Check list for 132/33 kV Substation Commissioning
Client:
Site:
Bay:
(a) Current Transformer Remarks
R Y B
1 Insulation resistance
2 Ratio and polarity
3 Magnetization curve
4 Burden
5 Star point check
6 Double grounding check
7 Body grounding
8 Core allocation
9 Unused core grounding
(b) Potential Transformer Remarks
R Y B
1. Insulation resistance
2. Ratio
3. Burden
4. Body grounding/
primary grounding
5. Core Allocation
(c) Breaker Remarks
1 Insulation Resistance
2 Remote/Local Operation
3 Interlock
4 Contact Resistance
5 Timing test
6 Anti-pumping
7 TCS Relay
8 Pressure monitor
9 Body grounding
(d) Lightning Arrester Remarks
1. Insulation Resistance.
2. Counter
3. Body grounding
(e) Isolator Remarks
1.
Insulation Resistance
2. Contact resistance
3. Remote & Local operation
4. Motor Current
5. CT switching
(f) Earth Switch Remarks
1. Interlock
2. Operation
3. Contact resistance
4. Grounding
(g) Relay and Control Panel Remarks
1. Panel grounding
2. Relay body grounding
3. DC changeover
4. Cable dressing.
(h) Transformer Remarks
Insulation Resistance
2
Winding resistance
HT, LT excitation
Turn ratio
Magnetic balance
Tan-delta
BCT test
Oil BDV
WTI and OTI
PRD and Buchholz relay
Arcing horn gap
Fan operation
Tap changer remote and local operation & auto mode
Air release from all valve and valve position
Neutral and body grounding
(i) Battery charger and battery Remarks
Charging test
Battery capacity test
Cell voltage
Specific gravity of electrolyte