Method Statement for Power Block Cable Installation

This method statement outlines the procedures for installing power block cables for the 800 MW Phase III PV solar power project for DEWA in Dubai. It details the necessary permits, personnel, equipment, materials, inspections, and safety precautions for cable pulling, laying, termination, and mounting. Hazards are identified and controlled through a risk assessment process to ensure work is completed safely according to the project's health, safety and environment plans and procedures.

Uploaded by

Anandu Ashokan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
473 views20 pages

Method Statement for Power Block Cable Installation

This method statement outlines the procedures for installing power block cables for the 800 MW Phase III PV solar power project for DEWA in Dubai. It details the necessary permits, personnel, equipment, materials, inspections, and safety precautions for cable pulling, laying, termination, and mounting. Hazards are identified and controlled through a risk assessment process to ensure work is completed safely according to the project's health, safety and environment plans and procedures.

Uploaded by

Anandu Ashokan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

PROJECT COMPANY

PROJECT COMPANY ENGINEER

EPC CONTRACTOR

PROJECT

DEWA PHASE III 800 MW PV SOLAR POWER


PROJECT
ORIGINATOR

DOCUMENT TITLE

METHOD STATEMENT: POWER BLOCK CABLE INSTALLATION

PCO Document Code


Responsible
Project Phase Number Discipline System Document Type Serial Number LBS
Organization

EPC Company Code


Serial Number
Project Group Issuing discipline Document type Originator Company

DWA 00 EE MS GNF 0001

Rev Date Reason of issue Drafted by Reviewed by Approved by

00A 02-11-2017 Approval RP PP VM


DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

DOCUMENT CHANGES LOG

Section/
Revision Remarks
Paragraph

00A Initial Issue All

Page 2 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

TABLE OF CONTENTS

1 DEFINITIONS ..................................................................................................................................................... 5
2 PURPOSE & SCOPE ........................................................................................................................................... 5
3 REFERENCES AND ABBREVIATIONS................................................................................................................... 5
4 CONSTRUCTION METHODOLOGY ..................................................................................................................... 6

4.1 SUMMARY .......................................................................................................................................................... 6

4.2 METHODOLOGY ................................................................................................................................................... 6

4.3 PERMIT, ACCESS, APPROVAL AND SITE PREPARATION.................................................................................................. 6

4.4 SET & ASSEMBLY FOR POWER CABLE INSTALLATIONS (SET, LAYING CABLES) ...................... ERROR! BOOKMARK NOT DEFINED.

4.4.1 General ......................................................................................................Error! Bookmark not defined.

4.4.2 Material Handling / Preparation of Cable Drum ..................................................................................... 6

4.4.3 Cable Pulling / Laying .............................................................................................................................. 7

4.4.4 Mounting of termination Kit, Glanding and Termination........................................................................ 7

5 NATURE OF WORK............................................................................................................................................ 8
6 REQUIREMENT OF TEMPORARY WORKS .......................................................................................................... 8
7 ACTIVITY SCHEDULE & MILESTONES ................................................................................................................. 8
8 CONSTRUCTION RESOURCES ............................................................................................................................ 8

8.1 PERSONNEL......................................................................................................................................................... 8

8.2 PLANT & EQUIPMENT .................................................................................................................................... 11

8.2.1 Key Plant / Equipment Type .................................................................................................................. 11

8.2.2 List of personal protective equipment ................................................................................................... 11

8.3 MATERIALS ....................................................................................................................................................... 12

8.4 HAZARDOUS SUBSTANCES .................................................................................................................................... 12

8.5 SURVEY AND SET OUT ......................................................................................................................................... 12

9 INSPECTION .................................................................................................................................................... 12

Page 3 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

10 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL ........................................................................ 13

10.1 LIFTING PLAN .................................................................................................... ERROR! BOOKMARK NOT DEFINED.

10.2 PERMITS REQUIRED ........................................................................................................................................ 13

11 EMERGENCY PROCEDURES & RESPONSE PLAN ............................................................................................... 13


12 RISK ASSESSMENT (RA)................................................................................................................................... 14
13 RELATED DOCUMENTS ................................................................................................................................... 20

Page 4 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

1 DEFINITIONS
In this Document, the following words and expressions shall have the meanings stated:

- HSE: Health, Safety and Environment

- MS: Method Statement

- MV: Medium Voltage

- FO: Fiber Optic

- HV: High Voltage

- TBT: Tool Box Talk

- MS & RA: Method Statement and Risk Assesstment

- HSEMS: Health, Safety, Environment Management System

- CESMP: Construction Environmental and Social Management Plan

- PPE: Personal Protection Equipment

- CSE: Confined Space

2 PURPOSE & SCOPE


This Method statement is to define the methods, procedures and activities, which will be
used for Power Block Installation for DEWA PHASE A of PHASE III 800 MW PV SOLAR
POWER PROJECT as per the approved shop drawings to ensure that all works are
executed in a safely manner in accordance with the Health, Safety, Environment
Management System.

3 REFERENCES AND ABBREVIATIONS


 UAE Rules & Regulations.

 Code of Construction Safety Practice of Dubai Municipality.

 Project HSE Plan & Procedures.

 Project Contract Documents.

 International Safety Codes and Standards.

Page 5 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

4 CONSTRUCTION METHODOLOGY

4.1 Summary
This MS will be outlining the sequences and methods of works intended for the Set & Assembly for
Power Stations.

4.2 Methodology

Step Description

1 Permit, Safety and Site Preparation

2 Method Statement for Power Block installation

4.3 Permit, Access, Approval and Site Preparation


a. Obtain necessary permit such as Permit To Work (PTW) from the contractor.
b. Check relevant items like PPE’s, access of working area, equipment to be used etc. to
ensure safety, workability and environmental requirements.
c. Review Specification and drawings. (Approved Drawings / Specification )
d. Ensure that the material’s type, size, area classification etc. conform to the project
specifications and drawings.
e. Ensure that proper materials are available and approved for use.

4.4 Set & Assembly for Power Cable Installations (Set, Laying cables)

4.4.1 General
a) The work area should be inspected for safety prior to start the installation.
b) Obtain relevant work permit from authorities.
c) All relevant approved shop drawings are available at site for the execution of job
d) Ensure all control measures stated in the corresponding risk assessment are adhered to
when carrying out the job.
e) The cables shall be laid in a sequenced manner.
f) After cable pulling is completed and testing has done, inspection to proceed for cable
laying.

4.4.2 Material Handling / Preparation of Cable


a) Route measurement shall be done and identification of drum placement point prior to
material being shifted.
b) Necessary care shall be taken while transporting the cable drum on site.
c) Cable drum shall be transported on the trailer / cable trolley and ensure that the cable
drum stands on the flanges and well strapped during the transport stage.

Page 6 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

d) All necessary precaution shall be taken while unpacking the cables drums or removal of
battens to avoid damage on the cable.
e) Rolling the drum shall not be allowed for longer distance and drums must be rolled only
in the direction of arrows marked on the drum.
f) Position the transport vehicle in a suitable area where the crane can easily reach and
access.
g) Place the cable drums as close as possible to the location where the cables to be laid.

4.4.3 Cable Pulling / Laying


a) Prior to laying cables on trays or racks, these will be inspected to ensure the routing.
b) Cable pulling will be carried out according to the cable schedule.
c) Minimum 2 meters of cable has to be coiled for carrying out the termination as per the
respective drawings / cable schedules.
d) Each joint shall be made at an interval according to site requirement as per QCP-
(Jointing, Glanding & Termination of cables) and also refer the jointing kit
manufacturer’s recommendations.
e) Ground shield of cable at terminations, and separable insulated connectors. Ground
metal bodies of terminators, cable and separable insulated-connector fittings, and
hardware

4.4.4 Mounting of termination Kit, Glanding and Termination


Mounting of Termination and Joints Kits

a) Follow manufacturer termination and joint kits instructions.


b) Prior to use the termination kit, check the materials and all accessories against the
materials list provided by the manufacturer inside the box of each termination kit. If any
accessories are missing keep the termination kit separate, informed the engineer to
coordinate the supplier / manufacturer.
c) Do not use any sub materials or modified accessories.

A) Termination
.
a) Prior to termination necessary testing of the cable shall be done.
b) When all testing required was done and accepted by the Contractor/Engineer prepare
the cable for termination.
c) Check and ensure the lug properly crimps and stress free fit to the terminal.
d) Ensure that correct size and type of bolt, torque wrench with valid certificate is available.
e) Clean and degrease the equipment terminal.
f) Carefully fit the cable on the equipment terminal, check and align cable in proper
manner.
g) Insert the bolt and tight carefully, torque the bolt according to manufacturer
recommendation.
h) Provide torque mark after each bolt has been done / torque.
i) Provide contact grease / moisture protection on bolt / terminal (Only if required by
manufacturer or engineering specification).
j) Fix necessary terminal cover/protection.

Page 7 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

k) Clean the area as well as internals of panels/termination box/ cubicles/All leftover / cut
piece cables/wires shall be returned to the stores or designated/ disposal area as
instructed by client
l) Connection to SS shall be performed and followed DEWA specification and standards.
m) Regarding FO splicing, all requirements shall be followed (e.g. FOC Splicing area should
be free of dust installing some tend around the work area, etc.)

5 NATURE OF WORK

a) Confined Space - Confined Space Permit shall obtain and copy must be available at site when the
activities is being done under confined space area like cable pit etc. Section 6.2.2.7 Confined space
work of the HSE Management Plan must be observed (and mentioned) and also document DWA-00-
SS-PR-UTE-0027 Confined Spaces.In addition, section 4.1.Work in ditches and manholes from Doc.
DWA-00-HS-PR-EPC-0016 Excavation and Earthworks must observed and mentioned. Only CSE
trained workers are allowed to work in CSE.
b) Work at Height – Work at Height Permit shall be obtained and copy must be available at site. When
the activities to be done above 1.8 meters, flat form or scaffold must be erected.
c) Working During Summer Time – Working direct exposed to sunlight during summer season shall not
be permitted as directed by the labor law. Ensure to provide proper sun shades, drinking water at site.
d) Trenches access – Excavations greater than 1.2 m. in depth shall be provided with stairs, ladders or
ramps. Ladders used as access ways shall extend from the bottom of the excavation to not less than
90 cm above the surface. At least two stairs, ladders or ramps, one on each side of excavation shall
be provided with maximum of 15 meters travel distance to facilitate access and egress of employees
from excavation.
e) Working during the night – in case that some work are going to be performed during the night, them
shall be made under the properly conditions of light and safety.

6 REQUIREMENT OF TEMPORARY WORKS


 Necessary warning signs shall be provided around the working areas.
 Erect / install scaffold when working at height.

7 ACTIVITY SCHEDULE & MILESTONES

Activity Duration Remarks

Completion of activities
Power Block Cable Laying As per activity schedule depends site access and site
condition

8 CONSTRUCTION RESOURCES

8.1 Personnel
 Dy. General Manager - Overall In-charge of the project and report to General Manager.

Page 8 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

 Project Manager:

 Responsible to implementation and proper completion of the project.


 Responsible for proper planning of all resources required to complete the works in accordance with
the program, ensure all persons at site are adequately experienced and trained to carry out their
allocated tasks.
 Responsible for the day to day management of the project, both on and off the site, together with
proper delegation of duties in accordance with the organization chart and for the effective
implementation of the project management system.
 Take prompt corrective actions to remove any unsafe or unhealthy work conditions and to
 Maintain effectively such corrections made.
 Ensure good housekeeping is practiced on site.
 Ensure the delegated site personnel are conversant with and operate the prescribed QMS and
Safety Plans correctly.
 Able to properly communicate with and manage all persons on site.
 Ensure that all dangerous activities are carried out under Permit to Work Procedure.
 Ensure that all training requirements are put in place (scaffolding, machinery operator certificate, first
aider, fire watcher, etc.)
 To ensure the effective implementation of all Plans, Procedures and Forms included in the HSE
Management System. Ensure that all equipment and machinery have third party certificate (when
applicable).
 Lead all construction activities and enforce strict adherence to all project requirements. Report to Dy.
General Manager
 Implementation of HSE Policies and Procedures as per the HSEMS requirements.

 Engineers –

 Responsible for the site coordination and execution of the project construction.
 Prepare technical document, material, and shop drawings submittals.
 Raising RFI’s, IR’s to the client.
 Preparing weekly look ahead reports.
 Attending coordination meetings between client and consultant.
 Transmitting client instructions to the project manager and the construction team.

Page 9 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

 Managing the QA/QC team, coordinating and assisting in all QA/QC documentation as per project
quality plan.
 Establish and maintain a programme for the identification and assessment of hazards.
 Assist in the investigation of every serious or fatal accident and dangerous occurrence and
 Recommend preventive measures.
 Ensure that method statements, hazard analysis and safe work procedures for hazardous
 Operations must be submitted before commencement of work on site.
 Preparing Method Statements and lias with HSE officer for Risk Assessements.
 Ensure that al dangerous activites are carried out under Permit to Work Procedure.
 Implementation of HSE Policies and Procedures as per the HSEMS requirements.
 HSE Officer

 Provide HSE trainings, TBT, Training on MS & RA and Daily site inspection.
 To ensure that the activities are performed as to the project HSE plan so that the work is at
minimum risk to the construction personnel at site.
 Coordinate and ensure with various levels of people at site to have a safe Working place.
 To ensure that the work is carried out with minimum impact to the
Environment.
 To ensure and monitor the condition of machinery and plant and report any hazardous defect to
the plant department.
 To investigate site accidents and prepare accident reports to the EPC contractor.
 To provide safety induction program to workers, prior access to site.
 To contact client associated personnel in case of an accident or injury.
 Attend HSE teams meetings with the HSE manager and transmit instructions to site personnel.
 Prepare Risk Assessment as per project HSE plan
 Ensure that all dangerous activities are carried out under Permit to Work Procedure.
 Ensure that all training requirements are put in place (scaffolding, machinery operator certificate)
 To ensure the effective implementation of all Plans, Procedures and Forms included in the HSE
Management System.
 Ensure that all equipment and machinery have third party certificate (when applicable).
Report to Dy. Project Manager.
 Implementation of HSE Policies and Procedures as per the HSEMS requirements.

Page 10 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

 Supervisor / Technicians
 Ensure that all activities to be done in accordance with the approved MS/RA,
 Supervisor shall monitor site installation, conduct tool box meeting and discuss to crew member the
hazard of the activities to be done.
 Supervisor also ensure that site installation shall be as per project specification.
 Technician shall be attended and pass necessary trainings required for the job to ensure the
competency and to comply with the requirements of Contractor/Engineer.
 Site activities / installation shall be executed in compliance to quality, safety and standard
requirements. Report to Engineer.
 Implementation of HSE Policies and Procedures as per the HSEMS requirements.

 Workers
 All workers must follow the safety rules, as described in the project HSE plan & procedures.
 All workers must report any accident, near miss, or any other hazardous situation to his supervisor.
 All workers must always wear proper PPE.
 Shall attend TBT daily and comply HSE with requirements.

8.2 PLANT & EQUIPMENT

8.2.1 Key Plant / Equipment Type


a) Cable Winch, Cable rollers.
b) Tools (cutting. machine, spanners)
c) Drum supports and cranes.
d) Cable Jacks
e) Multi-meter.
f) Megger – 1 to 5 KV

8.2.2 List of personal protective equipment

a. Mandatory PPE Requirements

 Safety helmets.
 Safety footwear.

Page 11 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

 High visibility vests.


 Safety Glasses.

b. Work Specific PPE


 Hand gloves.
 Ear defenders.
 Filter mask.

8.3 Materials
a) Measuring Tape
b) Cable Tie
c) Termination Kit
d) Cable

8.4 Hazardous Substances

Hazardous Substance Volume Hazardous Substance?


Name Required (Y/N)

Electrical cleaning solvent As required N

WD40
As required N
(for lubricating rollers)

8.5 Survey and Set Out


 N/A

9 INSPECTION

Type of Inspection Witness Approval Remarks

Cable Laying, Glanding and Contractor/


Engineer/Client
Termination Engineer

Page 12 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

10 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL

The Sub-Contractor will be responsible for all necessary safety measures at all time. All works
related will be executed in accordance with the Client and Contractor Project Health, Safety Plan and
MS & RA.

The work will only proceed when all necessary permits has been obtained or when required. The
permit will be kept on site for consultation during any site works.

Special attention will be given to:


 Cordoning off specified working area and provision of applicable safety warning sign boards.
 All the Important Task Activities and Potential Hazards including existing controls have been properly
mentioned on the Risk Assessment made.

10.1 Permits Required

Permit Required Issued By

PTW Contractor

WORK AT HEIGHT Contractor

CONFINED SPACE Contractor

11 EMERGENCY PROCEDURES & RESPONSE PLAN


 PHASE III 800 MW PV SOLAR POWER PROJECT EMERGENCY CONTACT NOS.

Contact
Contact Person Designation Company
Numbers

CLINIC/AMBULANCE Clinic Nurse EPC +97156 5067404

MIGUELANGEL MOYA HSE Manager EPC +97155 684 6144

Page 13 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

DAVID DE LARA Site Project Manager EPC +97156 422 5800


CHOUSA

JOSE MIGUEL PLAZA Construction Manager EPC +97156 522 0618

ANANDAN PILLAI Sr. HSE Officer EPC +97150 106 8046

SYED OWAIS AHMED Accident Prevention Officer EPC +97156 415 6639

JINISH HSE Officer EPC +97152 518 9809

ESPIRITUFIESTA Environmental Engr. EPC +97156 422 5737


ABUAN

INBARAJ MARIYAN Site Manager PLQC +97155 9421634

ANAND HSE Officer PLQC +97155 9418364


CHINNACHAMY

SECURITY -- EPC +97152 894 1684

12 RISK ASSESSMENT (RA)

Page 14 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

A INJURY SEVERITY B FREQUENCY of OCCURENCE RATING

RISK
0 No injury 0 Has not occurred in last two years RISK VALUE
CLASSIFICATION

Minor laceration, wound (first aid


2 2 Occurs very seldom LOW 0---6
case)

More severe injury medical


4 4 Occurs occasionally MEDIUM 7---16
attention

Serious injuries, broken bones,


8 8 Occurs often HIGH 17---32
amputation etc

10 Loss of life / fatality 10 Could / has happened CRITICAL 33---40

C POTENTIAL DAMAGE / LOSS D ENVIRONMENT ACTION REQUIRED

Supervision, training, certification, method/risk


No damage, minimal costs (UAE
0 0 No effect LOW assessments, safe work procedures training, Good instruction.
Dirhams)
toolbox talks.

Competent supervision, training certification,


Minor damage, small costs (UAE
2 2 Minor effect MEDIUM method/risk assessments, safe work procedures Change method, mitigate
Dirhams)
training, toolbox talks.
Spillage, noise, water,
Competent supervision, training certification,
Med damage, stoppage (On site Serious effect dust/ vapours/ faun
4 4 HIGH method/risk assessments, safe work procedures Change method, mitigate.
repair) medium cost (UAE Dirhams) (Short term) and flora
training, toolbox talks.

Very serious
8 More serious damage 8 effect (Long
Close competent supervision, training certification,
Term) Intolerable, change method,
CRITICAL method/risk assessments, safe work procedures,
transfer risk.
PJO’s, work permits, training, and toolbox talks.
Severe damage, long term Catastrophic
10 10
stoppage, high costs effect

Page 15 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

Hazards Identified Whom/ A B C D R Controls Additional Responsibility R


What Controls
Affected
 Provide safe access and egress to work
Access to Work Slip /Trip Accident Workers 2 2 4 0 16 area Supervision & Site Engineer/ 4
Areas  All material stored in proper area. frequent monitoring Supervisor
With moving vehicle  Segregate pedestrain from vehicle
worker and staff movement area
Environment  Not temporary crossing/access across
trenches shall be provided.
 During cable laying any hindrance of
transportation shall be avoided.

 Manual handling awareness


Manual Strains and sprains such workers 4 2 2 0 16  Kinetic manual handling techniques More awareness Site Engineer/ 5
Handling as a back damager  Adequate rest periods allowed, job rotation, should be given in Supervisor
minimise repetitious twisting and form of trainings
shoverlling. and tool box talks
 Ensure competent supervisión
Hands  Trained and competent operatives allowed
to work
 Wear adequate PPE (Hand Gloves, Hard
Hat, high visible reclected Jacket, Safety
Back muscle strain, crush Goggle, etc.,)
injuries  Team Lifting, if posible use mechanical aids
to lift, only lift objects within your capability
 Ensure body parts area not under load
when lowering.
 Trained & competent worker allowed to
Delivery and Strains and sprains such Workers 2 2 4 0 16 shifting to the material under Competent Supervision & Project 4
Shifting Material as back damager / operators/ Supervision. frequent monitoring Manager/Engineer/
drivers  Provide Task Related TBT. supervisor
Hit to the operator.  Ensure Appropriate PPE. ( Hard Hat, Safety
Shoe, Goggle, Ear Plugs, Hand Gloves,
Material damage Safety Goggles, . Etc..)
 Ensure Material shifting near to site by
Fall material adequate safe transportation.
 Ensure adequate safe lifting equipment for
Material hit to the shifting to material near to work area from
ground floor. Mobile crane / Service lift.
operator’s  Ensure manual handling techniques for
when lifting by manually.
 Ensure dm approved 3rd party certificate for
operators / Flag men/ any machinery

Page 16 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

operators. Use any machinery.

 Clear access shall be marked and sign


Stack of Obstruction to the walk Workers 2 2 4 0 16 boards shall be kept prior to identify and Supervision & Project Manger/ 4
materials way / property area shall be marked for different materials frequent monitoring Engineer/ supervisor
Damage and kept in its location.

 Slip/Trip/Fall  Working area to be barricaded and placed


Cable Laying  Pulling Sock Coming Employ 2 2 4 0 16 appropriate signage. Supervision & Project 4
Loose From Cable ees /  Always Use Banding To Secure Pulling frequent monitoring Manager/Site
 Trench Wall Collapse Property Socks To Cable Engineer/ Supervisor
While Standing At Damage  Drum lifting jack to be inspected and
Edge certified
 Excavations deeper than 1.2 will be More awareness
considered confined space. Section 6.2.2.7 should be given in
Confined space work of the HSE form of trainings
Management Plan must be observed (and and tool box talks
mentioned) and also document DWA-00-
SS-PR-UTE-0027 Confined Spaces. In
addition, section 4.1.Work in ditches and
manholes from Doc. DWA-00-HS-PR-EPC-
0016 Excavation and Earthworks must
observed and mentioned.
 Weight of the cable hence avoid single
person has lift the cable and arrange two
helper for the lifting of cable minimum 5 mtr
distance we have to arrange two helpers
arrange more than one person during lifting
of cable .
 Cable cutting  Engage only trained and experienced
Cable Jointing /  Sheath removal Workers 2 2 4 0 16 personnel. Supervision & Project 4
Termination  Heat Shrink tubes / property  Provide tool box talk frequent monitoring Manager/Site
damage.  Use appropriate PPE. Engineer/ Supervisor
 Use appropriate tools for cutting the cables, Follow the hot work
 Keep fire extinguisher & Fire blanket near Permit procedure.
by.

Page 17 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

More awareness
should be given in
form of trainings
and tool box talks

 Keep manual handling tasks to a minimum,


Inject 1kV DC Electrical shocks Workers 2 2 4 0 16 seek help from others. Supervision & Site Engineer/ 4
voltage from the / property  Keep work place tidy and free from trailing frequent monitoring Supervisor
testing kit Damage leads.
 Test equipment to be in serviceable
condition with current calibration certificate.
 Isolated end shall be proper barricades to
prevent unauthorized entry. Safety watch
must be provided
 Use of insulated tools only
 Provide Fire Extinguisher/ FA kit for
emergency
 Esnure Trained flag persons, signs, signals,
Plant Movement Plant hitting any moving Worker 2 2 4 0 16 and barricades. awareness Project Manger/ 4
vehicle or personnel injured  Barrier shall be used when necessary, should be given in
eliminate. form of trainings Engineer/
 Put temporary Barricading such Warning and tool box talks supervisor
signs & cones Cautions Signages as
Plant prohibitated area for unwanted persons.
damaged

 Provision of Awareness About the heat


Summer Fatality / Muscle cramp Workers 4 2 0 0 24 stress hazards and importance of ideal More awareness Project Manager/ 5
Working Hours /fever rehydration schedule. should be given in Engineer/Supervisor
(Heat stress) disorientation/Sweating/ form of trainings
feeling Thirsty/ tiredness  Ensure competent supervision in all time and tool box talks
or weakness / fast
heartbeat/Dizziness  Ensure all worker wear light loose clothing
/occasional
headache/Coolwet  Must be following the ideal re-hydration
skin/nausea, schedule.
vomiting/feeling
sick/breathing quickly
 Must be provided Rest in a cool shady spot
during break time.

 Must be Provided Cool Drinking Water for


all.

Page 18 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

 Avoid the beverage such as a tea coffee/


eating hot & heavy meal during summer
time.

 Sleep at least seven hours every night

 Must be provided isotonic / lemon drinks to


workers from will provide to EPC
contractor. 15th June to 15th September,
preventive de hydration. ( we are provide
lemon drink every day)
 After 12 Work Must be stopped during
afternoon hours and time schedule ( Mid
Day Break June 15th to September 15th,
12:30 Pm to 3:00 Pm)

 Controlled speed limit at site 15 kms
Environmental Water quality, Land Workers 2 2 4 4 24 Supervision & Project Manager/ 5
 Spray water to ground on daily basis
contamination, /environme  Proper maintenance for the vehicles. frequent monitoring Engineer/Supervisor
ntal
 Use Funnel while filling the diesel.
Environmental, Air
 Keep Deep trays underneath while filling the
Spills-Diesel Quality,
diesel.
 Designated area for the oil storages.
Dust Water Quality,
 Shaded area to avoid sunlight.
Noise Land Contamination  Install sufficient fire extinguishers
 Convey the procedure in case of Emergency. More awareness
Fumes,  Provide adequate Signgages should be given in
form of trainings
Concrete spill  Proper maintenance for all machines and and tool box talks
Cutting tools. Only
 Competent operatives carry out the
operation.
 Follow the permit to work procedure.
 All operatives using cutting tool must be
certified by the safety department and
should be the holder of Competency test
certificates.
 Carry out the operation with normal speed.
 Ensure fire extinguishers are available near
the operating area.
 Install required warning signage's near the
work area.

Page 19 of 20
DWA-00-EE-MS-GNF-0001-Rev.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT

METHOD STATEMENT: POWER BLOCK


CABLE INSTALLATION

13 RELATED DOCUMENTS

 DOC0027836-000-Gransolar DEWA Installation Manual_watermarked


 D0016893-001 Gransolar DEWA System Circuit Diagram_watermarked
 DEWA-A-000215-LV and POWERBLOCKS CABLING (GenFocus)
 DWA-00-HS-PL-EPC-0001 HEALTH, SAFETY AND ENVIRONMENTAL PLAN rev2
 MP0092-A-EE-TS-EPC-0001_Rev000_Electric Installation and Assembly
 MP0092-A-EE-SL-EPC-0004_Rev000_INVERTER STATION - SLD POWER SYSTEM BLOCK
 MP0092-A-EE-SL-EPC-0004_Rev000_INVERTER STATION - SLD POWER SYSTEM BLOCK
 MP0092-A-EE-DI-EPC-0001_Rev000_POWER STATION I-O DETAILS

Page 20 of 20

PROJECT COMPANY 
 
PROJECT COMPANY ENGINEER 
 
 
EPC CONTRACTOR 
 
 
 
PROJECT 
 
DEWA PHASE III 800 MW PV SOLAR POWE
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET
DWA-00-EE-MS-GNF-0001-Rev.00A                     DEWA PHASE III 800 MW PV SOLAR POWER PROJECT 
                          MET