0% found this document useful (0 votes)
190 views1 page

SOW - ODU Swapping

The document provides instructions for swapping an ODU (outdoor unit) at an Idea site. It outlines 11 activities, including obtaining site access and permission, safely receiving equipment, using proper safety gear, documenting existing equipment, installing the new ODU without disturbing the antenna, ensuring the new configuration meets Rx level requirements, documenting removed equipment, and ensuring compliance with health, safety and work procedures. The vendor is responsible for providing manpower, tools, and conducting several of the activities while the site owner is responsible for others like providing access and permission.

Uploaded by

sarokarthikar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
190 views1 page

SOW - ODU Swapping

The document provides instructions for swapping an ODU (outdoor unit) at an Idea site. It outlines 11 activities, including obtaining site access and permission, safely receiving equipment, using proper safety gear, documenting existing equipment, installing the new ODU without disturbing the antenna, ensuring the new configuration meets Rx level requirements, documenting removed equipment, and ensuring compliance with health, safety and work procedures. The vendor is responsible for providing manpower, tools, and conducting several of the activities while the site owner is responsible for others like providing access and permission.

Uploaded by

sarokarthikar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

SOW- ODU Swapping

S. VIL Vendor Remarks/Explanatory


Activity type
No Scope Scope Note
1 Site key management & access S R
Display a valid ID for site access
2 Get permission from Idea Site In-charges for access & perform R
activity
Receive and acknowledge of Material Receipt in good
If not, same will be
3 condition from Transporter and Reporting VIL immediately S R
debit from vendor.
in case of any shortages / Damages.
Eg. Safety belt & cap
Supply of Adequate skilled manpower, standard & Safety
4 R are mandatory for
tools
working on tower
Obtaining and sharing Snap shots of existing HOP Rx level
5 and Serial Numbers of IDU/ODU 1+0, 1+1, WS card, Modem R
card and interface card etc.
De-installation of existing ODU & Installation of new ODU & If misaligned,
6 earthing without disturbing antenna and proper R alignment to be
weatherproofing corrected.
7 Stickering of ODU Site Name & Site ID R
Commissioning of IDU with New SPOT frequency and
retaining all other parameters unchanged. Snap shots of HOP
8 Rx level is to be attached and it shall be remain or improved R
RX level only, No Degradation is allowed. Ensure NMS
connectivity.
9 Snapshot of dismantle equipment S R
Ensure Proper packing of all removed materials and Handing
10 S R
over to IDEA Representative
11 Ensuring HSW Compliance, PTW and TT before activity R