Appendix 5
Check List for Change Control Assessment
Non Critical Materials Critical Materials
Impact on site SOPs, batch documentation X X
etc.
Impact on supply X X
Training of personnel X X
Process validation X
Cleaning Validation X X
Equipment Qualification X
Safety X X
Environmental X X
TSE assessment X X
Stability Impact and the minimum period X
before release
Impact on testing of final product X
Extra testing for material received X X
Extra testing during production X
Extra testing requirements to assess the X
impact of the change
Regulatory impact on the filed product with X
all appropriate agencies.
For new product, the filing strategy is
developed in partnership with research.
For old product the filing may be needed
to be updated
Down stream impact on customers X