Procedure For Occupancy

This document outlines the procedure for applying for an occupancy permit in Quezon City, Philippines. Applicants must first obtain required documents like a fire safety inspection certificate. They then submit an application at the receiving section of the Department of the Building Official, including forms, documents, and plans arranged in folders. If the documents are complete, the applicant will get an acknowledgement slip and can check the status after 7 days. If incomplete, documents will be returned with deficiencies noted. After 7 days, if compliant, an order of payment will be issued. If non-compliant, documents will be returned with advice for corrections before resubmitting.

Uploaded by

pa3ckblanco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
895 views1 page

Procedure For Occupancy

This document outlines the procedure for applying for an occupancy permit in Quezon City, Philippines. Applicants must first obtain required documents like a fire safety inspection certificate. They then submit an application at the receiving section of the Department of the Building Official, including forms, documents, and plans arranged in folders. If the documents are complete, the applicant will get an acknowledgement slip and can check the status after 7 days. If incomplete, documents will be returned with deficiencies noted. After 7 days, if compliant, an order of payment will be issued. If non-compliant, documents will be returned with advice for corrections before resubmitting.

Uploaded by

pa3ckblanco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROCEDURE IN THE APPLICATION FOR

OCCUPANCY PERMIT
REQUIRED DOCUMENTS FROM OTHER OFFICES

• FIRE SAFETY INSPECTION CERTIFICATE (FSIC) from the QUEZON CITY FIRE MARSHALL.

Note: Applicant must present the Tax Declaration for the Improvement to the Releasing Section of DBO as
a condition for the release of the occupancy permit as per Executive Order No. 17 Series of 2012.

PROCEDURES IN THE DEPARTMENT OF THE BUILDING OFFICIAL


1. Get application forms and checklist of requirements from the INFORMATION WINDOW of the
Department of the Building Official (DBO), 9/F, High Rise Bldg., Quezon City Hall Complex or download
them from our official website. ([Link])

Compile and fasten the duly accomplished forms and other documents enumerated in the checklist
(except the plans and the technical supporting documents) in 3 long folders labeled as follows:
OWNER’s and DBO’s. Inside the OWNER’s folder are the original / certified true copies of the
documents, arranged according to their order as appearing on the checklist. Inside DBO’s folder are the
photocopies of the documents (except for the application forms which must be originally signed &
sealed), arranged accordingly.

2. Submit your application at the RECEIVING SECTION of DBO:


a. If your documents are complete, as determined by the Receiving Officer, you will be issued an
acknowledgement/follow-up slip (afs). Check the status of your application after 7 working days,
through SMS (texting) and through landline phones. Contact numbers and text format are written
on your afs.

b. If your documents are incomplete, they will be returned to you together with a list of deficient
documents. Complete your documents as noted on the checklist provided then resubmit.
Incomplete documents will not be accepted.

3. After 7 working days:


a. If your application is compliant with the provisions of the National Building Code (NBC), you
will be given the order of payment (OP). Get your OP from the RELEASING SECTION of DBO
and pay at the cashier of the Quezon City Treasurer’s Office. Bring the official receipt (O.R.) of
the permit fees to the Releasing Section of DBO.

Come back after 5 working days, and present your afs to the RELEASING SECTION to claim
your permit.

b. If your application is non-compliant with the provisions of the National Building Code (NBC),
your documents will be returned to you for you to comply based on the attached advices of
action. Get your documents from the Releasing Section of DBO. Refer with your professionals
on record for the necessary corrections.

Return your corrected documents to the TECHNICAL PROGRAM UNIT (TPU) of DBO and
follow Step 3.

[Link]

OFFICE OF THE BUILDING OFFICIAL