ID Task Name Duration Start Finish Successors Predecessors Oct '18 Nov '18 Dec '18 Jan '19
tart Finish Successors Predecessors Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 5
1 LLI PAKET GAS COMPRESSOR (ref. KPM OG) 378 days Mon 10/15/18 Sun 10/27/19
2 Engineering 30 days Mon 10/15/18 Tue 11/13/18 3FS‐15 days
3 Fabrikasi 196 days Tue 10/30/18 Mon 5/13/19 4 2FS‐15 days
4 Shipping 69 days Tue 5/14/19 Sun 7/21/19 6 3
5 Instalasi Paket Gas Compressor 56 days Mon 7/22/19 Sun 9/15/19
6 Instalasi Gas Com A 12 days Mon 7/22/19 Fri 8/2/19 7 4,74
7 Instalasi Gas Com B 11 days Sat 8/3/19 Tue 8/13/19 8 6
8 Instalasi Gas Com C 11 days Wed 8/14/19 Sat 8/24/19 9 7
9 Instalasi Gas Com D 11 days Sun 8/25/19 Wed 9/4/19 10 8
10 Instalasi Gas Com E 11 days Thu 9/5/19 Sun 9/15/19 11 9
11 Pre‐Comm 18 days Mon 9/16/19 Thu 10/3/19 12 10
12 Comm & Start Up 24 days Fri 10/4/19 Sun 10/27/19 11
13 EPC FASILITAS PENDUKUNG GAS COM 389 days Thu 10/4/18 Sun 10/27/19
14 TENDER 90 days Thu 10/4/18 Tue 1/1/19 15
15 DED 90 days Wed 1/2/19 Mon 4/1/19 16FS‐45 days,3214
16 Procurement Mtl (pipa, valve, kabel, instr., paket fuel gas, IA, Flare) 215 days Sat 2/16/19 Wed 9/18/19 15FS‐45 days
17 Mechanical Procurement 154 days Sun 3/3/19 Sat 8/3/19
18 Suction Scrubber 150 days Sun 3/3/19 Tue 7/30/19 102 15FS‐30 days
19 Discharge Scrubber 150 days Thu 3/7/19 Sat 8/3/19 103 15FS‐26 days
20 Fuel Gas System 150 days Sun 3/3/19 Tue 7/30/19 104 15FS‐30 days
21 Over Head Crane 135 days Thu 3/7/19 Fri 7/19/19 105 15FS‐26 days
22 Instrument Air Compressor 142 days Thu 3/7/19 Fri 7/26/19 106 15FS‐26 days
23 Flare Package 150 days Sun 3/3/19 Tue 7/30/19 107 15FS‐30 days
24 Piping Procurement 150 days Sun 3/10/19 Tue 8/6/19
25 Pipes 150 days Sun 3/10/19 Tue 8/6/19 109FS‐60 days 15FS‐23 days
26 Flanges 120 days Mon 3/18/19 Mon 7/15/19 15FS‐15 days
27 Fittings 120 days Mon 3/18/19 Mon 7/15/19 15FS‐15 days
28 Gaskets 14 days Mon 3/18/19 Sun 3/31/19 15FS‐15 days
29 Valves 150 days Sun 3/10/19 Tue 8/6/19 15FS‐23 days
30 Bolts & Nuts 120 days Mon 3/18/19 Mon 7/15/19 15FS‐15 days
31 Instrument Procurement 180 days Sat 3/23/19 Wed 9/18/19
32 Control Valve / Regulator Valve 180 days Sat 3/23/19 Wed 9/18/19 128 15FS‐10 days
33 SDV/BDV 180 days Sat 3/23/19 Wed 9/18/19 129 15FS‐10 days
34 PSV 165 days Sat 3/23/19 Tue 9/3/19 132,131,130 15FS‐10 days
35 Flow Recorder 135 days Sat 4/6/19 Sun 8/18/19 136,137 15FS+4 days
36 Orifice & RO 135 days Sat 4/6/19 Sun 8/18/19 134,135,133 15FS+4 days
37 Pressure / Level Controller 120 days Fri 4/5/19 Fri 8/2/19 138 15FS+3 days
38 Pressure Switch 120 days Fri 4/5/19 Fri 8/2/19 139 15FS+3 days
39 Pressure Gauge 120 days Fri 4/5/19 Fri 8/2/19 140 15FS+3 days
40 Level Switch 120 days Thu 4/4/19 Thu 8/1/19 144 15FS+2 days
41 Level Gauge Glass 120 days Thu 4/4/19 Thu 8/1/19 141,142,143 15FS+2 days
42 Temperature Gauge 120 days Thu 4/4/19 Thu 8/1/19 145,147,146 15FS+2 days
43 Sounder/Beacon 120 days Wed 4/3/19 Wed 7/31/19 148 15FS+1 day
44 Rotameter 120 days Wed 4/3/19 Wed 7/31/19 149 15FS+1 day
45 Instrument Cable 120 days Wed 4/3/19 Wed 7/31/19 148,139,144 15FS+1 day
46 Instrument Wiring Accessories 120 days Tue 4/2/19 Tue 7/30/19 139,144,148 15
47 Instrument Hook Up Material 120 days Tue 4/2/19 Tue 7/30/19 128,129,136,13 15
48 Instrument Fabrication Material 75 days Tue 4/2/19 Sat 6/15/19 150 15
49 Electrical Procurement 168 days Sat 2/16/19 Fri 8/2/19
50 a. UPS system and battery 150 days Wed 3/6/19 Fri 8/2/19 115 15FS‐27 days
51 b. Lighting panel 97 days Wed 3/6/19 Mon 6/10/19 116 15FS‐27 days
52 c. Electrical cable 75 days Sat 2/16/19 Wed 5/1/19 120,118,119 15FS‐45 days
53 d. Cable tray 120 days Wed 3/6/19 Wed 7/3/19 120,118,119 15FS‐27 days
54 e. Penangkal Petir 60 days Tue 3/5/19 Fri 5/3/19 121,123,122 15FS‐28 days
55 f. Lighting Fixture 120 days Tue 3/5/19 Tue 7/2/19
56 Outdoor 120 days Tue 3/5/19 Tue 7/2/19 124,126 15FS‐28 days
57 Indoor 90 days Tue 3/5/19 Sun 6/2/19 125 15FS‐28 days
58 g. Bulk material 90 days Mon 3/4/19 Sat 6/1/19 117
59 Cable Glands 90 days Mon 3/4/19 Sat 6/1/19 15FS‐29 days
60 MCT 37 days Mon 3/4/19 Tue 4/9/19 15FS‐29 days
61 Termination Material 45 days Mon 3/4/19 Wed 4/17/19 15FS‐29 days
62 Mobilisation & Preparation 24 days Sat 2/9/19 Mon 3/4/19 15SS+21 days
63 Mob & Demobilisasi Peralatan Pancang Diesel Hammer 7 days Tue 2/26/19 Mon 3/4/19 69SS,75 68
64 Mob & Demobilisasi Alat Berat (Crane, Vibro, Grader) 7 days Tue 2/12/19 Mon 2/18/19 65SS,70SS‐3
65 Mob & Demobilisasi Tenaga Kerja 7 days Tue 2/12/19 Mon 2/18/19 66SS 64SS
66 Pengukuran dan Bouwplank 7 days Tue 2/12/19 Mon 2/18/19 67 65SS
67 Pembuatan Kantor Sementara (Direksi Kit) 7 days Tue 2/19/19 Mon 2/25/19 68SS 66
68 Pembuatan Gudang Sementara (Bouw Kit) 7 days Tue 2/19/19 Mon 2/25/19 63 67SS
69 Workshop 7 days Tue 2/26/19 Mon 3/4/19 90 63SS
70 Temporary Mess Untuk Pekerja 7 days Sat 2/9/19 Fri 2/15/19 64SS‐3 days
71 Constr. & Fas. Pendukung, NDT 226 days Tue 3/5/19 Wed 10/16/19
72 Civil Work 226 days Tue 3/5/19 Wed 10/16/19
73 PEKERJAAN PEMBANGUNAN PONDASI COMPRESSOR 70 days Tue 3/5/19 Mon 5/13/19
74 Pondasi Compressor (5 unit) 49 days Tue 3/26/19 Mon 5/13/19 6 75SS+21 days
75 Tiang Pancang Pondasi Compressor (5 unit) 35 days Tue 3/5/19 Mon 4/8/19 74SS+21 days,7863
76 PEKERJAAN PEMBANGUNAN SHELTER PONDASI COMPRESSOR 191 days Tue 4/9/19 Wed 10/16/19
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: Schedule Retender EPC Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/9/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 1
ID Task Name Duration Start Finish Successors Predecessors Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 5
77 Pondasi Telapak Bangunan Compressor 30 days Tue 4/16/19 Wed 5/15/19 81 78SS+7 days
78 Tiang Pancang Pondasi Telapak Shelter Compressor 14 days Tue 4/9/19 Mon 4/22/19 77SS+7 days 75
79 Steel Works incl. Material + Consumable + Fabrikasi + Konstruksi 21 days Thu 9/5/19 Wed 9/25/19 80,105,121 96
80 Pekerjaan Atap & Dinding 21 days Thu 9/26/19 Wed 10/16/19 124FS-14 days 79
81 PEKERJAAN PEMBANGUNAN SUCTION SCRUBBER 14 days Thu 5/16/19 Wed 5/29/19 82,102 77
82 PEKERJAAN PEMBANGUNAN DISCHARGE SCRUBBER 14 days Thu 5/30/19 Wed 6/12/19 93,103 81
83 PEKERJAAN PEMBANGUNAN FUEL GAS SCRUBBER 7 days Tue 6/18/19 Mon 6/24/19 84,104
84 PEKERJAAN PEMBANGUNAN SLEEPER KO DRUM 7 days Tue 6/25/19 Mon 7/1/19 83
85 PEKERJAAN PEMBANGUNAN SLEEPER HEADER MANIFOLD 35 days Tue 5/14/19 Mon 6/17/19
86 PEKERJAAN PEMBANGUNAN PONDASI INSTRUMENT AIR 49 days Tue 7/2/19 Mon 8/19/19 106
87 PEKERJAAN PEMBANGUNAN PONDASI FLARE 14 days Tue 6/11/19 Mon 6/24/19 88,107 98
88 PEKERJAAN PEMBANGUNAN PONDASI PANEL FLARE 7 days Tue 6/25/19 Mon 7/1/19 107,95 87
89 PEKERJAAN SLEEPER DAN PIPE SUPPORT 84 days Tue 3/5/19 Mon 5/27/19 120
90 Pipe Sleeper 49 days Tue 3/5/19 Mon 4/22/19 91,110 69
91 Pipe Support 35 days Tue 4/23/19 Mon 5/27/19 98,110 90
92 PEKERJAAN PARIT & BAK KONTROL 21 days Tue 8/20/19 Mon 9/9/19
93 PEKERJAAN KONSTRUKSI JALAN 1 35 days Thu 6/13/19 Wed 7/17/19 96 82
94 PEKERJAAN KONSTRUKSI JALAN 2 35 days Tue 6/25/19 Mon 7/29/19
95 PEKERJAAN OIL CATCHER 14 days Tue 7/2/19 Mon 7/15/19 97 88
96 PEKERJAAN PANEL ROOM 49 days Thu 7/18/19 Wed 9/4/19 115,116,125,122, 93
97 PEKERJAAN PAGAR KELILING 35 days Tue 7/16/19 Mon 8/19/19 100 95
98 PEKERJAAN CABLE DUCT 14 days Tue 5/28/19 Mon 6/10/19 116,87,115,117,1 91
99 PEKERJAAN PEMBUATAN PONDASI TIANG LISTRIK 14 days Tue 8/27/19 Mon 9/9/19 126,123 100
100 PEKERJAAN PEMBUATAN PONDASI TIANG INSTRUMENT 7 days Tue 8/20/19 Mon 8/26/19 99,148,138,139 97
101 Mechanical Work 64 days Wed 7/31/19 Wed 10/2/19
102 Suction Scrubber 14 days Wed 8/28/19 Tue 9/10/19 106,130,141,14 18,81,103
103 Discharge Scrubber 14 days Wed 8/14/19 Tue 8/27/19 102,131,142,14 19,82,104
104 Fuel Gas System 14 days Wed 7/31/19 Tue 8/13/19 132,144,103,14 20,83
105 Over Head Crane 7 days Thu 9/26/19 Wed 10/2/19 79,21,107
106 Instrument Air Compressor 7 days Wed 9/11/19 Tue 9/17/19 22,86,102
107 Flare Package 7 days Wed 7/31/19 Tue 8/6/19 105 23,87,88
108 Piping Work 114 days Sat 6/8/19 Sun 9/29/19
109 Fabrication pipe spool 60 days Sat 6/8/19 Tue 8/6/19 110FS‐30 days 25FS‐60 days
110 Instalasi pipa 49 days Mon 7/8/19 Sun 8/25/19 111FS‐14 days,1109FS‐30 days,90,91
111 Tie‐in works 21 days Mon 8/12/19 Sun 9/1/19 110FS‐14 days
112 Hydrotest 21 days Mon 8/26/19 Sun 9/15/19 113FS‐7 days,15110
113 Painting 21 days Mon 9/9/19 Sun 9/29/19 112FS‐7 days
114 Electrical Work 101 days Thu 7/4/19 Sat 10/12/19
115 Pekerjaan UPS system and battery 30 days Thu 9/5/19 Fri 10/4/19 151FF 50,96,98
116 Pekerjaan Lighting panel 14 days Thu 9/5/19 Wed 9/18/19 151 51,96,98
117 Pekerjaan Modifikasi Eksisting MCC 21 days Thu 9/5/19 Wed 9/25/19 151 96,98,58
118 Pekerjaan Cabling System 1 ‐ new panel room to existing panel 21 days Thu 7/4/19 Wed 7/24/19 151,124,125,12 52,53,98
119 Pekerjaan Cabling System 2 ‐ new panel room to field 21 days Thu 7/4/19 Wed 7/24/19 151 52,53
120 Pekerjaan Cabling System 3 ‐ eksisting panel room to field 21 days Thu 7/4/19 Wed 7/24/19 151 52,53,89
121 Pekerjaan Penangkal Petir dan grounding 1 (shelter) 6 days Thu 9/26/19 Tue 10/1/19 152 54,79
122 Pekerjaan Penangkal Petir dan grounding 2 (panel room) 4 days Thu 9/5/19 Sun 9/8/19 152 54,96
123 Pekerjaan Penangkal Petir dan grounding 3 (open area) 4 days Tue 9/10/19 Fri 9/13/19 152 54,99
124 Pekerjaan Lighting Fixture 1 (shelter) 10 days Thu 10/3/19 Sat 10/12/19 152 56,80FS‐14 days,118
125 Pekerjaan Lighting Fixture 2 (panel room) 5 days Thu 9/5/19 Mon 9/9/19 151 96,57,118
126 Pekerjaan Lighting Fixture 3 (process area) 10 days Tue 9/10/19 Thu 9/19/19 152 99,56,118
127 Instrument Work 77 days Wed 7/31/19 Tue 10/15/19 152
128 Pemasangan Control Valve / Regulator Valve 21 days Thu 9/19/19 Wed 10/9/19 151FF‐7 days 32,47,112,138
129 Pemasangan SDV/BDV 14 days Thu 9/19/19 Wed 10/2/19 151FF‐7 days 33,47,112,139,144
130 Pemasangan PSV (Suction Scrubber) 5 days Wed 9/11/19 Sun 9/15/19 151FF‐7 days 34,102
131 Pemasangan PSV (Discharge) 5 days Wed 9/4/19 Sun 9/8/19 151FF‐7 days 34,103
132 Pemasangan PSV (Fuel Gas) 4 days Wed 9/4/19 Sat 9/7/19 151FF‐7 days 34,104
133 Pemasangan Orifice & RO (1,2) 18 days Mon 9/16/19 Thu 10/3/19 136 36,47,112
134 Pemasangan Orifice & RO (3,4) 18 days Mon 9/16/19 Thu 10/3/19 136,137 36,47,112
135 Pemasangan Orifice & RO (5,6&7) 27 days Mon 9/16/19 Sat 10/12/19 137FS‐9 days 36,47,112
136 Pemasangan Flow Recorder (1,2,3) 12 days Fri 10/4/19 Tue 10/15/19 151FF‐7 days 35,47,133,134
137 Pemasangan Flow Recorder (4,5&6) 12 days Fri 10/4/19 Tue 10/15/19 151FF‐7 days 35,47,134,135FS‐9 day
138 Pemasangan Pressure / Level Controller 21 days Tue 8/27/19 Mon 9/16/19 128 37,47,150,100
139 Pemasangan Pressure Switch 21 days Tue 8/27/19 Mon 9/16/19 129 38,45,46,47,150,100
140 Pemasangan Pressure Gauge 14 days Mon 9/16/19 Sun 9/29/19 151FF‐7 days 39,47,112
141 Pemasangan Level Gauge Glass (Suction Scrubber) 7 days Wed 9/11/19 Tue 9/17/19 151FF‐7 days 41,47,102
142 Pemasangan Level Gauge Glass (Discharge Scrubber) 7 days Wed 8/28/19 Tue 9/3/19 151FF‐7 days 41,47,103
143 Pemasangan Level Gauge Glass (Fuel Gas) 7 days Wed 8/14/19 Tue 8/20/19 151FF‐7 days 41,47,104
144 Pemasangan Level Switch 21 days Wed 8/14/19 Tue 9/3/19 129 40,45,46,47,104
145 Pemasangan Temperature Gauge (Suction) 2 days Wed 9/11/19 Thu 9/12/19 151FF‐7 days 42,47,102
146 Pemasangan Temperature Gauge (Discharge) 3 days Wed 8/28/19 Fri 8/30/19 151FF‐7 days 42,47,103
147 Pemasangan Temperature Gauge (Fuel Gas) 2 days Wed 8/14/19 Thu 8/15/19 151FF‐7 days 42,47,104
148 Pemasangan Sounder/Beacon 21 days Tue 8/27/19 Mon 9/16/19 151FF‐7 days 43,45,46,47,100,150
149 Pemasangan Rotameter 7 days Mon 9/16/19 Sun 9/22/19 151FF‐7 days 44,47,112
150 Fabrikasi Steel Work 7 days Wed 7/31/19 Tue 8/6/19 138,139,148 48,47
151 Pre‐Comm 20 days Sat 9/28/19 Thu 10/17/19 152 112,115FF,116,120,11
152 Comm & Start Up 10 days Fri 10/18/19 Sun 10/27/19 151,127,121,122,123,
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split Slack
Project: Schedule Retender EPC Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 10/9/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 2