Mahanagdong Geothermal Project Overview

The document outlines a 28-day work schedule for excavation and trenching works for an above ground fire water loop at the Mahanagdong Geothermal Powerplant B project. The schedule details 6 main activities - excavation works, rebar works, forms and shuttering, concreting, pipe installation, and inspection - broken down into specific tasks to be completed each day.

Uploaded by

Ramces Asisi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views1 page

Mahanagdong Geothermal Project Overview

The document outlines a 28-day work schedule for excavation and trenching works for an above ground fire water loop at the Mahanagdong Geothermal Powerplant B project. The schedule details 6 main activities - excavation works, rebar works, forms and shuttering, concreting, pipe installation, and inspection - broken down into specific tasks to be completed each day.

Uploaded by

Ramces Asisi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

WORK SCHEDULE FOR EXCAVATION ANG TRENCHING

MAHANAGDONG GEOTHERMAL POWERPLANT B

ABOVE GROUND FIRE WATER LOOP

EXCAVATION AND TRENCHING


C/S DESCRIPTION NO. OF DAYS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 EXCAVATION WORKS
1.1 Clearing and Grubbing
1.2 Setting Out
1.3 Excavation
1.4 Backfilling and disposal of surplus earth
2 REBAR WORKS
2.1 Fabrication of Reinforcement for Trench
2.2 Fabrication of Reinforcement for Trench Cover
2.3 Rebar Installation and Alignment
3 FORMS AND SHUTTERING
3.1 Formworks alignment and bracing
3.2 Formworks for trench cover
3.2 Stripping of forms
4 CONCRETING
4.1 Casting of lean concrete
4.2 Casting of concrete on bottom slab
4.3 Casting of concrete on perimeter walls
4.4 Casting of concrete on trench covers
4.5 Concrete repairs and finishes
4.6 Concrete curing
5 PIPE INSTALLATION
5.1 Pipe support fabrication
5.2 Alignment and Installation
6 INSPECTION
6.1 Punchlists correction
6.2 Placement of trench cover
`
Prepared by:

Engr. Ramces M. Soliman


Project Engineer
ASISI SYSTEMS CORP.