Project/Job No : JSA No : 001/COMM/HEC Rev: 0
Client : SARULLA OPERATION LIMITED Date : 08 February 2019
JOB SAFETY ANALYSIS (JSA) & HSE Prepared by : Mr. Leem Jong Hak (HEC Commissioning Manager)
WORK PROGRAM Patut Butarbutar ( HEC Comm PTW Coordinator)
Probability, Consequence & Risk levels: Review by : Mr. Choi (HEC HSE Manager)
H : High
Personal Protective Equipment
M : Medium Helmet, Kacamata, Sarung tangan, Baju Lengan Panjang, Sepatu karet
L : Low Helmet, Safety Glass, Hand Glove, Long Sleeve, Rubber Shoes,
SWITCHYARD ENERGIZING
RISK
HAZARD CLASIFICATION
RESIDUAL
No TASK HAZARD MITIGATION PLAN PIC
EFFECT P C R RISK
1 Preparation, safety 1. Work area there is 1. Issuing sparks, 1. Install barricades, and alarms, create safe road access,
materials such as fire high voltage explosions and determine safe distance to workers in the area and
extinguishers, light fire (Area perkerjaan burning when prohibit workers from doing work while the authorities
extinguishers, personal terdapat tegangan electrocuted are preparing
protective equipment for tinggi) (Mengeluarkan (Memasang barikade, dan tanda bahaya, membuat
workers, install alarms percikan api, akses jalan yang aman, menentukan jarak aman kepada
from the job site 2. Dropped when ledakan dan pekerja di area tersebut dan melarang pekerja
(Persiapan, material carrying tool and terbakar apabila melakukan pekerjaan disaat orang yang berwenang
keselamatan seperti titik material tersengat listrik) sedang melakukan persiapan)
pemadam kebakaran, (Terjatuh pada
pemadam api ringan, saat membawa 2. Damage to the 2. Ensure load capacity before bringing it to work site
alat pelindung diri untuk alat dan material) equipment and (Memastikan kapasitas beban sebelum mebawa ke AA,IA,PTW&
pekerja, memasang injury to the M M M lokasi kerja) L HSE
tanda bahaya dari lokasi 3. The impact noise affected part
pekerjaan tersebut) of plant 2 operates (kerusakan pada 3. Use ear protection before going to work location
(kebisingan alat serta cidera (Menggunakan alat pelindung telinga sebelum ke
dampak plant 2 pada bagian yg lokasi kerja)
beroperasi) tertimpa)
3. Communication is
disrupted and
leads to hearing
ear damage
(Komunikasi
terganggu dan
mengakibatkan
rusak telinga
pendengaran)
2. Using local/remote 1. Incorrect wiring 1. CT can’t work 1. Ensure that cable connections are compatible with
system position for and connection normally when tagging as well as make sure no connection is
open/close circuit resulting in it has been M M M loose
(Menggunakan sistem damage to burned (Memastikan koneksi kabel yang sudah sesuai
manual buka tutup equipment (CT tidak bisa dengan penandaan serta pastikan koneksi tidak
sirkuit) (salah berfungsi ada yang kendur)
pemasangan kabel normal apabila
dan koneksi telah terbakar) 2. Ensure the installation of the cable path as well as
mengakibat kan the correct connection
kerusakan 2. Damage to (Memastikan pemasangan jalur kabel serta
peralatan) cable insulation koneksi yang benar)
and result in
2. Causes sparks disconnected 3. Ensure the cable path that is installed using a
from incorrect cable multimeter
cable connections (Kerusakan pada (Memastikan jalur kabel yang sudah
(Menimbulkan isolasi kabel terpasang menggunakan multimeter)
percikan api dari serta L AA,IA,PTW&
salah koneksi mengakibatkan 4. Install barricades and warning signs in the area of
HSE
kabel) kabel terputus) the cable path, electrical panel, establish the
evacuation path and ensure safe distance from the
3. causing injury to 3. Causes burns on source of electrical energy
the entire body untouched skin, (Pasang barikade dan tanda-tanda peringatan di
the impact of a and area jalur kabel, panel listrik, membuat jalur
current leak when unconsciousness evakusi dan memastikan jarak aman dari sumber
touched (Mengakibatkan energi listrik)
(mengakibatkan terbakar pada
cidera pada kulit yang 5. Use the radio as a communication tool when the
seluruh tubuh tersentuh, serta work will begin
dampak dari tidak sadarkan (Menggunakan radio sebagai alat komunikasi
kebocoran arus diri) pada saat pekerjaan akan dimulai)
apabila tersentuh) 6. Ensure no worker is on the cable line as well as in
the electrical panel area
(Memastikan tidak ada pekerja yang berada di
jalur kabel serta di area panel listrik)
7. Make sure the grounding system is working
properly
(Pastikan sistem pembumian berfungsi dengan
baik)
3 Energized 3. Rotation Motor 4. Injuries to 4. Inform the operational not to use the system that will
(Berenergi ) (Putaran motor) workers (Melukai be repaired, and ensure the circuit has been switched
pekerja) off and apply the lotto
4. Electric shock (Informasi kepihak operasional tidak menggunakan
(Sengatan Listrik) 5. Fainting or sistem yang mau di perbaiki, dan memastikan sirkuit
burning sudah dimatikan dan terapkan loto)
3. Short circuit (Pingsan atau
(hubunga arus terbakar) 5. Ensure the switch on the circuit there is no electric
singkat) current and voltage by using multi meters
4. Noise 6. damage to (Pastikan saklar pada sirkuit tidak ada arus listrik dan
(kebisingan) equipment tegangan dengan menggunakan multimeter)
(kerusakan
5. Fallin down terhadap 6. After disconnecting the connection cable on the
(Terjatuh) peralatan) motor, then isolation on the exposed part of the
M M M L AA,IA,PTW&
cable and do not touch the induction material or
7. Impaired hearing HSE
water
and damage the (Setelah melepaskan kabel koneksi pada motor,
ears
kemudian isolasi pada bagian kabel yang terbuka
(Mengganggu
pendengaran dan
dan jangan menyentuh bahan induksi atau air)
merusak telinga)
8. broken bone injury 7. Always use ear protection and body harness when
(Cedera patah starting the job is complete
tulang) (Selalu menggunakan alat pelindung telinga dan
body harness pada saat memulai pekerjaan
selesai)
4 Running test & 4. Control System 4. The comp air M M M 1. Inform the operational not to use the system that will
Function test error system is not be repaired, and ensure the circuit has been switched
(tes running & tes (Kesalahan sistem function off and apply the lotto
L
fungsi) kontrol) (Sistem (Informasi kepihak operasional tidak menggunakan
sistem yang mau di perbaiki, dan memastikan sirkuit
sudah dimatikan dan terapkan loto)
5. Allocate workers compresor AA,IA,PTW&
in the field tidak berfungsi) 2. Ensure the switch on the circuit there is no electric HSE
(Menbahayakan current and voltage by using multi meters
pekerja di 5. Injured to (Pastikan saklar pada sirkuit tidak ada arus listrik dan
lapangan) death (Cedera tegangan dengan menggunakan multimeter)
sampai dengan
6. High noise kematian) 3. Use radio for communication tools
(Kebisingan tinggi) (Menggunakan radio untuk alat komunikasi)
6. Destruction of
4. Always use ear protection and body harness when
ear hearing
starting the job is complete
(Selalu menggunakan alat pelindung telinga dan
(Merusak
body harness pada saat memulai pekerjaan
pendengaran
selesai)
telinga)
Prepared by Reviewed by Approved by,
Date : ……………………2019 Date : ……………………2019 Date : ………………………2019
Area Authority HSE Manager Site Manager
HEC Commissioning (HEC) (HEC)
NO TASK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Tool Box Meeting
2 PPE Inspection
3 Equipment Inspection
4 Sign Board Inspection
5 House Keeping