VOL 02 - 02 - Tech. Spec. (P.02) PDF
VOL 02 - 02 - Tech. Spec. (P.02) PDF
CONTRACT DOCUMENT
( ... ...../ ........../ ..........)
Volu1ne 2 of 2
Technical Specifications
Part/I
PART(II)
Chapter Description
CHAPTER ELEVEJ\T
CAPACITOR BANKS
CHAPTER ELEVEN
CAPACITOR BANKS
TABLE OF CONTENTS
I
11.2 Technical specifications 4
11.4 Tests 17
CHAPTER ELEVEN
CAPACITOR BANKS
The Egyptian Electricity Transmission Co. (EETC) requires to continue the process of
improve power factor of the unified power system and to reduce voltage drop of the 22 KV
three phase system, capacitor banks are needed to be installed to improve power factor and
voltage profiles at loads on the substations defined according to the attached S.L.D.
The automatic power factor control for each transfo1mer outgoing feeder shall be a three
stages switching system. The system shall be operated on the principle of power pre-
selection using isolators in the no load state and a circuit breaker for switching the power
of the whole bank. Each capacitor bank should consist of three groups rates of 1: 2: 2 (1.8,
3.6 and 3.6) MVAR to achieve a total 9.0 MVAR in fonn of three switching steps.
Each group must be equipped with unbalance cu1Tent protection and the capacitor bank
will be equipped with the following protective devices: over cu1Tent and short circuit relay,
under voltage relay, surge mTester and interlocking system between the circuit breaker of
the capacitor bank and the circuit breakers (22KV) of the transformer.
Each capacitor bank is constructed as a modular system and has a volume as small as
possible to suit the available space in the substation.
The capacitor bank could be installed outdoors or indoors according to the available space
existing in the substations taking into consideration the climatic conditi9P-s"1nenftoned in
0
item 1.5 the upper limit of temperature category of the required capac.:fror shall be 55°C
(fifty five degree) according to IEC 60871-1. /~
The capacitor banks shall comply with legal conditions and shall be coristrncted a11cl·r~ted
in accordance with the latest standard specifications of an approved loading society
(IEC ... ) or any approved standard in case such aspect are not covered in the international
standards expect where otherwise specified in these specifications.
All materials shall be of the best quality and of the suitable class to meet the working and
climatic conditions.
Electric Power Systems Engineering Company Exhibit D Page 3/20
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 1 !
6 th October Eastern Extensions 220/22/22 kV GlS S/S
Sharp daily ambient air temperature fluctuations for outdoor banks are possible. The
atmosphere is heavily polluted and it shall be taken into consideration by both indoor and
outdoor installations.
The climatic conditions prevailing in zones are shovm in volume (2) chapter (2).
11.1.7 Guarantee
A full guarantee, for a period that stated in the Bid Documents, shall be given for the
·capacitor bank, controller, switchgear protection systems and capacitor units.
The Bidder should submit a spare paii list including the individual price. The list should
include suitable number of the following.
Control box.
Spare capacitor_ units.
Spare circuit breakers and accessories.
C.B for steps connections.
- Spare parts for control and protective relays.
The required automatic P.F controller as described in item 1.2 is a shunt capacitor bank
(three groups).
The groups have rating of [Link], (1.8, 3.6 and 3.6) MVAR, to achieve a total 9.0 MVAR in
fonn of three switching steps. Each group shall have a C.B (C.B. for each step connection).
Switching from step to step should be carried out automatically and manually. The
operation sequence which could be carried out after closing the isolator and C.B is:-
.. Measuring the reactive power in the load (regulator or controller).
• If the power factor is lag and reactive power= MVAR of step 1 + 0.4 MVAR
Step 1 C.B closes after time delay.
• Measuring again the reactive power in the load.
• If the compensation still not enough (reactive power = MVAR for step2 + 0.4
MVAR).
Step 2 C.B closes after time delay.
Note: Delay time (5min for step 1&5.5 for step 2 & 6 for step 3) and measuring by
time delay relay in controller.
The neutral of the capacitor bank shall be fully insulated from the ea1ih.
The power capacitors are incorporated in welded steel cases and fitted with he1metically
sealed bushings. The capacitor bank should be completely assembled in one metallic
cubicle. The high ·voltage coru1ection, C.B, switches, inrnsh current coils, measuring
transformers and auxiliaries should be installed in metallic cubicles which have a
protection degree and insulation level of IP 54 for outdoor type and IP40 for indoor type.
The capacitor bank will be connected to 22 kV, SOHZ, 3 phase distribution systems.
The capacitor units are installed in racks and covered with H.V protective cover (metal
enclosure). High voltage terminals for external connection of the bank should be provided
by the supplier.
In additional to the main C.B. located as capacitor bank feeder C.B. in 22 kV switchgear,
the capacitor bank shall be equipped with coils to limits the inrush cunent, surge anesters,
C.B for steps connection, disconnector with earthing switch and measu;ing .transfonners
for over cmTent and unbalance cunent protection. // ·
(
11.2.2 Canacitor Unit
. II
\
[Link] Insulation Material:-
,,,,
The insulation of the capacitor unit shall be of synthetic foils (poly p;opylene- film),
however the bidder can submit paper insulation as an alternative.
All PCB impregnates are not allowed for use in Egypt. Insulation shall be of the low film
type, each capacitor shall be completely vacuum impregnated with no voids or air pockets
to prevent corona and permit mounting in any position.
[Link] Bushin!!s:-
Capacitors shall be of the two bushings and bushing shall be of well process porcelain.
All bushings shall be hermetically soldered to the steel case. Heavy tin plated clamp type,
ten11inals suitable for standard copper conductors.
The insulation level should be not less than 3.5 crn/kV for outdoor installation and 2.5
cm/kV for indoor installation.
• Power frequency a.c withstand test voltage (r.m.s) for 22 kV capacitor ba..rik 50kV,ms
(IEC 60871-1) latest edition.
• Withstand impulse test voltage crest value for 22 kV capacitor bank 125 kVp (IEC
60871-1).
• For external insulation. The power frequency withstand voltage under pollution
severity not less than 50 µS or higher for capacitor banks is 1.25 Un
[Link] Ratings
• The rated voltage of the capacitor unit is 13.85 kV (line rated voltage is 24 kV
highest system voltage U is 24 kV).
• Rated frequency is 50 Hz.
• The upper limit of temperature category of the required capacitor unit shall be 55
~C. (fifty five degree centigrade) according to (IEC 60871-1) the lower limi1js-02 G.
o Capacitor unit shall be suitable for operation of voltages as follows (IE060871-l).
100% UN Continuous operation f,· 1 ··.
110% UN For 8 hours every 24 hrs. f
115% UN For 30 minutes in every 2411rJJ
120% UN For 5 min. '\ ..
130% UN For 1 min. ·,<
(The latest version ofIEC- should be applicable in any case). '"
• Capacitor unit should be suitable for continuous operation at r.m.s cmTent of 130%
of the current that occurs at rated sinusoidal voltage and rated frequency. The
capacitor unit should withstand a maximum current of 150% In due to the combined
effect ofhan11onics and over voltages up to and including 110% UN (IEC 60871-1).
Electric Power Systems Engineering Company Exhibit D Page 6/20
Yolmne 2: Technical Specifications Rev. (0)
New Urban Communities Au1!1vrity (NUCA} Chapter 11
6th October Eastern Extensions 220/22/22 kV GlS SIS
Losses in steady state rated voltage and frequency at 25°C indoor and 55°C outdoor
ambient temperature should not be more than 0.2\V/kVAR (lower values are preferable).
The capacitor units shall be protected by internal fuses. The fuses shall, in event of element
punctures, function correctly at both, the operating voltage range (0.9) ✓2UN of the bank
and momentary over-voltages up to the limit of 2 J2UN. In the event of faults external to
the unit, a fuse must not blow at a voltage of2 ✓2UN nor in conditions corresponding to the
thennal stability test.
The fuse must withstand the relatively high imush current due to the switching operation.
When using internal fuses, the unit shall remain in operation in the event of element
punctures specified above. An internal fuse must operate in this way also when another
fuse of the unit has blown out. Regarding to further element punctures, the internal fuses
- -
. must be capable of clearing the fault at the rated voltage. The fuses shall/ ,..be--:able,
,, withstand all type and routine tests of capacitor unit in accordance with IEC.f0871-1...
. '
to
•· .
•
11.2.3 Capacitor Banks: I
!/
The capacitor banks shall include the racks for the capacitor units and mJt11tenclosure foi-
. live high voltage parts of t11e bank. Also metal connection box for lo\¥ ,_voltage ''
and
,,
secondary connections of the bank must be mounted on the bank at the works. ·~~··
Terminal blocks, internal wiring and cabling to the bank shall be included.
The bidder shall provide the banks at the work with the necessary high voltage wiring of
the capacitor units and other equipment and terminals of the bank.
The metallic parts of banks such as racks, connection and relay boxes shall be hot-zinced
(at least 600g/m2), unless of aluminum.
The degree of protection of the connection and relay boxes shall be IP54 for outdoor
installation and IP40 for indoor installations.
The capacitors shall be installed in such a way that there is adequate dissipation by
radiation an.d convection of the heat produced by the capacitor losses. For indoor capacitor
banks, one or more fans can be mounted in the bottom of the capacitor compartment to
provide forced ventilation.
The required C.B should be SF6 or vacum type with operating mechanism of spring
operated device (motor-charged spring).
The C.B shall be equipped with mechanical under voltage release for protection against
missing of auxiliary volt1tge.
Every capacitor bank _should be equipped with 9 pieces of imush current coils (3pieces per
capacitor step, one per phase). The inductance of each coil shall be calculated by the
manufacturer. The calculation should be submitted to owner for review and approval.
Each capacitor bank should be e_quipped with three phase 22 kV [Link] for steps connection
(one per capacitor step).
The C.B switches on or switches off the capacitor step according to c01mnaiids-~fro1""the
/ , '>,,,
Surge arresters shall be heavy duty lOKA station class "Zinc Oxide" type with
impulse characteristics suitable for use witl1 SF6 switchgear (or conventional type)
acc. to IEC 60099-4.
- System voltage 24
- Rated voltage of aiTester 24
- Energy discharge capability KJ/rated voltage 2.5
Suitable means shall be provided to remove surge counter without disconnecting surge
arrester.
- Insulators shall be of suitable colour glazed porcelain, all exterior metallic surface
shall be by aluminum, or any oilier suitable rec01mnended material.
- A suitable copper ground strap shall be provided to follow the most direct route
from arrester to a clainp type ground connector mounted at fue base of structure.
- Pressure relief directional apparatc1s or parts shall be located at each and of each
surge arrester unit to relieve the internal pressure which would occur in the event of
sustained 50HZ po,ver frequency current through the arrester, and prevent bursting
of the porcelain housing. Surge arrester paiis used for insulating purposes and
which are continuously subjected to applied voltage shall be of ceramic.
The following test shall be perfonned (or certified to have been perfonned)
according to the latest IEC standard which is applicable of the date of bidding:-
The following standard acceptance tests shall be carried out in accordance with the
latest IEC standard applicable at the date of bidding:-
Bidders shall fi!l technical particulars schedules with the required information
concerning the offered type.
The 3-phase disconnecter should be capable of opening and closing the capacitor bank
and canying cunent under normal circuit conditions and carrying for 3 sec. short circuit
cunent.
RatedMVAR 9.0
System voltage (kVnn,) 22
A.C withstand voltage (kVrm,) 50
Impulse withstand voltage (kVp) 125
Rated nonnal cunent (A) 800
Rated S.C current (kA for 3 sec.) 31.5
Auxiliary D.C voltage 220
Specific leakage path cm/ kV 3.5 I 2.5
The current transfonners shall be of the dry type and short circuit proof and shall have
adequate rated burden with the specified ratios.
[Link] Current transformers for over current and short circuit protection:
Every capacitor bank (with C.B and without C.B) shall be equipped with at least three
current transformers to be installed on the main bus bars of the capacitor banks for the
over current and short circuit protection.
The specifications of these cunent transformers are 400/1/lA for 22 kV; 50 Hz power
frequency test for 1 min is 50 kV and for impulse withstand voltage (peak) is 125 kV.
Every capacitor bank shall be equipped with three cmTent transformers (one for each
capacitor step). Each current transfonner will be installed on the neutral vvire
connecting the nvo star points of every step, for monitoring the unbalance current and
for the unba]a,_7.ce current protection.
30/l/lA, 22 kV 50 HZ, power frequency test for 1 min. is 50 kV, impulse withstand
voltage (peak) is 125KV.
There shall be a control unit (box) for each capacitor bank. These control boxes will be
installed in the control room of the substation. The control box shall be provided with
devices, relays for operating, monitoring, controlling and protection of capacitor bank.
The commands to connect or disconnect the capacitor steps to nenvork come from the
reactive power controller. The groups have rating of [Link] (1.8, 3.6 and 3.6) MVAR to
achieve the switching steps.
The operation of the steps is done by the Q-controller in a certain sequence as follows:-
Switching from step to step should be cruTied out automatically and manually. The
operation sequence which could be carried out after closing the isolator and C.B is:-
• Measuring the reactive power in the load (regulator or controller).
• If the power factor is lag and reactive power= MVAR of step 1 + 0.4 MVAR.
Step 1 C.B closes after time delay (3 min. for controller + 2 min. in time delay
relay).
Electric Power Systems Engineering Company Exhibit D Page 12/20
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 1 J
6'" October Eastern Extensions 220122/22 kV GJS SIS
After some delay (discharge time), the regulator may operate and switch the C.B of step
(1) on automatically as mentioned before.
Note: Delay time> (5min for step J & 5.5 min for step 2 and 6 min for step 3 and
measuring by time delay relay in controller.
The bidder shall define exactly the time delay from step to step in the bid and
shall explain the whole circuit for the controller.
The capacitor steps of the bank shall have a two-stages unbalance protection, the first
step an alarm and the second causes tripping. The alarm shall be amply delayed, while
the tripping shall be instantaneous or slightly delayed.
Technical Specification
Input rating IA
Rated burden 1.5 VA
Two input setting range (alarm-trip) 0-100%
Inaccuracy class 5
Rated frequency 50HZ.
Alan11 delay 1s-l0s (adjustable)
Trip delay [Link]-ls (adjustable)
Reset time appr. 50ms.
Reset ratio 99.8%
Protection class IP 51
Operating temperature -5 to 60°C
Contact ratings 0.15A 220 VDC
Power supply 220 VDC (150m.A Max)
Every capacitor bank shall be equipped with over ClllTent and short circuit protective relay
which is situated in the control box.
The purpose of this relay is to protect the capacitor bank against over ClllTents and S.C
faults and time delay.
In case of short circuit or sho1i circuit, the relay will open the main circuit breaker and
close some alarm contacts in the control box, at the same time, [Link]
,' '
breakers
'':¾,,
of the
capacitor steps will open.
\
Technical Data:-
Energizing inputs
Rated cunent IN lA
Rated frequency FN 50HZ
Thermal current withstand 3A
continuous
Thennal current withstand, for ls l00A
Input impedance <150mohm
Current Measurimr Circuits:
Setting current I> sating range 0.5 ... 4A
Setting cmTent I>> sating range 3 .... 20A
Dial accuracy applies overfull setting range. +5% of any setting
Repetitive accuracy +2%
Transient ove1Teach of the high set stage I>> <5%
Drop -off/pick-up ratio >0.96
Timing Circuits :
Instantaneous operating time of the I>and >> stages. 20 .... 40ms
Preset operating time of the I> and>> stages l00ms +10%
Time-lag setting range of the I>stage. 0.2 ... 30.0s
Dial accuracy, applies over full setting range. +5% of any setting
Repetitive accuracy. +2%
Drop-off time from de-energization including the :::,60ms
output relays. I
Auxiliary Supply Voltage:
Sta.11dard relay 40 ... 275VDC
Auxiliary supply burden relay :understand by tripping ""'-3W/'z6W
conditions
Influence on the relay operating values of the auxiliary ±0,5%
sunnly within is pennitted range of variation.
Pennitted rinnle in d.c supply as per IEC 60255-11 <12%
Every capacitor bank will be equipped with an over-voltage protective relay to be installed
in the control box.
This relay will measure the voltage from the potential transfom1er of the main busbar of
the transfonner without filtration. This is a special type relay which will be responsible for
the voltage at power frequency (50HZ) and the voltages accruing due harmonic of 250HZ,
""OHz, etc.
.J) / /~.. .,
;✓'
When the overvoltage relay operates, the three phase C.B's of the three capacitor S!eps
open, at the same time one of the potential phases would be cut from the reactive power
controller and will be automatically reconnected through an auxiliary contact in the
overvoltage relay when it resets again when the busbar voltage becomes of UN value.
Every capacitor bank shall be protected against under voltages by an under voltage relay
situated in the control box.
The set value for tripping is 60% UN and the rest value is 75%UN. The relay will be
provided with a time delay circuit for resetting. This delay time should be longer than the
reset time of the reactive power controller to avoid hunting and any over voltages on the
capacitor units.
The under voltage relay shall open the three phase C.B's of the three capacitor steps when
it operates.
11.3. 7 Protection Against Operation at Low Pressure of SF6 Gas of The Switching
Devices:
Every control box shall be equipped with relay and contacts to trip the main circuit breaker
in case the pressure of the SF6 gas of the main circuit breaker or any of the three C.B's
becomes lower tha11 ce1iain value.
Every control box shall have some tenninal in the trip circuit of the main circuit breaker of
the capacitor bank to be used and connected through auxiliary contacts with the trip circuits
of the 22 KV and 66KV circuit breakers of the main transfom1er. The C.B of the capacitor
will automatically switch off when any of the transformer's circuit breakers switches off or
tripped.
Electric Power Systems Engineering Company Exhibit D Page 16/20
Vo1ume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter I I
61h October Eastern Extensions 1201~2121 kV GiS SIS
Every control box wiil have three selective switches (one for each capacitor step).
The selective switch has 3 different positions (modes), for automatic mode, manual
mode and standby mode.
Every control box will have the following meters and indicating lamps on the front
panel:-
11.4Tests
General:
Owner Engineer shall attend the herein after specified tests for capacitor banks in
accordai1Ce with the latest IEC publication, in addition tests are requested by the purchaser
as mentioned in the following sections:-
Other equipment such as discharge devices, fuses, cmTent and voltage transformer,
measuring instruments, control units, post insulators and switchgears shall be subjected to
routine tests according to the relevant IEC standard.
However, the manufacturer must submit a test report for type and sample tests caJTied out
within Syears.
The capacitor unit ai1d other equipment should meet at least the minimum requirements
mentioned in the general technical specifications.
The hot-spot temperature shall be measured instead of state conditions at the rated reactive
power at an ambient temperature of 55°C by calibrated thern1ocouples placed at three
points betv,een units expected to be near the hottest spot. The hot spot temperature rise of
any unit to be delivered, detern1ined in this way must not exceed the declared value.
C) Endurance Test:
Some of the capacitor units will be subjected to endurance test according to (IEC 60871-2).
D) Routine Test:
2) Tests On Controller:
The electronic reactive power multi-step capacitor controller for high voltage three phase
networks shall be tested in accordance to the latest IEC publication (IEC 60 688-1).
a) Response Time:
The test shall be caiTied out under ambient conditions (-2+55°C) and the auxiliary circuit
shall be energized for at least the preconditioning time unless it is energized from one of
the measuring quantities and is not separately accessible.
The response time shall be in accordance to that mentioned in the item of the sequence
time of operation of the Q-controller.
All measuring circuits and auxiliai-y circuits of the control box shall be subjected to 120% ·
of the values assigned by the manufacturer for a period of 24 hours. All influence
quantities shall be maintained at their reference values. The power factor shall have its
Electric Power Systems Engineering Company ExhibitD Page 18/20
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authoriry (NUCA) Chapter 11
6'" October Eastern Extensions ??Q/02/22 kV GIS S/S
nominal value. The controller shall comply with the requirements appropriate to its class
index.
Tl1e mputs
. l 11 b e aoo r1ed to th e contro 11,er as D
s1a ·o 11ows:-
l\1ultiplying No. of Duration of each Interval between
Factor Annlications application(s) successive annlications
Current 20 5 1 5 min
Voltage 2 10 1 10 sec.
The controller shall comply with the requirements appropriate to its class index.
The ripple content of the output shall not exceed 1% of the span, careful consideration
should be given to the selection of test equipment with regard to the rnaxilnuin-freque:[Link]
to be expected. // · ·· ..
e) Voltage Tests:
(
t
Insulation tests and other safety requirement will be as in IEC 61010-1.
In accordance to IEC 60 688-1 (General pmpose transducer) 521 class 0.5 and 2 alternating
cun-ent watt-hour meters.
After completion of the impulse voltage test, the controller shall comply with the
requirements appropriate to its class index.
h) Special Tests:
The manufacturer shall submit a test report to insure that the controller shall comply with
relevant limits of intrinsic error specified for their respective accuracy 1 for a period of one
year.
One complete assembly of capacitor bank shall be tested at factory to insure and check the
functioning of different requiremen1s defined in the specification. The bidder shall sugges1
the testing method in the bid book.
The following tests will be perforn1ed by the purchaser, in the presence of manufacturer's
representative if the considers it necessary:-
Capacitor units are retested by applying a d.c voltage of 0.75 x 84.3 x UN for
10sec. between the tenninals.
- The capacitance of each capacitor unit (or units group) will be measured and
the test results corrected to +20°C (dielectric) are compared with the rating
plate values of the units.
The capacitance of each phase is measured.
- The temperature rise of the cubicle, at specified load.
- Functioning test for one week.
CHAPTER TWELVE
CHAPTER TWELVE
TABLE OF CONTENTS
12.4 Terminals 9
12.5 Protection 9
12.7 Accessories 10
12.8 Submittals 10
CHAPTER TWELVE
MEDIUM: VOLTAGE SWITCHGEAR SPECIFICATION
[Link] All incoming and outgoing cubicles shall be equipped with cable
potential tester to indicate the presence of voltage.
[Link] Each cubicle shall have on its front a mimic diagram showing the
control and operating switches as well as magnetic indicator to indicate
positions of circuit breaker and earthing switch.
[Link] Ancillary devices, such as control switches, indicating lamp etc. shall
be according to IEC standards, also identification labels.
12.2.2.l0The sheet steel cells and all their metallic structures shall be painted
with a rust resisting primer, followed by two coats of heat treated paint.
[Link] Construction of the cubicles shall be of cold rolled steel sheet of not
less than 2 mm in thickness.
[Link] Shutters shall be provided to isolate automatically live parts when the
circuit breaker is withdrawn.
[Link] Each cubicle shall be provided with the necessary heaters to reduce
internal humidity inside the cable and C.B compartments. Heaters are
controlied by humidistat.
[Link] The circuit breaker operation shall be achieved by motor and manual
charged spring mechanism. The circuit breaker should have the
facility for switching on/off electrically and mechanically from the
front of the cubicle. Mechanical indication showing spring charging
status must be provided.
[Link].3 An aux. switch with not less than five (5) N.O contacts and five (5)
N.C contacts to be provided for owner use.
[Link].4 A counter shall reflect the number of operation cycles, which shall be
capable of counting at least 99999 C.O. operation cycles; it shall not be
possible to reset the counter.
[Link].9 Motors may be sized for intermitted operations, but shall be capable at
rated voltage to charge the spring ten successive times without
impennissible rise in temperature and without tripping the motor
protections.
[Link].10 SF6 gas circuit breaker has to be provided \vith gas density device to
indicate the gas pressure with tvm signal stages one for alarm and the
other for blocking the operation of the breaker.
[Link].11 Breaker shall have a manual trip push button which mechanicaliy
trips the breaker ,vith no common components with the electrical trip. It
shall not be possible to mechanically lock the trip mechanism of C.B.
[Link].12 Circuit breaker for incoming feeders and bus tie must have the
facility of ON/OFF electrically from the front of the cubicle and
remotely from the S/S control room - local / remote switch shall be
provided.
12.2.4 Busbars
[Link] The busbars shall be made of electrolyiic grade copper with rated
current 3150A. The phase shall be marked with red, yellow and blue
colors, and mounted on 1ibbed, cast resin post insulator sized to bear
the the1mal stress and electro dynamic forces resulting from 3 phase
short circuit Cl!lTent 31.5 kA for 3 sec without adding any current
limiting equipment.
[Link] The cross section of the busbar shall be designed for a [Link]
allowable temperature rise of 30°c, above an ambient temperature of
50 °C, Calculation shall be submitted for approval.
[Link] Connection between bus and any other instrument shall be perfonned
using conductors encased in an insulated or heat shrinkable shroud.
[Link] The ground bus shall be erected along the entire length of the
switchgear at the bottom. It must be of electrolytic copper ,yith-a~.,.,..
suitable size. A stranded 185 111111 2 copper cable will be attycbed to
this bus at both ends. i · ·
-~-
[Link].2 The primary and secondary windings of current transfom1er shall be
made of copper.
[Link].4 Accuracy for measuring core and protection core is specified as per
SLD and protection scheme.
[Link].5 Rated primary cu1Tent and rated secondary current are specified as
per SLD and protection scheme.
[Link].2 The voltage transfonner shall be on the three phases. And shall be
protected by 22kV fuses. The secondary circuit shall be protected by
MCB with aux. contacts.
[Link].4 Voltage transformer may be also fixed with one load break switch
[Link].9 Rated primary voltage and rated secondary voltage are specified as
per SLD and protection scheme.
12.2.6.l Surge arrester shall be of Metal Oxide type and shall be sealed.
12.3 .3 All wiring shall be carried out without intermediate splicing. Flame
proof plastic "wiring ducts" shall be provided at sides and bottom of
panels to carry wiring vertically to terminal blocks. Ducts shall be
perforated and shall be provided with a detachable cover.
12.3.4 Wire ends shall be fitted with crimped type tenninals in which the end is
inserted along the full length of the tem1inal. Not more than one wire
shall be terminated on any one (1) stud or tenninal. Each tenninal point
on block shall be indelibly labeled in accordance with wiring
designations.
12.3.5 Incoming power supply to each panel shall be through dedicated circuit
breakers in such a maimer that supply to any one (1) panel can be
isolated from re~aining pa11els. All cubicle and control wiring s h a l ~ .
confonn to followmg color code: // · · · • ·
[Link] Black - AC control wiring other than current a11d voltage transfonn~r ····-·-···· ·
c01mections in AC/DC circuits.
12.4. Terminals
12.4. l Terminals blocks, socket and connection shall be provided to
acco1mnodate all circuits entering or leaving the panels and cubicles.
12.4.2 Tenninals shall be of screw type, unit construction, suitable for
mounting on a common bracket. Tenninals shall be rated for minimum
insulation class of 600 V. Tenninals with a disconnecting link shall be
provided to enable isolation of a circuit when necessary. Isolation of
current transfonner's circuit must short the circuit.
12.4.3 A minimum of twenty (20%) spare terminals shall be provided as spare
or future circuits. Terminals blocks shall be aiTanged vertically, mounted
at sides of cubicle and set towards rear so that ferrule numbers may be
easily read. Tenninals shall be grouped and labeled according to their
duty by strips securely attached to each terminal block.
12.4.4 Fenules identified with appropriate wire numbers shall be fitted at both
ends of each wire within pa..TJ.e!s and cubicles.
12.4.5 Terminals should be fire resistant.
12.5. Protection
12.5.2 Relays ai·e equipped with self monitoring alann system, especially for
DC supply and abnonnal level of DC voltage.
[Link] Bus-Tie
[Link].l One voltmeter with 7 position selector switch for each bus bar to
measure phase and line voltage.
12.7. Accessories
12.8. Submittals
12.8.1 Supplier shall submit with his offer in a bound fonn and under serial
number all the drawings and catalogues sufficient to explain their offer.
12.8.2 The drawings and catalogues shall include but not limited to the
following:
[Link] Detailed catalogue, pamphlets and description necessary to explain the
constructional features and function characterization of the different
apparatus [Link] are offering.
[Link] Layout of the supplied equipment with sections.
[Link] Type test report.
[Link] Single line diagram.
~ ~
SECTION THIRTEEN
�.1
f: 1h
6 October Eastern Extensions '220/22/22 kV GIS S/S
·.
SECTION THIRTEEN
[Link] Detectors 9
[Link] Alarm signal devices 10
[Link] Cables and interconnections 10
[Link] Pmver supplies 11
[Link] Fire alarm control panel 11
[Link] Submittals 11
SECTION THIRTEEN
13.1.1. General:
A) Ventilation is the process of supplying air to or removing air from a space
by mechanical fans means. Such air may or may not be conditioned.
- Filters.
Sizing of the air conditioning and supply & exhaust fans should be in
accordance with the volume of the rooms, the essential loads & their
characteristics and the climatic conditions of the site.
e) The system shall be connected to power supply rated 380/220 ±5% volts
50 Hz, three phase, four wire with solidly eaiihed neutral.
i) Air conditioning units shall be sized so that the space temperature does
not exceed the above mentioned requirements and not larger than 115%
of the total cooling load at the design conditions.
k) Ventilation system shall supply fresh air to buildings and rooms through
sand traps and filters.
Electric Power Systems Engineering Company Exhibit D Page 4/17
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 13
6 th October Eastern Extensions 220/22/22 kV GIS SIS
m) The type of the air conditioning split units for substation shall be
convenient to the zone of the substation location and from the best quality
manufacturer. The manufacturer should be approved by the owner
n) One fan (supply or exhaust) shall be provided for the control building and
FIF, Pump room as standby
13.1.5. Fabrication:
Supply & exhaust fans shall have a specified static pressure (SP) with
maximum speed (r.p.m) selected according to referenced codes and
standards.
All fan outlets shall be fitted with gravity shutters and wire mesh screen
to prevent the entrance of insects, dusty air and rain water
Louvers and/or ducts shall be used wherever, needed for the areas
ventilated by fans.
All fan systems shall be controlled by main control board (MCB). Fans
shall shut down when main control board receives a signal from fire
alarm system.
One split unit extra shall be provided for the 22 kV hall as standby.
[Link]. 7. Basement:
The basement will be ventilated by forced [supply and exhaust] fans
provided with fixed wire mesh screen.
Extra fans (supply + exhaust) shall be provided for the basement as
standby as per active system.
Filters with high efficiency shall be used to reduce the diJ.i content of the
air supplied to the different areas and to keep equipment on a clean
environment.
Filters percent efficient shall be determined by the dust spot test specified
in ASHRAE standard 52.
Filters shall be a drawer washable type and re-used.
Sand traps shall be provided for all suction openings as well as the needed
course and fine fitters as specified in EUS E-26.
13.2.1. General
Electric Power Systems Engineering Company Exhibit D Page 8/17
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chupter 13
6'" October Eastern Extensions 220i22/22 kV GIS S/S
2) The fire alann devices monitor all spaces in the building concerned.
4) Fire alann and fire protection shall be designed and installed to comply
with the latest editions of national and international standards and codes
of practice including:-
EUS (E24, E25, E26).
NFP A: National fire protection association.
IEC: International Electromechanical Commission.
BS: British Standard
IEEE - 979 guide for substation fire protection.
[Link]. Detectors:
The detectors installation will include.
- Ionized smoke detectors.
- Optical smoke detectors.
- Heat detectors.
- Duct smoke detector (if applicable).
Smoke detectors should be sited so that the sensing element is not less
than 25 mm not more than 600 1mn below the ceiling or roof, if a
protected space has a pitched or northern light roof, then smoke detectors
should be installed in each apex.
Heat detectors should be sited so that the sensitive element is not less than
25 1mn not more than 150 1mn below the ceiling or the roof.
Under flat horizontal ceiling and corridors more than 5 m wide, the
maximum horizontal distance for point type smoke detectors should not
exceed 7 .5 m and 5.3 m for heat detectors.
a. Beams have a depth greater than 150 mm but less than 10% of the ceiling
height than the maximum horizontal distance between any point in the
area and the nearest detector shall be decreased by twice the depth of the
beams.
b. Beams have a depth greater than 10% of the ceiling height in this case the
area either side of the obstruction shall be considered as a separate rooms.
c. Beams have a depth less than 150 mm. This can be ignored.
b. Sounders:
Sounders shall be electronic type.
Sound level shall be a minimum of 65dB, or 5 dB above any
background noise likely to exceed 30 seconds.
The number of the fire aiarm sounders shall be sufficient to
produce the sound level recommended with at least two sounders.
All sounders throughout the building must produce a similar
sound.
The sounders shall be a1Tanged in at least two separate circuits.
One sounder shall be mounted in the control room.
The main supply for the fire alann control panel shall be derived from the
main AC board.
Both batteries and charger shall be located in fire alarm contr;ol panel.
[Link]. Submittals
In addition to EUS - E 24 clause 8 the following submittals shall be
provided after award of contract:-
!. Wiring diagrams showing connections between all system components.
2. Description of system operation.
3. Annunciator schedule showing titles for each fire alarm and supervisory
zone.
4. Manufacturer's literature marked to show model and catalogue the
number of equipment.
5. Manufacture's installation instructions, operations and maintenance
Electric Power Systems Engineering Company ExhibitD Page 11117
Volume 2: Technical Specifications Rev. (0)
New Urban Commw1ities Authority (NUCA) Chapter 13
6 th October Eastern Extensions 220/22/22 kV GIS SiS
instructions.
6. A complete layout of the entire system including conduit routing, conduit
sizes, wire sizes and types.
7. Battery sizing calculations indicating circuit loading and power supply
loading, voltage drop calculations shail be submitted for all notification
appliance circuits.
[Link]:
'""-~
-•··> · ·¼~: ..
, ,:)
[Link]. In order to prevent or reduce a fire in case of oil spill, transformer oil
collection pits shall be provided.
[Link]. The fire fighting systems shall instantaneously act as soon as fire staii
to open the spray hydrant to extinguish the fire in a shortest possible
time. The fire protection systems shall be suitable for manual aI1d auto-
operation.
[Link]. The manual operation is carried out with an excitation valve in the
valve station.
[Link]. In case of a fire in any transfonners the fire detection system shall
instantaneously come into action isolating the transformer by tripping
the transfonner circuit breakers and put the fire extinction system into
action.
[Link]. The number of the11110 element detectors shall not be less than 12 for
220/22/22 kV transfonners and shall be suitable to the transfonners
size and shall be mounted at the cover level of the transfonners.
[Link]. The detectors shall detect at every moment ai1 abnonnal temperature
rise generated by a fire on the tank, the tenninal or even on the
transfo1mer bed.
[Link]. The detectors shall be designed and equalized such that they do not
operate at slow temperature rise which may occur due to variation of
ventilation, variation load, solar beam, etc.
[Link]. The design of the detectors shall ensure complete security, such that it
will not operate due to any reason except fire, and complete
dependability in case of fire.
[Link]. The detectors shall be series mounted by a fire resistance electric cable
which is connected to a detection unit.
[Link]. Provision shall be made for a guard current following through the
detectors, interruption of the gnard current due to break of the elements
series connecting cable or loose terminal shall activate an audible and
visible alann signal at the detection unit of the equipment, indicating
interruption of guard current.
[Link]. This signal must not activate the extinction system and the signal can
be used for blocking of the extinction system on request.
[Link]. In order to prevent the activation of the system due to false indication,
the detection system is doubled with one piping system pressurized by
air and with thenno activated nozzles and with one electric
differential thermo activated system. The water spray system is
activated only when fire detection signal is given from the two
detection systems at the same time. Activated system as in A or B
below shall be indicated in a central unit and activates the a~ea-firee-,....,
alarm signal ./.:
[Link]. The fire protection system shall be suitable for manual and auto
operation.
\
[Link]. The water pressure shall meet the requirements of efficient operation
of the spraying nozzles.
[Link]. The storage vessel shall be equipped with filling inlet, discharge
outlet, discharge pipe in direction of compressed air.
[Link]. The water pressure system shall have jockey pump sufficient to
charge the water vessel to the specified pressure within a time not
more than (3) three hours. The jokey pump shall not be less than 10
1113/hr for 220/22/22 kV transformers.
[Link]. Primary water tank shall be hot dip galvanized at less than 1000 liter.
[Link]. One compressor system (with two heads & two motors) and Two
Jockey pump shall be provided for each transformer to be one system
in operation and the other as [Link]. The compressed air vessel of
the compressor shall not be less than lO00L Letter size for 220/22/22
kV transformers. Each system shall have its own control, protection
power supply etc, and will be adjusted on operation mode or, standby
mode by a selector switch.
[Link]. The water of frre fighting system shall be supplied from the main
water tank and will be included in scope ofF.F work. f,,/~---
_/'
13.6. SUBMITTALS . ;
Submit drawings, design, calculation, test rep01is and literaturJ peiiaining
to specified items. Submittals shall include but not limi\ed to the
following: \ ·
- "" ·~",,.
·--~,,~
a) With Elevender:
1. Reference list of all components of each system.
2. Schedules, performance curves, charges, instruments, diagrams,
catalogues and any other information necessary to demonstrate the
requirements, operation of a complete system and compliance to
specification requirements as well as codes and standards.
3. A complete electrical connection diagrams for each electrically
controlled components having control device shall also be
submitted.
4. A complete detailed calculations for H.V.A.C system
5. Others which are required by the tender documents.
CHAPTER FOURTEEN
CHAPTER FOURTEEN
TABLE OF CONTENTS
f'?
.. 14-7 Tests on Cu1Tent Transformers 50 t{
Iii" :"
I ,, -J
.•
t.t 14-8 Tests on Inductive Voltage Transformer 52
14-9 Tests on Lightning [Link] 54
14-10 Tests on M.V. Switchgear 56
Li
14-18 Tests on Capacitor Banks 79
14-19 Tra.1sformer Fire Fighting System Tests 82
14-20 Power Transformer Factory Test 84
14-21 Transformer Site And Commissioning Tests
14-22 Telecommunication Tests
./
/.
,/•'.,
,. .j "' -·>',.
ii:::\�
i
l!
u
Ll
CHAPTER FOURTEEN
14-1) General
I. Oualitv Assurance
1.1 All material shall comply with and shall be manufactured and tested in
accordance with requirements and the latest editions of relevant
publications of the international electro-technical commission. Where no
IEC publication has been issued to cover a particular subject then a
recognized national standard with same or higher quality shall be applied
and approved by the owner.
1.2 In cases of conflict between this specification and any of the referenced
codes and standards, the following order of precedence shall apply:-
1.3 The Contractor is totally responsible for the good function and the
quality of the delivered plant equipment. To ensure this, a Master
Quality Assurance Programme must be adopted and in service ·within
the Contractor's entire organization.
The Quality Assurance Prograimne shall cover but is not limited to the
following items:-
1) Contractor's organization.
2) Contract review.
3) Design assurance.
4) Document Control.
5) Measuring and test equipment.
6) Purchasing.
7) Incoming inspection.
8) In-process inspection ( Field inspection ).
9) Final inspection /conunissioning.
10) Inspection status.
11) Identification and traceability.
12) Handing and storage.
13) manufacturing and erection.
14) Special processes.
15) Packing and shipping.
L
New Urban Communities Authority (NUCA) Chapter 14
61h October Eastern Extensions 220/22/22 kV GIS S/S
2. Tests
General
b) Two English copies of the applied standards other than IEC should be
[Link] to Owner with the test procedure.
f) The expenses of all tests carried out during and after manufacturing at
works shall be included in the FOB or CIF price of the equipment. Also
expenses of tests at site after erection which will be carried out by the
contractor, shall be borne by the contractor.
g) The costs of the tests at works and site shall cover all expenses,
including cost of apparatus and instruments used, equipment, labor etc
required for carrying out of the tests.
h) All instruments used for the purpose of the testing shall be of approved
type and shall have been calibrated by a recognized laboratory which
must be accepted by Owner, particulars of the calibration shall be given
on the test certificate.
j) Type test to be carried out within the last ten years and test certificate to
be submitted with the offer (for evaluation) on one unit, of apparatus of
the same type to ensure that the apparatus under test satisfies the
specified working and all the conditions laid down as regards, design,
dimensions, quality of the principal materials and workmanship.
/---~
k) Special test to be carried out on one/All (according thejt)'pe-_
/
of~,_ ,'. -, '-:' -~-,
, l;\
o) Bidder shall submit with his bid all type test ce1iificates and special test
certificates for items of equipment including power transfom1ers where
items of the same design and rating have previously been subjected to
the required tests.
furnish the test repo1is to the Owner inspection Engineer, who 'Nill select
by random, samples equal to the higher whole number to the square root
of the number of the equipment of or 10% of the total nubmer of
equipment the consignment which to be tested in his presence, as a first
test of this selected equipment if the results of the tests on these samples
are same as results on their test repo1is, then the inspection Engineer
shall approve the routine test reports of the consignment, otherwise the
routine tests on all the consigmnent shall be can-ied out in presence of
the Owner inspector.
r) All equipment shall be tested in accordance with the latest edition of IEC
·and as specified herein. Following completion of the tests, two certified
copies of the test rep01is shall be submitted to the purchaser for approval.
No equipment shall be delivered until the test rep01is have been approved
by the purchaser. The purchaser, at his discretion, may waive type test
requirements where type tests have previously been carried out and
where acceptance type test ce1iificates are provided by the supplier. The
acceptance of such type test certificate shall be based on thytatet
requirements for type testing contained in this specification. / ./.
,,
·· · -·· ·· . ···· •.
Test ce1iificates are considered valid if the tests have beJii\ ,.carried
{'•
.out
within the last ten years on equipment identical to that on offer using the
test methods outlined in this specification. ·,. ·~
t) Location of Tests
u) Inspection
The purchaser may be wish to witness test or to visit the factory during
manufacture of any or all items covered · by this specification.
Accordingly, the supplier shall give the purchaser adequate notice of
manufacturing schedules and one month notice oftest schedules.
v) Type Tests
Type tests shall be carried out in accordance with the latest edition of
relevant IEC.
Type tests which have been carried out to prove the design of the
equipment shall be supported by a test certificate, giving the type,
description, location and date of the tests carried out at an approved
independent testing laboratory or witnessed by the representative of an
approved independent testing laboratory.
w) Sampling
Type tests shall be cai-ried out in one of each type of equipment offered.
y) Delivery \
Packing
The sides and top of each case shall be marked clearly with the supplier's
name, purchaser order no., item no., case serial no. and gross weight and
shall be accompanied by a detailed packing note in Arabic and English.
The supplier shall provide a guaranteed delivery time from the date of
receipt of the official order.
z) Guarantee
3. Factory tests:
The factory tests shall be specified in latest edition of IEC and this
specification, .including all optional tests, the tests shall include byt"not--~."' _
limited to the tests mentioned in the following subsections. ·
4. EXECUTION
4.1 INSPECTION
Perfonn the following checks upon an-ival of the substation equipment at site
prior to off-loading from the transporter
Report any inconsistencies noted during the inspection upon receipt to the
transport company representative and Owner.
Record all inspection observations and tests made (during the inspection upon
receipt for reference at a later date).
ii) Plan, schedule, monitor and control al! method procedures and
precautions to be followed.
iii) Measure alignment, clearances recommend adjustments and other
matters pe11aining to quality of installation.
iv) Recommend the placement of equipment, starting up adjusting and
testing the equipment, to achieve satisfactory operation and specified
performance guarantees.
(b) During assembly of the equipment cleanliness is essential.
( c) Provide all tools and equipment required during the erection.
(d) Inspect equipment transport units for external damage. Replace damaged
components prior to energization of equipment. Take care to prevent
dust and dirt particles from entering the equipment during erection.
6. FIELD TESTING
(1) Perform tests of each substation component in accordance with the relevant
subsections.
(2) Perfonn tests and verifications after erection of the substation switcl1g~-~.
as specified in the relevant sections and IEC. ' · ·
(2) Perfo1m tests of the substation switchgear as specified herein and the
relevant IEC.
A- General:
1- Bidder should submit with his bid site tests standard.
3- A program of tests shall be agreed upon between the contractor and the
owner, and a test program in conjunction with the erection and
commissioning program shall be prepared by the contractor, subject to
the approval of the owner.
7- The contractor shall record the results of the tests clearly, in a.'1
approved form and with clear references to the equipment and items to
which the refer, so that the equipment, the site tests result records shall
be provided by the contractor to the owner as soon as possible after
completion of the tests. In addition after the c01mnissioning period is
completed a test report book shall be prepared to include the results»f~
all factory and field tests. ,0 · . · ·. ·•
•
8- Details of the test equipment and instruments used shall be no{ecfin t/1e
test sheets in case where the instrument of equipment [Link] can
have a bearing on the test results.
11 - All tests agreed upon in the approved test program shall be carried out.
Any changes in the test program shall be subject to the owner review. If
agreement is reached owner will approve the changes in writing.
12 - Owner on his discretion may do any tests by his staff and his testing
equipment ,vhich to be supplied under the contract before the issuance
of the construction completion certificate, during these tests if the
owner ,vill observe any defects or deviations from the contract, the
owner, without limitation of his right to use the plant, will not issue the
construction completion ce1iificate till the contractor fulfill his
contractual obligations.
(i) All parts of the installation are dimensioned with due regard to
operating cun-ent, sh01i-circuiting effects and climatic conditions and
are sufficiently far apart for insulation purposes in all positions.
(ii) Fixed earthing devices are provided at the requisite points and are
con-ectly positioned and dimensioned. ✓~-:--,
/
.{
--- "'~,,,,
(iii) Neutral earthing is can-ied out with due regard to the main eahhing of
. h. . d ~ I ~
the network to wh1c 1t 1s connecte . t
!
(iv) The auxiliary power facility is suitably designed and dimensioned with
regard, for example, to the necessity of dependable operating [!nd
emergency disco1U1ection equipment (redundancy requirements).
(vi) Cables are of an approved type and properly dimensioned with regard to
load, voltage drops derating factors etc.
(vii) Plant is suitably designed from the point of view of operation and
maintenance (positioning of apparatus, distances, spaces, risk of
confusion, lighting etc.)
(viii) The requisites signs are provided for the identification of important
parts of the facility, and that they worded and positioned c01rectly.
(x) The relay protection system is suitably designed and complies with
current standards (functional principles, functional areas, component
selections etc.).
(xi) Indicating and recording instruments are suitable calibrated with regard
to normal loads and have adequate measuring ranges for the abnonnal
operating load occuning.
2- All ocular inspection and that all equipment installed is thus inspected.
Ocular inspection is particularly concerned with ensuring that:
(iv) The installation has been properly made (both mechanical and electrical · -
quality, eaiihing, positioning of wiring, cable areas, marking, tensipmng •.
oftenninal and·connection screws).
l
(v) · The marking of subsidiary circuits agrees with the drawings. '
(vii) The requisite signs are provided for the identification of important parts
of the facility and that text and positioning are conect, special
· allowance being made for the risk of confusion. Notices warning of
personal danger, e.g. reverse cunent, must be positioned in such a way
that they cannot be obscured by an open compartment door.
(viii) Data and markings on marking plates with the values give in drawings
and specifications.
(ix) The mimic diagrain ai1d the drawings agree with each other
simplifications in mimic diagrams and drawings are pem1itted on
3- All electrical and mechanical equipment being measured and tests and
all measurement and testing being conducted in accordance with a
previously complied list, particular care being taken to ensure that:
(v) The batteries of facility with their associated charging and monitoring
equipment have been tested in keeping with current requlations.
(vi) The D.C. circuits of the control equipment are correct lD.C. feed,
collaboration between the different paiis of the protection devices and
between the different relay protections in different combination of fault,
blockages, indication, automatic control devices, co-operation betwee~--
the protector and the auxiliary terminals of the connecting members)/" · · - "',,,
(viii) Tripping and control circuits are con-ect in all operating facilities
(switches, disconnectors, blocking and indicating devices).
(x) All signaling circuits are con-ect and all alaim devices 111 proper
working order.
(xii) All mechanical relays are in proper working order and are set and
tri1mnecl according to plan (gas-operated relay, pressure switch etc.).
(xiii) All gauging relays and time relays are in proper working order and are
set in accordance ·with a selective plan.
(xiv) The fault and signal sequence recording devices are calibrated and
programmed according to the current plan.
4) . -
Alterations occasioned bv the above review are to be entered in original
drawings.
5) Corrected drawings are to be transmitted to the personnel concerned
and to the owner.
C- Commissioning Procedures:
(i) That relay protectors are finally tested with regard to gauging relays and
direction of cmTent.
(ii) That high voltage apparatus is voltage tested at nonnal and elevated
operating voltage.
/~---~"'.,.,,,
(iii) That phasing equipment and automatic operating devices are f(nally · ·\.:1,
4-
tested.
{\
A separate testing system shall be used for these tests if possilile. The
·.'
\
test current shall be at least 10 percent of the nominal current fpr the
apparatus included in the facility.
8- All primary tests are to be carried out and documented by the contractor
under the supervision of the owner.
D- Primary Testing:
1 - Primary Faults Fed From System:
Short circuits and single-phase ground leaks are to be applied.
These tests must verify that:
(i) The relay protectors must be completely tested, which means that
they can disconnect any faults arising in connection with the
energisation of the facility.
1- On load tests:
(ii) When the transformer is energised, the circuits will still not have
been completely tested. Great imp01iance will therefore have to
be devoted to the gas-operated relay and the tripping circuits
being in proper working order. After the transfom1er has been
energised, the running cU1Tent is to be brought up to full load as
far as possible.
8. Test Certificates:
Bidders are requested to enclose with their offer S.C. test for typical
transformer to the offered transfom1er. Also type test certificates for
OLTC shall be submitted with the bid.
Test certificates are considered valid if the tests have been carried out
within the last ten years on equipment identical to that on offer using
the test methods outlined in this specifications.
In case this certificate will not be enclosed in any bidder's offer, such
bidder should take into consideration that this test will be performed on
his own account in an international neutral laboratory. In case of
account, a sepai·ate price for this test should be declared separately in
the price schedule and will be included in total reevaluated comparing
pnce.
9. Re;ection of Plant:
In the event of a defect of any item being of such a nature that the
requirements of this specification can not be fulfilled neither to be
adjusted or modified, such item shall be replaced by the Contractor, on
his own expenses, to the entire satisfaction of the Owner Engineers.
10. Submittals:
a) \Vith Bid:
3- Factory tests of the components of the plant which are not given
in this section such as:
(i) Control boards with all components.
(ii) Relay boards with all components.
(iii) A.C. and D.C. boards. /
i
(iv) Fire alam1s.
(v) Fire Fighting.
(vi) Ventilation.
(vii) Testing Equipment.
3- Reference of the testing laboratories for type test and special tests
1. Tests:
1.1 General:
1.1.1 Contractor shall perform type and routine test on the gas insulated metal-
enclosed switchgear GIS these tests shall generally be in accordance
with IEC (62271-203) and associated documents returned to that
standard and the relevant standards for switchgear components called for
in this Specification.
1.2.1 Factory type tests shall be conducted on at least one (1) of each different
type transportable assemblies of bolted, welded, plug-in and otherwise
jointed compartments to verify that all components of the specified GIS
as assembled can perfo1m satisfactory both electrically and mechanically
at or better than, the rating specified. Tests shall be in accordance with
IEC 62271-203 and Amendments subject to the following modifications
and additions:
(a) Lightning Impulse Voltage Tests, with devices in open as well
as closed position.
(b) Switching Impulse voltage Tests, with devices in open as well
as closed position.
(c) Power frequency voltage Tests, with devices in open as well
as closed position.
(d) Partial Discharge Tests 1.2Ur/✓3 according to IEC 62271-203
(e) Artificial pollution tests.
(f) Mechanical operation tests, on components of identical
L; design, voltage class and ratings.
(g) Dielectric test on the auxiliary circuits.
(h) Proof Tests for Enclosures during pressure test including
pressure test on partitions. If this test will he caJTied out in
(i) . The isolating switch due to transient over voltages resulting from
-restrikes and/or flashover of the switch to ground during capacitive
cmTent intenuption.
(ii) Other switchgear components resulting from the transient over
voltages produced by the isolator operation
1.2.3 If certified test reports for the above modified and additional tests
conducted on identical equipment are available, Bidder shall submit
them in English with the bid. In the event that these reports are not
available, the tests shall be performed at Contractor's expense. The cost
for such tests shall be included in the tender price.
The test assembly shall duplicate the high voltage conductors and
earthed pmis of the switchgear so that the same values of
electrical field stress are obtained. Tests shall be performed at the
minimum SF6 operating density for the switchgear.
(b) Lightning Impulse Voltage Dry Tests, at the rated lightning
impulse withstand voltage.
(c) Partial Discharge Tests, at 120 percent of maximum operating
voltage. This test shall be conducted on the downward excusion
of the voltage from the one (1) minute power frequency test
voltage and discharge extension shall occur above ti'1e 120 percent
voltage value. At 120 percent of maximum operating voltage the
transpo1i unit shall be partial discharge free, with due
consideration of the sensitivity of the measuring system and the -
partial discharge background level.
(d) Power Frequency voltage withstand test, one (1) minute, to be
conducted in conjunction with the partial discharge tests specified
above.
(e) Gas Leakage Tests, in accordance with Contractor's non11al
procedure, details, including test procedure and acceptance
criteria
(f) Dielectric tests on auxilim-y and control circuits
(g) Verification of correct wiring.
r~
If (h) Measurement of resistance of the main circuits.
•\L,c
(i) Pressure tests of enclosures.
G) Mechanical operation tests.
(k) tests of auxilim-y circuits, equipment and interlocks in the control
mechanism.
(1) Design and visual check.
they shall be submitted with the bid. In the event that appropriate type
test reports are not available, such tests shall be perfonned at
contractor's expense and will be witnessed by Owner.
The cost for such tests shall be included in the bid price.
When the unit test method is adopted, tests on closing and opening units
shall be made at rated closing and opening cunent with not less than one
hundred(l00) percent of rated recovery voltage.
Where the output capacity of the test plant makes it possible to meet
these requirements on two (2) or more making or breaking units 111
series, the maximum number of units shall be tested.
The rate of rise and peak value of the inherent restriking voltage applicable
to each test duty shall be the values specified, or the values guaranteed by
Contractor, which ever is the higher.
If the average of the arc duration in the three (3) tests of the one
hundred· (100) percent test duty No.1 - IEC 62271-203 is greater
than for the thirty (30) percent test duty No.2- IEC 60056, then a
supplementary test duty shall be made at five (5) percent of the
rated symmetrical breaking current.
i) Thirty five (35) Make and break operations covering the range
between lockout and normal operating pressure of the operating
mechanism and/or extinguishing medium.
ii) Five (5) Make and Break operations at nonnal operating pressure
of mechanism and/or arc extinguishing pressure of mechanism
and/or arc extinguishing medium.
iii) Five (5) Make and break operations at maximum operating
pressure of mechanism and/or, arc extinguishing medimn.
iv) Five (5) Auto-Rec!ose operations at appropriate lockout pressure
of mechanism and/or arc extinguishing medium.
v} It must also be proven that the circuit breaker operates
satisfactorily from [Link] remote and emergency manual trip device.
(b) No-load Timing Tests, as specified herein under type Tests and to be
made at the conclusion of the Mechanical operating Tests:-
The following tests shall be made and records taken to enable
all relevant parameters. e.g. contact travel, main and resistor
contact open and close etc., to be detem1ined
.. During the above operation and timing tests, the resistance of the trip and
close coil circuit shall be modified such that the current flowing is that
which would be contained under the maximum an1bient temperature
specified.
Each interrupter unit shali be assembled complete with making and breaking
resistor units etc, and shall perform fifty (50) operations comprising the
--·-.. . following:-
a) Thirty five (35) Make and Break operations covering the
range between lockout and nonnal operating pressure of the
circuit breaker.
3) Leakage Tests
Each base unit assembly shall be subjected to the following routine tests,
the operating mechanism and pull rods being artificially loaded in order
to simulate the stressing to which they are subjected in nonnal service.
(1) General
The isolators and ground switches shall be tested in accordance with the
routine and type tests stated in IEC 62271-102 and IEC 60694, subject to
the modifications stipulated in this Specification.
The cost for such tests shall be included in the bid price.
All routine tests will be witnessed by owner, both routine and type3/ tesi:s
on components supplied by Sub Contractor(s) will be also witnessed by
Owner with their expense. 1
a) With the blade locked in the closed position, the blade shall not move
with an attempted motor and manual operation. Manual operation shall
consist of the application of a 445 N force to the actuating mechanism.
During the test the switch and the switch actuating mechanism and
auxiliary switches shall not be damaged.
b) Capacitive Current Switching Test, on isolators only to demonstrate
that isolator capable of interrupting capacitive current at value
guaranteed by contractor.
c) Mechanical Endurance Test, per IEC 62271-203.
d) Sh01i CmTent Test, to verify short time current rating. The incoming
and outgoing test connections to switch shall simulate as closely as
possible those of the particular installations for which it is being
supplied.
4. SF6-to-Air Bushings:
General
SF6-to-air bushing shall be tested in accordance with the type and routine
tests stated in IEC 6013 7.
5. Instrnment Transformers:
The cun-em transformers, the voltage transformer and the control panels
and cubicles shall be tested in accordance with IEC 60044(1,2).
1. Type Tests:
2. Routine Tests:
2.1 Verification of tenninal marking.
2.2 Power-frequency withstand test on secondary windings.
2.3 Power-frequency withstand test between sections of primary and
secondary widings.
2.4 Inter tum over voltage test.
2.5 Power - frequency withstand test on primary winding.
2.6 partial discharge measurement.
2. 7 Detennination of errors.
2.8 Tests as required by IEC 60044.l & 60044.2.
2.9 Design and visual check.
3. Special Tests:
3.1 Chopped lighting-impulse test.
3.2 Measurements of dielectric dissipation factor (tan8) and capacitance.
r
j
3.3 Tests as required by IEC 60044.1 & 60044.2.
3 .4 Design and visual check.
3.5 !vfechanical tests.
1. Type Tests:
1.1 Insulation withstand tests: These tests demonstrate the ability of the
arrester housing to withstand voltage stress under dry and wet
conditions.
1.2 Residual voltage tests: These tests demonstrate the protective levels of
the arresters.
1.3 Long duration current impulse withstand tests: These tests
demonstrate the ability of the resistor elements to withstand possible
dielectric and energy stresses withstand puncture or flash over.
1.4 Operating duty tests: These tests demonstrate the stability of the
arrester under defined conditions.
1.5 Pressure relief test: For arresters fitted with the ability of the housing
to withstand short circuit cmTents without violent shattering of the .
housing under specified test conditions.
1.6 Artificial pollution test: This test is made to show that the internal
parts of the arrester including its grading system, are able to withstand
pollution without any damage and that the external insulation does not
flashover.
1. 7 Partial discharge: this test measures the internal partial discharge.
1.8 Seal leakage test: This test determines the integrity of the arrester
seals.
1.9 Current distribution test for multi -column arrester: This test
determines the current through each column of parallel resistors when
there is no electrical connection between colmI111s. /~··
./
1.10 Testing of the bending moment.
1.11 Shot circuit test procedure.
1.12 Radio interference voltage test.
2. Routine Tests:
3. Acceptance Tests:
The following tests shall be made on the nearest lower number to the cube
root of the number of anesters to be supplied.
3. l Measurement of power frequency voltage on the complete anester at
the reference cmTent measured at the bottom of the [Link].
3.2 Lightning impulse residual voltage on the complete arrester or arrester
unit at nominal discharge current.
3.3 For the partial discharge test the power frequency voltage applied to
the complete arrester or arrester unit shall be increased up to its rated
voltage ai.1d after less thaJ.1 10sec. decreased operating voltage at that
voltage the partial discharge according to IEC C270 shall be
measured. The measurement values for the internal partial discharges
shall not exceed.
3.4 Special thennal stability test.
7. Execution
7.2 INSPECTION
Perform the following checks upon arrival of the GIS at site prior to
off-loading :from the traJ.1sporter
II) Plan, schedule, monitor and control all method procedures and
precautions to be followed.
III) Measure aligmnent, clearances reconunend acljustments and other
r IV)
matters pertaining to quality of installation.
Recommend the placement of equipment, starting up acijusting
and testing the GIS, to achieve satisfactory operation and
specified performa..,ce guarantees.
9. FIELD TESTING
(2) Perform tests and verifications after erection of the gas insulated
switchgear as specified in IEC 62271-203.
(3) Perform fluid leakage test across partitions to verify the leakage rate
(4) Results ohests recorded.
Gas monitoring system test: conduct checks on the gas monitoring systems,
pressure gauges, gas density relay settings.
1. TESTING
a) All structures shall be tested in accordance with the latest edition of IEC
60652, DIN 17100 and as specified herein.
r
1 Fallowing completion of the tests, 4 certified copies of the test rep01is
L shall be submitted to the purchaser for approval. No item shall be
supplied until the test reports have been approved by the purchaser. The
purchaser, at his discretion, may waive type test requirements.
where type tests have already been carried out and where acceptable type
test certificates are provided by the supplier. The acceptance of such
type test certificates shall be based on the stated requirements for type
testing contained in this specification.
b) Test Certificates
c) Location Of Tests
2. Inspection
The purchaser has the right to witness tests or to visit the factory during
manufacture of any of all items covered by this specification.
Accordingly, the supplier shall give the purchaser adequate notice of
manufacturing schedules and one month's notice oftest schedules.
The inspector (s) shall have free access during nonnal working hours to
the shop and testing laboratories in connection with the inspection and
testing of materials
3. Tests
Type tests shall consist of a load test carried out in accordance with IEC
60652 on a complete structure of each type ordered.
The steel used for the manufacture of bolts and nuts shall meet the
requirement tests specified for material, dimensions, galvanizing and
mechanical properties and tests for bolts and nuts shall be catTied out in
accordance v,rith DIN standard 7990 and 267. Hot dip galvanization for
steel items, bolts and nuts shall be catTied out according to ASTl\11,
Al 23, A 153, A239 and A385.
4. SAkIPLING
Samples taken for routine testing shall be not less than 2% of the
consigm11ent. Specimens of plates and structural sections used in the
portals rhay be used as allowed in specification of galvanizing.
5. METHOD OF TEST
All tests shall be canied out strictly in accordance with IEC 60652, DIN
17100 and as outlined herein.
b) Assembled Portals
c) Galvanized Coatings
should the sample items fail the tests outlined in galvanized specification
the consignment represented by the sample shall be rejected. H...owever;"',..
the consignment that has been rejected may be regalvaniseq/apd then
resubmitted for test. (•
t
\
\ '
1. Type tests:
a) Mechanical Operation Tests
This test shall be carried out in accordance with IEC 62271-100. The
results shall be recorded,
d) Dielectric Tests
These tests Shall be carried out according to IEC 60694 including the
following:-
These tests shall be made on the circuit breaker closed and across the
pole tenninals with the circuit breaker open in accordance with IEC
62271-100. The voltage levels shall be those specified in system
parameters volume (2), chapter (2).
These test shall be carried out in accordance with IEC 62271-100. for
1J1e test duties listed therein. For these tests 100% rated sh01i circuit
breaking cunent sha!l be [Link].
These tests shall be caiTied out in accordance with all clauses of IEC
62271-100.
n) Tighti,ess test.
2. Routine Tests
This test shall be carried out in accordance with IEC 62271-100. The
results shall be compared with that obtained during the type tests.
f) Tightness Test
1. Type Tests:
a) Lightning impulse tests to the levels specified in system parameters,
volume (2), chapter (2) and in accordance with IEC 62271-102. These
tests shall be applied to all poles and across the open disconnector as
specified in IEC 60694.
The test for temperature rise shall be made on the dicsonnector at the
rated normal cunent in accordance wit..1-i IEC 62271-102.
d) Short - time withstand and peak cunent tests and making cunent test
for earthing switch.
These tests shall be carried out in accordance with IEC 60694, 62271-
102 and IEC 60270.
The test shall be carried out in accordance with IEC. 62271-102 and IEC
60694.
2. Routine Tests
a) Routine tests shall be carried out in accordance with latest edition of IEC
62271-102.
The test shall be carried out in accordance with IEC 60694 and 62271-
102 for routine tests. The result shall be compared with that obtained
during the type test.
These tests shall be carried out in accordance with all clauses of IEC
60270.
4. Bushings:
4.1. Type Tests:
• \Ve! power-frequency voltage withstand test.
" Dry lighting impulse voltage withstand test.
o Dry or wet switching impulse voltage.
" Thermal stability test.
• Temperature rise test.
• Thermal short-time cunent withstand test.
• Dynamic current withstand test.
• Cantilever load withstand test.
5. Tests on Accessories
6. SAMPLING
6.4. INSULATORACCESSORIES
The sample tests shall be taken m accordance with BS 3288 or
equivalent.
1. Type tests:
f) Mechanical test:
The static loads that cmTent transformers shall be capable withstanding
is 1.25 KN. The dynamic loads (e.g. short circuit) shall be not exceeding
1.4 times the static withstand test load according to IEC 60044-1.
2. Routine Tests
2.1 Routine tests shall be carried out in accordance ,vith IEC 60044-1, and
~
i
as specified herein.
' 2.2 The required routine tests are:
f) Test of accuracy
Verification that the accuracy of the metering winding in appropriate for
th.e accuracy class specified accordance with IEC 60044-1.
i) Visual inspection
On hollow insulator, in accordance with IEC 60233.
1. Tvpe tests:
d) Ferro-Resonance Test
Sho1t-circuiting of the secondary terminals 111 accordance with
procedures specified in IEC 60044-2.
j) Tightness test
This test shall be carried in accordance with lEC 60044-2.
k) Mechanical Test
This test shall be [Link] in accordance with IEC 60044-2.
2. Routine Tests
2.1. Routine tests shall be carried out in accordance with the followings:
e) Sealing Test
This test shall be canied out in accordance with IEC 60358.
g) Visual Inspection
This test shall be carried out on hollow insulator in accordance with
IEC 60358 and IEC 62155ED.1.0.
1. Tvpe Tests:
a) Insulation withstand tests on the arrester housing.
b) Residual voltage tests
c) Long duration current impulse withstand test.
d) Operating duty tests.
e) Short circuit test.
f) Internal partial discharge test
g) Test of bending moment.
h) Seal leak test.
i) Enviromnental tests.
j) Artificial pollution test.
According to IEC 60099 - 3.
k) Test of an·ester disconnectors / fault indicators if fitted.
2. Routine Tests:
2.1. Routine tests shall be carried out in accordance with IEC 60099 - 4
(clause 9.1)
2.2. The bidder shall provide details of all quality control checks / routine
tests which will be performed on individual Zno blocks (including
verification that the material is homogeneous) and on complete arresters
with a minimum requirement being the following:
3. Acceptance Tests:
3.1. Standard Acceptance Tests:
Acceptance tests shall be canied out in accordance with IEC 60099 - 4
(clause 9.2). The following tests shall be made on the nearest lower
whole number to the cube root of the number of arresters to be supplied:
3.2. Special thermal stability test. The test shall be carried out accordance
with clause (9 .2.2) with IEC 60099 - 4.
4. SAMPLING
4.1. Type tests shall be carried out on (one - three) of each type of
anester offered according to the latest IEC specification.
4.3. Acceptance tests shall be -carried out on the nearest lower whole
number to the cube root of the number of arresters ordered.
1. Tvpe Tests:
Complete Assembly:
The following tests shall be carried out in accordance with IEC 62271-
200, unless otherwise specified:
Irnpluse voltage dry tests.
Power frequency voltage dry tests.
Temperature rise test.
Short-time current tests on earthing circuits.
Verificatim1 of making and breaking capacities.
Mechanical operations tests.
Verification of degree of protection.
2. Routine Tests:
Complete Assembly:
The following tests shall be carried out in accordance with IEC 60694 -
and 62271-200, unless otherwise specified:
Power frequency voltage dry tests.
Voltage tests on auxiliary circuits.
Mechanical operations tests.
Tests of auxiliary electrical devices.
Verification of wiring.
1. Tvpe Tests:
2. Special Tests:
1. Tvpe tests
1.2.2 Type tests which have been corrected out to prove the design of the
aiTesters or its components shall be supported by a test certificate, giving
the type, description, location and date of the tests carried out at an
approved independent testing authority or witnessed by representive of
approved independent testing authorities.
2. Routine Tests
Routine tests shall be carried out on all neutral point equipment
assemblies and on individual components according the relevant
.,.,.-,-·
]EC-~--~.. ,
recommendations.
2.2.1 Routine test shall be canied out in accordance with IEC 60099-4.
2.2.2 The purchaser shall provide details of all quality control checks/ routine
tests which ,vill be performed on individual zone blocks (including
verification that the material is homogenous) and on complete arresters
· with minimum requirement being the following:
i) Measurement of reference voltage as per IEC 60099-44 (cl [Link]).
ii) Residual voltage test for lightning impulse current in range
between 0.01 and 2 time discharge current.
iii) Partial discharge test on complete arrester as per relevant to IEC.
iv) Housing seal test as per relevant to IEC clause 8.1 d.
v) Verification of surge counter operation.
2.3.3 Power frequency voltage test at the voltage level specified in system
parameters volume (2), chapter (2) as appropriate and in accordance
with relevant IEC.
Earthing Resistor
Routine tests shall be carried out in accordance with the relevant IEEE
ST 32 and IEC.
1. 1. Type test shall be carried out for one of each particular type or design of
unit type test shall be accordance with latest version ofIEC.
1.2. Insulation resistance test at 1000 V, AC for one minute are, if possible to
be cmried out on all protection, control, alarm and indication circuits to
ensure that wiring is in satisfactory condition.
1.3. Visual inspection shall ½e made on cable gland, cable joints, circuit
breaker rating and small panel items, such as indicating lamps.
1.8. Vector group, phasing, synchronizing and alann test shall alfo be carried
out. [
\
'
1.9. All panel equipment is to be examined to ensure that it is in proper
working condition m1d correctly adjusted, correctly labeled. and that
cases, covers, glass and gaskets are in good order and properly fitted.
1.13. For cables installed in a three phase 220/380V, 50Hz system the test may
be applied with a 2000 V megger insulation tester.
2. Test Facility
Terminal blocks shall be provided to accommodate all circuits entering
or leaving the panels and cubicles. The tem1inal blocks should be of fire
resistant type. For CT's circuits, tenninal blocks should be provided with
short circuit facility. For VT's circuits, tenninal blocks should be
provided.
1. Routine Tests:
Routine tests shall be carried out by the supplier on all finished cables to
demonstrate their individual integrity.
The tests shail be carried out generally in accordance with IEC
publication 60840.
(a) Electrical Test
For non metallic sheath shall be in accordance with IEC 60229.
(b) Partial Discharge Test
The partial discharge test shall be carried out in accordance with IEC
60885-3. The magnitude of the discharge at 1.5 U 0 shall not excie-od 10
PC.
(c) High Voltage Test:
No breakdown of the insulation shall occur when the cable is tested at
the voltage 2.5 U 0 between conductor and the metallic screen for 30 min.
at ambient temperature in accordance with IEC 60840.
2.2. The sampling and test procedure shall be carried out in accordance witli".. ··
IEC 6081.
3. Type Tests:
3 .1. Type tests shall be carried out be the supplier in order to demonstrate
satisfactory perfonnance of the cable design covered by this
specification.
3.2. EETC at his discretion, may waive any or all of the type tests where such
tests have been carried out previously on a cable of "similar design", and
where acceptable type test ce1tificates are provided by the supplier. The
acceptance of such type test certificates shall be based on the stated
requirements for type testing contained in this specification.
The type tests shall be carried out generally in accordance with IEC
60502-2. Tests on the serving shall be carried out in accordance with
IEC 60811.
5. Inspection:
EETC has the right to witness tests or to visit the factory during
manufacture of any cables covered by this specification. Accordingly,
the supplier shall give the purchaser at least one month's notice of
manufacturing and test schedules.
6. Sampling
21-30 .J
etc. etc.
6.2.2. The mechanical tests and the tests on the anti-c01Tosion serving shall be
carried out on samples taken from cables manufactured for the contract
in accordance with the following:-
7. Method Of Tests
All tests shall be canied out in accordance with the above mentioned and
other relevant JEC publications.
8.1. The supplier shall forv,ard to the purchaser two copies of certificates
proving that all the required tests have been carried out and that the
materials and construction comply with the specified requirements.
1. Routine Tests
l. 1. Routine tests shall be carried out on the following accessories m
accordance with test schedule attached to the relevant chapter.
" Porcelain insulators.
• Bonding leads.
1.2. W11ere manufacturer's test certificates are supplied then the tests
required on porcelain insulators may be waived at the discretion of
EETC.
2. Special Tests
Special tests shall be carried out on porcelain insulators in accordance
with test schedule attached to the relevant chapter.
3. Type Tests
3. l. Type tests shall be carried out on the following accessories m
accordance with test schedule attached to the relevant chapter:
• Straightjoints, terminations.
• Link boxes.
• Porcelain insulators of outdoor sealing ends.
3.2. EETC, at his discretion, may waive any or all of the type tests where
such tests have been carried out previously on the following and where
acceptable type test certificates are provided by the supplier.
• joints and tenninations of "similar design" where "similar design" is
as· defined in IEC publication 60141-1, IEC 60811-1 where
applicable.
• Link boxes having the same insulation level and the same
closure/sealing mechanism as those being supplied.
3 .3. The acceptance of such type test certificates shall be based on the stated
requirements for type testing contained in this specification.
4. Inspection
EETC may wish to witness tests or to visit the factory d1:1rirrg~·-
manufacture of any or all items covered by this specification.
Accordingly, the supplier shall give EETC at least one month's µotice of
manufacturing and test schedules. /'
\
"' '
5. Sampling \
5.1. Routine tests .•. .· >
Routine tests shall be can·ied out on all of the completed accessories i ~ -
accordance with the relevant chapter and IEC.
r~
6. Method Of Test
All tests shall be carried out in accordance with the above mentioned
standards and other relevant IEC publications as detailed in the test
schedules attached to the relevant chapter.
7.1. The supplier shall forward to EETC, two (2) copies of certificates
proving that all test required type tests have been canied out and that the
· materials and construction comply with the specified requirements.
1. Routine Tests:
1.1. Routine tests shall be carried out by the supplier on all finished cables to
demonstrate their individual integrity.
1.2. The tests shall be carried out generally 111 accordance with IEC
publication 60502-2.
2. Type Tests:
2.1. Type tests shall be carried out be the supplier in order to demonstrate
satisfactory performance of the cable design covered by this
specification.
2.2. EETC, at his discretion, may waive any or all of the type tests where
such tests have been carried out previously on a cable of "similar
design", and where acceptable type test certificates are provided by the
supplier. The acceptance of such type test certificates shall be based on
the stated requirements for type testing contained in this specification.
The type tests shall be carried out generally in accordance with IEC
60502-2. Tests on the serving shall be carried out in accordance wit.]}
IEC 60811.
After the impulse test the cables shall withstand a 15 minute power
frequency voltage test as follows:
3. Inspection:
EETC has the right to witness tests or to visit the factory during
manufacture of any cables covered by this specification. Accordingly,
the supplier shall give the purchaser at least one month's notice of
manufacturing and test schedules.
4. Sampling
1.2.2. Switchgear after fabrication, shall meet the requirements of the routine
tests listed in IEC 60439.
1.2.3. All control wiring, instruments, relays, etc. c:hall be tested at 2,00-0V i:o.
ground, 50 Hz for one minute in accordm1ce with IEC 60439/
2.1.2. Any [Link] unit or units may, at purchases discretion, be chosen for
testing.
2.2.2. Panels assembly, shall meet the requirements of the routine tests.
2.2.3. All control wiring shall be tested at 2000 V to ground, 50 Hz for one
minute.
4. Tests on Chargers:
4.1. General
4.1.1. All equipment shall be tested in accordance with the latest standards and
as specified herein. .
4.1.2. The supplier shall- provide acceptable type. Test ce1iificates for his
equipment.
4.1.3. The purchaser at his discretion may wish to have additional/ repeat type
tests carried out.
4.1.4. The routine tests specified shall be carried out on all units.
4.1.5. Following completion of all tests, two certified copies of the test reports
shall be submitted to the purchaser for approval. No equipme1}t.,s~af1 be···
transported until approval of the test reports has been giyen 'by the
purchaser. /
4.1. 7. Type tests shall be [Link] out at an independent testing agency or at the
supplier's laboratory and shall be witnessed by representative of an
independent testing agency or other representative acceptable to the
purchaser.
4.2. Inspection
The Purchaser has the right to witness tests or visit the factory during
manufacture of any or all item covered by this specification.
Accordingly, tl:te supplier shall give the purchaser adequate notice of
manufacturing and test schedules.
4.3. Sai.11pling
4.3. l. One unit of each different design shall be subjected to the type tests.
5. i\1ethod Of Tests
All tests shall be carried out in accordance with the above mentioned and
other relevant IEC publications as detailed in the test schedules attached
to the relevant chapter.
1. General:
Owner Engineer shall attend the herein after specified tests for capacitor banks
in accordance [Link]. the latest IEC publication, in addition tests are requested by
the purchaser as mentioned in the following items.
However, the manufacturer must submit a test report for type and sample tests
ca1Tied out within 5years.
The capacitor unit and other equipment should meet at least the mmnnum
requirements mentioned in the general technical specifications.
A) Tvne Tests:
The required type tests are:-
The1111al stability test.·
Capacitor loss tangent (tan8) measurement at elevated temperature"
'"'-~-
A.C voltage test between tenninals and container.
Lightning impulse voltage test between tenninals and container.
Sh01i-circuit discharge test.
Ionization test.
C) Endurance Test:
Some of the capacitor units will be subjected to endurance test according to
(IEC 60871-2).
D) Routine Test:
The required routine tests are acc. to IEC 60871-1
• Capacitance measurements.
• Capacitor loss tangent (tan 8) measurements.
3. Tests On Controller:
The electronic reactive povsTer multi-step capacitor controller for high voltage
three phase networks shall be tested in accordance to the latest IEC publication
(IEC 60 688-1).
a) Response Time:
The test shall be can-ied out under -ambient conditions (-2+55°C) and the
auxiliary circuit shall be energized for at least the preconditionin.g time unless it
is energized from one of the measuring quantities and is not separately
· accessible.·
The response time shall be in accordance to that mentioned in the item of the
sequence time of operation of the Q-controller.
,,.
..···
e) Voltage Tests:
Insulation tests and other safety requirement will be as in IEC 61010-1.
In accordance to IEC 60 688-1 (General purpose transducer) 521 class 0.5 and
2 alternating current watt-hour meters.
After completion of the impulse voltage test, the controller shall comply with
the requirements appropriate to its class index.
h) Special Tests:
The manufacturer shall submit a test report to insure that the controller shall
comply with relevant limits of intrinsic error specified for their respective
accuracy 1 for a period of one year.
b) Motor:
Installation check.
1. Insulation resistance measurement.
11. Bearing and winding temperature detectors installation and
calibration check. ·
111. Lubrication check.
1v. Visual inspection: Aligmnent, leveling plumpness and bolting
down, tenninal connections, cable cover, ground connections
general workmanship and cleanliness.
v. Results of tests certified:
v1. Lr1 order to proved completion of the works, the following tests
for taking over and acceptance shall be perfom1ed in presence
of owner representative.
b) l\1otor:
1. Energization.
IL Phase sequence/ rotation check.
111. Motor operation check- uncoupled and coupled staii and rmming
cmTent; tern1inal voltage; vibration.
JV. Functional tests of control logic and alann system.
V. Visual inspection.
Vl. Results oftests recorded.
Vll. Results oftests certified.
c) Piping:
1. Piping equipment inventmy check.
ii. Piping installation inspection.
111. Results of tests recorded.
1v. Results of tests certified.
J. The factory tests shall be as specified in latest edition of IEC, including all
optional tests, the tests shall include but not limited to the following tests:
1.1. Bushings:-
All type tests and routine tests mentioned in latest edition of IEC shall be
carried out. The test ce1iificates shall be submitted to the owner.
1.2. Transfonners:-
a. All type and special tests to be canied out on one unit of each type in
addition to routine tests shall be carried out on all units of same
equipment in accordance with the latest edition of IEC 60076, m
presence of owner inspector.
Test on wiring:
Insulation resistance test at 2000 V AC for one minute are, if possible, to
be canied out on all protection, control, alarm and indication circuits to
ensure that wiring in satisfactory condition.
Factory witness tests shall be conducted on the RTU equipment (in the
manufacturer's factory in presence ofEETC representative).
All RTU materials, hardware, and firmware to be furnished and all work to
be performed under this Specification shall be subject to inspections and tests.
The RTU shall not be shipped until all required inspections and tests have been
made, demonstrating that the equipment conforms to the Specification and that
ilie hardware and finnware have been approved for shipment by EETC
2. Inspection:
Representatives ofEETC shall have free entry into the facilities of the RTU
manufacturer at any time while design, fabrication, or testing of the equipment
is taking place and into any mill, shop, or factory where the hardware or
firmware described in this Specification is being produced.
3. Test Procedures:
The Contractor shall submit the RTU test plans for approval eight (8) weeks
prior to the sta1t of factory tests. Fully approved test procedures shall be
submitted to EETC at least four (4) weeks prior to the conunencement of the
tests. EETC will only approve test procedures if they are inclusive, thoroughly
testing each section of the equipment. The Contractor shall use ANSI N1C8.1,
"Recommended Practice, Hardware Testing of Digital Process C01nputers,~ as a
guide in preparing the RTU test procedures. The test procedur6shall inchld~
the following: 1
" The test schedule, including provision for eight hoi;irs of unstructured
tests to be performed by EETC. \, .
',
• The purpose of each test. '
• The function to be tested.
The Contractor shall maintain a complete record of the results of all tests.
This record shall be keyed to the steps enumerated in the previously approved
test plan. The record shall include the following items:
(i) Reference to the appropriate section of the test plan. _____ ..•
(ii) Description of any special test conditions or special action tak~n.
(iii) Test results passed/failed.
5. Factory Tests:
The RTU shall successfully pass a complete test before being accepted. This
complete test shall include, but hot be limited to, all of the following functional
performance tests:
(i) Inventory check and inspection for general appearance, cabling
drawing confonnance and labeling.
(ii) Checks of proper fnnctioning of all hardware and finnware a
thorough exercising of all RTU functions, both individually and
collectivity.
(iii) Simulation of inputs, including noise and transient conditions,
using convenient test panels, which allow each input to be varied
over its entire range via individual setters.
(iv) Checks of power supply voltage margins, ripple levels and sh01i
circuit protection.
(v) Test of all digital input points.
(vi) Test of all SOE input points including time synchronization and
time stamp accuracy.
(vii) Test of all control outputs.
(viii)Checks of analog accuracy, temperature coefficient, noise rejection,
and over-voltage protection on 10% of all analog point.
The Contractor personnel shall conduct the field performance test after::
installing, starting, and checking the equipment at field location. All hardware
shall be aligned and adjusted, interfaces all inputs and outputs established, ·.
operation verified, and all test readings recorded in accordance with the'
Contractor's reco1mnended procedures. The field perfonnance test shall .
exercise all functions of the RTU and duplicate selected factory acceptance
tests to the extent possible. This testing shall include but not be limited to the
following conditions:
(i) RTU initialization.
(ii) Diagnostics.
(iii) Checks of proper functioning of hardware and firmware by
exercising of selected RTU functions.
(iv) RTU c01mnunication interfaces including failure modes.
(v) Database modifications, including point changes and download
capability.
(vi) End to end closed loop test to EMS/SCADA system, which covers
all field signals connected to the MIC. Necessary c9orclirtirlion'~· ..
work with switchgear Contractor shall be made to/successfully
perform this test.
(
Type Tests:
Bidder should submit all equipment test certificates and type test,r.e.p_01:ts,/
valid through the last ten (10) years according to IEC standard.
CHAPTER FIFTEEN
CHAPTER FIFTEEN
TABLE OF CONTENTS
CLAUSE j
1 DESCRIPTION I Page
15.1. General 3
15.2. Type and Main Characteristics I
15.3. Limits of Temperature Rise I
4
15.4. Continuous Power Rating 4
15.5. Limited Periods Ratii7.g 5 I
15.6. Ability to \Vithstand Short circuit 5
15.7. Efficiency and Losses 5
15.8. Harmonics 7
15.9. Noise Level 7
15.10. Transformer Parallel Operation 8
15.11. Transfonner Cooling System 8
15.12. Neutral Point I [; 10
15..13. . Eady Fault Detection I
I '·lff
-� ? i
15.14. Transformer Construction 10
15.15. On Load Tap-Changer 12
15.16.· Oil Preservation System 15
. 1s.1r . Bushings ..: , , 15
15.18. Current Transformers :116
15.19. Oil For Transfonners '" 16
15.20. Transformer Monitor and Protection 18
15.21. Terminal Cabinet !9
15.22. Accessories and Fittings 19
15.23. Remote Control and Protection 19
15.24. Gas Protection 19
15.25. Protection Against Excessive Heating 19
15.26. Protection Against Heating ofTransfom1ers 20
15.27. Protection Against Low Oil Level 20
15.28. Painting 20
15.29. Nameplates --~ . ·~� I 20
15.30. Maintenance Materials ·. •, :-'e,· ,>/ ',t\ 20
r"
-"
,/
. . . i"i1?)
Electrical Power Systems Engineering Company Exhibit D Page 2/21
Volume 2: Technical Spedtications Rev. (0)
New Urban Communities Authority (NUCA) Chapter ] 5
61h October Eastern Extensions 210/22/22 kV G1S S/S
CHAPTER FIFTEEN
15.1. General:
[Link] loading conditions with voltage ratio at main tap, full load 0.8 P.F
shall fulfil the following rates:
[Link] transfonners shall be equipped with on-load tap changers on the H.V winding
and all accessories such as fans, radiators, oil conservators (expansion tanks), etc.
[Link] the star connection windings, neutral-bushing insulators shall be foreseen.
[Link] three terminal bushfr1gs of each delta winding of the 220/22/22 kV
transfonner shall be fully covered by a cover ofIP54 and ready for interconnection
with medium voltage switchgear using cables and suitable to be connected with
three surge [Link].
[Link] principal tapping is the tapping corresponding to 100 °/o tapping factor.
i-77-v,
,:l.-. .
. 01tage rat10
.
TR's rating 125MVA TR,
No load voltage ratio at central tap. 220/24/24 kV ·••.
Full load, 0.8 P.F at central tap voltage ratio 220/22/22 kV
125MVA
ONAN Upto 60%
ONAFl > 60 to <80%
ONAF2 ?.. 80%
[Link] continuous power ratings should be verified by the temperature rise test.
[Link]. In case the transformer losses duririg rests exceed the guaranteed values in
the offer, but within the IEC standard pennissible tolerance, a penalty
according to the following formula:
Penalty= [K x EF x 8760 x C (.6. Wir + .6. \1/cu x aP 2 +bx .6. fc)] in L.E.
11 \1/fr and .6. Wcu are difference between the test and guaranteed value of
iron losses at full voltage and copper losses at full load on one transformer
at main tapping.
Based on the aim fonnula the penalty shall be calculated according to the
following rates:
L.E. 38703.5 L.E/ kW exceeds the guaranteed NO-Load losses.
L.E. 15481.4 L.E / kW exceeds the guaranteed load losses.
L.E. 15481.4 L.E i kW exceeds the guaranteed fans consumption.
If the excess loss values measured during factory tests exceed the allowable
tolerance set in IEC standards, as well if the excess in the fans consumtition is
higher than 15% then the owner has the right to reject such transfonner.
No credit shall be given for any decrease in the values of losses below the
guarantee values.
15.8. Harmonics
15.8.1. The transfom1ers shall be designed with particular attention to the suppression of
harmonic voltages, especially the third and fifth, so as to eliminate wave f01m
dist01iion and any possibility of high frequency disturbance by inductive effect or
of circulating currents between the neutral points of different transformers and
generators reaching such a magnitude as to cause interference with telephone or
communication circuits or other undesirable effects.
[Link] percentage deformation, appearing in the voltage wave of one winding of a
transformer, when the other winding is energized from a source of pure sine wave
shall not exceed 5 % (five percent) of the fundamental wave amplitude.
[Link] design and clamping of the core and windings shall be such that excessive
vibrations shall not be transmitted from the magnetic circuits to the tank and
accessories.
15.10.1. The transformers shall work satisfactory in parallel under this various
load conditions.
15.10.2. Similar rated transformer shall exactly replace of each other.
15.10.3. Tap changer mechanism shall automatically adjust the tap changer to maintain
the secondary voltage equal on all transformers to avoid circulating cunent.
15.10.4. Parallel operation of power transfonner and the mode of panllel operation can
be selected ([Link]/ Follower/ Independent).
The climatic. conditions, as specified in the relevant section, shall be taken into
consideration with respect to the cooling system.
15 .11. 1. Radiators
J5.1 l.i.1. The radiators shall be installed directly on the transformer's tank and shall
be provided with shutoff valves, drain plugs in each section of cooler pipe
work, vent plugs in each section of cooler pipe work and lifting eyes. Each
shut-off valve shal! be provided with a lever to indicate (valve open) in line
with the pipe and (valve closed) when at right angles to the pipe.
[Link]. The radiators shall be designed and constructed such as to eliminate pockets
where moisture can accumulate or which can prevent application, of a
continuous film of pajnt.
[Link]. Flexible connections in the pipe work between the main tTapsfontrer .tank
and [Link] headers to compensate thennal expansion.otcon1Tactio~ of
pipe where necessary shall be provided.
15.14.2. Insulation
15: 14.2.1. The insulation for transforn1er ,vindings and connections shall be of class A
unless otherwise approved. Contractor shall submit the test certificates and
all the details of the insulation for approval.
[Link]. The terminals, turns and tapped coils shall be provided with reinforced
insulation.
Elect1ical Power Systems Engineering Company ExhibitD Page l 0/21
Volume 2: Technical Specifications Rev. (0)
New Urban Communilies Amhor!ty (NUCA) Chapter l 5
6th October Eastern Extensions 2'0122122 kV GlS SIS
15.14.3. \Vindirnzs
[Link]. The windings conductor shall be made of high conductivity copper.
[Link]. The c111Tent density should not be more than 2.5A/mm2 for each winding
including the tertiary.
[Link]. The winding coils shall be designed to be mechanically and dielectrically
strong and facilitate dismantling and repair.
[Link]. In case of 220/22/22 kV Y/t:,./t:,. transfonner, 220 kV winding shall have
uniform graded insulation and 22 kV winding shall have full uniform
insulation.
[Link]. The terminals, turns and tapped coils shall be provided with reinforced
insulation.
[Link]. The insulmion for transformer windings connections shall be of class A.
[Link]. The windii7gs and com1ections shall be properly braced to withstand shocks
and vibrations during transport or due to short circuit current.
[Link]. Full description of the insulating material and the method of insulation shall
be given in the bid.
[Link]. In order to limit the short circuit current the percentage impedance voltage
foLtransfonner shall be as specified i,7 relevant sections.
[Link]. The percentage deformation appearing in the voltage wave on one v.:inding
of a transfonner when the other winding is energized from a source of pure
sine wave shall not exceed 5% of fundamental wave amplitude. i
[Link]. The weight of each winding to be given in guarantee schedule, calculation
for detennining these weights should be submitted.
[Link]. Provisions shall be taken to measure and record the actlla~winding
temperature at the hottest points by means of adequate sen~m's built in with
a recording facility on the transformers. ·
15.14.4. Tank
[Link]. The transfonner tank and cooler banks shall be made of best boiler of steel
plate with thickness not less than 10mm and shall be designed to withstand
without defonnation: ······-· ·
(a) Full Vacuum
(b) Positive pressure higher than the set operating pressure of the
installed pressure relief device or 125% of nonnal operating
pressure, whichever is the higher shall applied to the top of the main
tank for a period of 24 hours.
[Link]. The tank shall be provided with bi-directional detach-able cast iron wheels
provided with locking arrangement.
[Link]. The base of the tank shall be so designed, that when the wheels are
detached, it shall be possible to move the complete transformer with oil on
rollers ofjacks in any direction.
[Link]. The tank's cover shall be bolted type, equipped with manholes equipped
with lifting devices. The location and dimensions of the manholes should
facilitate the inspection of the windings and should be approved by owner.
[Link]. The tank shall be capable of withstanding the different conditions for
treatment of insulated oil especially under full vacuum.
Electtical Power Systems Engineering Company ExhibitD Page 11/21
Volume 2: Technical Specifications Rev. (0)
New Urban Cornrnunities Amhorhy (NUCA) Chapte:· 15
6:h October Eastern Extensions ?20/22/22 kV GlS S/S
of the tap changer shall be installed on the connection between the container
and expansion vessel partition
[Link]. The tap-changers shall be three phase enclosure type.
[Link]. The rated current for the on load tap-changers shall be chosen 20% higher
than the highest transfonner winding current. The tap-changer shall be
designed to withstand the routine and type tests specified in IEC 602 I 4 for
its own rated tlu·ough current.
[Link]. The tap-changer shail sustain the nonnal and abnormal operating conditions
of the transformer.
[Link]. The manufacturer of the tap-changer should be reputable manufacturer in
case the manufacturing of the tap changer is by license, the manufacturer
should has th•, experience as requested by bid document and the type test
certificates on his production should be submitted with bid.
[Link]. The manufacturer of the tap changer should confirm that the contacts of the
selector and diverter switches shall be subject to a number of cycles of
operation corresponding to (500 000) operation when can-ying cmTent
correspo_nding to the 1.1 rated through current at principal tapping. The step
voltage by marked curves showing the relation between the number of
operation and rated through current.
[Link]. Oil sampling cock at the top cover of the tap changer tank shall be
provided.
15.15.2. On-load Taos
15.15.2.l. On-load taps shall be controlled iocally and remotely by motor operated on-
load tap changing equipment of proven reliability and requiring a minimum
,_..---~ of maintenance.
/15 .15 .22:· •.. Overload and short-circuit characteristics shall be compatible with those of
/ · the transfom1ers.
[Link]. The diverter switch or the selector switch should be incorporated in its own
oil filled compartment. This oil compartment should be provided with its
own oil conservator which has no connection to the conservator of the
t~ansformer on either air or oil sides. The conservator of the tap-changer
compartment may be a separate portion of the transfonner conservator, the
oil compartment with its own conservator should be provided with the
following.
[Link].1. Excessive oil flow relay and rapid pressure relay with trip contacts.
[Link].2. Pressure relief valve with trip contact.
[Link].3. Fault pressure relay with trip contacts shall be provided in the pipe to the
conservator.
[Link].4. Dehydrating type breather mounted at eye level, the breather shall contain a
color indicator and shall be of a type in which the desiccant is not in
continuous contact with the atmosphere.
[Link].5. 1'1agnetic oil level gauge with alarm contacts, visible from the ground level.
[Link].6. Filling and oil filtering valves with dummy flanges
[Link].7. Drain valves with dummy flanges.
[Link].8. Oil sampling valves to collect the oil sample from the ground level during
the operation of the transfonner.
[Link].9. Shut off valves to be provided in the conservator pipe on the conservator
side of the relays.
[Link]. The contacts of diverter or selector switch to be copper- Tungsten or similar
approved alloy.
[Link]. The drive mechanism shall be designed so that it is impossible for the tap
changer to stop in any non-continuously rated position, if any of the on-load
tap changer components are not continuously rated. This shall apply whether
the tap changer is driven by the motor or by manual hand operation.
[Link]. When the design of tap changer requires an oil expansion tank, it shall be
piped to a separate compartment in the conservator. This separate
compartment shall be provided with its own; magnetic oil level gauge with
low level alann
[Link]. The tap changer operation shall start on a (raise) or (lower) impulse of short
duration and shall (seal-in) and complete the step by itself The duration of
a signal beyond the time required for operation shall not initiate a second
operation. In the event of a power failure during a tap change operation, Lli.e
tap changer shall automatically be changed to the next upper or lower tap
position as soon as power returns. The return of power shall not initiate a
second operation.
[Link]. Electrical limit switches· and mechanical stops or declutching device.!: shall
be incorporated to prevent over-travel beyond the maximum (raise) and
(lo,ver) positions.
[Link]. Electrical and mechanical interlocks on the (raise) and (lower) contactors
shall be provided.
[Link]. Tap-changer motor protection shall consist of an over-cun-ent automatic air
circuit breaker with manual reset.
[Link]. Provided line drop compensation of the resistance and reactance type
complete with the necessary cun-ent transformer(s).
[Link]. Provide Current and potential tenninals for test purposes
[Link]. Provide blocking facilities to prevent the tap changer from rising if the
voltage rises above an adjustable pre-set value and from lowering if the
yoltage falls below an adjustable pre-set value.
[Link]. Provide a dial type tap position indicator, a "Manual- Automatic, switch and
"Raise-Lower" push buttons or switch, loose with the transfonner, Remote
tap position indication shall be of the step by-step voltage divider type with
balance type indicating instrument whose accuracy is independent of nonnal
variations in applied voltage. Local/ remote selector switch at the
transformer shall be provided.
[Link]. A removable handle for manual hand operation of the tap changer shall be
provided. The handle shall automatically block the electrical control when in
its operating position. Manual hand operation shall preferably be practicable
from ground level. Alternatively, provide a platfonn and steps to provide
access for manual hand operation.
15.17. Bushings.
15.17.1. Type of bushings should be Air/Oil bushings as specified in volume (2)
chapter (2).
15.17.2. Bushing shall comply with IEC standard 60137, minimum leakage path shall
be in accordance with specification of the bushing shall be one part.
15.17.3. Each bushing shall have a rating nameplate showing the type designation and
catalogue number. For smaller bushings the designation can be stamped on the
flange, or be indicated on a special plate on the transformer.
15.17.4. The bushing shall be made of oil filled condenser type with means to indicate
oil level and power factor test taps.
15 .17 .5. Only one type of bushing for each insulation level shall be used on a
transfonner, each bushing should be one paii.
15.17.6. The design of bushing shall facilitate easy removal of the transfonner.
15 .17. 7. Compensation devices shall be included in order to meet as applicable Oil
expai1sion and/or building a11d equipment tolerai1ces
15.17.8. The Bidder should consider that all bushings should be porcelain type. The
bushing shall be made of brown glazed porcelain.
15.17.9. All bushings shall be designed to withstand the mechanical and thennal
shocks. Atmospheric conditions a11d temperature variations shall not affect
them.
15.17.10. Tne rated current of the bushing should be not less tha11 [1.2] times the
maximum continuous current of the relative winding.
[Link]. The rated thennal sho1i-time cmTent and duration of each bushing should be
·not less tha11 the specified short-circuit level and duration for the system that
the bushings are connected/ related to it.
15.17.12. Each bushing in addition to the spare bushing should be provided with its
clamp suitable for c01mection of incoming conductors with the tra11sfonner, the
sizes of the incoming conductors will be given at the design stage.
Transfo~·rner Manufacturers shall guarantee that the oil type can be mixed
with any percent ,vith another suitable oil type. ln that case, Manufacturers
should mention the names of oil and its specification, used for mixing
process and guarantee that there is no serious problems shall be happened
for oil quality and transformers safety.
15.19.5. The oil shall be clear and completely free from solid particles, and not give a
positive result when tested on corrosive sulphur.
15.19.6. The oil shall contain an oxidation inhibitor and fulfill the requirement
regarding oxidation resistance in accordance with IEC 1125.
15.19.7. The oil shall fulfill the requirements for class [lA] oil according to
IEC 60296.
[Link]. Container
[Link].J. The transformer oil shall be delivered in filled drums. Tnese drums shall be
~-
/,-"~-~ ~
new, of best quality and in general of a type normally used in the oil branch.
Internal surface of the drums shall be thoroughly cleaned and completely
free from any kind of particles. External surface shall be treated against
corrosion, painted with oil and weather resisting paint. The drum jacket shall
be painted in blue, and the end in white.
[Link].2. The drums shall be stenciled on bung sides with goods designation,
Consignee name and address, s·erial number and the oil and drum net
weights. These markings shall be of oil and weather- resisting black paint.
15.19.11. Transfonr,er Oil Analvsis Instrument \Vith Its Accessories (if required):
The analysis shall include but not limited to H 2, 0 2, CO, CH4, C2Hfo C2H2,
C 3H 8 , ·c2H 4 and CO 2 (PPM) with programmable 0/P relay for each Gas and
wired to control cabinet to transmit signal to control room.
15.28. Painting
The trm1sfomier tank, expa..rision vessel, coolers and all piping exposed to, direct
rays of the sun shall be painted with a non-metallic paint of approved quality and
color. .This paint shall give a compromise ben:veen low absorption and high
radiation characteristics.
15.29. Nameplates
15.29.l. The transformer nameplates shall be stainless steel.
15.29.2. The nameplates shall bear in addition to the information, specifiecrin•JEC
. '
60076-1, 1993, the following: · .. · '-
[Link]. For on-load tap changer transformers, the impedance on /i:he maxnnum,
minimum and main tapings.
[Link]. Load losses and no load losses of main and two extreme tapirtgs.
L 15.30.3.
normal operation and maintenance.
Staii-up Spare Pa1is: The Contractor shall submit a list for start-up spare
pa1is, which will be required for initial installation as well as testing
equipment for field testing of the trai1sfon11er.
15.31.2. During transport, each transformer core and coil shall be dried and shipped
preferably without oil in the tank, which shall be hennetically sealed. The
transformer shall be filled with nitrogen gas during transport, main and
spare nitrogen gas bottles should be available during transport. The bushing,
expansion vessel, breather, wheels and all other external parts might be
removed and shipped separately on condition that they can be mounted at
site without [Link] drying.
Cf/APTER SIXTEEN
CIVIL WORKS
CHAPTER SIXTEEN
CIVIL \VORKS
TABLE OF CONTENTS
16.7. Labeling. 63
CHAPTER SIXTEEN
CIVIL WORKS
General:
Since the works are required to be executed on "turnkey" basis in connection
with the installation of all building equipment and services, the works involved
in this part of contract shall comprise but not limited to design, construction
and completion in an respect, testing, setting to work, maintenance and final
handing over of substation works; all as shown in the successful tender's
approved drawings in accordance with the specification herein after.
tank.
Fire Hydrant System.
Sewerage system for S/S
Sanitary installation.
Eai-,hing system for the S/S.
Indoor and outdoor lighting and small power.
Ventilation and Air-conditioning system.
Fire detection for S/St buildings.
Any other civil works which would be essential for satisfactory of the
project (even through not specifically described in the documents and
shown in the approved drawings) shall deemed to be included in the
scope. of the work.
• The contractor should level the site at the zero level by excavating high
areas, backfilling and compacting the low areas, any soft soil or other
material which the owner consider unsatisfactory for backfilling works
should be removed from the site and replaced by clean sand without
extra charge.
• All banks and slopes (if any) should be fonned to a gradient not
exceeding one (vertical) and two (horizontal).
" Needful side pitching (if needed) should be carrying out round the
boundary wall to support the soil and according to site condition and
under the owner approval.
• Surfaces can be leveled with a suitable cross-gradient to prevent erosion
resulting from water and wind.
• The erosion protection will be provided for transformers /"area-:an(
outdoor equipments with a layer not less 10 cm of gravel/nigher than >.
final zero level.
• The surface finish should be durable enough so that ~y operations
performed during the transportation and installation of equipment sh!)li ..
not damage the surface finish.
• Roads level shall be (+0.10 m) above final zero level.
" The contractor should take into consideration that the required final zero
level of the substation area and the switching stations must not be lower
than the final levels of adjacency roads and neighbors.
• The required final zero levei of substation shall be (20) cm higher than
the access road front of the main gate.
.. The offer price should be included backfilling operations (for SiS area
and all buildings) using clean sand for backfiHing from average natural
ground level of their location up to the required final zero level and
using clean granular and well graded backfilling material for backfilling
around all foundations on layers, each layer not exceed than 25 cm,
sprayed with water, well compacting, proctor test not less than (95%)
and according to the worst soil investigation report.
[Link]. Foundations & structural and miscellaneous steel works for outdoor
equipments and receiving gantry:
" The contractor shall design and construct steel structural and fair-faced
reinforced concrete foundations for various appai-atus for the outdoor
equipment and receiving gantry. The foundations should be in adequate
dimensions to achieve the worst soil investigation report
recommendation and contour map 'and to prevent settlement, overhirningL
or other displacement and shall withstand the loadings caiculated. ·
• The end column of the receiving gantry with its foundation should be;
designed as an intermediated column.
& Foundations shall nonnally be placed on virgin soil or well compacted
fill unless otherwise specified in worst soil investigation report.
• All foundations underground surface and up to zero level must be water
proofed b'y two layers of polythene sheets of 200 micron (for each)
between the plain and reinforced concrete and the ve1iical surface sha!l
be water proofed by 3 coats of an approved type emulsion bituminous
paint unless otherwise mentioned in the worst soil investigation report
recommendations. All the visible parts and the top surface shall be of
fair- faced reinforced concrete and painted or brushed by 2 coats of
decorative water proof cementions base material.
e The height of concrete foundation over final zero level should be
3001mn.
• The erection work of steel structures shall not be started before the
involved foundation take approval, the backfilling done and the concrete
hardened sufficiently.
------
• The erection work should be performed carefully as not )6 cause ariy.
detrimental stresses to foundations and structural compof)ents.
• The anchor bolts must be fixed exact ve1iical. I
• The exact fixing must be checked also during the <1xecuting of the
foundation.
• The setting template must be fixed exact h01izontal and'Vertical ont]:ie
' , ,//
/
,,;,
formwork.
• The setting template must be dismounted before erecting the steel
structure.
Foundations on Soil:
• Foundations shall normally be placed on virgin soil or well-compacted
fill.
Foundations on Rocle
" A rock foundation is designed without any undercut. The chimney part
of the foundation is fastened to the rock by steel rods that are fixed by
mortar to the holes in the rock. Required number, depth and spacing of
the bars will depend on the quality of the rock. The contractor's
proposed solution should in each case be approved by the EETC. When
. the rock is weathered and weak, the foundation shall be designed as a
soil foundation.
Anchor Bolts: ·
• -Anchor bolts with hexagon nuts should be used to fix the equipment's in
R.C (slab, beams, "floor, wall) and designed to provide resistance to all
condilions of·compression, tension, shear and bending with sufficient
design diameter and embedded length to achieve the bond bet\veen steel
and concrete (designed according to the owner approval). ·
• The projecting part of foundation bolts and the length within 100 mm of
the concrete surface should be protected from corrosion by hot hip
galvanizing. The anchor bolts must be fixed exact vertical in foundation.
" 6.00111 the width of the main entrance lobby for the maintenance
purpose.
• 3.00m the width of the secondary lobby.
o 3.00111 the width of the longitudinal corridor on both side of the
switchgear.
• The contractor shall design and construct underground R.C oil pit, with
capacity not less than 1.2 times the volume of the oil of one transformer.
• The oil pit includes the connected PVC pipe to the sump of each of
transformers foundations with min slop 1: 100 and with diameter not
less than 150 1mn.
• The concrete should be composed of sulphate resisting cement mixed
with additional material Addicrete (D:M2) or similar kind.
• Outside concrete walls should be insulated by using two perpendicular
layers of water proofing membrane with thickness not less than 4 mm
for each layer.
,. The internal faces of R.C walls and ceiling should be smoothly cement
rendering and insulated by using oil resistance epoxy insulation pain1:ing -
according to owner's engineer approval. ·
• Kickers should be provided with water stop to prevent water penetration.
(
i
[Link] Fire Fighting Room:
" The ceiling wili be fair faced R.C paint with one primer coat & two
coats of putty and two coats of an approved type of plastic paint.
• The outside wails shall be 25 cm thick made of cement bricks size
25x12x6 cm, cement plastered from both side and internally painted with
one coats of primers, nvo coats of putty and nvo coats of an approved
type and colour of washable oil paint. The walls shall be externally
finished with an approved type and colour of high quality of cement base
whether resistant and colour stable decorative facades material (Dry mix
or equivalent), same as 220 kV switchgear GIS building.
• One meter height of the outside surfaces should be painted with nvo
coats of water proof transparency masonry points (sodium silicate base).
o The outer surfaces of the superstructure concrete elements (columns,
beams, parapet ... etc) shall be also cement plastered and finished with
the same material of walls but with different texture and/or colour.
• The ceiling will be fair-faced R.C painted with one coat of primer, nvo
coats of putty and nvo coats of an approved type of plastic point.
o The roof should be finished as follows:
o Light weight concrete having the slope towards roof drains with min.
thickness not less not less than 5cm covered with 2 cm thick cement
screed.
o 2-layers of (polyester reinforcement) water proofing membrane with
thickness not less than 4 1mn for each layer with overlap 15 cm
welding system, including skirting ended to a groove formed into the
roof parapet.
o Covering the area with geotextile for protection.
o Laying the thennal insulation 5-cm thickness from approved
exiruded polystyrene insulation board of 36 kg/m3 density.
o Covering the area with one layer of geotexti!es for protection.
o Covering with cement tiles 20x20x2 cm with cement mortar and
sand bed including skirting of same tiles.
o The roof should be accessed by a caged galvanized steel ladder.
e The floor should be as follows:
, - ~ Q Sandwich type slab consist of:
// . "·
· . □ 10 cm Plain concrete.
□ Insulation of 1wo layers of (polyester reinforcement) water
proofing membrane with thickness not less than 4 mm each layer
with overlap 15 cm welding system including skirting with 15 cm
height.
□ 15 cm thick reinforced concrete slab on grade topped with
hardener material, smoothly finished and painted with two coats
of an approved type and colour of epoxy paint.
□ 10 cm height cement skirting finished same as floor.
" Ceilings:
All ceiling· shall be painted with three coats of plastic paint except the
air conditioned rooms (main control room, all offices,
tdecommunication room and AC/DC room) shall be provided wi1h
false ceiling at 3.25 m clear height from finish floor level.
The ceiling of the Battery room shall be painted with anti-alkaline or
anti-acid paint according to the battery type which is not affected by
battery gases and fumes of an approve tested quality and color.
• Floors:
The floor of all lavatories and services rooms shall be covered with Don
slip ceramic tiles 30x30 cm of an approved quality and colour.
The floor of store room and work shop shall be R.C concrete painted
with two coats of epoxy putty and two coats of epoxy paint and ceramic
skirting of 10cm height of an approved quality and color.
The floor of the office rooms shall be covered with an approved type and
colour non-slip of porcelain tiles and porcelain skirting 10 cm height.
~The floor of the control room, telec01mnunication room, AC/DC should
be raised floor of an approved quality. The pedestal of the raised floor
should be fixed on concrete screed layer 10 cm thick finished smoothly
by Helicopter and treated with hardener material.
Note: The contractor should provide the store with 10% spare from
raised floors and false ceiling.
The floor of medium voltage room and Auxiliary transfonners rooms
should be covered screed not less than 10 cm thickness (above the R.C
slab) treated with hardener material and smoothly finished by Helicepter
and painted with two coats of an approved type and color of oil
resistance epoxy paint included skirting of cement plaster 10cm height
with smooth surface and painted with t\vo layers of epoxy putty and two
coats of oil resistant epoxy paint of an approved quality and color.
The floor of the main entrance and corridor/s should be covered with
granit tiles with minimum dimension 40x40x2 cm of fill approved
quality and color.
The floor of battery room shall be covered with anti alkaline or anti-acid
cerainic tiles somage or similar of an approved quality and colour. It
Electric Power Systems Engineering Company ExhibitD Page 13/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
. 6111 October Eastern Extensions 220/22/22 kV GIS SiS
., Roofing:
• Windows:
The windows shall be aluminum type (Technal sections or similar)
subject to the owner's approval. The windows shall be fixed to the wall
by wooden frames 2" x6" in a manner and work manlike in accordance
with the Engineers satisfaction.
\,Vindows for the ventilated room, such as 220 kV GIS room, battery
room, aux. rooms, shall be fixed type with wired glass (single) 6111111
thick.
Electric Power Systems Engineering Company Exhibit D Page 14/67
Volume 2: Technical Specifications Rev. (0)
New Crbari Communities Authority (NUCA) Chapter 16
6th October Eastern Extensions 220/?.2i22 kV GJS S/S
• Metal v\1orks:
The hand railing for platfonus, stairs, etc. should be of steel pipe of 2"
diameter and electro-statically painted with an approved quality and color
and fixed to steel balusters of square or round steel bars of approved
sections painted with two coats of red lead and two coats oil paint.
layer, smoothly finished with Helicopter machine and painted with two
coats of epoxy primer and two coats of epoxy paint.
,. Expansion joint should be carrying out every (30-35111) for hot region
and (40-45111) for moderate region.
" The building should to provided with lighting, ventilation and fire
detection systems all as specified in the relevant specifications.
" The building should be provided with sufficient windows for the day
light and t\vo sectional doors for equipments and enough personal doors.
• The building shall be provided with basement as specified hereinafter.
" The building should be provided with two reinforced concrete secondary
staircases from the finished floor level to the basement. It shall be R.C
firr;shed smoothly treated with hardener and painted with (2) coats of
epoxy paint. Steps corners should be protected by steel angles 50 x 50 x
5 1mn painted with the steps.
• The external walls shall be 25 cm thick made of cement bricks 25xl2x6
cm, cement plastered from both side, internally and externally finished
same as 220 kV building. ·
•· One meter height of the outside surfaces should be painted with t\vo
coats of water proof transparency masonry points (sodium silicate base).
• The roof should be finished as follows:
- Light weight concrete having slope towards the roof drain with·
minimum. thickness (5) cm, topped with (2) cm thick cement screed.
- Two layers of water proofing bituminous type membrar1e (4) mm
thick for each, reinforced with polyester fibers with overlapping not
less than (15) cm welding system including skirting.
Covering the membrane with one layer of geotextile.
- Laying one layer of the thennal insulation high density extruded
polystyrene boards with thickness not less than (5) cm ar1d density
. not less than 36 kg/1113 •
- Covering the thermal insulation boards with one layer of geotextile
for top protection.
Covering the geotextile layer with cement tiles 20x20x2 cm with
morter ar1d sand bed including skiiiing.
- The roof should be accessed by galvanized caged steel ladder.
- The minimum clearance between the equipment ar1d the walls inside
the building shall be as per t11e manufacturer's recommendations but
should not be less than the following:
1.50 m between the wall & the back side of the equipment row.
1.50 m between the wall & the end of equipment row.
2.50 m bet\veen each two rows of22 kV equipment.
[Link] Basement:
The basement will be under the area of22 kV s-Yvitchgear room only.
The net height of basement (measured from the finish floor level to
the beam's soffits) 'will not be less than 2.20 m, and provided with
sufficient number of windows with height not less than 0.50m.
The windows shall be aluminum tilted type with ,vired glass 6mm
thickness, and fixed wire mesh screen.
The basement walls and ceiling shall be of fair-faced concrete and
the floor shall be R. C slab shall be treated with hardener material
added to the wet concrete surfaces and finished smoothly with
helicopter machine.
Access to ground floor by secondaTy stairs and hatch opening/s with
steel ladder/s shall be provided.
The R.C walls of basement should be provided with opening for
inlet and outlet medium voltage cables of trenches outside the
building.
Walls and floor of basement under zero level should be insulated by
using two layers of water proofing membrane with thickness not less
than 4mm each layer with overlap 15cm and ve1iically protected
with brick walls not less than 12cm thickness and horizontally ,vith
3cm cement screed.
Kickers and water stop should be provided to prevent the water
penetration.
The basement shall be ventilated as specified according to relative
section.
Access to ground floor by reinforced concrete secondary stairs with
steps smoothly finished, treated with hardener material and painted
with two cats of an approved type and colour of epOA')' paint. The
comers of the steps should be protected with steel angles 50x50x5
mm anchored to the concrete and painted with two coats of epoxy
paint. Handrail of steel pipe of 2" diameter and electro-statically
painted with an approved quality and colour and fixed to steel
balusters of square or round steel bars of approval section, the steel
balusters should be fixed in R.C. stairs with suitable method.
One door with dimension not less than l.0x2.2m of steel sheets
reinforced with sufficient steel stiffeners and bracing angles should
be provided and painted with (2) coats of primer and 3 coats of
washable oil paint of an approved quality and colour.
Trays for medium voltage and control cables shall be provided as
specified in EUS - El9 - part (1).
shall be provided.
• The lower part for all gates should be covered with steel sheet
plates of 0.8 m height and with thickness not less than 4 1mn and
vvith total weight not less than the following:
o 750 kg for main gate.
o 150 kg for each personal gate.
• All the steel sections and details of all gates will be according to
owner's engineer approval.
" All gates should be painted with (2) coats of primer and (3) coats of
washable oii paint of an approved quality and colour.
• Lighting work (supply and erection) of the boundary brick wall
fence should be provided with street light fittings to illuminate the
areas on both sides of it and to be include all bulbs, tubs, lamps .. etc,
according to relative section in specification.
• Unless otherwise specified in the lighting specification section, the
light fitting for the bo"undary brick fence will be directly mounted to
its top with maximum ·of spacing 21.0 m (6 panels) using brackets
suitable for two luminaries including a lamp 250 w to illuminate the
boundary fence froni both sides according to relative section in
specification.
Q The contractor's offer shall include total price for the boundary wal(
and unit price for one longitudinal meter of the fence.
·• In case of difference between: Inside and outside levels for S/S area
is more than 50 cm. The contractor should construct reinforced
retaining wall for fences instead of reinforced foundation according
to soil investigation report and approved design.
a) Guard Room:
• A guard room (not less than 4 x 6 m) shall be erected as near as
possible to the main gate.
• The guard room for guards shall accommodate four persons
including rest facilities, toiles of western type and hand wash basin.
• The floor should be as followings:
o Sandwich type P.C slab consist of:
o 10 cmP.C.
o Insulation of two perpendicular layers of water proofing
membrane with thickness not less than 4 mm each layer with
overlap 15 cm welding system including skirting with 15 cm
height.
o 15cmR.C.
Electric Power Systems Enginee1ing Company Exhibit D Page 21/67
Volume 2: Tech.>1ical Specifications Rev. (0)
L
New Urban Communities Authority (NUCA) Chapter !6
6t!' October Eastern Extensions 220/'12/22 kV G1S S/S
b) Guard towers:
Note: All the requirement of the general department of the electricity
police regarding the specifications of the guard towers should be
fulfilled.
• Guard towers to be erected at the corners of the fence other guard
towers shall be constructed if the distance between any two adjacent
towers exceeds (125) meters window back and floor shall be made as
safeguard and the platform area shall be minimum of 2 square meter.
Electric Power Systems Engineering Company Exhibit D Page 22167
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter I 6
6111 October Eastern Extensions 220/22122 kV GJS S/S
The level of the platform shall be elevated 20 cm higher than the top
of boundary wall.
• Accessing to the platform shall be with a penrnment steel ladder to
the crital door at the wall of the guard tower.
e Building to be R.C skeleton of cast insitu concrete .
., The walls and ceiling to be plastered and painted four coats of oil
paint.
" The external finishing of the guard tmver shall be the same as
boundary wall.
" The windows shall be crital type with transparent plastic sheets.
• The floor should be as·following:
o R.C designed slab.
o Sand and cement mortar with average thickness 6.0 cm.
o The floor covered with ceramic tiles 30x30x3 cm of an approved
quality and colour.
o The skirting should be ceramic of 10 cm height.
• The floor shall be covered with ceramic tiles.
" The roof shall be covered with same finishing layers of insulation of
the buildings and-covered by cement tiles 2 cm thick.
•. The contractor offer should include total price of guard towers and
include unit price for one-guard tower.
a The contractor shall design and cany out the fire fighting line covers the
·-·-··· whole area of the substation:-
o The fire hydrant line should be of flanged connecting galvanized
steel pipe 6" diam from high quality type.
o The fire hydrant line should be above ground fixed to plain concrete
supports with suitable dimensions and with height not less than 50
cm aboveground on distance equal to the line pipe unit or fixed to
the R.C columns of boundary fence.
o Wnen the pipe line is crossing road/s, it should be laid inside rigid
PVC sleeves. In case of the line need to be imbedded (subject to the
Engineer's approval), the embedded p01iion/s should be insulated
against c01Tosion by an approved manner.
o The above ground pipe line should be painted with two coats of
suitable primer and three coats of oil paint in red colour.
o Enough vertical fire hydrants (Morise type) with diameter 2.5"
properly fixed to steel and/or concrete supp01is at approved positions
with distance not exceed 50m between them, included all necessary
accessones.
o Fire hose made of linen (Morise type) with diameter 2.5" and length
not less than 30111 with all accessories on approval of fire brigade
before supplying.
o Cabinet for keeping fire fighting tools (extinguishing hose, ... etc.)
vvith dimension not less than 80x80x35 cm made of steel sheet plat
with l .51mn thiclmess, painted with 4 coats of red oil paint, provided
with glass door 6111111 thiclmess and all accessories.
o Bronze valve control for high pressure covered with Nickel material
with circular handle should be provided.
o Full details of the fire fighting line (design and drawing) should be
submitted for owner's engineer approval.
o The fire hydrant pipeline should be tested on 10 bar and the work
pressure should not be less than bar at th.:; end of the line.
• The contractor should take into consideration the civil drawings and the
specification to cotnplete the scope of this item.
" The contractor is obliged to design and install sewerage system inside
the substation and handed over to owner in good working condition, the .
system shall include but not limited to the following:-
o Complete sewerage (supply and installation) system for substation
buildings sufficient for 30 person at least.
o Manholes.
o Exact route, location and level of each pipe line and manholes are to
be checked before executing to secure suitable slope of sewerage
system.
o The contractor shall submit a complete description of his proposed
sewerage system the design should be according to soil investigation
report and precautions subjected to the approval of owner's engineer.
o All outside pipes material and waste water piping for acid
contaminated water should be (HD Polyethylene) pipe with diameter
not less than 6" included all fittings.
o The sewage system shall be locally closed system (i.e not connected
to external sewage plant).
o The [Link] water of the air-conditioning system should be
drained to the S/S draining system.
a. Manholes.
• The contractor shall design and construct underground fair-faced R.C.
manholes and it should be at the road level beside the sidewalk of the
buildings, the distance between two manholes not exceed 30m and the
depth according to the slopes of the pipe line and the direction of flow
with slope 0.005:0.007 between outlet and inlet of the manhole.
• R.C waste sump, approximately one meter cub. should be installed
outside the S/S building with special drain connection from the battery
Electric Power Systems Engineering Company Exhibit D Page 26/67
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Aut11ori1y (NlJCA) Chapter 16
6111 October Enste1T1 Extensio:is '20/22122. kV GIS S/S
room for alkaline or acid contan,inated water, manhole cover should be.
provided with a limit access warning sign showing battery alkaline or
acid contents (waste sump alkaline or acid contaminated water).
• All sides of manholes and its base shouid be R.C with min steel 5010/rn'
in both directions depending on the design and worst soil investigations
report.
• The concrete should be composed of sulphate resisting cement mixed
with additional material Addicrete (Dlv12) or similat.
~ i\.1anhole within the road shouid be provided with heavy duty cast iron
cover and medium duty for the other man-holes.
b. Sewerage Tanks.
• The contractor shall design and constn1ct undergrounc£ R.C (septic tank,
filter tank and coilecting tank) sufficient for 30 person at ieast, and with
min. (discharging time 1.5 month), the dimensions, design and details
shall be according to owner's engineer approval.
• The reinforced concrete should be composed of sulphate resisting
cement mixed with addition_al material Addicrete (DM2) or similar kind
of an approved type.
e Inside faces shall be smoothly cement rendered and insulated by epoxy
insulation pafr1ting, outside concrete surfaces should be surrounded with
two perpendicular layers of water proofing membrane with thickness not
less than 4mm each layer with overlap 15cm welding sys-cem and
protected ·with brick walls not less than 12cm thick.
• Kickers should be provided with water stop to prevent water penetration .
., All [Link] have upper R.C. slab included enough rnanholes opening
(O.6xO.6m) provided with cast iron cover and inside steel ladder.
• Proper access should be provided to the sewage tanks to facilitate foe
discharging work.
S-:initary installation as specified hereinafter rn clause 15.5.13.
16.1:2.18 Lighting:
o The lighting fitting should be decorative type.
• All lighting units should be of saved energy type.
• The contractor shall supply and install the interior and exterior lighting
for firefighting buildings guard room, guatd tower, shed roof for
vehicles, boundary wall fence, gates, main roads, secondary roads this
lighting should be designed to achieve the specified levels of
illumination and lighting colors.
• The main lighting circuit, the routing of lighting cables, the number of
lighting switches and the routing of telephone cable as indicated in
relative section in specification.
,. The contractor should supply and install telephone cables and their
required plugs for offices, PLC room, controi room guard room.
Electric Power Systems Engineering Company Exhibit D Page 27/67
Volume 2 : Technical Specifications Rev. (0)
New Urbar. Communities Authority (NUCA) Chapter 16
6th October Eastern Extensions 220/22/22 kV GIS S/S
· • Access road leading to the main gate of S/S should have the same
lighting fitting as the main roads inside the S/S; all necessary drawings
for lighting poles (locations, structural sections and foundations) should
be according to owner's engineer approval.
• Each guard tower should be provided with at lest one street light fitting
to illuminate the area around.
• All necessary drawings for lighting poles (locations, structural sections
and foundations) should be according to owner's engineer approval.
2
- The contractor shall provide an office (min. area 60111 ) for the sole use
of the supervising civil and Electrical Engineers in addition to a
meeting room with adequate area and suitable furniture. The office shall
be erected as soon as the contractor commences operations at site. The
office shall be composed of two rooms with adequate space and
furniture and toilet facilities. It shall be provided with a damp-proof
floor as well as insulated walls and ceiling. The office building has to
be fitted with opening windows with sunblind, electric light and air-
conditioning units. The Contractor shall provide staff for cleaning and
for general duties in the Engineer's office. The office facilities and all
services specified above shall provided and maintained to the
Engi.J.1"er's satisfaction for such a period as the Enginee~ may require,
but not exceeding one month after the date of the provisional
Acceptance of the substation.
16.2.10 SAMPLES:
E1ecrric Power Systems Engineering Company ExhibitD Page 31/67
Volume 2: Technical Specifications Rev. (0)
New Urban Ccnnnunities Authority (NUCA) Chapier 16
611, October Eastern Extensions 220/221:22 kV GTS SIS
The Contractor shall submit samples of all materials for approval before
using them in the works.
16.2.11 The contractor must submit the quality surveillance program and
concrete repair system for Owner approval.
16.2.12 Safetv:
The contractor should fulfill the requirements indicated in the general
conditions of the contract in this regard.
16.2.13 SA.l\lf'LES:
The Contractor shall submit samples of all materials for approval before
using them in the works.
16.2.14 Tests:
- All shop and field testing assuring the quality of the works shall be
performed at the contractor's expense.
A testing program should be submitted by the contractor to owner for
approval indicates all tests expected to be canied out ascertain its
fulfilling to the contractual obligations.
All tests procedures and results should be complied with the standards
and regulations of the Egyptian code.
16.3.3 Loadings:
16.3.3.i General:
- All buiidings and other constructions shall be designed for maximum
influence of the following loads combined in different load cases:
2 Dead weigh.
• Pay load, permanent and movable.
• Wind load.
• Seismic load.
• Load from conductors.
• Short-circuit impacts.
• Open1tion loads.
• Mounting loads.
[Link].1 Seismic load design shall be done according to the Egyptian Code.
[Link].2 Minimum total lateral seismic force V assumed to act non-
concurrently in the direction of the main axes of the structure is
taken as: V = ZIKCSW Where:
• V: The total lateral force or shear at the base
• Z: Numerical coefficient dependent upon seismic zone
• I: Occupancy importance factor
• K: Numerical coefficient depending on energy reception.
• C: Numerical coefficient depending on the period of vibration of
the building.
S: Numerical coefficient for site structure resonance.
VI: The total dead load.
16.3.4 Grouting:
16.3.5 Drainage:
aforesaid.
The contractor shall dispose the soil from the excavation on site m
accordance with the provisions of subclause (1.1), and in a manner to be
approved by the Owner Engineering in writing.
- All foundations beds shall be surveyed and inspected from time to time
during their excavation by the Owner Engineer, and shall be passed by
him previously to any masonry or other work being deposited thereon.
Due notice shall be given by the contractor when he considers that any
foundation bed has been properly and finally prepared, so that the
Owner Engineer may arrange to make the necessary survey and
inspection at the first favorable opportunity. If, after a bed has been
inspected and passed by the Owner Engineer, the trough for any cause
·whatsoever becomes obstructed with debris, mud or other materials, the
contractor shall remove the same in a satisfactory manner at his own
cost then the bed will again be inspected by the Owner Engineer before
pouring of concrete. If the levels or dimensions of the foundation pits are
greater than those stipulated, the excess shall be with concrete by the
contractor at his own expense.
All costs and charges what's over, in connection with carrying out the
excavation in accordance with the provisions of this clause and the
contract Documents, including the provisions of all main and subsidiary
. suds dams piling, timbering, strutting and all temporary works also all
Dumping denaturing and draining, fonnation of steps between slopes in
excavation for foundations and whatever else that may be necessary for
the proper and satisfactory carrying out of work, are to be taken as being
included in and covered by the schedule prices and rates for excavations.
In the absence of any express conditions in the contract Documents, no
soil shall be transp01ied more than one hundred and fifty (150) meters
witi'[Link] the previous order or approval in writing of the owner Engineer
specifyil;g the approximate quantities to be so transported and the [Link]
or places from and to which soil is to be taken. The quantities of soil
actually and duly transported according to such order or authorization
shall be checked and accorded by the Owner Engineer and the
Contractor's Engineer at the time of the execution of such work. Soil
· shall be transp01ied to a place, which will be chosen by Owner Engineer,
and no extra price would be paid. The execution of the building works
for the reactor station shall also include the following:
., · All necessary excavation, earth filling and raising the gro1md to th~
final approved level without extra charge
• The excavation in any kind of soil and subsoil water shall be taken
into consideration.
• All cable trenches suitable to carry necessary cables in t,'i.e whole S/S
area up to the boundary fence ..
,. Switchyard foundation, reactor foundations and its oil pits.
• All embedded parts for every paii of the installation.
• Proper execution of internal and external lighting.
• Any other works in S\S site.
The .ground, before any concrete is laid thereon, must be weli rammed,
· and any soft part of sand must be removed and replaced with concrete or
strengthened by any other approved means until capable of retaining
with great safety the maximum loads on site.
- In case that the contractor after carrying out his soil investigation or after
- ~----- beginning the execution of works find that the type of the foundation
~ ···'rn,ust be different from that stated in the attached soil report, or if the
"dimension and quantities of [Link] foundations must be bigger than those
cakulated on the basis of the attached soil investigation report, or if the
[Link].y·e in the attached soil report and these differences result in
::{dclitional requirements such as an increase in the depth of the
(oundation level, use of soil replacement. .. etc, all of these modifications
shall be carried out by the contractor, without extra Payment.
It means that the contractor should stick with the worst soil report either
it is attached with tender document report or contractor soil report
without extra payment and time.
]Vote:
The Contractor should nominate the name of the soil investigation consultant for
approval by owner's engineer piior to start the investigation procedures.
- The contractor should carry out the leveling and grading of S/St area to
the finish yard level (zero level) as described hereinbefore in clause
[Link].
- The substation finish yard level (zero level) shall be higher than the level
of the asphalt road front of the main gate by 20 cm unless otherwise
decided and agreed up on by the owner and the contractor.
- The contractor has to compare the contour map with the actual levels of
site and prepare another one on his responsibility and account without
Electric Power Systems Engineering Company Exhibit D Page 40/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
6'" October Eastern Extensions 220/22/2? kV GJS S/S
extra charge.
- The site should be leveled at the zero level by excavating and backfilling
and compacting according to specification, any soft soil or other
material.
- 1be finish floor level of the control building ground floor shall be
(+ 1.1 Om) above the road level in the S/S and for the other building shall
be subject to the approved drawings ..
- Road level inside S /Swill be(+ 10 cm) above zero level.
Side walk level will be (+25 cm) above zero level.
In case that the soil below the bed level of foundation V>'as not suitable
for withstanding ,vith great safety the maximum loads on site according
.to the soil investigation report, it should be removed and replacesed by
proper replacement material.
- The crnshing strength for R.C cubes after 28 days should not be less
than 28 kN/mm2 •
- The cement content for reinforced concrete should not be less than 350
kg/1113.
- The cement content for plain concrete should not be less than 250 kg/1113 .
- Mixing:
o Cement, Sillld and gravel will be so mixed and the quantities of
water added should be such as to produce a homogeneous mass
of proper unifonn consistency, dirt and other undesirable
substances should be carefully excluded.
o The ordinary and reh1forcement concrete will be supplied from
an approved batch plant, otherwise the contractor is obliged to
use computerized mobile mixer (self loading included electronic
scale. for weighting the concrete mixture materials).
o The contractor will submit the data and test certificate for the
batch plant for owner approval.
Placing:
a) No concrete shall be laid before an order has been obtained from
the owner Engineer.
b) Concrete shall be used on the work inn11ediately after mixing, mid
any concrete not !aid ill place within half an hour after mixing shall
not be used n the work and shall iimnediately be removed from the
vicinity.
c) Unless otl1erwise specified h1 writing by the Owner, ordinary
concrete shall be placed in layers twenty-five centimeters thick,
a.1J.d each layer shall be [Link] carefully and its surface kept damp
and clean.
d) In case of rei..-tforced concrete construction, concrete shall be placed
in horizontal layers, stirred and damped ·with suitable tools and
mechanical :vibrator until it completely fills the fonns, closes
enough agaillst all surfaces and is ill perfect and complete contact
with all the reinforcement.
eJ Concrete shall not be placed in water, unless it is absolutely
necessary, and then only after tl1e necessity and method of
tlrrowing the concrete in water have been as approved by the
owner's Engineer in writing.
f) All vertical edges of concrete below ground level must have
strongly ai1d neatly made coffrage and must not be poured against
the sides of the excavation.
g) Ibe surface of the ground and cofftage must be well & watered
before any concrete is placed.
h) When placing of concrete is to be interrupted long enough for the
concrete to take its final set, tl1e working face shall be given a
shape by the use of keyways or other means that will secure a
proper union \Vith subsequent work. All concrete smface on or
against which concrete is to be placed shall be roughened before
Electric Power Systems Engineering Company Exhibit D Page 42/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
6'" October Eastern Extensions 220/22122 kV GIS SIS
n) Fonnwork, either sown or wrought required for the works shall not
Electric Power Systems Engineering Company Exhibit D Page 44167
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapier 16
6th October Eastern Extensions 220/2?./22 kV GIS S/S
be measured separately.
- Reinforcement:
16.5.1 Brickwork:
- Bricks must be of best quality and of the required strength not less than
100 kg/cni and density not less than 1.8 t/m3 and the bricks in each
coarse shall be so laid as to break joint with those of the coarse above
and below, by overlapping to the extent of from one-quaiter to one-half
of the length of a brick.
- In rio circumstances are false joints to be made by cutting the bricks so
as to make the pints appear more regular. Any masomy disfigured in
this manner will be immediately demolished ai1d reconstructed by and at
the expense of the Contractor.
- Pieces of bricks shall not be used except when absolutely necessaiy to
make a -closure.
- Each brick shall be placed on a bed of m01tar and the side faces shall be
plastered with mortar. The mo1tar shall not be introduced into the joint.
- Samples of bricks shall be submitted for approval before the
conunencement of the works, and all bricks used in the works shall be
Electric Power Systems Engineering Company Exhibit D Page 45/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
6'" October Eastern Extensions 220/22/22 kV GIS S/S
Insulating of Basement:
The whole area of the bottom surface of basement floor and basement
. walls up to zero level shall be insulated as follows:
" Two layers of bituminous membrllile 4 mm thick foi each, reinforced
with polyester fiber with overlapping not less thllil 15 cm.
• These two layer of membrllile shall be laid on a the surface of plain
concrete under the R.C footing in a m31111er according to the
m311ufacturer's instruction llild shall be extended to cover the
basement walls up to the finish ground level.
" The water proofing membrllile should be protected against da111age
horizontal by 3 m thick cement screed and vertically with 12 cm thick
brick wall, the brick wall shall be painted with two costs of bitumen
point before t.'Je back-filling.
16.5.3 Rendering:.
All the inside faces of walls 311d ceilings shall be cleaned wet enough
before rendering 311d shall be sprinkled with cement rno1iar composed of
.//- ~ .450 kg cement for one cubic meter sand for all project excluding the
false ceiling area which mentioned before. The rende1ing must be made
of two layers as follows
a) Ceilings:
o. ·Cement rendered of average total thickness of 2 cm of cement mortar
composed of 300 kg cement for one cubic meter sand for all
project excluding the false ceiling area, which mentioned before.
16.5.4 Paintings:
1. Oil Paint: Ali internal walls shall be painted with one coat of primer,
two coats of putty and two coats of paint of an approved quality and
color.
2. Plastic Paint: All ceiling shall be painted with one coat of primer,
two coats of plastic paint of a good and approved quality and color.
3. Anti-Alkaline Oil Paint: The ceiling of the battery room shall be
painted with one coat of epoxy primer and two coats of anti-alkaline
epoxy paint which not affected by battery gases and frames. The
Contractor shall submit a sample of this paint to be tested and
approved before commencing the painting. Walls shall be covered
with anti alkaline or anti acid ceramic tiles with the full height of the
wails.
4. All iron and steel work including necessary fittings (which are not
hot dip galvanized as specified), gates, frames, pipes, .. etc and timber
for use in the permanent work shall be painted with two coats of red
lead primer and: two coats of oil paint. They shall be painted and
fixed to the walls by means of iron collars in 1: 4 cement and sand
mmiar.
16.5.5 Windows:
The. windows shall be aluminum type (Technal sections or similar)
subject to the owner's approval. The windows shall be fixed to the wall
by wooden frames 2" x6" in a manner and work manlike in accordance
with the Engineers satisfaction.
Windows for the ventilated room, such as 66 kV building, battery room,
aux. rooms, store, workshop, firefighting & pumps room shall be fixed
type with wired glass (single) 61m11 thick.
The windows for. the switchgear rooms (220 kV GIS, 66 kV building and
22 kV room) should be with the full width of walls panels, fixed from
/..--------,, outside only. No windows to be provided for the wall panel which have
· 'through [Link] [Link]. The ·windows of22 kV switchgear room
shall be single glass 6 mm thick wired and 80% reflected type with wire
fly screen.
Windows for lavatories and kitchen shall be single glass tilted type.
All windows should be fixed to concrete frames (not to be fixed to brick
walls).
16.5.6 Doors:
The external and internal doors shall be (Marie & Scott or Similar) for
equipment rooms shall be double or single leaves of steel sheets as per
the approved drawings reinforced with sufficient steel stiffeners and
bracing angles fixed on R.C frame and painted with (2) coats of primer
and (3) coats of washable oil paint of an approved quality and colour.
For offices, service room and lavatories the doors shall be of wooden
type an.d painted with (2) coats of primer and (3) coats of oil paint of an
approved quality and colom.
Unless otherwise specific in the HVAC requirements, the external doors
of the ventilated rooms should be provided with louvers and sand traps
Electric Power Systems Engineering Company Exhibit D Page 48/67
Volume 2 : Technical Specifications Rev. (0)
I
New Urban Communities Authority (NUCA) Chapter 16
6'" October Eastern Extensions 220/22/22 kV GIS S/S
.16.5. 7 Pavine::
- All kinds of paving are placed by using a mortar composed of 300 kg cement
to one cubic meter sand.
= All the tiling shall be provided with a colored border round the walls and
machine beds. _
- Steel-crete Tiles: The steel-crete tile shall be 20x20x3 cm of an approval
quality and color. The tile shall be made as follows:
• !iace tile not less than 8 mm thick of mortar in the proportion of 2 parts
/Colored cement + one part sand + 80 kilograms of steel powder of
· silverseet to everyone cubic meter of mix.
• 2nd layer made of2 parts sand+ 1 part cement.
- Ceramic Tiles:
• The ceranuc tiles shall be of the first grade quality of an approved color,
about 1 cm thick.
" T11e tiles may be square, hexagonal with dimension not less than 20x20 cm
and shall be-according to the approval of the owner's engineer.
"All the lavatories, and kitchen shall be covered with non-slip ceramic tiles
of an approved quality, color and dimension.
- Cement Tiles: The cement tiles for roofing shall be 20x20x2 cm of gray color
Electric Power Systems Engineering Company ExhibitD Page 49/67
Volume 2 : Technical Specifications Rev. (0)
New Urban CommunHies Authority (NUCA) Chapter 16
6 1h October Eastern Extensions 220/22/22 kV GIS SIS
made as follows:
" Face of thickness not less than 6 1mn thick composed of2 parts cement and
one pati sand.
o 2nd layer composed of 2 paiis sand + 1 pare cement.
- Porcelain Floorirnz: All the offices shall be covered with Porcelain tiles v,;ith
tl1ickness not less than 1. 0 cm and porcelain Skirting.
Mosaic tiles shall be laid to the rooms or areas specified in the tender
drawing or finishing schedules.
Tiles shall also be free from defects such as cracking, hairing, fractures,
shell shak, erosion, ..... etc.
The thickness of the face layer shall not be less than (15)mm contains
big size of marble pebbles.
The complete floor system shall comply with the following static
loading:
Concentrated load not less than 4.5 kN over 25 111111 2
Uniformly distributed load : not less than 18 ld~/n/
. The system shall not deflect by more than 1/250 of the shmiest span or
2.5mm whichever is less. The system shall not excessively bounce or
move when subjected to pedestrian and light wheeled traffic.
16.5.12 Roofing:
./ 16.S.13Stair:
16.5.16 Material:
- General:
l. All materials used in the works shall be of the best of their kind, and
shall conform in quality and treat..'1lent to the conditions specified in
· the following clauses.
2. The Contractor shall be responsible to an-ange ai,d obtain all the
materials as (gravel, ·sand, cement, steel reinforcement, etc.) without
any supp01i from Owner and without extra charge.
3. The Contractor shall submit samples of all materials, fittings and parts
which he proposes to incorporate in the works, for approval and shall
not use any of the same unless and until so approved.
4. Before entering into any sub-contract for materials, or iron works and
steel works, the names of the merchants or finns shail be submitied
for approval. ·Should the owner's Engineer at any time during the
execution of the work not be satisfied with the materials supplied
from such a finn, he shall have the power to cancel his previously
given consent as regards supply of any material from the same finn.
5. In case the Contractor does not submit, for the approval of Owner's
Engineer [Link] [Link] first class finns for the supply of
the materials, the Owner's Engineer shall have the power to specify
. any particular merchant or fmn for supply of such materials, and the
Contracto_r shall, obtain such materials from the same firm or !
manufacturer without extra charge.
Gravel:
l. All gravel is to be dese1i gravel well washed, free from all soluble
salts or other impurities. It is to be well graded and is norn1ally to pass
a mesh of30 millimeters and be retained on mesh of 6 millimeters.
2. When ordered by the Owner's Engineer, gravel shall be sieved and
thoroughly wetted at least on day before being used in t'ie concrete
Electric Power Systems Engineering Company ExhibitD Page 54/67
Volume 2 : Technical Specifications Rev. (0)
Ne\v Urban Communities Authority (NUCA) Chapier i6
6th October Eastern Extensions 220/22/22 kV GJS S/S
mixture.
- Sand:
1. Sand shall have clear sharp angular grit; the grains must be well
graded. It shall be free from organic matter and salts or other
impurities. In case sand is in need of washing, this should be
thoroughly done at least a day before using such sand in the concrete
m01tar.
2. Sand for ordinary work shali pass a mesh of five millimeters and 75
percent shall pass a mesh of 3 millimeters, and it shall be retained on
a sieve having 1,600 meshes per square inch.
- ·cement:
1. The cement shall be of the best quality of artificial Portland cement or
sulphat resistance cement as recommended in the worst soil
investigation report; locally manufactured cement shall be used,
provided that it shall have first passed the tests of the Government
chemical Department.
2. The Contractor shall at his uwn expense, construct at the site of the
work suitable acconm10dations for storing and protecting all the
cement delivered at the site of the work.
3. This cement store shall be of suitable size, dry and well ventilated,
great care being taken that a perfectly dry floor or floors, either of
wood or concrete, be provided so as to prevent effectually any
dumbness rising to the cement. It shall be stored into covered separate
·independent compartments.
4. Each consignment is to be kept in a separate compartment that can be
looked. The key of the store and its compartments shall be kept with
the Owner Engineer.
5. The Contractor ha.s to supply full particulars as to the number of tons
of each consignment, date of grinding, result of test the Owner's
Engineer may require its brans and further infonnation as.
6. No cement shall be used in the works without the pennission of the
Owner's Engineer.
7. Cement shall be delivered to site at least 21 days before it is required
. · for use.
8. All cement shall fulfill the conditions of the latest standard
Specifications for Portland cement, cement certified by the chemical
Department as not conforming with the above specifications cannot
be used on the works and shall have to be removed as soon as
possible from the cement store.
9. The Contractor shall supply all labour and materials for packing
samples and shall bear the cost of their dispatch to the destination
prescribed above.
10. The contractor shall use Portland cement for all finishing works
Electric Power Systems Engineering Company Exhibit D Page 55/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
6'" October Eastern Extensions 2?0/21/22 kV GIS S/S
" General: All parts of the work shall be protected against corrosion
under service conditions. The protection shall also prevent c01Tosion
during transport, storage and erection.
• Painting: All un-galvanized external surfaces which may be removed
for niaintenanc_e purposes, shall be painted at the manufacture's work .
.• Galvanizing: Except where otherwise specified, all ferrous paiis shall
be
- The zinc coating shall meet the requirements according to ASTM, A123,
A153, A239, .and A385. All steel shall be fully fabricated before
galvai1izing, no machine or shop work, boring, punching etc., will be
allowed after galvanizing. Minor dainage to the galvanizing resulting
from transportation and the like, shall be repaired at site in an approved
manner, ·e.g. by painting with approved zinc-paint, containing at least 92
weight percent zinc powder.
Exceptional load
Factor Norma
Item (Short circuit
Based on I load
load)
Steel structures Yield point 1.5 1.1
Tubular busses Yield point 1.5 1.0
Post insulator Failing load 2.8 1.25
String insulators Failing load 2.8 1.5
Insulator fittin2:s Yield point 1.45 1.0
Insulator of forged steel Failin2: load 2.25 1.25
Insulator fittings of cast iron Failing load 2.8 1.5
a. Seismic load:
- Seismic load design shall be done according to the Egyptian code from
which the lowest value is applied.
- Minimum total lateral seismic force V assumed to act no concmTently in
the direction of the main axes of the structure is taken as:
V = Z 1 K C S W where,
U = 1.4 D + 1.6 L
U = 0.8 (1.4 D + 1.6 L + 1.6 \V)
U = 0.8 (1.4D +1.6 L +i.6 E) Where,
D: Dead load. -
L: Live load
E: Earthquake load
b. Wind Loads:
- Wind loading shall be applied in the most dangerous direction from the
point of view of the structure equipment.
- Short Circuit Loads: The structures shall be designed for a short circuit
current of (50) k/1. (1sec). These loads shall be calculated in accordance
Electric Power Systems Engineering Company ExhibitD Page 60/67
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter I 6
6'" October Eastern Extensions 220/22/22 kV GJS S/S
c. Vertical Loads:
d. Longitudina! Loadings:
Structures shall be so rigid and stable that all equipment and apparatus
will operate properly and deflection of members will not be excessive.
The loads shall be taken from the manufacturers recommendation.
- All structures shall be able to withstand the stresses to which they may
be subjected under erection and stringing operations.
- The worst load combination for the electrical equipment and the
supporting structures results from some combination of the above
loadings.
Item L/t
Compression members. 120
-·
Main legs. 120
7. During transport and erection special care be taken not to damage the
galvanizing and the painting of the members. Structures shall be cleaned
from any foreign matter deposited during transport or after erection.
8. Each member shall be plainly marked in a conspicuous place with
identification mark for erection purposes.
bolt diameter.
6. The distance from the center of a bolt to the face of the outstanding
flange of an angle or other members shall be such as to permit the use of
a socket wrench in tightening the nut.
7. Pennitted ultimate bearing stress for bolts as weil as members is equal to
1.9 times the Yield point of the steel.
8. Permitted ultimate shearing stress is equal to (0.6) times the Yield point
of the steel.
9. All bolts must be either mild steel or high strength steei in order to
prevent confusion. More than, two dimensions of bolts should preferably
not be used for each type of structure. An ample surplus of bolts, nuts
and washers shall be supplied.
16.6.8 Welding:
16.7 LABELLING:
16.7.1 General:
- Labels shall be so designed and placed as to facilitate orientation both
within the switchyard and when approaching it from outside. All parts of
the installation shall be easily identifiable. Label text shall be in English
and comply with IEC standards, (where specifically mentioned English
& Arabic will be provided).
Electric Power Systems Engineering Company ExhibitD Page 63/67
Volume 2 : Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter 16
6'h October Eastern Extensior.s 220/22/22 kV G!S SIS
- Type of label:
• Necessaiy -labels for orientation in a switchyard are apparatus
designation labels and phase markings.
• The desigl'.2-tion labels shall have the same symbols as used in the
station layout diagram.
• The phase markings shall have the symbols Ll, L2 and L3 for the
three phases.
- Label size
• Labels shall have dimensions according to Table 1.3 below.
• The size shall be chosen with regard to location.
• The same size shall be chosen for designation label and phase
markings in each case.
~
Size No Unit 1 2 .) 4 5
Frame width mm 5 6 8 15 15
- Outdoor Equipment:
• Location:
- Labels shall be placed on bases, cross-arms, consoles etc, or on other
earthed parts of the apparatus which normally carmot be removed, in
such a way as to be ea~ily readable.
- Labels shall be placed on the normal and/or inspection side of
the apparatus
• Desi2:nation labels:
- Line Exits:
1. One label, size 5, on both sides of the cross-am1, in the
middle phase.
2. One line-destination label, size 4, on both sides of the cross-
arm, in the middle phase.
- Capacitive volta2:e transfonners: One label, size 3, in. the middle
phase.
- Earthing switches: One label, size l, on each operating
mechanism.
- Line traps: One label, size 3, in one phase or, if required, in both
phases.
- Li2:htnin2: arresters: One label, size 3, in the middle phase.
- Transformers: One label, size 5, on the service side.
• Phase markings:
- Line exits: One label, si-z:e 5, in each phase, on both sides cross-
arm.
- Earthin2: switches: One label size 1, on each operating mechanism.
- Other apparatuses: One label, size 3, in each phase.
l. All switchboards, distribution boards and control boards and units thereof,
components mounted therein, wiring and cables, shall be labeled and
marked.
2. The purpose of the labeling and marking being to make possible the
identification of switchboard and control board and parts thereof and t.'1eir
relation to the relevant technical documentation in order to facilitate a
rational and simple manner of installation, operation, trouble-shooting,
maintenance and repair. Labeling and marking shall apply as follows:
a) Each switchboard and control board shall have one label stating the
make, the maker's identification data and rates, insulation voltage
class and one label identifying the board in the plant.
b) Each unit of switchboard or control board (such as a cell, panel,
cubicle or box as well as remote located switching and control
devices) shall have a label identifying the unit and stating its
purpose in the plant.
c) The latter infonnation is in more suitably given in a mimic diagram.
d) All apparatus or units of apparatus in the panels, cell, etc, shall have
labels or markings identifying the apparatus or units thereof
(normally the relevant apparatus numbers used in the technical
documents for the switchgear or control gear). In some cases this
marking shall be completed with fanction marking in plain te:>,.'1.
e) Apparatus labels shall be fixed by means of screws or rivets on the
f) Framework, so they remain in place when the apparatus is
dismounted or changed.
g) All terminals of apparatus or apparatus units shall be clearly
marked. However this marking may be omitted when the design
and arrangement of the apparatus is such that marking obviously is
unnecessary.
h) All electronic printed circuit boards shall have type marking. The
elec1ronic cubicles shall have item marking for each circuit board
for [Link] of the circuit board in the schematic diagram.
i) All instruments indicating devices and control devices shall have
identification marking in plain text or simple symbols or, colors.
Control devic~s shall in addition have marking of control positions
(e.g. MANUAL - AUTOMATIC, OPEN-CLOSE) in plain text,
simple symbols or col_ors.
j) Control cable terminals and, for small load circuits also power
tenninals shall be clearly marked for identification.
k) The marking system shall be logically built-up from letters and/or
figures in one system consistently used within the switchgear or
control gear.
1) Internal wiring within switchboard, control board or apparatus units
shall have all wire ends marked, the marking to include as a minimum
the same marking as has the tenninal to which the wire end is
connected. The marking shali be canied out with sleeves or similar.
Tape is not pennitted.
m) Cmrent and voltage circuits shall also have phase marking and, where
necessary, polarity marking. Protective earth wires shall be marked
with green/yellow.
f n) Cables connected to switchboard, control board, external apparatus
L etc., shall be marked with cable numbers according to the cable list and
core number according to the external connection _diagram. In addition
all cable cores shall bear the same marking as the tenninals to which
Electric Power Systems Engineering Company ExhibitD Page 66/67
Volume 2: Technical Specifications Rev. (0)
New Urban Communities Authority (NUCA) Chapter !6
6th October Eastern Extensions 220/22/22 kV GJS SIS
CHAPTER SEVENTEEN
SPARE PARTS
SPECIAL TOOLS AND TESTING EQUIPMENT
CHAPTER SEVENTEEN
SPARE PARTS
n SPECIAL TOOLS AND TESTING EQUIPMENT
J
t...._;
TABLE OF CONTENTS
,,·"!:
17.1 Spare Parts. 3
I
I.
'.
i..... )
17.2 Special Tools. 12
17.3 Testing Equipment. 15
17.4 Submittals. 19
Annex 1
Annex2
[I - Annex3
r·· .
IQ :_
!. ... :�
[j
r·'.,
I •
t.i,}
L
·····:-
L j
t ,/ '·
[J
-.,_ ..>·
.
.. ....... _ .. _.. _ . -� �--
CHicPTER SEVENTEEN
SPARE PARTS
SPECIAL TOOLS AND TESTING EQUIPMENT
[Link] Parts:
17.1.1 General:
a) Spare palis are necessary for trouble-free operation and overhaul the
components of the plant for, at least five years after the warranty period.
c) Owner [Link] spare palis and bidders recommended spare palis (if
needed) are for the owner use only after the warranty period, and should be
handed over to the owner before the c01mnissioning of the plant.
d) All spare palis supplied under the contract shall be strictly inter changeable
with the palis for which they are intended to be replacements and shall be
treated and packed for long storage under the climatic conditions prevailing at
the site. Each spare palis shall be clearly marked or labeled on the outside of its
packing with its description and purpose, and when more than one spare parts is
packed in single case or other container a general description of its contents is
to shown on the outside of such cases or containers and a detailed list enclosed
inside. All cases, containers, and other packages must be suitably marked
numbered for purposes of identification.
e) All cases, containers or other packages are liable to be opened at the site for
examinations as the owner may consider necessary and all such opening and
subsequent repacking shall be at the expense of the contractor.
f) Bidders should submit with his bid the spare parts catalogues of all the
components of the plant with sufficient details to identify each piece of the
spare parts and ensure that the spare parts comprise all the replacement
components.
g) Bidders shall mention the reference number of each spare parts piece.
h) If it is observed during the wa1Tanty period of the plant that, any required spare
parts has not been recommended by the contractor or the delivered spare-parts
are not sufficient for five years, then, the contractor is obliged to deliver the
shortage without compensation and its site delivery cost shall be considered
included in the contract price, the works will not be considered as complete and
final certificate will not be issued until these spare parts delivered by the
contractor.
1.5. Motor with oil pump for operation mechanism (for hydraulic
mechanism C.B).
1.6 Complete motor spring mechanism (for three phase circuit
breaker)
2 ~onn_.¥dors and ~_artgin,g s'1'..l!ches: .
. .,.· ,, ·• /7
··.
6.4 Per bus bar section / .
.
,''
Catalog Item
Item Description
No. Reference
10 Single phase outdoor CCVT 2J; / ~ / ~ / ~ CL0.5, CL3P, 100,200,
200VA
11 Set of temperature compensating bellows.
12 Set of gas filler for one bay
13 Set of pressure relief devices.
14 Set of SF6 pipes per bay.
15 SF6 gas bottles of 40 kg. size.
B Protection of220 kV:
1 Line fecjer protection relay (main 1)
2 Line feeder protection relay (main 2)
3 Module of bus bar protection relay.
4 Module of bus bar breaker failure relay.
5 Bus coupler protection relay.
6 Synchro-check relay.
C · . .22 kV Switchgear
1. Transformer incoming circuit breaker/ Bus section with rated
.
.
current 3150 A complete with its truck.
y' 2 Outgoing feeder circuit breaker with rated current 1250 A
complete with its truck.
C
:, Outgoing feeder circuit breaker with rated cmTent 800A N.A
comnlete with its truck
4 Sets of each of fixed and moving contacts, or three pieces of
vacuum tubes for 1250 A circuit breaker
5 Sets of each, fixed and moving contacts, or three pieces of
vacuum tubes for 3150 A circuit breaker
6 Sets of each of, fixed and moving contacts, or three pieces of N.A
vacuum tubes for 800 A circuit breaker
7 · Po1table detector for SF6 leakage.
8 Complete circuit breaker mechanisms (assembled), including
· .anti-pumping relays.
9 Closing coils. .. ..... /···
..
10 Tripping coils. /.
11 . l trans fiormers wit
p otentia . l1 rat10
. (11000)
..f3
/ 100 / 100
, ~ volt
/
13
12 Three phase current transfonners for each rating supplied
according to S.L.D. \ .
Catalog Item
Item Description
No. Reference
17 Medium voltage local earthing 22 kV.
18 Phase sequence meter.
19 Socket for testing.
D Control, Metering And Protective Eguipment For Both 220
kV & 22 kV Circuits -
1 One of each type of metering instruments.
2 One of each type of measuring instruments.
0
J One complete relay for each supplied type.
4 Set of one card for each group equal or less than ten similar
cards, included testing card.
5 Signaling and intermediate relays from each supplied type.
6 One set of auxiliary switches from each sunn1ied type.
7 One complete event recorder.
8 One p01iable laptop.
E Conventional out door surge arresters
..
1 One single phase 220 kV surge arrester .·.
2 Battery cell. /
3 LVDrelay.
4 One of each relay type of used in the system. '
:i Cell connectors
' •.
·..
6 Consumable lamps, fuses, special cables
.
H Cables:
1 I 0% of each size and type of power cables supplied.
2 10% of each size ofL.V cables sunnlied.
0
J I 0% of each size of control cables sunn!ies.
I Ca:Qacitor Bank:
Catalog Item
Item Description
No. Reference
l Control box
2 Capacitor unit
,
C.B and accessories
"4 Spare for control and protection relays
N.B: Please note that one set of contacts means the necessary
number of contacts required for completely renew a circuit
breaker.
J Telecommunication svstem:. !
1 48 V DC svstem:
1.1 One card/module of each supplied card/module of charger.
1.2 Battery cell.
1.3 LVDrelav.
2 Special cables, sockets, adapter, connectors, etc ......
3 Consumable spares i.e lamps, fuses .. etc of each type.
K UPS Svstems
i) i
Bidder has to recommend spare parts list with orices. ..
Catalog Item
Item Description
No. Reference
~
Complete set of gaskets together with gaskets cement for one
.)
transfonner
4 Complete breath set
5 Motor drive for cooling fans
6 Set ofbuchholz relay
Set of temp. instrnment for oil & winding with its remote
7
indicator.
8 Ivfotor drive for OLTC
9 Oil equipment to 25% of the first filling of one transfonner
10_ Set of pres~ure relief device
/
1
Bidders shall list his recommended spare parts vvith catalog and reference
numbers with option price for each piece of the recommended spare pa1is as
follows:
[Link]:
1) Owner recommended special tools: Which are specified here bidder shall
submit the firm (not subject to escalation) price breakdown for these special
tools on the prices of the owner recommended special tools inclu-:bd in
schedule of quantities and prices" are for supplying all the owner recommended
special tools.
a) Special tools should be handed over to the owner before the commissioning
[Link] plant.
b) Bidder should submit with his bid catalogues containing all the special tools
with their reference numbers and their use.
Catalog Item
Item Description Qty
'' No. Reference
1 SF6 gas handling trolley suitable for GIS compartments
including C.B. complete with all accessories such as hoses,
! valves manometers, storage tank etc... for filling, evacuation,
discharge, storing, regeneration, etc.
L 2 Eaiihing set for eaiihing three pole circuits of voltage higher
than (1)/kV complete with clamps, hot stick, etc.
3 Complete set of tools necessary for maintenance and
[ adjustment of220 kV equipment.
•·
Bidders should list the special tools recommended by him with catalog
reference numbers of each piece of the special tools, with option prices as
follows:
Catalog item
Item Description Qty Price
No. Reference
--
-- -- - ----- -- ·~ ,. -- . ~- -· ~ - --
--- ----
- --
\_. .
_____ _______
-- ----~- -
17.3Testing Equipment:
[Link]:
a) Testing equipment are necessary for early fault detection, fault location,
performance checking, testing after; erecting, repairing, overhauling etc for
all the components of the plant.
d) Bidders should submit with his tender catalogues of the testing equipment
with their reference numbers and the options facilities, accessories and their
uses.
Catalog Item
Item Description Qty
No. Reference
1- Portable set complete with all accessories
sensor and adaptors for detection, measuring
recording and analysis the partial charges in
GIS equipment using the buiit in pmiial
.
discharge sensors and the internal sensor.
2- Portable se~ complete with all access•;;ries of
ultrasonic equipment for detecting,
measuring and locating of partial discharges
at high voltage-switchgear and equipment as
specified.
~
.:,- Complete set of circuit breaker analyzer with i
motion analyzer and all accessories as
specified in Annex (2).
4- Earthing resistance and earth resistivitv
~ - J
Catalog Item
Item Description Qty
No. Reference
17- j One frequency generator for under and over
frequency relay(45-55Hz). (Refer to Annex
3).
18- Phase angle meter (cuITent-current and volt-
volt) 0-360.
19- Primary current injection test sets (0-3000A)
with its accessories (cables, clamps and
. meters).
-
20- SF6 decomposition product measuring
device & Gas percentage.
21- Dew point measuring device.
22- Tan 8 device (0 P.F-100 µf) up to 55 °C &
3000 VA, (0 - 12) kV.
23- DC Resistance for winding device, 3 ph.
>60V, up to 55 °C.
24- Turns Ratio measuring device, 3 ph. up to
55°C.
25- Poly phase circuit analyzer device (P.A.F).
26- Transfonner oil analysis tester, dissolved
gases in oil.
27- Telecommunication system:
According to specification chapter (8).
27.1 One level generator.
27.2 One selective level meter.
27.3 One balanced attenuator.
27.4 One oscilloscope.
27.5 Transfonner oil breakdown high voltage
tester up to 100 kV/ 2.5 mmgap.
..
Catalog item
Item Description Qty Price
No. Reference
---
I-
1_·
____- . -- - - ---
-
17.4. Submittals:
a) With bid:
2. Catalogues of all the components of the plant showing tbe replacement parts
and tbeir item reference.
3. Catalogues oftbe special tools showing their use and tbeir item reference.
4. Catalogues of the testing equipment with all accessories showing their use
and item reference.
5. All the details of tbe partial discharge measuring set with all accessories.
5. Instmction manuals.
Annex (1)
Di!!ital measuring instrument
The digital measuring instrument will be with phase sequence indicator, (2)
inputs Ammeter/voltmeter, measure and display the current and voltage of (2) inputs,
for measnring, cunent, voltage and phase angle, cmTent should be measnred without
interrupting the circuit by using clip-on transforn1er, the instrument should measure
and display the phase angle between two inputs, the instrument should be supplied
with all accessories full details should be submitted with bid, the specification will be
as follows:
Measnring range:
Cunent: 0.02 to lOA
Voltage: 0.2 to 500 V
Phase angle: 0 to 360
Supply Voltage:
100 to 120 V AC, 50 Hz
220 to 240 V AC, 50 Hz
Annex (2)
Circuit Breaker Analyzer
a. Function:
The function of the circuit- breaker analyzer shall include but not limited to the
following:
l. To measure the following times of each circuit- breaker ii,te1Tupter.
(i) :tvlaking time.
(ii) Closing time.
(iii) Opening time.
(iv) Breaking time.
2. To measure travel and speed (closing speed, opening speed, over travel etc.)
of the breaker contacts and mechanism.
b. Breaker Analvzer:
1. General
(i) Number of channels not less than (16)
(ii) Timing range: from Oto 6 sec.
(iii) Time resolution: 0.1 m sec.
(iv) Accuracy: 0.1%.
2. l\1otion Analvzer:
(i) Number of channels; not less than (4).
(ii) Measuring range; up to 1000 m sec.
3. Power Supply:
A.C supply: 220 V, 50 Hz.
With built-in- re-chargeable battery for at least one hour continuous
operation.
c. Accessories:
The analyzer should be supplied with all accessories and spare parts for five
years operation after the wa1Tanty period taking into consideration that the
aiialyier·v.,illheiEiedTorsitetests:
Bidders should submit with his bid full details of the analyzer and its
accessories and spare pai1s.
[Link] (3)
1. One Computer aided test set having the following features :
Computer aided test set shall have the following features suitable for
secondary injection for secondary injection
Can simulates any type of fault,
Shall have the facility of displaying vector diagram
Suitable for all relay types offered for this project (Dista..11ce, over current,
etc.).
Suitable for all types of relay Characteristics (mho polygonal. etc.) .
. Shall have the facility of measuring frequency
Shali have the facility of testing the operating time of relay and output
contacts (NO&NC)
2. One Frequency generator for under and over frequency relavs (45-55 Hz)
Technical data:
- ------------ ---- - - - - -- - -- - - - --