014
Page 32 of 181
2.6.2 PWA Representative Review Process
Within three (2) working days from receipt of the Consultants Payment Application, PWA
Representative shall sign the Payment Certificate, initial the PWA memorandum and forward
the Payment Document to the EBSD.
2.6.3 The EBSD Review Process
Upon receipt of the Consultants payment from the PWA Representative, EBSD shall within
three (3) working days review, sign and forward the Payment Document and the signed
Payment Certificate to the concerned Department Manager.
In case of comments or clarifications, the EBSD shall contact the Engineer directly to fix the
comments or provide reply to the EBSDs clarifications.
2.6.4 Department Manager Review Process
Two (2) hardcopies of the Payment Document and Payment Certificate signed by the
Department Manager will be forwarded to the PWA Finance & Administrative Department for
authorization. The duration of this process shall not be more than one (2) working days.
2.6.5 PWA Finance & Administrative Department Review Process
Within two (3) working days from the receipt of signed document, the PWA Finance &
Administrative Department shall authorize and issue the payment to the Ministry of Finance.
2.7
Key Performance Indicator (KPI) Payment Application1
In accordance to the Agreement Documents Schedule A Project Brief, the KPI amount will
be monitored and recorded as notional amount on periodical basis. The KPI amount will be
derived from the outcome of the KPI measurements via the KPI record Scorecard.
The review and approval of the scorecard submitted by the Consultants shall be in accordance
with the timelines indicated in the following Exhibit 3: KPI Adjustment Timeline or as agreed by
the Authority.
The notional KPI amount at year-end (the end of Agreement Year, which is Commencement
Date + 1 year) shall be at the % age in each Consultant Contract of the total invoiced amount
for the year, or as agreed by parties.
The Agreement Price is divided into two amounts as follows:
1.
Agreement Price Excluding the KPI Amount: from which the Consultants interim
monthly payments will be paid without any deductions or retentions.
2.
KPI Amount: which will be divided over the Agreement Duration as agreed with PWA.
This amount will be used to pay the KPI amounts referred to in the above paragraph.
In the event that the review of the KPI Scorecard results in an addition, the amount shall be
added to the Work Done to Date of the payment application month. The KPI addition amount
shall not be subject to advance payment recovery.
Revision 2.2
5 February 2014
Page 33 of 181
The balance amount between the addition KPI amount and the notional KPI amount for the
year will be deducted from the Agreement Price. The determined KPI amount in the Agreement
Price will then be adjusted for the next year by deducting the complete notional amount of the
previous year.
2.8
Countersignatures and Counter Initialing of Documents
Countersignature of the Payment Certificate by the Consultant, the Engineer and the Authority
is acceptable for holiday cover or leave of absence subject to the required delegated authority.
Counter initialing of any document by the Consultant, the Engineer and the Authority is
acceptable for holiday cover or leave of absence subject to the required delegated authority.
No alteration or change to the template of the Payment Certificate shall be permitted without
express approval of the Authority with reasons given for any proposed alteration or change.
2.9
Error Corrections and Reverse Process
In case of any error found during the above review processes, the party who found the error
shall return the payment documents to the concerned party for correction along with the check
list. Once corrected, the Payment Documents shall be processed in the same order of the
above steps. The errors and corrective actions shall be clearly recorded in the payment
tracking sheet in order to be prevented in the future. The date the Engineer received the
corrected application is the date from which the payment due date is calculated.
3.
PROCEDURE
Payments shall be administered by an Nine (9) steps process as illustrated in the Process Map.
Revision 2.2
5 February 2014
Page 34 of 181
PUBLIC WORKS AUTHORITY
4. PROCESS MAP FOR
CONSULTANT
(DESIGN & SUPERVISION)
PAYMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 35 of 181
Project Type:
PWA-led Project
Title
PMC-led Project
PAYMENT PROCESS
Payment For:
Contract Type:
Consultant
Contractor
Supplier
Design & Supervision
Construction
PWA1/Client2
PMC/MC3
PMC
Secondment
Workorder & Supply
In-house supervision
Operation & Maintinance
Consultant4
Contractor
(Engineers representative)
(Principle)
- Initiate Payment
Requisition
Other Stakeholders
Request for
Payment
EBSD
- Review & Approve
Review
PWA rep. (PM)
No
PWA PWA Stakeholder might be the
President, Affairs, O&M Department
2
Client: Only applied for the building affairs
3
PMC: Program Management Consultant
MC: Management Contractor
4
The consultant title might be GEC (General
Engineering Consultant), SC (Supervision
Consultant), DCSC (Design Construction
Supervision Consultant
Note: in case of PWA-led projects without
PMC/MC, just skip the PMC/MC related
activities
Accepted?
Review
Yes
No
Accepted?
Yes
Finance & Adm.Dpt.
- Process the payment
- Update the System
Head of Section
Head
Section
days
Advance payment
Penultimate Payment
Final payment
Review and Approve the
payment requisition
1
Interim Payment
Ministry of Finance
Approve
Phase
Document Flow
- Processing the Payment
Dpt. Manager
Revision 2.2
No. of Working Days
Calendar Day
2
5 February 2014
45
Level 2 process
(External Process
Page 36 of 181
PUBLIC WORKS AUTHORITY
5. PAYMENT CHECKLISTS FOR
CONSULTANT
(DESIGN & SUPERVISION)
AND TEMPLATES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 37 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
FIRST RP FOR CONSULTANT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Approval of PWA for the services completed Design Contracts
4.
Daily, monthly attendance, & calculation sheets Supervision Contracts to
be signed by the project Manager Refer to Appendices A11 & A12.
5.
Copy of signed authorisation to mobilise staff (ATM)
6.
Copy of award Letter, Notice of Agreement or Notice to Proceed
7.
Copy of Performance Bond or any Extension Refer to Appendix A5
8.
Copy of Insurance certificates
9.
Copy of Valid Commercial Registration or Municipality valid certificate
10.
I. D. Copy of the authorized signatory
11.
Bank Account Information Letter (stamped by the Bank) Refer to Appendix
A8
12.
In case penalty full breakdown shall be submitted
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 38 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
INTERIM RP FOR CONSULTANT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Approval of PWA for the services completed Design Contracts
4.
Daily, monthly attendance, & calculation sheets Supervision Contracts to
be signed by the Project Manager Refer to Appendices A11 & A12,
5.
Copy of signed authorisation to mobilise Staff (ATM)
6.
In case penalty full breakdown shall be submitted
7.
Copy of approved addenda in case of extension or additional cost
8.
In case of fluctuations to be added or deducted to payments certificate,
calculations to be attached
9.
Copy of Valid Commercial Registration
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 39 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
FINAL RP FOR CONSULTANT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Approval of PWA for the services completed Design Contracts
Daily, monthly attendance, & calculation sheets Supervision Contracts
4.
Refer to Appendices A11 & A12
5.
Copy of signed authorisation to mobilise (ATM) staff
6.
Copy of Valid Commercial Registration or Municipality valid certificate
7.
I. D. Copy of the authorized signatory
8.
In case of penalty Details breakdown must be attached
9.
Copy of approved addenda in case of extension or additional/omission
cost
10.
Original Completion Certificate Refer to Appendix A13
11.
Copy of Maintenance Certificate for supervision contracts, in case
Construction Contract not yet closed. Refer to Appendix A14
12.
Original Final Account Statement Refer to Appendix A15
13.
Copy of valid Income Tax I.D.
14.
Original DCU Clearance
15.
In case the Bank account changed, the Consultant must submit No
Objection Letter from previous bank
16.
In case of fluctuations to be added or deducted to payments certificate,
calculations to be attached
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 40 of 181
PUBLIC WORKS AUTHORITY
SECTION 3
PAYMENT PROCEDURE FOR
CONSULTANT
(PMC & SECONDMENT)
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 41 of 181
PUBLIC WORKS AUTHORITY
DESCRIPTION OF CONSULTANT
(PMC & SECONDMENT)
PAYMENT PROCESS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 42 of 181
DESCRIPTION OF CONSULTANT
(DESIGN & SUPERVISION) PAYMENT PROCESS
1.
1.1
DEFINITIONS AND ACRONYMS
Definitions
For the purpose of this document, the following definitions shall be used:
PWA Representative shall mean the delegated representative by the Public Works Authority
(PWA). The representative will vary for each programme as per the blow table.
The Engineer shall have the same meaning as provided in the General Conditions. The
Engineer will vary as delegated for each programme as per the below table.
The Design/Supervision Consultant hereafter called the Consultant. The Consultant will
vary for each programme as per the below table.
Authority shall mean the Public Works Authority (Ashghal) of the state of Qatar.
Engineering Business Support Department shall mean that department within the Authority
so titled.
Department of General Financial Affairs of the Ministry of Finance shall have the same
definition as provided in the Agreement General Conditions of Engagement.
Revision 2.2
5 February 2014
Page 43 of 181
Item
Programme
Programme Management
Consultant
(PMC)/Management
Contractor (MC)
Local Roads & Drainage
Parsons Brinckerhoff
Manager of Roads Projects
Department or delegated
Area Engineer
PMC
General Engineering Consultant
(GEC)
Expressway
KBR
Manager of Expressway
Department
PMC
Supervision Consultant (SC)
Building Projects
Mace/Ec_Harris
Director of Building Affairs
PWA
Representative/
PMC
Design Construction Supervision
Consultant (DCSC)
IDRIS
CH2MHill
Director of Infrastructure
Affairs
PMC
Supervision Consultant (SC)
Highways Asset
Management
Amey
Director of Assets Affairs
PWA
Representative
The Consultant
Drainage Asset
Management
MWH
Director of Assets Affairs
PWA
Representative
The Consultant
Al Sharq Crossing
Fluor
B. Yacob Al Kazem
PWA Representative
The Engineer
The Consultant
PMC
General Engineering Consultant
(GEC)
Table 1: Parties Involved in the Process
Revision 2.2
5 February 2014
Page 44 of 181
2.
2.1
SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES
Subject:
The subject matter of this procedure is the methodology in accordance with which the
Consultants applications for payment shall be administered by the parties.
2.2
Purpose:
To provide a specific, detailed and transparent process to facilitate timely certification and
authorisation of the Consultants applications for payment.
2.3
Scope:
This procedure shall be applicable to all Consultants applications for payment.
This document represents the Consultant Payment Procedures based on the Authority General
Conditions of Engagement 1984 & 2010 Edition. These procedures should be adapted, after
discussion with PWA Representative as appropriate for each programme, to reflect the different
conditions of contract.
2.4
Parties:
The parties required to administer this procedure are:
A.
The Consultant: Delegated representative;
B.
The Engineer: Delegated representative;
C.
Relevant Departments within the Public Works Authority (PWA):
a)
PWA Representative to endorse the Consultant Payment Application;
b)
Engineering Business Support Department (EBSD) representative
c)
Finance & Administrative Department representative.
The Parties shall have, and hold, full delegated powers from their respective departments to
review and endorse the Consultant Payment Applications.
The Authority (being Area Engineer, Department Manager, Finance & Administrative and
Engineering Business Support Departments) shall accept in full without recourse to further and
/ or additional review the endorsements of the Payment Application carried out on their behalf
by their delegated representatives.
Revision 2.2
5 February 2014
Page 45 of 181
2.5
Application for Payment
The 28 day certification and authorisation period in General Conditions of Engagement (GCoE)
Sub-clause 4.2.2 B commences upon formal date of receipt by the PWA of the correct Payment
Application from the Consultant.
The Consultant shall submit the application for payment in compliance with the Agreement.
For the sake of clarification:
application for payment refers to the process of payment application, invoicing and
reimbursement
Payment Application refers to the document, proforma contained in the Check lists,
issued by the Consultant to the Engineer for review and endorsement. This document:
The Consultant shall submit the Payment Application within the first week of each calendar
month to the Engineer. The Cut-off date of each Payment Application is the last working day of
each calendar month. The Engineer shall use the forms in the check list & Templates. The date
of receipt by the Engineer is the date from which the payment due date is calculated.
2.5.1 The Consultant application for payment shall comprise the following:
1. Cover letter, refer to the proforma in appendices covering letter to Finance & Administrative
Department.
2. Fly sheets to separate each Payment Item Support Sheet and supporting documents;
3. Payment Application Summary Sheet, refer to proforma in the check lists & Templates.
2.6
Payment Application Review
The Consultant shall submit the Payment Application to the attention of the Engineer.
2.6.1 The Engineer Review Process
Upon receipt of the Consultant Payment Application, the Engineer shall within five (5) working
days review, prepare, approve, sign the Payment Certificate and forward the Consultants
payment document to the PWA Representative for final approval. The Engineer shall forward to
the PWA Representative two (2) hardcopies including the following as a minimum:
1. Original Consultants Payment Documents stamped by both Consultant and Engineer;
2. Signed and stamped Payment Certificate by the Engineer; and
3. Engineer recommendation.
Within the review process, The Engineer shall check and make sure that system entries are
correct and up to date.
In coordination with the PWA Representative and EBSD, the Engineer shall check the
availability of funds to process the Consultants payment. If no funds are available, the
Engineer shall prepare a Budget Transfer Request for the approval of the PWA Representative.
The approved Budget Transfer Request shall be attached to the Payment Documents for the
authorization of the PWA Finance & Administrative Department.
Revision 2.2
5 February 2014
Page 46 of 181
2.6.2 PWA Representative Review Process
Within three (2) working days from receipt of the Consultants Payment Application, PWA
Representative shall sign the Payment Certificate, initial the PWA memorandum and forward
the Payment Document to the EBSD.
2.6.3 The EBSD Review Process
Upon receipt of the Consultants payment from the PWA Representative, EBSD shall within
three (3) working days review, sign and forward the Payment Document and the signed
Payment Certificate to the concerned Department Manager.
In case of comments or clarifications, the EBSD shall contact the Engineer directly to fix the
comments or provide reply to the EBSDs clarifications.
2.6.4 Department Manager Review Process
Two (2) hardcopies of the Payment Document and Payment Certificate signed by the
Department Manager will be forwarded to the PWA Finance & Administrative Department for
authorization. The duration of this process shall not be more than one (2) working days.
2.6.5 PWA Finance & Administrative Department Review Process
Within two (3) working days from the receipt of signed document, the PWA Finance &
Administrative Department shall authorize and issue the payment to the Ministry of Finance.
2.7
Key Performance Indicator (KPI) Payment Application1
In accordance to the Agreement Documents Schedule A Project Brief, the KPI amount will
be monitored and recorded as notional amount on periodical basis. The KPI amount will be
derived from the outcome of the KPI measurements via the KPI record Scorecard.
The review and approval of the scorecard submitted by the Consultants shall be in accordance
with the timelines indicated in the following Exhibit 3: KPI Adjustment Timeline or as agreed by
the Authority.
The notional KPI amount at year-end (the end of Agreement Year, which is Commencement
Date + 1 year) shall be at the % age in each Consultant Contract of the total invoiced amount
for the year, or as agreed by parties.
The Agreement Price is divided into two amounts as follows:
1.
Agreement Price Excluding the KPI Amount: from which the Consultants interim
monthly payments will be paid without any deductions or retentions.
2.
KPI Amount: which will be divided over the Agreement Duration as agreed with PWA.
This amount will be used to pay the KPI amounts referred to in the above paragraph.
In the event that the review of the KPI Scorecard results in an addition, the amount shall be
added to the Work Done to Date of the payment application month. The KPI addition amount
shall not be subject to advance payment recovery.
Revision 2.2
5 February 2014
Page 47 of 181
The balance amount between the addition KPI amount and the notional KPI amount for the
year will be deducted from the Agreement Price. The determined KPI amount in the Agreement
Price will then be adjusted for the next year by deducting the complete notional amount of the
previous year.
2.8
Countersignatures and Counter Initialing of Documents
Countersignature of the Payment Certificate by the Consultant, the Engineer and the Authority
is acceptable for holiday cover or leave of absence subject to the required delegated authority.
Counter initialing of any document by the Consultant, the Engineer and the Authority is
acceptable for holiday cover or leave of absence subject to the required delegated authority.
No alteration or change to the template of the Payment Certificate shall be permitted without
express approval of the Authority with reasons given for any proposed alteration or change.
2.9
Error Corrections and Reverse Process
In case of any error found during the above review processes, the party who found the error
shall return the payment documents to the concerned party for correction along with the check
list. Once corrected, the Payment Documents shall be processed in the same order of the
above steps. The errors and corrective actions shall be clearly recorded in the payment
tracking sheet in order to be prevented in the future. The date the Engineer received the
corrected application is the date from which the payment due date is calculated.
3.
PROCEDURE
Payments shall be administered by an Nine (9) steps process as illustrated in the Process Map.
Revision 2.2
5 February 2014
Page 48 of 181
PUBLIC WORKS AUTHORITY
4. PROCESS MAP FOR
CONSULTANT
(PMC & SECONDMENT)
PAYMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 49 of 181
Project Type:
PAYMENT PROCESS
Payment For:
Contract Type:
Consultant
Contractor
Supplier
Design & Supervision
Construction
PWA-led Project
Title
PMC-led Project
PWA1/Client2
PMC/MC3
In-house supervision
Operation & Maintinance
Consultant4
Contractor
(Engineers representative)
(Principle)
- Initiate Payment
Requisition
- Initiate Payment
Requisition
PMC
Secondment
Workorder & Supply
Other Stakeholders
EBSD
Review
PWA rep. (PM)
No To be reviewed between PM and Consultant
Review
Accepted?
1
PWA PWA Stakeholder might be the
President, Affairs, O&M Department
2
Client: Only applied for the building affairs
3
PMC: Program Management Consultant
MC: Management Contractor
4
The consultant title might be GEC (General
Engineering Consultant), SC (Supervision
Consultant), DCSC (Design Construction
Supervision Consultant
Note: in case of PWA-led projects without
PMC/MC, just skip the PMC/MC related
activities
Yes
Yes
No
Accepted?
Finance & Adm. Dpt.
- Process the payment
- Update the system
Head of
of Section
Head
Section
Review and Approve the
payment requisition
1
days
Advance payment
Penultimate Payment
Final payment
MOF
Dpt. Manager
- Processing the Payment
Approve
Calendar Day
45
Interim Payment
Document Flow
Level 2 process
(External Process
Phase
Revision 2.2
No. of Working Days
5 February 2014
Page 50 of 181
PUBLIC WORKS AUTHORITY
5. PAYMENT CHECKLISTS FOR
CONSULTANT
(PMC & SECONDMENT)
AND TEMPLATES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 51 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
FIRST RP FOR PMC & SECONDMENT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Daily monthly attendance, & calculation sheets to be signed by the Project
Manager Refer to Appendices A11, A12 & C1
4.
Copy of signed authorisation to mobilise Staff (ATM)
5.
Copy of award Letter, Notice of Agreement or Notice to Proceed
6.
Copy of Performance Bond or any Extension Refer to Appendix A5
7.
Copy of Insurance certificates
8.
Copy of Valid Commercial Registration
9.
I. D. Copy of the authorized signatory
10.
Bank Account Information Letter (Stamped by the Bank) Refer to Appendix
A8
11.
In case penalty full breakdown shall be submitted
Note: For secondment contracts & Contracts under Condition of Engagement 1984 Edition.
Salary per day = Monthly salary *12 months/365 days; Calculation of Absence=(monthly
salary) (salary per day*no of days absent)
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 52 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
INTERIM RP FOR PMC & SECONDMENT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Daily, monthly attendance, & calculation sheets to be signed by Project
Manager Refer to Appendices A11 & A12
4.
Copy of signed authorisation to mobilise staff (ATM)
5.
(KPI) Calculation sheet for Key Performance Indicator
6.
In case penalty full breakdown shall be submitted
7.
Copy of approved addenda in case of extension or additional cost
8.
In case of fluctuations to be added or deducted to payments certificate,
calculations to be attached
9.
Copy of Valid Commercial Registration
Note: For secondment contracts & Contracts under Condition of Engagement 1984 Edition.
Salary per day = Monthly salary *12 months/365 days; Calculation of Absence=(monthly
salary) (salary per day*no of days absent)
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 53 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
FINAL RP FOR PMC & SECONDMENT
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Daily, monthly attendance, & calculation sheets to be signed by Project
Manager Refer to Appendices A11 & A12
4.
Copy of signed authorisation to mobilise staff (ATM)
5.
I. D. Copy of the authorized signatory
6.
In case penalty full breakdown shall be submitted
7.
Copy of approved addenda in case of extension or additional/omission
cost
8.
Original Completion Certificate Refer to Appendix A13
9.
Original Final Account Statement Refer to Appendix A15
10.
Copy of Valid Income Tax I.D.
11.
(KPI) Calculation sheet for Key Performance Indicator
12.
In case the Bank account changed, the Consultant must submit No
Objection Letter from previous bank
13.
In case of fluctuations to be added or deducted to payments certificate,
calculations to be attached
14.
Copy of Valid Commercial Registration
Note: For secondment contracts & Contracts under Condition of Engagement 1984 Edition.
Salary per day = Monthly salary *12 months/365 days; Calculation of Absence=(monthly
salary) (salary per day*no of days absent)
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 54 of 181
PUBLIC WORKS AUTHORITY
SECTION 4
PAYMENT PROCEDURE FOR
SUPPLIER
(WORKORDER & SUPPLY)
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 55 of 181
PUBLIC WORKS AUTHORITY
DESCRIPTION OF SUPPLIER
(WORKORDER & SUPPLY)
PAYMENT PROCESS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 56 of 181
DESCRIPTION OF SUPPLIER
(WORORDER & SUPPLY) PAYMENT PROCESS
1. DEFINITIONS
For the purpose of this document, the following definitions shall be used:
PWA Representative shall mean the delegated representative by the Public Works Authority
(PWA). The representative will vary for each programme as per the blow table.
The Engineer shall have the same meaning as provided in the Agreement General Conditions
of Engagement. The Engineer will vary as delegated for each programme as per the below table.
The Design/Supervision Consultant hereafter called the Consultant. The Consultant will
vary for each programme as per the below table.
Authority shall mean the Public Works Authority (Ashghal) of the state of Qatar.
Engineering Business Support Department shall mean that department within the Authority
so titled.
Department of General Financial Affairs of the Ministry of Finance shall
have the same definition as provided in the Agreement General Conditions of Engagement.
Electronic System shall mean the software which will be used for each programme, as
agreed with the Authority, to manage and track the Payment Applications.
Period End Date shall mean the last working day of the calendar month for which the
Contractor is applying to.
Revision 2.2
5 February 2014
Page 57 of 181
Item
Programme
Programme Management
Consultant (PMC) /
Management Contractor
PWA Representative
The Engineer
The Consultant
PMC
General Engineering Consultant
(GEC)
Local Roads & Drainage
Parsons Brinckerhoff
Manager of Roads Projects
Department and/or
delegated Area Engineer
Expressway
KBR
Manager of Expressway
Department
PMC
Supervision Consultant (SC)
Building Projects
Mace/Ec_Harris
Director of Building Affairs
PWA Representative/
PMC
Design Construction Supervision
Consultant (DCSC)
IDRIS
CH2MHill
Director of Infrastructure
Affairs
PMC
Supervision Consultant (SC)
Highways Asset
Management
Amey
Director of Assets Affairs
PWA Representative/
Management Contractor
The Consultant
Drainage Asset
Management
MWH
Director of Assets Affairs
PWA Representative/
Management Contractor
The Consultant
Al Sharq Crossing
Fluor
B. Yacob Al Kazem
PMC
The Consultant
Table 1: Parties Involved in the Process
Revision 2.2
5 February 2014
Page 58 of 181
2. SUBJECT, PURPOSE, SCOPE, PARTIES AND RESPONSIBILITIES
2.1.
Subject:
The subject matter of this procedure is the methodology in accordance with which the
Suppliers applications for payment shall be administered by the parties.
2.2.
Purpose:
To provide a specific, detailed and transparent process to facilitate timely certification and
authorisation of the Suppliers applications for payment.
2.3.
Scope:
This procedure shall be applicable to all Suppliers applications for payment.
2.4.
Parties:
The parties required to administer this procedure are:
A. The Supplier: Delegated representative
B. The Engineer: Delegated representative;
C. Authority:
a) Engineering Business Support Department (EBSD) representative;
b) Finance & Administrative Department representative with delegated.
The Parties shall have, and hold, full delegated powers from their respective departments to
review and endorse the PMC Payment Applications.
The Authority (being Finance & Adminsitrative and Engineering Business Support Departments)
and the Engineer shall accept in full without recourse to further and / or additional review the
endorsements of the Payment Application carried out on their behalf by their delegated
representatives.
3.
PROCEDURE
Payments shall be administered by 7 steps process as illustrated in Table 2. Process Map for
Suppliers Payment
3.1
Application for Payment
The Supplier shall submit the application for payment in compliance with the Contract. The
supplier shall issue application for payment by the end of the job or as per the conditions of the
contract. The Supplier shall submit a h ardcopy as well as a softcopy through the Electronic
System. A copy of the Suppliers submission shall be uploaded into the Electronic System.
The date of receipt by the Engineer is the date from which the payment due date is calculated.
3.1.1. The Engineer Review Process
Upon receipt of the supplier payment, the Engineer shall within Five (5) working days review
the payment, approve, sign and forward the suppliers payment certificate to the EBSD for final
approval. The Engineer shall forward to the EBSD the Payment Document through the
Electronic System and (2) two hardcopies including the following as a minimum:
1. Original Suppliers Payment Documents stamped by the Engineer;
2.
Revision 2.2
Signed and stamped Payment Certificate by the Engineer;
5 February 2014
Page 59 of 181
3. Check and validate PWA Standard Checklist submitted by the Supplier and verified by
the Engineer as appropriate for each type of payment; and
4. The Engineer recommendation.
Within the review process, The Engineer shall check and make sure that the Electronic System
entries are correct and up to date.
3.1.2. Engineering Business Support Department (EBSD) Review Process
Upon receipt of the Suppliers payment from the Engineer, EBSD shall within three (3) working
days review, sign and forward the Payment Document and the signed Payment Certificate to
the concerned PWA Representative/Area Engineer through the Engineer.
3.1.3. PWA Finance & Administrative Review Process
Within three (3) working days from the receipt of signed document, the PWA Finance
& Administrative Department shall authorise and issue the payment to the Ministry of Finance.
3.2 Error Corrections and Reverse Process
In case of any error found during the above review processes, the party who found the error
shall return the payment documents to the concerned party for correction along with the check
list. Once corrected, the Payment Documents shall be processed in the same order of the
above steps. The errors and corrective actions shall be clearly recorded in the payment
tracking sheet in order to be prevented in the future. The date the Engineer received the
corrected application is the date from which the payment due date is calculated.
4.
TRACKING OF PAYMENT
Upon the payment collection, The Supplier shall update the appropriate fields in the Electronic
System and notify the Engineer.
The Finance & Administrative Department will advise the Engineer when Supplier has received
payment and upon which date payment was received.
5.
COUNTERSIGNATURES AND COUNTER INITIALLING OF DOCUMENTS
Countersignature of the Payment Certificate by the Engineer and the Authority is acceptable for
holiday cover or leave of absence subject to the required delegated authority.
Counter initialling of any document by the Engineer and the Authority is acceptable for holiday
cover or leave of absence subject to the required delegated authority.
No alteration or change to the template of the Payment Certificate shall be p ermitted without
express approval of the Authority with reasons given for any proposed alteration or change.
Revision 2.2
5 February 2014
Page 60 of 181
PUBLIC WORKS AUTHORITY
6. PROCESS MAP FOR SUPPLIER
(WORKORDER & SUPPLY)
PAYMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 61 of 181
Project Type:
PWA-led Project
Title
PMC-led Project
PAYMENT PROCESS
Payment For:
Contract Type:
Consultant
Contractor
Supplier
Design & Supervision
Construction
PWA1/Client2
PMC/MC3
PMC
Secondment
Workorder & Supply
Consultant4
Supplier
(Engineers representative)
(Principle)
Initiate Payment
Requisition process
In-house supervision
Operation & Maintinance
Other Stakeholders
Request for
Payment
EBSD
Review
3
1
PWA rep. (PM)
Review
PWA PWA Stakeholder might be the
President, Affairs, O&M Department
2
Client: Only applied for the building affairs
3
PMC: Program Management Consultant
MC: Management Contractor
4
The consultant title might be GEC (General
Engineering Consultant), SC (Supervision
Consultant), DCSC (Design Construction
Supervision Consultant
Note: in case of PWA-led projects without
PMC/MC, just skip the PMC/MC related
activities
No
Accepted?
0
Yes
No
Yes
Accepted?
Finance & Adm.Dpt.
- Process the payment
- Update the system
Head of
of Section
Head
Section
days
No. of Working Days
Review and Approve the
payment requisition
1
Ministry of Finance
- Processing the Payment
Dpt. Manager
Approve
Calendar Day
45
Phase
Revision 2.2
5 February 2014
Page 62 of 181
PUBLIC WORKS AUTHORITY
7. PAYMENT CHECKLISTS FOR
SUPPLIER
(WORKORDER & SUPPLY)
AND TEMPLATES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 63 of 181
ENGINEERING BUSINESS SUPPORT DEPARTMENT
PAYMENT CONTROL CHECK
RP FOR WORK ORDER & SUPPLY
Commitment No.
Department
Contractor/Consultant
Project Manager
RP No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice
2.
Original RP
3.
Copies of Delivery Notes
4.
Original Performance Certificate Refer to Appendix A16
5.
Original Taking over certificate Refer to Appendix A17 not applicable for House
6.
Original Final Account Statement Refer to Appendix A15 not applicable for House
connection work orders less than fifty thousands
7.
Copies of Warrantee certificates
8.
Copy of Valid Commercial Registration
9.
Work Order Completion Certificate Refer to Appendix D1
10.
I. D. Copy of the authorized signatory
11.
Bank Account Information Letter Stamped by the Bank Refer to Appendix
connection work orders
A8
12.
Copy of Valid Income Tax I.D.
COMMENTS
1.
Payment To Be Returned For Corrections, etc, as detailed below:
Checked by:
Date:
This Payment Control Check Sheet Must Be Returned as the front
cover to all returned documentation
Revision 2.2
5 February 2014
Page 64 of 181
PUBLIC WORKS AUTHORITY
GUIDELINES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 65 of 181
PUBLIC WORKS AUTHORITY
1. PAYMENTS FOR CONTRACT
ITEMS REMEASUREABLE
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 66 of 181
1.
VALUATION OF WORKS - REMEASUREMENT ITEMS
1.0
Purpose of the Report
(a) To enhance the payment procedure for re-measurable items for the purpose
of cost control which shall be part of the items in PWA Payment Control
Check List.
(b) The procedure shall be part of the requirements to be fulfilled while preparing
the payment certificate in regard to the re-measurable items.
(c) Payment may be d elayed due to any excess in the quantities above the
B.O.Q where no VO is in place, particularly at the end of the project.
2.0
Documents required
The following are the documents which are to be attached along with the
payment application.
(a) Measurement sheets
(i)
The actual work completed on s ite is to be re-measured progressively
once in every month or within certain period as stated in the Contract or
up to the period ending date agreed with the Contractor for the purpose
of the application.
(ii) The quantities are to be re-measured from the approved Construction
Drawings / Shop drawings or any approved supporting documents and
these drawings / documents used are not required to be attached to the
payment submission. Approved construction drawings/shop drawings
should be issued under a V.O. where approved construction drawings
have been issued estimated quantities are measured, where approved
shop drawings have been produced by the Contractor actual quantities
are measured. The shop drawings and actual quantities and unit rates
shall replace the estimated quantities and unit rates measured from
construction drawings. These documents may be revised by the
Engineer Representative on s ite. All documents are to be provided to
PWA upon request for random checks.
(iii) Only the re-measurement sheet summaries need to be submitted for the
current application.
(iv) The quantity shown in the measurement sheet shall be ascertained and
certified by the Engineer Representative and Project Management
Consultant (PMC) or Engineer or any other party stated in the Contract.
3.0
Payment format
Each of the re-measured items claimed shall be presented in the format as
shown in Appendix 1. The previous certified quantities should be inserted to
avoid duplication in quantity measured while the current certified quantity shows
the net amount of works completed for that particular month or between the
period ending date.
Revision 2.2
5 February 2014
Page 67 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
JSM
JOINT MEASUREMENT SHEET
Contract No.
Project Title
19.6
3.5
Turfing for R1 left side
Claim No.
A
900 x 900
Chaunage 700 to 750
3.7
12.5
0
53.7
4.0
10
20
3.8
4.3
4.1
30
40
Keys :
7.5
4.0
Premix A
20.5
= x 19.6 x 3.8
50
= 37.24 ms
14.7
49.5
Brick sump
Premix B
Manhole chambering
Length mark
Length , L
Width , W
Area , L x W
600mm pipe culvert
(m)
(m)
(m)
( m )
450mm pipe culvert
0
10
10.00
3.70
0.00
3.70
37.00
20
10.00
4.00
40.00
30
10.00
4.30
43.00
40
10.00
4.10
41.00
50
10.00
4.00
40.00
Total
School
201.00
Premix B - road opening
= ( 20.5 + 7.5 ) x 14.7
= 205.8 ms
1.5
1.0
DESCRIPTION
ITEM
1
3.2
7.1
5.7
UNIT
QTY
manhole chambering
no
REMARKS
1200 x 1200 x 3.6m (H)
refer to SK02
Turfing - left side of R1 road
ms
228.65
600mm pipe culvert
103.20
refer RW08 & RW10
Premix A
ms
37.24
ACWC 14 only , refer RW09
Premix B ( R1 )
ms
406.80
Crusher run and ACWC 14 , refer RW09
900 x 900 brick sump
no
450mm pipe culvert
16.00
SUBMITTED BY:
EVALUATED BY :
refer attached calculation
y
refer RW10
VERIFIED BY:
APPROVED BY:
________________
___________________
___________________
___________________
Contractor
Consultant
Project Manager
Engineer
Name:
Name:
Name:
Name:
Date:
Date:
Date:
Date:
Revision 2.2
5 February 2014
Page 68 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
JMS
JOINT MEASUREMENT SHEET
Contract No.
Project Title
Claim No.
School
Chainage 150 to 200
16.0
7.2
1200 x 1200 x 1000 (H)
7.7
1200 x 1200 x 1650 (H)
key
brick sump
13.9
900mm pipe culvert
block drain
1200 x 1200 x 1650 (H)
cascading
4.8
900 x 900 x 1500 (H)
900 x 1000 x 1100 (H)
11.5
Item to dismental
9.0
existing brick sump
25.0
12.2
key
brick sump
600mm pipe culvert
excavation work,concrete base
and brick laying
excavation work & concrete base
ITEM
UNIT
QTY
Block drain
DESCRIPTION
40.00
Cascading
7.20
900mm pipe culvert
13.90
1200 x 1200 x 1000 (H) brick sump
no
1200 x 1200 x 1650 (H) brick sump
no
900 x 900 x 1500 (H) brick sump
no
900 x 1000 x 1100 (H) brick sump
no
600mm pipe culvert
12.20
excavation work,concrete base & brick
9.00
10
excavation work & concrete base
25.00
SUBMITTED BY:
EVALUATED BY :
REMARKS
Qtel Contract , refer SK03
Temporary Road Contract , refer SK03
VERIFIED BY:
APPROVED BY:
________________
___________________
___________________
___________________
Contractor
Consultant
Project Manager
Engineer
Name:
Name:
Name:
Name:
Date:
Date:
Revision 2.2
Date:
2 OF 2
5 February 2014
Date:
Page 69 of 181
MEASUREMENT SHEET
Revision 2.2
5 February 2014
Page 70 of 181
Table for Remeasurable Contract
Ref
Scenario
Rate included in
BoQ?
Description
Written
instruction
required?
Yes
Action required?
Payment
To prepare VO.
To get approval of new rate
and prepare VO.
Payment will be made after
approval of VO based on
progress of work on site.
New / additional / varied item (not part of This item not shown in the contract
original scope)
documents, i.e. the drawings /
specifications due to:
a) changing the character or quality or
kind of any work
b) change the levels, lines, position and
dimensions
c) additional work of any kind
d) Increase / decrease quantities of works
shown on contract documents
e) omission of items shown on contract
documents
Yes
No
Original contract item - quantity less than Works shown on the contract documents,
BoQ
i.e. the drawings / specifications & BoQ
Yes
No
No VO Required
Payment will be made based
on actual work completed on
site, joint-measured by the
Consultant and the
Contractor.
Original contract item - quantity more
than BoQ
Works shown on the contract documents,
i.e. the drawings / specifications & BoQ
due to actual site condition / operation
and not because of engineer's instruction
Yes
No
Payment will be made based
on actual work completed on
site joint-measured by the
Consultant and the
Contractor.
Original contract item - no quantity
inserted in the BoQ
Yes
No
Original item - no item in the BoQ
Works shown on the contract documents,
i.e. the drawings / specifications & but no
quantity in BoQ (Rate only item in the
BoQ)
Works shown on the contract documents,
i.e. the drawings / specifications but not
in BoQ
To prepare either:a) VO showing anticipated
completion quantities (if final
quantities cannot be
determined at the time)
b) VO with estimated quantities
and measured as works
progress.
No
No
VO
Variation order contains a schedule of items with final quantities and agreed / BoQ rates.
PVO
Provisional Variation order contains a schedule of items with anticipated completion quantities and agreed / BoQ rates.
Quantities within the PVO will be remeasured at the completion and Final VO will be prepared.
The purpose of the PVO is to formally adjust PWA budget for payment and monitoring & controlling.
Revision 2.2
5 February 2014
To get approval of new rate
Items
a)VO with estimated quantities
and measured as works
progress
Page 71 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
Quantity Summary
Commitment No. :
Project Title :
BOQ Item Ref.
: 9.10
Item Description
: Bituminous spray prime coat
Unit
:m
Previous Certified
Quantity
Road A Area 1 from CH. 1.000 to 2.275
xxxx
Road B Area 1 from CH. 1.000 to 2.275
xxxx
Current Certified
Quantity
Road A Area 1 from CH. 2.275 to 3.275
xxxx
Road B Area 1 from CH. 2.275 to 3.275
xxxx
xxxx
SUBMITTED BY:
__________________________
Contractor
Name:
Date:
Revision 2.2
Cumulative Certified
Quantity
xxxx
xxxx
APPROVED BY:
__________________________
Consultant
Name:
Date:
5 February 2014
Page 72 of 181
PUBLIC WORKS AUTHORITY
2. PAYMENTS FOR CONTRACT
ITEMS LUMP SUM
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 73 of 181
2.
VALUATION OF WORKS LUMP SUM ITEMS
2.1 Purpose of this Procedure
To emphasize the requirements which are to be fulfilled to process the payment in
regards to the Contract Items as listed herein. These requirements shall be an addition to
the Payment Control Checklist.
2.2 Provisional Sums / Contingencies
The expenditure of Provisional Sums or Contingency Sums set out in the BOQ shall be
instructed by the Engineer under a variation order and maybe undertaken by:(a) Main Contractor (awarded existing Contract)
(b) Nominated Sub-Contractor (work to be done by third party)
The work is to be treated as a Variation to the Contract and the varied amount to be
valued in accordance to the procedures as stipulated in the Contract. The Variation Order
(VO) shall be prepared for approval and the approved VO is to be attached in the
payment application for payment.
2.3 Prime Cost Items
All sums in the BOQ which are stated as Prime Cost Items shall be utilized upon
instruction by the Engineer. The Engineer may request the Contractor to submit
quotations and invoices for the accepted works in connection with expenditure in respect
of the prime cost items. The work to be treated as a Variation to the Contract and the
varied amount to be valued in accordance with the procedures as stipulated in the
Contract. The Variation Order (VO) shall be prepared for approval and the approved VO is
to be attached in the payment application for payment.
2.4 Payment to Nominated Sub-Contractors (NSC)
The following are items to be considered before issuing the Payment Certificate which
include payment related to NSC.
(a) Contractor has paid the sum to the NSC before applying for the said sum from the
PWA
The Contractor has to submit proof that all payments in respect of the works or
goods of such NSC have been paid by the Contractor and all related supporting
documents shall be attached in the payment application.
Revision 2.2
5 February 2014
Page 74 of 181
(b) Contractor unable to pay to the NSC with reasonable cause
In the case of Contractor unable to pay the NSC, then the amount shall be paid direct
by PWA to such NSC upon the Certificate of the Engineer and to deduct by way of setoff the amount so paid by PWA from any sums due from the PWA to the Contractor.
Where the Engineer has certified and the PWA has paid direct as aforesaid the
Engineer shall in issuing any further certificate in favor of the Contractor deduct from
the amount thereof, the amount paid direct..
2.5 Payment for Variation Works
Payment for Variation Works which have been completed on site shall be certified as
follows :(a) Variation Order Approved by the PWA
To be paid 100% of the value of the Variation Order
(b) Variation Order in process with the PWA
(i) 80% of the value of the attached Variation Order for content which includes unit
rates and items listed in the Original Contract B.O.Q or
(ii) 60% of the value of the Variation Order which includes new unit rates and new
items that were not contained in the Original Contract B.O.Q
(iii) 80% of the value of the Variation Order where the VO has mixture of works that
have unit rate and items in B.O.Q plus new items of works that were not
contained in the Original Contract B.O.Q
The amount certified for Variation works shall be substantiated with relevant documents
i.e Site Instruction, Variation Order Form, Bill of Quantities, measurement sheets,
purchase orders, delivery notes etc.
2.6 Materials on /off Site
(a) Materials on site
The materials delivered to the site shall be paid at 70% of the original invoice amount
or any other percentage stated in the Contract. The amount certified to be supported
by relevant supporting documents i.e original invoice or certified true copies of the
invoice, delivery notes and Material test certificates. Refer to attached template F.
Notwithstanding the percentage of materials to be paid based on the invoice
amount, the quantity of the said materials shall be adjusted in the subsequent
payments where the materials are used or fixed and incorporated into the
permanent works. The used or installed materials shall be evaluated under the
Revision 2.2
5 February 2014
Page 75 of 181
progress of work on site. Materials for the temporary works like formwork shall not
be paid for as materials on site.
(b) Materials off Site
If the Contract allowed the Contractor/Supplier to claim for materials off-site, then
the claim for this item shall be supported by the documents as required under the
Contract which the submission shall not limited to the following :(1) Vesting Certificate
(2) Insurance Policy which covers the materials during the transportation whether
through land, sea or freight shipment, at the port during the custom clearance
and any transmission to locate the materials before deliver to the site.
(3) If the materials required for inspection and need a factory visit, then the claim
shall be submitted with Report on the materials assessed and recommended for
payment including the insurance coverage as mentioned in Item (2) above.
(4) A material guarantee.
(5) Where there is no provision in the contract to materials off site, the contractor
may submit a request to PWA through the Engineer for material off site to be
paid under contract. If granted, items 1 to 4 should be required from the
Contractor.
The materials off site can only be considered for payment if the materials are
completely ready for shipment and installation.
Revision 2.2
5 February 2014
Page 76 of 181
PUBLIC WORKS AUTHORITY
3. PAYMENT & MEASUREMENT
FOR DRAINAGE CONTRACTS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 77 of 181
PAYMENT & MEASUREMENT FOR DRAINAGE CONTRACTS
3.1 Introduction
The Consultant shall ascertain the works completed on site up to a the period ending
date in the payment certificate. Accuracy of the total amount certified by the Engineer
up to a certain period ending date depends on t he certified quantities by the
Engineer. The quantities are measured from the Contractors issue drawings and are
deemed as estimated quantities. Where the Contractor has produced the shop/asbuilt drawings there shall be us ed for re-measurement and t he actual quantities
determined. These actual quantities shall replace the estimated quantities.
Construction issue drawings can be used for valuation of the works as described
below. Once the approved shop/As-built drawings are produced be t he Contractor
then these shall be used to re-measure the actual quantities.
To determine the quantity to be certified for a particular item on a particular date, it is
important to prepare proper re-measurement sheets and backup calculation sheets.
The items re-measured under BOQ/variation item should be considered. (E.g. Items
such as excavation, disposal of excavated material, backfilling, pipes, etc. are
measured under pipes according to CESMM3. (The percentage breakdown of the
unit rates into the various operations as mentioned above shall be mutually agreed
between the contractor and the Engineer for the B.O.Q / variations of the works prior
to the first application for payment)
3.2 Purpose
The purpose of this Guidance is to explain how the measurement sheets and backup
calculation sheets are prepared for some selected items to enhance the accuracy of
the certified amount by the Consultant in a drainage work contract.
3.3 Guidance Measurement/Calculation Sheets
a. Pipes (Appendix-1 and 2)
As the works such as excavation, pipes, backfilling, etc. are measured under Pipes,
as a composite item, the percentage of each of these items should be shown in the
measurement sheet. The percentages shown in the Appendix-1 are to be agreed by
the Contractor and the Consultant prior to measuring the work of Pipes.
To calculate the work of a pipe run between two locations, the work operation
percentage of each item shown under Pipes should be assessed and shown in the
re-measurement sheet.
E.g. Length of completed pipework between MH1 and MH2 = Length between MH1
and MH2 x ((percentage completion of excavation and di sposal of excavated
materials x 40%) + (percentage completion of laying and j ointing of pipes x 20%) +
(percentage completion of backfilling x 35%) + (percentage completion of compliance
testing of pipelines x 5%))
After assessing the progress of work of all the pipe runs, the cumulative work done to
date is calculated.
Revision 2.2
5 February 2014
Page 78 of 181
In addition to Appendix-1, Appendix-2 is prepared to monitor the total quantity of
pipes between two locations or in a particular area. As the depth of the pipe is not
constant between two locations, the pipe between two locations may not be
measured under one BOQ/variation item. If the certified pipe quantities are shown in
Appendix-2, the total claimed quantity in a particular area can be controlled. The
length of pipes claimed cannot exceed the total length between two manholes.
b. Manholes (Appendix-3)
Items such as excavation, blinding, base slab, GRP walls, etc. in a manhole and the
percentage of each of these operations should be s hown in the re-measurement
sheet. The percentages shown in the Appendix-3 are to be agreed by the Contractor
and the Engineer prior to measure the work progress of manholes and prior to the
first application for payment.
To calculate the work of a manhole, the work percentage of each item shown under
manholes should be assessed and s hown in the measurement sheet. After
assessing the progress of work of all the manholes, the cumulative work done to date
is calculated.
c. Calculation Sheet (Appendix-4)
Calculation sheets should be pr ovided to show how the pipe length, pipe depth,
manhole depth, etc. are calculated.
Revision 2.2
5 February 2014
Page 79 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
PIPES
Measurement Sheet
Commitment No. :
Project Title :
Payment Certificate No :
Period Ending Date
BOQ Item Ref.
Item Description
Unit
Location
:
: I123
: Clay pipes to BS 65 with spigot and socket flexible joints nominal bore 225mm
in trenches. Depth: 1.5 - 2 m.
:m
Length
Excavation and
disposal of
Laying and
excavated
jointing of pipes
materials
40%
%
Backfilling
20%
Length
Length
Compliance
testing of
pipelines
35%
%
Length
Total
Length
5%
%
Length
Between manholes
MH1 and MH2
Between manholes
MH2 and MH3
Between manholes
MH3 and MH4
Cumulative Work Done to Date (m)
SUBMITTED BY:
__________________________
Contractor
Name:
Date:
Revision 2.2
APPROVED BY:
__________________________
Consultant
Name:
Date:
5 February 2014
Page 80 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
PIPES SUMMARY
Pipes Length Summary Sheet
Commitment No. :
Project Title :
Payment Certificate No
Period Ending Date
Unit
:
:
:
Item Description
BOQ Item
Ref.
Clay pipes, nominal bore 225mm in trenches. Depth: 1.5 - 2 m.
I123
Clay pipes, nominal bore 225mm in trenches. Depth: 2 - 2.5 m.
I124
Clay pipes, nominal bore 225mm in trenches. Depth: 2.5 - 3 m.
I125
Clay pipes, nominal bore 225mm in trenches. Depth: 3 - 3.5 m.
I126
Between
Between
Between
manholes MH1 manholes MH2 manholes MH3
and MH2
and MH3
and MH4
Total Length
Total length claimed to date
Total length between manholes
SUBMITTED BY:
__________________________
Contractor
Name:
Date:
Revision 2.2
APPROVED BY:
__________________________
Consultant
Name:
Date:
5 February 2014
Page 81 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
Manholes
Measurement Sheet
Commitment No. :
Project Title :
Payment Certificate No
Period Ending Date
BOQ Item Ref.
Item Description
Unit
MH No.
:
:
:
:
:
nr
Excav.
Blinding
Base
Slab
GRPWalls
15%
5%
10%
30%
GRP
Wall
Tanking
Benching Concrete
2%
10%
5%
Cover
Slab
Backfill
DI Frame
Total
10%
10%
3%
100%
MH.1
MH.2
MH.3
MH.4
Cumulative Work Done to Date (nr)
SUBMITTED BY:
__________________________
Contractor
Name:
Date:
Revision 2.2
APPROVED BY:
__________________________
Consultant
Name:
Date:
5 February 2014
Page 82 of 181
- COMPANY'S NAME -
COMPANY'S
LOGO
Calculation sheet
Dimension Calculation Sheet
Commitment No. :
Payment Certificate No
Period Ending Date
Unit
Manhole No.
Ground
Level
Project Title :
:
:
:
Cover
Level
Down
Stream
Grad
Down
Stream
Invert
Up
Stream
Invert
Down
Stream
Length
Chain
Pipe Size
Manhole
Int. Dia
Pipe
Length
Bed
Length
Pipe
Depth
Manhole
Depth
MH1
MH2
MH3
MH4
MH5
SUBMITTED BY:
__________________________
Contractor
Name:
Date:
Revision 2.2
APPROVED BY:
__________________________
Consultant
Name:
Date:
5 February 2014
Page 83 of 181
PUBLIC WORKS AUTHORITY
4. PAYMENT & MEASUREMENT
FOR ROAD CONTRACTS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 84 of 181
MEASUREMENT AND PAYMENT GUIDE FOR ROAD WORKS
Notes:
1. This guide summarizes some important elements in re-measurement and payment of road works, which are to be considered by the PWA, the Consultant and the Contractors.
2. Details given here shall not limit or supersede the respective details mentioned in the Contract and are intended to be used as a general guide only. The Consultant and the PWA shall ensure that work is remeasured
and paid exactly in accordance with the Contract, irrespective of this guide.
3. This guide shall apply to the BOQs prepared based on CESMM3 and with amendments to the same to suite the Qatar Construction Industry.
4. Any discrepancy between this guide and Preamble to Contract BOQ, CESMM3 and any other Contract Document, then the said Preamble, CESMM3 and other Contract Documents shall prevail.
ITEM
DESCRIPTION
General Site
Clearance
UNIT
ha
Work Operations
Removal of
items
nr/sum
Clearing and Grubbing
Excavation
Disposal of excavation
materials
Disposal of
excavation materials
Backfilling
Revision 2.2
Excavation
Filling
m3
Start sides of
excavations
Working space
Subbase
m3
Asphalt
m2
m2
Supply of Materials
Supply of Materials
Place, Spread & Level
Place, Spread & Level
Supply of
Materials
Lay
Watering
Watering
Compaction
Compaction
Compaction
Joints
5 February 2014
Prime Coat &
Tack Coat
m2
Supply of Materials
Spray
Kerbs
Paving blocks
m2
m
Excavation
Disposal of
excavation materials
Preparation of
surfaces
Concrete
Formwork
Reinforcement
Mortar beds
Supply & installation
Joints & cutting
Preparation of
surfaces
Granular sub base
Sand bedding
Joints & cutting
Supply & installation
Page 85 of 181
MEASUREMENT AND PAYMENT GUIDE FOR ROAD WORKS
Notes:
1. This guide summarizes some important elements in re-measurement and payment of road works, which are to be considered by the PWA, the Consultant and the Contractors.
2. Details given here shall not limit or supersede the respective details mentioned in the Contract and are intended to be used as a general guide only. The Consultant and the PWA shall ensure that work is remeasured
and paid exactly in accordance with the Contract, irrespective of this guide.
3. This guide shall apply to the BOQs prepared based on CESMM3 and with amendments to the same to suite the Qatar Construction Industry.
4. Any discrepancy between this guide and Preamble to Contract BOQ, CESMM3 and any other Contract Document, then the said Preamble, CESMM3 and other Contract Documents shall prevail.
ITEM
DESCRIPTION
UNIT
Work Operations
Traffic Signs
nr
Excavation
Disposal of excavation
materials
Road Marking Lines, Letters
and Shapes
Pipes in trenches
m/nr/m2
m
Stencils
Excavation
if m2 - net area of Disposal of excavation
paint is measured materials
Manholes
Ducts in trenches
nr
Excavation
Excavation
Disposal of excavation
materials
Disposal of excavation
materials
Upholding sides of
excavation
Beddings
and
Surrounds
m
Excavation
Disposal of
excavation
materials
Street Lighting &
High Mast
Lighting Columns
nr
Columns
Luminaires
Upholding sides of
excavation
Upholding sides of
excavation
Upholding sides of
excavation
Backfilling
Preparation of surfaces
Foundations
Preparation of
surfaces
Backfilling
Backfilling
Upholding
Fittings
sides of
excavation
Preparation of surfaces Preparation of Internal cables
surfaces
Backfilling
Backfilling
Bolts and Nuts
Supporting posts
Supply & lay
Concrete
Supply & lay
Joints
Concrete
Formwork
Joints & cutting
Marker tapes
Formwork
Reinforcements
Joints & cutting
Fittings
Finishes
Joints
Finishes
Waterproofing
Ladders and step iron
Internal pipes
Covers & cover frames
Marker tapes
Reinforcements
Supply & installation
Revision 2.2
5 February 2014
Cables - In
trenches
Cables - In ducts
and conduits
m
Excavation
Disposal of excavation
materials
m
Cleaning ducts
Conduits and fittings
Upholding sides of
excavation
Supply & lay
Preparation of
surfaces
Backfilling
Jointing
Supply & installation Supply & lay
Termination &
connections
Draw wire
Jointing
Terminations &
connections
Warning tapes
Protection tiles
Page 86 of 181
PUBLIC WORKS AUTHORITY
5. PAYMENT & MEASUREMENT
FOR BUILDING CONTRACTS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 87 of 181
PAYMENTS FOR LUMP SUM CONTRACT ITEMS IN BUILDING PROJECTS
5.1 Purpose of the Report
To maintain uniformity among all the building contracts payment procedures for
Contractors
5.2 Procedure for Payment Recommendations
(a) determination of progress of construction items
(i) Progress percentage (%) shall be determined by the Consultant based
on the following formula, where the actual work done (actual quantity
completed) at site against the total contract quantity taken from the
contract drawings (total contracted quantity), but not from the total
quantity stated in the BOQ.
Progress % =
Actual Quantity completed on site (A) x 100
Total Contract Quantity (B)
Where,
shall be either the work-done quantity measured from the
contract/shop drawings or joint site measurement.
The purpose of this formula is to determine actual progress of
construction items where quantity errors evident in the BOQ.
(b) BOQ items
(i) Preliminaries
-the preliminary items shall be broken down to fixed charges and time
related charges. Fixed charges may be further broken down to
mobilization & demobilization.
Accordingly, any preliminary item shall include one or more of the
following components within its amount.
a)
b)
c)
Time related charges [ cost per month x contract duration (
months)]
Fixed Charges - Mobilization
Fixed Charges - Demobilization
Consultant may request Contractor to submit the relevant breakdown of
preliminary item (s) in a tabular format as shown in Template A3.
Revision 2.2
5 February 2014
Page 88 of 181
- Time related charges shall be certified against the time
incurred/spent
- Fixed charges shall be certified either,
against the actual cost incurred
If the actual cost incurred is less than the relevant fixed charges in
the above breakdown, the Consultant may certify the actual cost
incurred + (balance between actual cost and allowed cost in the
item x % progress of the permanent works).
Or
against the amount in the breakdown if it is difficult to determine
the actual cost.
(ii) Work items (with unit quantity provisional quantity)
(c) Any item with Provisional Quantity shall be re-measured and paid.
(d) The Consultant may certify a quantity more than the BOQ quantity as
a result of re-measurement.
(e) Measurement sheet shall always be attached to the interim payment
for the work-done during the particular month.
iv)
Contractors design portions
a. Procedure set out in the BOQ items Lump sum items [Section
2.0.(b) (ii)] shall be followed.
b. Design approval by the PWA, as decided by the PWA
representative, shall be attached as backup and submitted to
PWA.
Revision 2.2
5 February 2014
Page 89 of 181
Notes:
1. If any of the component of the item is not required or seperately measured, progress for that component shall be considered as fully completed within the item.
Eg: Main item - Excavation
Sub item - dewatering (
If dewatering measured separately or dewatering is not required, Qty % should be taken as 100%
2.
Y = A or B or C or D .
Y1 = Actual quantity done at site/ Total quantity in contract drawings
Y2 = Y1 x Y
3. Consultant shall prepare a breakdown for new items not covered by this document, to show how progress is calculated.
Revision 2.2
5 February 2014
Page 90 of 181
A1. Excavation
BOQ Ref
Description
Excavation (A=55%)
Qty (%)= A1 Progress (%) = A2
A.1
Dewatering (B=25%)
Qty (%) = B1 Progress (%) = B2
Earth Work Supports (C=10%)
Qty (%) = C1 Progress (%) = C2
Trimming & Compaction (D=10%)
Qty (%) = D1 Progress (%) = D2
Total Progress
for Excavation
(A1+B1+C1+D1)
Excavation
A2. Disposal
BOQ Ref
Description
Disposal (A=100%)
Qty (%)= A1 Progress (%) = A2
A.2
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Disposal
(A1+B1+C1+D1)
Disposal
A3. Filling
BOQ Ref
Description
Filling (A=100%)
Qty (%)= A1 Progress (%) = A2
A.3
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Filling
(A1+B1+C1+D1)
Filling
A4. Dewatering (if measured separately)
BOQ Ref
Description
Dewatering (A=100%)
Qty (%)= A1 Progress (%) = A2
A.4
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Dewatering
(A1+B1+C1+D1)
Dewatering
Revision 2.2
5 February 2014
Page 91 of 181
B1. Concrete
BOQ Ref
Pouring (A=70%)
Description
Qty (%)= A1 Progress (%) = A2
B.1
Curing (B=20%)
Testing (C=10%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Concrete
(A1+B1+C1+D1)
Concrete
B2. Form Work
BOQ Ref
Fixing (A=70%)
Description
Qty (%)= A1 Progress (%) = A2
B.2
Removing (B=30%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Fixing (B = 20%)
Protective coatings for continuing
r/f (5%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Form Work
(A1+B1+C1+D1)
Form Work
B3. Reinforcement
BOQ Ref
Bar Bending (A=75%)
Description
Qty (%)= A1 Progress (%) = A2
B.3
Qty (%) = D1 Progress (%) = D2
Total Progress
for
Reinforcement
(A1+B1+C1+D1)
Reinforcement
When barbending is considered, material on site for reinforcement should not be considered for the same portion.
B4. Lintels (if measured separately)
BOQ Ref
Description
Form work Fixing (A=18%)
Qty (%)= A1 Progress (%) = A2
B.4
R/f fixing (B = 25%)
Concrete Pouring (40%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Protection Boards (20%)
Dampproof membrane (50%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Curing (10%)
Form Work Removal (7%)
Qty (%) = D1 Progress (%) = D2
Qty (%) = E1
Qty (%) = D1 Progress (%) = D2
Total Progress
for Dampproofing
(A1+B1+C1+D1)
Progress (%) = E2
Total Progress for
Lintels
(A1+B1+C1+D1+E1)
Lintels
B5. Damp-proofing (if measured as one item)
BOQ Ref
Description
Bituminous painting (A=30%)
Qty (%)= A1 Progress (%) = A2
B.5
Damp proofing
If these components are measured separately, those shold be considered separately.
Revision 2.2
5 February 2014
Page 92 of 181
C1. Block/ Brick Works
BOQ Ref
Description
Brick/ Block Work (A=100%)
Qty (%)= A1 Progress (%) = A2
C.1
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Block/Brick
(A1+B1+C1+D1)
Brick/Block
C2. Waterproofing to wet areas
BOQ Ref
Description
Levelling Screed (A=20%)
Qty (%)= A1 Progress (%) = A2
C.2
Waterproofing (A=60%)
Qty (%) = B1 Progress (%) = B2
Protective Screed (A=20%)
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for
Waterproofing
(A1+B1+C1+D1)
Waterproofing
Revision 2.2
5 February 2014
Page 93 of 181
D1. Flat roofing
BOQ Ref
Description
Leveling screed (A=10%)
Qty (%)= A1 Progress (%) = A2
D.1
Waterproofing (B=70%)
Qty (%) = B1 Progress (%) = B2
Top Finishing (20%)
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Flat Roofing
(A1+B1+C1+D1)
Flat Roofing
D2. Pitched Roofing (steel)
BOQ Ref
Description
Fabrication of Roof frame
(A= 40%)
Qty (%)= A1 Progress (%) = A2
D.2
Erection of roof frame (B=10%)
Qty (%) = B1 Progress (%) = B2
Roof Covering (35%)
Qty (%) = C1 Progress (%) = C2
Fixing Ridge/ Hip cap (10%)
Qty (%) = D1 Progress (%) = D2
Fixing Facia (5%)
Qty (%) = D1 Progress (%) = D2
Total Progress
for Pitched Roof
(A1+B1+C1+D1)
Form Work
Revision 2.2
5 February 2014
Page 94 of 181
E1. Strutural Steel Elements
BOQ Ref
Description
Fabricating including protective
coatings (A=60%)
Qty (%)= A1 Progress (%) = A2
E.1
Erecting (B=30%)
Qty (%) = B1 Progress (%) = B2
Fire casings (C=10%)
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Strutural
steel
(A1+B1+C1+D1)
Structural Steel
Revision 2.2
5 February 2014
Page 95 of 181
F1. Doors & Windows
BOQ Ref
Description
Fixing frame (A=30%)
Qty (%)= A1 Progress (%) = A2
F.1
Fixing door/window leaves (B=
60%)
Fixing other door/ window
accessories (C=10%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for Doors &
Windows
(A1+B1+C1+D1)
Doors & Windows
Revision 2.2
5 February 2014
Page 96 of 181
G6.Suspended ceilings
BOQ Ref
Description
Fixing runners (A=20%)
Qty (%)= A1 Progress (%) = A2
G.6
Fixing panels (80%)
Qty (%) = B1 Progress (%) = B2
Qty (%) = C1 Progress (%) = C2
Qty (%) = D1 Progress (%) = D2
Total Progress
for suspended
ceiling
(A1+B1+C1+D1)
Suspended ceiling
Revision 2.2
5 February 2014
Page 97 of 181
PUBLIC WORKS AUTHORITY
6. PAYMENT FOR CONSULTANT
DEDUCTED FROM THE
CONTRACTOR
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 98 of 181
PAYMENT FOR CONSULTANT DEDUCTED FROM THE CONTRACTOR
6.1 Subject:
The subject of this procedure is the methodology in which Payment is to be made for the
Supervision Consultant where the contractor is in delay and where the period of delay is
caused by the Contractor and penalties apply.
ie,
EOT granted
Commencement
of contract
Contract
completion
date
Contractor delay period
Revised
completion
date
Actual
completion
date
The value of fees for the supervision consultant in the Contractor delay period is to be
inserted into deduction of additional supervision charge for Consultants/Sub-Consultants
in the Payment Certificate. A note is to be stated at the bottom of the Payment Certificate
that this sum is to be pai d to the Supervision Consultants to Bank and B ank account
details. All the supporting documents must be at tached with the Payment Certificate as
stated in the check lists.
6.2 Method of Payment:
The Recommendation for payment to be pr epared from the contractor contract and t he
amount to be included in the filled for Deduction of additional Supervision charge for
Consultants / Sub Consultants at the recommendation for payment.
A note to be m entioned at the bottom of the recommendation for payment stated that this
payment to be made for the consultant, bank account no,
All the supporting document must be at tached with the Recommendation for payment as
stated in the related check lists.
Revision 2.2
5 February 2014
Page 99 of 181
PUBLIC WORKS AUTHORITY
7. PAYMENT FOR CONTRACTOR
DEDUCTED FROM THE
CONSULTANT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 100 of 181
7 PAYMENT FOR CONTRACTOR DEDUCTED FROM
THE CONSULTANT
7.1 Subject:
The subject of this procedure is the methodology in which refunding back to the Contractor.
The amounts deducted from his account and paid previously to the Consultant for supervision
services.
This may occur where subsequent extension of time for revised completion dates have been
granted under the contract.
7.2 Method of Payment:
Once the completion certificate has been issued under the construction contract, a c hange
addendum should be prepared for the consultant to add the total amount deducted from the
contractor for supervision services provided during the Contractor delay period. Once the
change addendum is approved and the system updated a recommendation for payment can
be prepared under the consultant contract. The recalculated amount for the Consultant can
be paid and any amount to be returned to Contractor is determined.
A note is to be mentioned at the bottom of the recommendation for payment stating that this
sum is to be made to the Contractor, bank account no,
All the supporting document must be at tached with the Recommendation for payment as
stated in the related check lists.
Revision 2.2
5 February 2014
Page 101 of 181
PUBLIC WORKS AUTHORITY
8. RECOVERY OF THE ADVANCE
PAYMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 102 of 181
8 DESCRIPTION OF RECOVERY
(RE-PAYMENT) THE ADVANCE PAYMENT
8.1 Amount of Advance Payment:
(a) Contract Value < QR 50 Million, The Advance payment shall be 20% of
the Contract price limited to a maximum of QR 5,000,000 or
(b) Contract Value > QR 50 Million, The Advance payment shall be 10% of
the Contract price or
(C) The advance payment maybe stated as an amount in the contract and
not as percentage.
An advance payment certificate will be i ssued when the contractor submits
his Performance bond, invoice, Bank guarantee for the advance payment,
and all necessary insurances are in place under the contract.
The construction contract may not have been signed & executed at the time
the advance payment is certified and paid.
8.2 Recovery (Re-payment) the Advance Payment:
The percentage for recovery of the advance payment shall be stated in the
contract. Recovery of the advance payment shall be t hrough each interim
payment certificate until all the advance payment is recovered, and shall be
recovered within the time for completion and not any extended period to the
time for completion. Where the contract is terminated full recovery of any
balance of advance payment will be required at date of termination.
Revision 2.2
5 February 2014
Page 103 of 181
PUBLIC WORKS AUTHORITY
9. INCOME TAX REQUIREMENTS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 104 of 181
9 INCOME TAX REQUIREMENTS
The income tax requirements as per the Circular 02/2011 and the letter of
Finance & Administration Affairs Department dated 03/11/2011:
Companies has a commercial registration in Qatar:
The Valid Income Tax Card required for all companies (Qatari or nonQatari).
Companies or persons not registered in Qatar:
No financial limit for the contracts, the final RP will not be process
unless the company or the person submit valid Income Tax Card.
Revision 2.2
5 February 2014
Page 105 of 181
PUBLIC WORKS AUTHORITY
APPENDICES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 106 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A:
TEMPLATES / FORMS APPLIED
TO ALL PAYEES
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 107 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A1
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 108 of 181
TRANSMITTAL FORM FOR PAYMENT
RP TRACKING SHEET
Contract/Payment Details
Project Title:
Contractor:
RP No.:
Commitment No:
Work done as of:
Contract Type:
Application Date:
Payment Type:
Appln. Received by Engineer:
Payment Due Date:
Payment Period:
Budget Ref.:
Document No.:
Document Progress Record
Details
Name
Designation
Date In
Date Out
Signature
Contractor
Prepared by:
Supervising Consultant
Recommended by:
PMC/MC Quantity
Surveryor
Checked by:
PMC/MC Programme
Director
Recommended by:
Reviewed by:
Ashghal EBSD
Checked by:
Ashghal Representative
Approved by:
Ashghal Dept.Manager
Approved by:
Infrastructure Affairs
Director
Processed by:
Ashghal Finance
& Adm Dpt.
Details of Digital Register
Program
Staff Name
Designation
Date
Signature
Tracking System
PCM
Revision 2.2
5 February 2014
Page 109 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A2
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 110 of 181
STATE OF QATAR
Public Works Authority
PWA
PAYMENT CERTIFICATE
Payment Certificate No. :
Budget Ref.:
Period Ending :
Date :
Payment Type :
Payment for
Advance/First
Contractor
Interim
PC
Consultant
Final
Supplier
Project Title
Project ID
Original Contract Value: QR
Commitment No.
Total Value of Addenda/Variation to date: QR
0.00
Contractors
Adjusted Sum :QR
0.00
Consultant
Payable by letter of credit
0.00
Last Addendum / Variation Issue No.
Work ValueTo Date QR
Materials on Site QR
0.00
Total QR
0.00
Total Deductions : QR
0.00
Total deduction of additional Supervision Consultant QR
0.00
Deduction : (* to be subtracted)
*
Retention % (From Total Work Value To Date) QR
* Penalties
0.00
0.00
Retention from Previous Certificate QR
0.00
New Retention QR
0.00
Retention to be Released QR
0.00
QR
0.00
QR
0.00
* Penalties Under Adjustments
0.00
Deduction of additional Supervision charge for Consultants / Sub Consultants
(Clause . Of conditions of contract)
Consultant / Sub Consultant / Sub Contractor
(* To be paid to Consultant and subtracted from the payment of Contractor)
Advance Payment :
Total Consultant Fee to date QR
0.00
Total Consultant Fee paid previously QR
0.00
Total Consultant Fee for this period QR
0.00
(* to be added)
Advance Payment No.1 . % (from Contractual Amount) QR
0.00
Total Recovery of Advance Payment no.1 (.. from Work Value To Date) QR
0.00
*Unrecovered from Advance Payment No.1 QR
0.00
Previously Recovered from Advance Payment no.1 QR
0.00
Recovered by this Certificate from Advance Payment No.1 QR
0.00
Additional Advance Payment No.2 ..% (from remaining Contract Amt... Qr) QR
0.00
Total Recovery from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.2 QR
0.00
Previously Recovered from Advance Payment no.2 QR
0.00
Recovered by this Certificate from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.1 & 2 QR
0.00
*QR
0.00
Total sum certified by this certificate QR
0.00
Total sum certified by previous certificates QR
0.00
Net Sum Certified by this Certificate QR
Supervision Consultant (if applicable)
Project Management Contract/The Engineer
PWA - EBSD (Payments Unit):
Name :
Name :
Name :
Signature:
Signature:
Signature:
Date :
PWA - Representative/Area Engineer
Date :
Date :
PWA - Head of Section (if applicable)
0.00
PWA - Department Manager
Name :
Name :
Name :
Signature:
Signature:
Signature:
Date :
/
/
Date :
/
/
Date :
/
/
Note: .
.
Revision 2.2
5 February 2014
Page 111 of 181
STATE OF QATAR
Public Works Authority
PWA
PAYMENT CERTIFICATE
Payment Certificate No. :
Budget Ref.:
Period Ending :
Date :
Payment Type :
Payment for
Advance/First
Contractor
Interim
PC
Consultant
Final
Supplier
Project Title
Project ID
Original Contract Value: QR
0.00
Commitment No.
Total Value of Addenda/Variation to date: QR
0.00
Contractors
Adjusted Sum :QR
0.00
Consultant
Payable by letter of credit
0.00
Last Addendum / Variation Issue No.
Work ValueTo Date QR
Materials on Site QR
0.00
Total QR
0.00
Total Deductions : QR
0.00
Total deduction of additional Supervision Consultant QR
0.00
Deduction : (* to be subtracted)
*
Retention % (From Total Work Value To Date) QR
0.00
New Retention QR
0.00
Retention to be Released QR
0.00
QR
0.00
QR
0.00
* Penalties Under Adjustments
0.00
0.00
Retention from Previous Certificate QR
* Penalties
Deduction of additional Supervision charge for Consultants / Sub Consultants
(Clause . Of conditions of contract)
Consultant / Sub Consultant / Sub Contractor
(* To be paid to Consultant and subtracted from the payment of Contractor)
Advance Payment :
Total Consultant Fee to date QR
0.00
Total Consultant Fee paid previously QR
0.00
Total Consultant Fee for this period QR
0.00
(* to be added)
Advance Payment No.1 . % (from Contractual Amount) QR
0.00
Total Recovery of Advance Payment no.1 (.. from Work Value To Date) QR
0.00
*Unrecovered from Advance Payment No.1 QR
0.00
Previously Recovered from Advance Payment no.1 QR
0.00
Recovered by this Certificate from Advance Payment No.1 QR
0.00
Additional Advance Payment No.2 ..% (from remaining Contract Amt... Qr) QR
0.00
Total Recovery from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.2 QR
0.00
Previously Recovered from Advance Payment no.2 QR
0.00
Recovered by this Certificate from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.1 & 2 QR
0.00
*QR
0.00
Total sum certified by this certificate QR
0.00
Total sum certified by previous certificates QR
0.00
Net Sum Certified by this Certificate QR
Supervision Consultant
Name :
Name :
Project Management Contract / The Engineer
Name :
Signature:
Date :
0.00
Signature:
/
Date :
Payments Unit (EBSD):
Signature:
Name :
/
PWA Representative
Signature:
Date : /
/
Date :
/
/
Note: .
.
Revision 2.2
5 February 2014
Page 112 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A3
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 113 of 181
STATE OF QATAR
Public Works Authority
PWA
PAYMENT CERTIFICATE
Payment Certificate No. :
Budget Ref.:
Period Ending :
Date :
Payment Type :
Payment for
Advance/First
Interim
Final
PMC
GEC
Secondment
Project Title
Project ID
Original Contract Value: QR
0.00
Commitment No.
Total Value of Addenda/Variation to date: QR
0.00
Contractors
Adjusted Sum :QR
0.00
Consultant
Payable by letter of credit
0.00
Last Addendum / Variation Issue No.
Work ValueTo Date QR
0.00
Total Deductions : QR
0.00
Total deduction of additional Supervision Consultant QR
0.00
Deduction : (* to be subtracted)
* Held KPI amount (from Work Value to Date)
QR
0.00
KPI amount held from Previous certificiates
QR
0.00
New KPI amount
QR
0.00
QR
0.00
Core Team amount held from previous certficates
QR
0.00
New Core Team engaged in Schedule A1
QR
0.00
* Retention % (From Work Value To Date) QR
QR
0.00
Retention from Previous certificiates
QR
0.00
New Retention
QR
0.00
* Penalties
QR
0.00
* Penalties Under Adjustments
QR
0.00
* Core Team engaged in Schedule A1
Deduction of additional Supervision charge for Consultants / Sub Consultants
(Clause . Of conditions of contract)
Consultant / Sub Consultant / Sub Contractor
(* To be paid to Consultant and subtracted from the payment of Contractor)
Advance Payment :
Total Consultant Fee to date QR
0.00
Total Consultant Fee paid previously QR
0.00
Total Consultant Fee for this period QR
0.00
(* to be added)
Advance Payment No.1 . % (from Contractual Amount) QR
0.00
Total Recovery of Advance Payment no.1 (.. from Work Value To Date) QR
0.00
*Unrecovered from Advance Payment No.1 QR
0.00
Previously Recovered from Advance Payment no.1 QR
0.00
Recovered by this Certificate from Advance Payment No.1 QR
0.00
Additional Advance Payment No.2 ..% (from remaining Contract Amt... Qr) QR
0.00
Total Recovery from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.2 QR
0.00
Previously Recovered from Advance Payment no.2 QR
0.00
Recovered by this Certificate from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.1 & 2 QR
0.00
*QR
0.00
Total sum certified by this certificate QR
0.00
Total sum certified by previous certificates QR
0.00
Net Sum Certified by this Certificate QR
PMC / The Engineer
PWA - EBSD (Payments Unit):
Name :
Name :
Signature:
Date :
0.00
Signature:
/
PWA - Representative (if applicable)
Date :
PWA - Head of Section (if applicable)
/
PWA - Department Manager
Name :
Name :
Name :
Signature:
Signature:
Signature:
Date :
/
/
Date :
/
/
Date :
/
/
Note: .
.
Revision 2.2
5 February 2014
Page 114 of 181
STATE OF QATAR
Public Works Authority
PWA
PAYMENT CERTIFICATE
Payment Certificate No.
Budget Ref.:
Period Ending :
Date :
Payment Type :
Payment for
Advance/First
Interim
PMC
GEC
Final
Secondment
Project Title
Project ID
Original Contract Value: QR
0.00
Commitment No.
Total Value of Addenda/Variation to date: QR
0.00
Contractors
Adjusted Sum :QR
0.00
Consultant
Payable by letter of credit
0.00
Last Addendum / Variation Issue No.
Work ValueTo Date QR
0.00
Total Deductions : QR
0.00
Total deduction of additional Supervision Consultant QR
0.00
Deduction : (* to be subtracted)
* Held KPI amount (from Work Value to Date)
QR
0.00
KPI amount held from Previous certificiates
QR
0.00
New KPI amount
QR
0.00
QR
0.00
Core Team amount held from previous certficates
QR
0.00
New Core Team engaged in Schedule A1
QR
0.00
* Retention % (From Work Value To Date) QR
QR
0.00
Retention from Previous certificiates
QR
0.00
New Retention
QR
0.00
* Penalties
QR
0.00
* Penalties Under Adjustments
QR
0.00
* Core Team engaged in Schedule A1
Deduction of additional Supervision charge for Consultants / Sub Consultants
(Clause . Of conditions of contract)
Consultant / Sub Consultant / Sub Contractor
(* To be paid to Consultant and subtracted from the payment of Contractor)
Total Consultant Fee to date QR
Advance Payment :
0.00
Total Consultant Fee paid previously QR
0.00
Total Consultant Fee for this period QR
0.00
(* to be added)
Advance Payment No.1 . % (from Contractual Amount) QR
0.00
Total Recovery of Advance Payment no.1 (.. from Work Value To Date) QR
0.00
*Unrecovered from Advance Payment No.1 QR
0.00
Previously Recovered from Advance Payment no.1 QR
0.00
Recovered by this Certificate from Advance Payment No.1 QR
0.00
Additional Advance Payment No.2 ..% (from remaining Contract Amt... Qr) QR
0.00
Total Recovery from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.2 QR
0.00
Previously Recovered from Advance Payment no.2 QR
0.00
Recovered by this Certificate from Advance Payment No.2 QR
0.00
*Unrecovered from Advance Payment No.1 & 2 QR
0.00
*QR
0.00
Total sum certified by this certificate QR
0.00
Total sum certified by previous certificates QR
0.00
Net Sum Certified by this Certificate QR
0.00
PMC / The Engineer
Name :
Signature:
Date :
Name :
Signature:
/
Payments Unit (EBSD):
Name :
PWA Representative
Signature:
Date : /
/
Date :
/
/
Note: .
.
Revision 2.2
5 February 2014
Page 115 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A4
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 116 of 181
~^=
MEMORANDUM
To
From
=3-^============^^=_^=^=^d= :
=|||||||||||||||d
=
= :
=|||||||||||||||
Date
=||_k^
Reference
=_^=
=Ij_f=!^===^
=
EKKKKKKKKKKF====h=W^
=
=
= r= = I`= _f= _^= ^= j= #= af= _v^= r= I`= ^= ^= d= _d
Wj_=^=m__f=I=gk^=m^^r^=hv=_==^=__f=k^
=^=h= =^=h=g
=^k^=
=^=
=_k^L_^=`
=
K_=_j=v==_
=
K^3v^=_=gf=^j
=
=KKKKKKKKKKKK^^==`==========
=KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK=^^=`
=
Copy To:
File; :
Attachments:
Consultant Original Invoice
Copy of valid Commercial
Registration
Original Store Clearance
Consultant's Original Letter
Of Recommendation
Copy of DFA Cash flow
Maintenance Dept. Clearance
Copy Of Award Letter
Original Completion certificate
Original PDS Clearance
Copy Of Performance
Bond / Extension
Original Maintenance
Certificate
Original Request for Transfer of Fund
Copy of Retention Bond /
Extension
Original Final Account
Statement
Original RP
Bank Account Information
Letter
Original Municipality Clearance
Original Attendance Sheets
Revision 2.2
5 February 2014
Page 117 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A5
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 118 of 181
For the 1st payment of every contract the Consultant/ Supplier is require to
confirm the Banking Details stated in their covering letter for that Contract by
submitting this letter which must be prepared on a company letter head and
signed by the company owner/sponsor.
Note:
Public Works Authority
Financial & Administrative Department
Must be in Company
Letterhead
P.O. Box 22188
Doha, Qatar
Attention: Manager of the Financial & Administrative Department
Dear Sir,
SUB: BANK ACCOUNT DETAILS FOR TRANSFERING PAYMENT DUES FOR CONTRACT
No. .
Please be informed that all monies due to us in respect of this Contract (..) are
to be paid into the following Bank and Account number:
XYZ BANK
PO Box xyz
Doha, Qatar
Account No. XYZ
XYZ (Account Holder Name)
We further confirm that the above details shall not be changed without prior written
notification from us and accompanied by the above Banks written
acknowledgement of such change.
We hereby acknowledge and accept that the Government and Public Works
Authority is not responsible for any liabilities arising in respect of the transference
of monies due under this contract to the above mentioned Bank/ Account No.
Note:
Bank Stamp
Yours faithfully,
SPONSOR/OWNER (NAME)
ID CARD NO..
Enclosures:
1) Copy of ID
2) Copy of Commercial Registration
Revision 2.2
5 February 2014
Note:
These documents must
accompany the letter
Page 119 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A6
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 120 of 181
INVOICE FROM CONTRACTOR
Public Works Authority
Affair.........
PO box 22188
Note:
Must be in Company
Letterhead
Doha, Qatar
Attention: Manager..
Dear Sir,
SUB: Contract No. (Commitment No.-----------), Project Title --------------, Invoice No.---------------------Please find below the details of our Invoice No..for the month.period
ending.., amounting to QR..(QR working..)
Contract Amount
Adjusted Amount..
Certified To Date.
Previous Certified..
Remaining ...
Yours faithfully,
CONTRACTOR/CONSULTANT MANAGER
Enclosures:
1) B.O.Q.
2) Summery Sheets
3) All Supporting Documents
Revision 2.2
5 February 2014
Page 121 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A7
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 122 of 181
DAILY ATENDANCE RECORDS
Department:
Project ID:
Project Title:
Consultant:
STATE OF QATAR
PUBLIC WORKS AUTHORITY
Sheet
Personal Daily Attendance Sheet
No.
Code
Position
Date
Name
of
Day
Time
Start
Finish
Signature
Remarks
1
2
3
4
5
6
7
8
9
10
11
12
Consultants Representatives
Engineers Representatives
Revision 2.2
Name
Signature
Position
Date
Name
Signature
Position
Date
5 February 2014
Page 123 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A8
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 124 of 181
MONTHLY ATTENDANCE RECORDS
STATE OF QATAR
PUBLIC WORKS AUTHORITY
Department:
Project ID:
Project Title:
Consultant:
Legend
Personal Monthly Attendance Sheet
No. Code POSTION
NAME
From
Worked Days
PH
Public Holiday
WE
Weekend
Absent
To
Summary (Days)
Day*
Actual Start
Date
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
PH
WE
1
2
3
4
5
6
7
8
9
10
11
12
*Day-identify day above date ie S=Sundya, M=Monday, T=Tuesday, W=Wednesday, Th=Thursday, F=Friday, S=Saturday
Notes and Remarks initial Start Date for all personel must be stated in the initial and all subsequent timesheets. All days worked, including weekend and public holidays are to be reccorded. The original completed time sheet shall be submitted, backed up by the Daily Attendance Sheet for each payment application
Consultants Representative
Engineer's Representative
Revision 2.2
Name
Signature
Position
Date
Name
Signature
Position
Date
5 February 2014
Page 125 of 181
Claimed
Days
PUBLIC WORKS AUTHORITY
APPENDIX A9
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 126 of 181
PUBLIC WORKS AUTHORITY
CERTIFICATE OF COMPLETION FOR PROFESSIONAL
SERVICE AGREEMENT
PSA Title:
:
:
PSA No:
Budget Ref:
Consultant:
Agreed date for Completion as per PSA:
Actual date of Completion:
.
I certify that the whole of the services to be performed under the above mentioned agreement have been satisfactorily
completed by the consultant. I recommend that by virtue of the consultant having discharged all his obligations under
the terms of the agreement all bonds held in accordance with the terms of the agreement be now released for
cancellation.
For comments & observations:
PROJECT MANAGEMENT CONTRACT
PWA Rep./Area Eng./H.o Section
PWA Department Manager
Signature
Signature
: ..
Signature
: .
Name
: ...
Name
: .....
Name
: .
Date
Date
: .
Date
Distribution
Original:
Copies:
Finance & Administrative Department
PWA Rep./Area Eng.
Head of Section
PMC
EBSD
Revision 2.2
5 February 2014
Page 127 of 181
:
:
PUBLIC WORKS AUTHORITY
APPENDIX A10
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 128 of 181
=_^=_^=
PUBLIC WORKS AUTHORITY
=_=_
MAINTENANCE CERTIFICATE
Contract Title:
:
:
Contract No:
Budget Ref:
Contractor:
Date of Completion of Maintenance:
=h|=_|^=|g=|=_k_|==#==_|=m|`=|=^=_f=_^=_^==`=`=I^===x=1=z=62=^===_==_f
=K=^===x=3=z=62=^==^=m_^k^==`=_d=`=_d===__==_^==K=^==kgo^=3^
In accordance with the clause 62 [ 1 ] of the Conditions of Contract, I certify that the whole of the Works for the above
mentioned contract have been completed and satisfactorily maintained by the Contractor for the period stipulated in the
contract. The Contractor shall remain liable for any unfulfilled obligations as defined in clause 62 [ 3 ] of the Conditions
of Contract.
SUPERVISION CONSULTANT
PMC
PWA Rep./Area Eng./Ho. Section
PWA Dept. Manager
Name & Date
Name & Date
Name & Date
Name & Date
Distribution
Original:
Copies:
Finance & Administrative Department
Contractor
Engineer's Rep
Project File
PMC
Revision 2.2
5 February 2014
Page 129 of 181
:
:
PUBLIC WORKS AUTHORITY
APPENDIX A11
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 130 of 181
Note:
Must be in Company
Letterhead
SPECIMENT FORM FOR FINAL ACCOUNT STATEMENT
FINAL ACCOUNT STATEMENT
CONTRACT TITLE
CONTRACT NO.
ORIGINAL CONTRACT SUM
QR
VARIATION (NET ADJUSTMENT) :
QR
FINAL ACCOUNT
QR
PREVIOUSLY PAID
QR
FINAL AMOUNT DUE
QR
We confirm that the Final Amount Due of QRis the
full and final settlement due to us against this contract.
We further confirm that on payment of the Final Amount Due by the Public Works
Authority, the Public Works Authority shall have honoured all of its obligations on
this contract and that we,
.
shall have no further claim against the Public Works Authority arising out of this
contract.
SIGNED for on behalf of
Revision 2.2
DATE and COMPANY STAMP
5 February 2014
Page 131 of 181
PUBLIC WORKS AUTHORITY
APPENDIX A12
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 132 of 181
PUBLIC WORKS AUTHORITY
PERFORMANCE CERTIFICATE
Contract Title:
Contract No:
:
:
Budget Ref:
Contractor:
Date of Completion:
In accordance with the clause 9.5 of the Conditions of Contract, I certify that the contractor has fulfilled all
his obligations in compliance with the terms of the contract in a satisfactory manner and that he has remedied
defects in the works, if any on the date stated above.
Both parties shall remain committed towards any unfulfilled obligation, as provided and in accordance with
the contract clause 9.6.
9 5
.
9.6
Comments:
Project Management
Contracts
PWA Representative
..
Area Engineer / H o. Section
.....
PWA/Manager of Dept.
..
Distribution
Original:
Copies:
Contractor
Finance & Administrative Department
Head of Section
PMC
Revision 2.2
5 February 2014
Page 133 of 181
:
:
PUBLIC WORKS AUTHORITY
APPENDIX A13
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 134 of 181
PUBLIC WORKS AUTHORITY
TAKING- OVER CERTIFICATE
:
Contract Name:
:
:
Contract No:
Budget Ref:
Contractor:
Contract date for Completion:
Actual date of Completion:
/ / * / 18
.
In accordance with the clause 8.1 of the Conditions of Contract, I certify that the WHOLE / *PART of the Works and/or
materials for the above mentioned contract has been delivered/completed and taken over for use by the Employer on
the above date excluding the outstanding work listed below. I further confirm having received the contractors written
undertaking to carry out all outstanding work during the contract period or within a mutually agreed period of time.
:) (
18
OUTSTANDING WORK (Details Attached):
Outstanding work to be completed in accordance with the conditions of contract clause 9.1
Supervision Consultant
Project Management Contract
..
PWA Rep./Area Eng./Ho. Section PWA Dept. Manager
....
..
Distribution
Original:
Copies:
Finance & Administrative Department
Contractor
Engineer's Rep
Project File
PMC
Revision 2.2
5 February 2014
Page 135 of 181
:
:
PUBLIC WORKS AUTHORITY
APPENDICES B:
TEMPLATES / FORMS APPLIED
TO CONTRACTORS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 136 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B1
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 137 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
REF
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
DESCRIPTION
CONTRACT AMOUNT
APPENDIX B1 - SUMMARY FOR VALUE OF WORK
PREVIOUS CUMULATIVE TOTAL
TOTAL THIS PERIOD
Quantity
Percentage(%)
Completion
Amount (QAR)
Quantity
Percentage(%)
Completion
Amount (QAR)
CUMULATIVE TOTAL TO DATE
Quantity
Percentage(%)
Completion
Amount (QAR)
Remarks
Sub Total
Contract Sum
Total Carried to Certificate
Revision 2.2
5 February 2014
Page 138 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B2
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 139 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS
PREVIOUS CUMULATIVE TOTAL
REF
DESCRIPTION
UNIT
QTY
UNIT RATE
CONTRACT AMOUNT
Quantity
Percentage(%)
Completion
Amount QAR)
CERTIFIED VALUE FOR THIS PERIOD (QAR)
Quantity
Percentage(%)
Completion
Amount QAR)
GROSS CERTIFIED VALUE (QAR)
Quantity
Percentage(%)
Completion
Amount QAR)
Remarks
Total to be Certified
Revision 2.2
5 February 2014
Page 140 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B3
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 141 of 181
APPENDIX B3 - BREAKDOWN OF PRELIMINARY ITEMS
BILLS OF QUANTITIES
BREAKDOWN
Time Related Charges
BOQ Item
Description
Unit
Quantity
Rate
Amount
Cost per
month
Fixed Charges
Cost of
Mobilization
Total
Cost of
Demobilization
Other (specify)
Total
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Revision 2.2
5 February 2014
Page 142 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B4
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 143 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
S/N
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B4 - PREVIOUS PAYMENT CERTIFICATES
Description
Date
Amount
Remarks
TOTAL SUM OF PREVIOUS PAYMENT
Revision 2.2
5 February 2014
Page 144 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B5
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 145 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
Item
Description
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B5 - SUMMARY OF CONTRACT VARIATION ORDERS
Quantity Unit
Rate
Estimated
Amount(QAR)
ON-ACCOUNT VARIATIONS
Previously Paid
Paid this Period
APPROVED VARIATIONS
Quantity
% Complete
Amount (QAR)
Quantity
% Complete
Amount (QAR)
Quantity
% Complete
Amount (QAR)
Cumulative
Quantity
% Complete
Overall Percentage increase to Contract Sum
Revision 2.2
5 February 2014
Amount (QAR)
0.00%
Page 146 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B6
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 147 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
S/N
Payment No.
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B6 - RETENTION SUMMARY
Description
Date
Cumulative Gross
Certified
Cumulative
Retention
Net Retention
Amount
Release of
Retention
Remarks
Totals
Revision 2.2
5 February 2014
Page 148 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B7
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 149 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
S/N
Payment No.
Revision 2.2
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B7 - ADVANCE PAYMENT SUMMARY
Description
Date
5 February 2014
Amount
Remarks
Page 150 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B8
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 151 of 181
Contract No.
Project Name:
Contractor:
Supervision Consultant:
APPENDIX B8 - MATERIAL ON SITE
RP No:
Period Ending:
As per BOQ
Ref
Material Delivered to Site
Material Used
Material
Unit
Qty
Rate
Previous
This Month
Cummilative (A)
Qty used (B)
Qty claimed in
Work Done
Rate
Balance Qty
(A-B)
Invoice Rate
70% of Invoice Rate
Material Component
of BOQ Rate x 70%
MOS Amount
Payable Rate
BOQ Items Contract Work
Variation Items
Revision 2.2
5 February 2014
Page 152 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B9
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 153 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
S/N
Payment No.
Revision 2.2
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B9 - SUMMARY OF PENALTIES
Description
Date
5 February 2014
Amount
Remarks
Page 154 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B10
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 155 of 181
Contract No.:
Project ID:
Description:
Employer: Public Works Authority
PMC:
Contractor:
Consultant:
S/N
Payment No.
Revision 2.2
Contractor's Application No.:
Interim Payment No.:
Period Ending:
Recommendation Date:
APPENDIX B10 - SUMMARY OF PENALTIES UNDER ADJUSTEMENTS
Description
Date
5 February 2014
Amount
Remarks
Page 156 of 181
PUBLIC WORKS AUTHORITY
APPENDIX B11
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 157 of 181
PUBLIC WORKS AUTHORITY
( / )
CERTIFICATE OF COMPLETION (Whole/Part)
:
Contract Title:
:
:
Contract No:
Budget Ref:
Contractor:
Contract date for Completion:
Actual date of Completion:
/ / 48
.
.
In accordance with the clause 48 of the Conditions of Contract, I certify that the WHOLE / *PART of the Works for the
above mentioned contract has been substantially completed and taken over for use by the Employer on the above date
excluding the outstanding work listed below. I further confirm having received the contractors written undertaking to
carry out all outstanding work during the period of maintenance or within a mutually agreed period of time. The period of
maintenance of the Works covered by this certificate shall commence from the above actual date of completion.
:( ) ()
OR, PARTIAL COMPLETION (*if applicable)(Details Attached):
:( )
: ( ) ( )
OUTSTANDING WORK (Details Attached):
Minor work (snags) to be completed during the Period of Maintenance (Details Attached):
Consultant
Engineer's Representative:
..
.
Name of Consultant
(if applicable )
Project Manager/Co-ordinator
Concerned Affairs/Dept.
Name of Signatory
The Engineer:
Date :
...
Director/Manager
Concerned Affairs/Department
Name of Signatory
Distribution
Original:
Copies:
Finance & Administrative Department
Contractor
Engineer's Rep
Project File
Finance Department
Revision 2.2
5 February 2014
Page 158 of 181
:
:
PUBLIC WORKS AUTHORITY
APPENDICES C:
TEMPLATES / FORMS APPLIED
TO PMC & SECONDMENT
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 159 of 181
PUBLIC WORKS AUTHORITY
APPENDIX C1
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 160 of 181
AUTHORISATION TO MOBILISE FORM
STATE OF QATAR
PUBLIC WORKS AUTHORITY
Department:
Project ID:
Project Title:
Consultant:
AUTHORISATION TO MOBILISE
PERSONNEL DETAILS
NAME
POSITION/ TITLE
SCHEDULE C CODE
GRADE
ORGANISATION CHART
REFERENCE NO
REQUESTED BY
NAME
SIGNATURE
CV ATTACHED
YES/NO
POSITION
JOB DESCRIPTION
ATTACHED
DATE
YES/ NO
ASSIGNMENT DETAILS
LOCATION
DURATION
MOBILISATION DATE
DEMOBILISATION DATE
PLANNED
ACTUAL
PLANNED
ACTUAL
APPROVAL DETAILS
APPROVED/
REJECTED
NAME
SIGNATURE
POSITION
DATE
BASIS FOR REJECTION
Revision 2.2
5 February 2014
Page 161 of 181
PUBLIC WORKS AUTHORITY
APPENDIX C2
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 162 of 181
Ashghal Rules - Public Holidays paid/not paid
F
Scenario 1
Scenario 2
Scenario 3
Scenario 4
Scenario 5
Scenario 6
Scenario 7
Scenario 8
Sa Su M
W
W
W
A
W
A
A
A
W PH W W
W W W PH
W PH A A
A A A A
W W W W
A A A A
A A A PH
A A A A
Sa Su M
W W W W
A A A A
A A A A
PH W W W
PH A A A
A A PH W
W W W W
A A PH A
W
A
A
W
A
W
W
A
Sa
Public Holiday Paid/Not Paid
Paid
Paid
Paid
Paid
Paid
Paid
Paid
Not paid
Key
W Working day
A Absent
PH Public Holiday
Weekend
Revision 2.2
5 February 2014
Page 163 of 181
PUBLIC WORKS AUTHORITY
APPENDICES D:
TEMPLATES / FORMS APPLIED
TO WORK ORDER & SUPPLY
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 164 of 181
PUBLIC WORKS AUTHORITY
APPENDIX D1
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 165 of 181
0HJGHJHJGH
Public Works Authority
Work Order Completion Certificate (Final)
:
Date Of Work Order :
Work Order No.
Budget Code / Ref. :
Job
.
. _________________
I certify that the work detailed on the above work order has been satisfactorily completed
according to the conditions stated and as per specifications. Payment of . .
Date of completion:
No retention is required
Date :
Remarks :
_______________
PWA
Revision 2.2
5 February 2014
Page 166 of 181
PUBLIC WORKS AUTHORITY
APPENDICES E:
FINANCE & ADMINISTRATIVE
DEPARTMENT CHECKLISTS
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 167 of 181
PUBLIC WORKS AUTHORITY
APPENDIX E
EBSD Payments Unit
Revision 2.2
5 February 2014
Page 168 of 181
Finance and Administrative Affairs
ADVANCE RP for CONTRACTOR
Commitment No.
Department
Roads Drainage- Buildings
Contractor
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award Letter
2.
Original Advance Bond or any Extension
3.
Original Bank Account Information Letter Stamped by the Bank
4.
Original RP stamped by the Consultant if applicable
5.
Original Invoice from the Contractor
6.
Consultant Original Recommendation Letter if applicable
7.
Copy of Valid Commercial Registration
8.
I. D. Copy of the authorized signatory
9.
Copy of Performance Bond or any Extension
10.
Copy of Insurance Certificates
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 169 of 181
Finance and Aministrative Affairs
FIRST RP FOR CONTRACTOR
IN CASE OF NO ADVANCE PAYMENT
Commitment No.
Department
Roads-Drainage-Buildings
Contractor
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award letter
2.
Original Bank Account Information Letter Stamped by the Bank
3.
Original RP stamped by the Consultant" if applicable
4.
Consultant Original Recommendation Letter if applicable
5.
Original Invoice from the Contractor
6.
Original B.O.Q Summary Stamped by Consultant & Contractor
7.
Original Retention Bond or any Extension
8.
Copy of Valid Commercial Registration
9.
I. D. Copy of the authorized signatory
10.
Copy of Insurance Certificates
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 170 of 181
Finance and Administrative Affairs
INTERIM RP FOR CONTRACTOR
Commitment No.
Department
Roads-Drainage-Buildings
Contractor
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP stamped by the Consultant if applicable
2.
Original Invoice from the Contractor
3.
Consultant Original Recommendation Letter if applicable
4.
Original B.O.Q Summary Stamped by Consultant & Contractor
5.
In case the payment for Sub contractor, Kharama, Consultant etc, supporting
document for this payment must be attached
6.
In case of penalty Details breakdown must be attached
7.
Copy of VO in case of extension or additional cost
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 171 of 181
Finance and Administrative Affairs
PENULTIMATE RP FOR CONTRACTOR
Commitment No.
Department
Roads-Drainage-Buildings
Contractor
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP stamped by the Consultant if applicable
2.
Original Invoice from the Contractor
3.
Consultant Original Recommendation Letter if applicable
4.
Original Completion Certificate "PCC" with Original B.O.Q Summary Stamped by
Consultant & Contractor
5.
In case the payment for Sub contractor, Kharama, Consultant etc, supporting
document for this payment must be attached
6.
In case of penalty Details breakdown must be attached
7.
Schedule of Variations, claims and day works executed
8.
Schedule of Provisional sums how they have been expended in the Contract if
applicable
9.
Copy of Valid Commercial Registration
10.
Original Municipality Clearance Roads & Drainage Contracts if applicable
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 172 of 181
Finance and Administrative Affairs
FINAL RP FOR CONTRACTOR
Commitment No.
Department
Roads-Drainage-Buildings
Contractor
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP stamped by the Consultant if applicable
2.
Original Invoice from the Contractor
3.
Consultant Original Recommendation Letter if applicable
4.
Original Stamped Letter Head Final Account Statement
5.
Original Maintenance Certificate
6.
In case of penalty Details breakdown must be attached
7.
Copy of valid Tax Card
8.
In case the Bank account changed, the Contractor must submit No Objection Letter
from previous bank + I. D. Copy of the authorized signatory
9.
In case the payment for Sub contractor, Kharama, Consultant etc, supporting
document for this payment must be attached
10.
Copy of Valid Commercial Registration
11.
Committee Approval Letter (Roads Contracts only)
12.
Original DCU Clearance
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 173 of 181
Finance and Administrative Affairs
ADVANCE RP for PMC/SEC
Commitment No.
Department
Roads Drainage- Buildings
PMC/Secondment
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award Letter
2.
Original Advance Bond or any Extension
3.
Original Bank Account Information Letter Stamped by the Bank
4.
Original RP stamped by the Consultant if applicable
5.
Original Invoice from the Contractor
6.
Consultant Original Recommendation Letter if applicable
7.
Copy of Valid Commercial Registration
8.
I. D. Copy of the authorized signatory
9.
Copy of Performance Bond or any Extension
10.
Copy of Insurance Certificates
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 174 of 181
Finance and Administrative Affairs
FIRST RP FOR PMC & SECONDMENT
Commitment No.
Department
Roads-Drainage-Buildings
PMC/Secondment
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award Letter
2.
Original Bank Account Information Letter Stamped by the Bank
3.
I. D. Copy of the authorized signatory
4.
Original RP
5.
Original Invoice from the Consultant
6.
Copy of Insurance certificates
7.
Copy of Valid Commercial Registration
8.
Daily, monthly attendance, & calculation summary sheet to be signed by the Project
Manager
9.
Copy of Performance Bond or any Extension
10.
In case penalty full breakdown shall be submitted
11.
ATM (Authorization To Mobilize) Copy.
Note:
Salary per day = Monthly salary *12 months/365 days
Calculation of Absence=(monthly salary)(salary per day*no of days
absent)
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 175 of 181
Finance and Administrative Affairs
INTERIM RP FOR PMC & SECONDMENT
Commitment No.
Department
Roads-Drainage-Buildings
PMC/Secondment
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP
2.
Original Invoice from the Consultant
3.
Copy of Valid Commercial Registration
4.
In case penalty full breakdown shall be submitted
5.
Copy of Approved Addenda in case of extension or additional cost
6.
Daily, monthly attendance, & calculation summary sheets to be signed by Project
Manager
7.
ATM (Authorization To Mobilize) Copy.
Note:
Salary per day = Monthly salary *12 months/365 days
Calculation of Absence=(monthly salary)(salary per day*no of days
absent)
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 176 of 181
Finance and Administrative Affairs
FINAL RP FOR PMC & SECONDMENT
Commitment No.
Department
Roads-Drainage-Buildings
PMC/Secondment
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original Invoice from the Consultant
2.
Original RP
3.
Daily, monthly attendance, & calculation summary sheets to be signed by Project
Manager
4.
Copy of Valid Commercial Registration
5.
Reason for Delay if applicable
6.
In case of penalty Details breakdown must be attached
7.
Copy of approved addenda in case of extension or additional/omission cost
8.
Original Completion of Certificate
9.
Original stamped letter head Final Account Statement
10.
Copy of valid Tax Card
11.
In case the Bank account changed, the Consultant must submit No Objection Letter
from Previous bank.
12.
ATM (Authorization To Mobilize) Copy.
Note :
Salary per day= Monthly salary *12months/365 days
Calculation of Absence =(monthly salary)-( salary per day *no of
days absent)
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 177 of 181
Finance and Administrative Affairs
ADVANCE RP for CONSULTANT
Commitment No.
Department
Roads Drainage- Buildings
Consultant
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award Letter
2.
Original Advance Bond or any Extension
3.
Original Bank Account Information Letter Stamped by the Bank
4.
Original RP stamped by the Consultant if applicable
5.
Original Invoice from the Contractor
6.
Consultant Original Recommendation Letter if applicable
7.
Copy of Valid Commercial Registration
8.
I. D. Copy of the authorized signatory
9.
Copy of Performance Bond or any Extension
10.
Copy of Insurance Certificates
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 178 of 181
Finance and Administrative Affairs
FIRST RP FOR CONSULTANT
Commitment No.
Department
Roads-Drainage-Buildings
Consultant
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Copy of award Letter
2.
Copy of Performance Bond or any Extension
3.
Original Bank Account Information Letter Stamped by the Bank
4.
Original RP
5.
Original Invoice from the Consultant
6.
Original advance guarantee if applicable
7.
I. D. Copy of the authorized signatory
8.
Approval of PWA for the services completed Design Contracts
9.
In case penalty full breakdown shall be submitted
10.
Copy of Commercial Registration
11.
Daily, monthly attendance, & calculation summary sheet to be signed by the
Project Manger
12. ATM (Authorization To Mobilize) Copy.
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 179 of 181
Finance and Administrative Affairs
INTERIM RP FOR CONSULTANT
Commitment No.
Department
Roads-Drainage-Buildings
Consultant
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP
2.
Original Invoice from the Consultant
3.
Approval of PWA for the services completed Design Contracts
4.
Copy of Valid Commercial Registration
5.
Copy of approved addendum in case of extension or additional cost
6.
ATM (Authorization To Mobilize) Copy
7.
Daily, monthly attendance, & calculation summary sheet to be signed by the
Project Manager.
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 180 of 181
Finance and Administrative Affairs
FINAL RP FOR CONSULTANT
Commitment No.
Department
Roads-Drainage-Buildings
Consultant
Payment No.
TERMS OF REFERENCE FOR CHECK
CHECKED
1.
Original RP
2.
Original Invoice from the Consultant
3.
Original Stamped Letterhead Final Account Statement
4.
Original Completion Certificate
5.
Copy of Maintenance Certificate for supervision contracts, in case Construction
Contract not yet closed.
6.
In case of penalty Details breakdown must be attached
7.
Copy of approved addenda in case of extension or additional/omission cost
8.
Copy of Valid Commercial Registration
9.
Copy of valid Tax Card
10.
Original DCU Clearance
11.
Daily, monthly attendance, & calculation summary sheet to be signed by the
Project Manager.
12.
ATM (Authorization To Mobilize) Copy.
COMMENTS
Checked by:
Date:
This Payment Control Check Sheet Must Be attached with each
recommendation of payment
Revision 2.2
5 February 2014
Page 181 of 181