0% found this document useful (0 votes)
820 views6 pages

Critical Path

The document describes three project planning problems with activities, durations, and precedence relationships. For Problem 1, the critical path is A-B-E-G-I with a duration of 23 days. If activity F takes 4 days instead of 2, the new critical path is A-D-F-G-I with a duration of 23 days. For Problem 2, expected durations and variances are calculated for each activity. The critical path is A-B-F-G with an expected project duration of 27 weeks. The probability of completing in 34 weeks is calculated using the normal distribution. For Problem 3, the student is asked to draw a node diagram, calculate slack times, and identify

Uploaded by

mashud sardar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
820 views6 pages

Critical Path

The document describes three project planning problems with activities, durations, and precedence relationships. For Problem 1, the critical path is A-B-E-G-I with a duration of 23 days. If activity F takes 4 days instead of 2, the new critical path is A-D-F-G-I with a duration of 23 days. For Problem 2, expected durations and variances are calculated for each activity. The critical path is A-B-F-G with an expected project duration of 27 weeks. The probability of completing in 34 weeks is calculated using the normal distribution. For Problem 3, the student is asked to draw a node diagram, calculate slack times, and identify

Uploaded by

mashud sardar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • Problem 1
  • Solution to Problem 1
  • Problem 2
  • Solution to Problem 2
  • Problem 3

Problem 1

A project has been defined to contain the following list of activities, along with their required
times for completion,

ACTIVITY

TIME

IMMEDIATE PREDECESSORS

A
B
C
D
E
F
G
H
I

1
4
3
7
6
2
7
9
4

A
A
A
B
C,D
E,F
D
G,H

Requirement:
a. Draw the critical path diagram (Node).
b. Show the early start and early finish times.c. Show the critical path.
d. What would happen if activity F was revised to take four days instead of two?

Solution Problem 1
The answers to a, b, and c are shown in the following diagram.

B(4)

E(6)

G(7)

I(4)

C(3)
A(1)

F(2)
D(7)

d. New Critical Path: A- D- F- G- I. Time of Completion is 23 days.

H(9)

Problem 2
A project has been defined to contain the following activities, along with their time estimates for
completion,

ACTIVITY
A
B
C
D
E
F
G

TIME ESTIMATES
a
1
2
3
6
3
6
1

m
4
6
4
12
6
8
5

IMMEDIATE PREDECESSORS
b
7
7
6
14
12
16
6

Requirement:
a. Calculate the expected time and the variance for each activity.
b. Draw the critical path diagram (Node).
c. Show the early start, early finish times and late start, late finish times.
d. Show the critical path.
e. What is the probability that the project can be completed in 34 weeks?

A
A,D
A
D
B,C
E,F

Solution Problem 2 Type equation here .


a. Calculation of expected time and activity variance:
ACTIVITY

EXPECTED TIME
ET=

a+ 4 m+b
6

ACTIVITY VARIANCE
ba 2
2
=
6

( )

4.00

5.50

25
36

4.17

1
4

11.33

16
9

6.50

9
4

9.00

25
9

4.50

25
36

b.
F(2)

B(4)

G(7)
A(1)

C(3)

D(7)

E(6)

c. Shown on diagram
d. Shown on diagram
e. We know that,
Transformation formula Z

Problem 3
A project consists of 9 activities. For each activity, the preceding activity is given and a
deterministic estimate of the length of time required to complete it.

ACTIVITY

TIME

IMMEDIATE PREDECESSORS

A
B
C
D
E
F
G
H
I

6
9
8
12
11
7
12
14
9

A
A
A
B
C,D
E,F
D
G,H

Requirement:
a. Draw a node diagram.
b. Calculate the slack time for each paths.
c. Determine critical path.

You might also like