Conservation of Zippori Mosaics
Conservation of Zippori Mosaics
1. INTRODUCTION
floor
This article describes the on-site conservation of a group of 12 polychrome
The interven-
mosaics found in a 3rd century AD public building in Zippori, Galilee'.
ty of Israel.
tion is included in a broader project directed by the National Parks Authori
t com-
The part of the project regarding the mosaics was implemented in two differen
tural roof-
paigns in 1994 and 1995 and is now concluded. Construction of fixed architec
masonry walls is actu-
ing and sealing the trenches left from the removal of the original
ns and
ally almost completed. Both campaigns were carried out in 'building yard' conditio
of the Nile was carried out al-
under temporary cover. The conservation of the mosaic
built for this purpose . We would
lowing the public to wach the work "live": a terrace was
t on various
like to describe the conservation intervention on the mosaics and commen
then consider the principl es and the
aspects. Starting with technical procedures, we will
followe d and we will conclud e with some
objectives behind the choice of the methods
general reflections.
University of
The building of the Nile has been excavated by Ze'ev Weiss from the Hebrew
Zippori, Jerusalem 1994.
Jerusalem and published in H. Netzer and Z. Weiss,
322
of Alexandria with the famous light-house, together with several scenes of wild animals
hunting each other. They all share a high aesthetic and technical quality.
The mosaics' state of conservation divides them into two groups, according to
whether or not original masonry is present. The masonry was stolen from part of the
building in ancient times, causing severe damage to the floor foundations, considerable
loss and upheaval to the mosaics themselves. Where the masonry (and the foundations)
are still in place, the floors have some hollows in the bedding and surface calcareous de-
posits, but are in a generally good state of conservation. The damages caused by struc-
tural collapse are visible everywhere.
The intervention took place in two separate campaigns: April/June 1994 and
May/August 1995. The first campaign was dedicated to the Nile mosaic; the second dealt
with the remaining floors (Fig. 3). The work teams comprised eight professional conser-
vators plus four local technicians. The division of the mosaics into two groups (one in the
first and eleven in the second) depended upon the working and 'strategic' requirements
of the site management: the work to be done on the -Nile, a very well known mosaic,
was meant to create the conditions needed to authorize and finance intervention on the
rest of the building. The apparently disproportionate time allotment (three months for
one mosaic and four months for eleven mosaics) was due to the typology of the Nile mo-
saic (50 square meters of extremely fine mosaic work) and to its poor state of conserva-
tion (large hollow areas in the preparatory layers, insoluble surface deposits, areas where
settling had crumbled the tesserae). This demanded considerable time, whereas during
the second campaign, the different state of conservation of the mosaics and the greater
familiarity of the conservators with the situation in general allowed a faster working pace.
The working-steps, in the order of their execution, were: planning documentation; pre-
ventive measures of protection; pre-consolidation; in-depth consolidation; cleaning; sur-
face consolidation; bordering; treatment of lacunae; final inspection; temporary protec-
tion; recommendations for final protection.
aspect of the plan, was its presence as a parameter for what was actually accomplished in
the field. The comparative analysis of plan data and effective data, and particularly the
study of errors in planning, furnished precious information to add to what we already
have in this sector.
To do this, we drew up tables to be filled in daily, showing the date, floor number,
technical operations, conservator's name, hours of work. The data thus collected became
instrumental in drawing up new plans. They can be distributed and will enrich the files
needed to plan the conservation and maintenance of archaeological sites.
Surface consol. lh 10m 10m 5m 15m lh 15m 40m 20m 10m 30m lh 30 min.
3.2 Documentation
Documentation is the first operation carried out on-site: each mark on the mosa-
ic's surface is classified and represented graphically on specific, pre-arranged drawings.
The process starts by entering the state of conservation (type of decay) of the mosaic, de-
tails of the original techniques of making the mosaic (sinopia, giornate, retouchings), of
the historic life of the building (uses, restorations, collapse). Documentation continues
throughout the intervention, entering the operations carried out and the areas treated and
will go on throughout maintenance 2.
2
Normal 1/88, Alterazioni macroscopiche dei materiali lapidei: lessico. CNR ICR, Roma 1990.
324
width of the floor. They were held by a track based on the foundations of two opposite
walls of the room. This allowed two different teams to work simultaneously on different
areas of the mosaic without trampling directly on the tesserae. These bridges were easily
moved when necessary, such as when tourists wished to view particular sections of the
mosaic or the conservator's schedule permitted the total view of the floor.
This construction added one week to the planned work period, but it was created
to ensure protection of the mosaic, the safe carrying out of the work and the correct de-
velopment of subsequent activities.
3.4 Preconsolidation
During this operation, those areas of the mosaic in which the tesserae have become
loose or detached from their original beds are temporarily set. The borders of the floor
mosaic are reinforced (exteriors and also the internal edges of lacunae) with lime-based
mortar (1/2 Lafarge hydraulic lime, 1/2 slaked lime, 2 sifted stone powder) set perpen-
dicularly to the mosaic plane in a very thin layer (12 mm). The areas where the tesserae
were detached and out of order and which needed consolidation and cleaning, were pro-
tected by gauze, once the areas were cleaned with varying kinds of dry and damp brush-
es. The gauze was applied with an acrilic resin, Paraloid B72, diluted in acetone 15%.
Paraloid was chosen after direct comparison with PVA (Polyvinil acetate). This, while
more practical because of lower toxicity, easier acquisition on the local market and greater
elasticity of the finished product (with respect to Paraloid's great rigidness) turned out to
be too vulnerable to the water that we would be using in a subsequent phase. The gauze
was removed after consolidation using acetone compresses and brushing. In the rare in-
stances of decohesion of the tesserae themselves, as for example with some vitreous pastes,
a protective treatment was established using Ethilsilicate Waker OH, applied by brush or
dropper.
3 D. Ferragni, M. Forti, J. Malliet, J.M. Teutonico, G. Torraca, 'Injection grouting of mural paint-
pp. 110-116. A. Costanzi Cobau,
ings and mosaics', in Adhesives and C,onsilidant.c IIC, London 1984,
R. Nardi, 'In situ consolidation of mosaics with techniques based on the use of lime', in ICCM News-
letter n. 5, 1992, pp. 9-13. A. Costanzi Cobau, The Roman Forum. On-site conservation of floor sur-
faces during excavation', Mosaicos no. 5. Conservacio n in situ, Palencia 1990, Roma 1990, pp. 127-138.
326
ing tape and is drawn on the relative graphic representation in the documen-
tation.
3.5.2 Creation of access points
In order to work beneath the tesserae layer, it is necessary to create several ac-
cess points depending upon the size of the area to consolidate, and the ease of
linking these points. It is usually preferable to work in the lacunae or in da-
maged areas. Where this is impossible, several tesserae are removed, momen-
tarily placed on a clay support, numbered, cleaned, and ready to be replaced.
3.5.3 Protecting the areas to be lifted with gauze
The hollows found near edges or lacunae are at times easier to reach from the
edges of the lacunae themselves. This means that the mosaic must be previ-
ously 'see with gauze in order to avoid sinking while the preparatory and con-
solidation work goes on. This is done as it was for "pre-consolidation."
3.5.4 Removing all non-cohesive material (infiltrated earth, original disaggregated
mortar) from the hollows
The prepared holes provide access to the hollows; cleaning is first done using
flexible steel instruments and an aspirator without water. After the initial dry
cleaning, a water cleaning is carried out inserting small flexible metal tubes in-
to the empty area. An aspirator is used to avoid accumulation of water and de-
bris inside the hollows. When all the access holes are linked and the hollow
has become one single even space, the procedure continues to consolidation.
3.5.5 Introducing new mortar
This operation is carried out with grouting mortar (Lafarge hydraulic lime,
sifted pulverized brick dust 1:1 with water added to obtain a fluid mixture).
The area to consolidate must be thoroughly wet. The infiltration is done with
catheter syringes starting from one side of the hollow and working progres-
sively towards the other. The process is slow and needs constant tapping up
until the space is completely saturated (Fig. 4).
3.5.6 Revision
The consolidation can be perfected only during the few moments the mortar
is liquid. It is therefore very important to check by hand and by ear' that the
area being treated is completely saturated by the new consolidant. If not, more
mixture is injected.
3.5.7 Removing the protective gauze
At least one day after consolidation (or more, depending on the climate), when
the mortar has reached a degree of solidity, the gauze is removed.
3.5.8 Closing access points
When the infiltration is completed, the tesserae that were removed are replaced
and the edges of the consolidated areas are stuccoed (where they reach the bor-
ders).
327
3.6 Cleaning
This was carried out preferably by using mechanical hand tools (scalpels, plastic
brushes, small chisels), and pneumatic tools (micro-vibrators and nylon brush drills).
p
Once the mechanical cleaning was done, and in order to touch up the results, paper-pul
sodium bicarbona te) 4 were applied for 4 hours. When the
compresses of AB57 (without
deposits were particularly resistent, the compress was applied more than once. Each AB57
application was followed by a distilled-water compress in order to lift away salt residues
(Fig. 5).
3.8 Borders
These were defined by creating an edge at right angles to the mosaic surface 12 mm
wide. The material used was a lime-based mortar made up of Lafarge hydraulic lime,
was applied to a carefully
slaked lime, sifted pulverized stone (1 /2:1 /2: 2). The mortar
wetted surface and then thoroughly polished.
L. Mora, P Mora, `Metodo per la rimozione di incrostazioni su pietre calcaree e dipinti murali',
a
CNR, Rome 1972.
328
was used wherever a layer about 5 mm beneath the final floor level had to be created. This
layer was made of slaked lime, non-sifted pulverized stone and washed residues of sifted
brick dust in a ratio of 1 : 2: 1 /2. At every 1 or 2 cm of mortar, a layer of washed ceramic
fragments embedded in the mortar itself was used. The ceramic and the mortar's bigger
granulometry (from 1-5 mm) acted as buffers as the mortar shrank during drying. The
washed residues of sifted brick dust were used to add hydraulicity and hardness to the
mortar without having to add Lafarge hydraulic lime (expensive and not easily found on
the local market).
The final treatment of the lacunae consisted of a thin layer (less than 5 mm) of light
coloured mortar similar to the white tesserae (Lafarge hydraulic lime, slaked lime, sifted
pulverized stone in the ratio of 1 /2:1 /2 : 2).
The surface was finished by repeated polishing for three days after the mortar was
applied; the surface was smooth (no sponging) instead of rough matte which is aestheti-
cally pleasing but dust-sensitive. The final surface of the lacunae was kept only 2 mm low-
er than the original to keep the two different materials separate (tesserae and mortar) with-
out weakending the edges too much.
In one case, the floor picturing the Amazons, where the lacuna was greater in size
than the remaining part of the original mosaic, a different surface finish was used. The
final layer of mortar was tapped with a stone to create a dappled effect typical of the lay-
er in which the tesserae are embedded.
This was done because the smooth finish, although neutral, assumes a definite 'per-
sonality' when it covers a large area, and would have interfered, in this situation, with the
final, over-all reading of the mosaic. With this solution the lacuna becomes simply one
of the preparatory layers of the floor without its tesserae. It was, obviously, the subject of
lengthy discussions. The comments, put synthetically, are: negative because of the low
dust resistence and close resemblance to the original foundation layer, but greatly posi-
tive for the aesthetic result and low interference with the mosaic design.
and se-
tion was planned to be inert in case of rain (no substances added to the mosaic)
cure in preventing plants growing .
of the
Unfortunately the protection was "improved" by applying plywood on top
to absorb
tuff. This, instead of offering extra protection, cut the ability of the grains
ting shocks to
mechanical stresses and produced rigid structures (dangerous for transmit
l additive s in case
the surface of the floors). An even greater risk is the emission of chemica
of rain, very common in winter time.
the last
In the light of this experience and following the experiences carried out over
a solution suggeste d for
years 5 on the temporary protection of mosaics, we now present
le, full of expande d clay (or
archaeological mosaics. This is made of "pillows" in geotexti
cm and 100 x 150. Those pillows
washed tuff), sealed and reusable measuring: 200 x 150
on to the
will be layed on a stratum of geotextile over the entire floor, directly applied
mosaic needs to be exposed and
mosaic. The pillows will be moved and stored when the
then re-laid onto the floor for further protection.
to the public
3.12 Recommendations for the presentation of the mosaics
s of pro-
The mosaics of the Building of the Nile call for some preventive measure
will be
tection before their opening to the public. The future conservation of the mosaics
directly linked to the architectural solution adopted.
ept rain and floods;
— They need to be roofed and protected from rain, wind-sw
be allowed to cross the corridor s between the mosaics (where the-
— Visitors can
to
re is no mosaic on the floor) but solid protective measures must be taken
prevent intrusions. Paths or bridges must be set to protect the mosaics from
being trampled on;
dust entering the area of
— barrier (even a textile wall) must be built to limit
A
the polychrome mosaics;
3.12.1 Trampling
The surface of the mosaic must be protected from the mechanical stresses
linked to the passing of visitors. The treated mosaic is now capable of sup-
porting one operator employed to execute the maintenance programme, but
is not physically capable of supporting the stress created by visitors. Peripheral
paths or bridges could be created or a structure that permits observing the
mosaic but avoids the direct contact between the visitors and the mosaic.
(this last point will be treated separately). To avoid the aforementioned risks
it will be necessary for the roofing to protect the mosaic from direct sun-
light. The covering will be efficient if it separates the mosaic from direct
contact with the sun's rays.
3.12.4 Flooding
In addition to the aforementioned risks, the risk of flooding must be men-
tioned. Such an event would bring a large quantity of debris (mud, various
clays) that would seriously compromise the cleaning of the mosaic. One
must therefore foresee the presence of structures (peripheral drainage) ca-
pable of collecting and draining excess water.
3.12.6 Biodeterioration
The growth of micro-organisms is among the factors most linked to the ar-
chitectural choices. The most efficient protection will be the constant main-
tenance of the floors.
3.12.7 Dust
It is probably one of the most urgent and macroscopic problems of the mo-
saics. This is obviously related to its setting in a rural environment. To avoid
dust deposits on the mosaic turning into an insoluble crust, one must im-
plement a continuous and frequent maintenance programme. It is suggested
that this factor is kept in mind when designing the architectural structure
and to foresee problems relating to an enviroment which is semi or com-
331
pletely protected from the infiltration of dust. This does not necessarily lead
to heavy, solid structures. The dust may be screened even by light and fle-
xible materials (textiles).
5,
6 G. de Guichen, A short history of the Committee, in ICCM Newsletter n. 1992, pp. 4-5.
332
The conservation of the Nile mosaic was strong propaganda in this sense: if the method
was successful with such an important mosaic, then it must work.
As we usually do, we invited, using a multilanguage questionnaire, public comment
on certain aspects we felt were important or perhaps dubious. At the question: " To con-
serve and to exibit to the public the mosaic ofthe Nile we had 2 possibilities": people answered
in the following way: 89% to restore the mosaic in situ and to construct a cover for protec-
tion" and 11% to detach the mosaic and to transfer it to a museum".
4.2 To maintain all the historical values visible on the mosaic surface and otherwise classified
as: reutililization, old restorations, settling, mechanical damage, lacunae, breakage
Directly connected to the in situ conservation of the mosaic is the theme of pre-
serving the aesthetic image of the floor as it has come to be through the centuries. Obvi-
ously we do not mean dirt deposits or other extraneous elements that interfere; we mean
the preservation of all natural and anthropic traces which have characterized the mosaic
as we know it. In order to understand the principle more clearly, we can use as examples
a modern mosaic and an archaeological mosaic. The place we would expect to find the
former is probably an interior design show; whereas the latter would be an archaeologi-
cal excavation. We must respect and satisfy the expectations of the public that comes to
visit a site, avoiding the trap of presenting a mosaic "bright, shiny, good as new." We
should, instead, encourage an historical interpretation through the marks left in time,
presenting a clean work of art, free of disturbing elements but complete in its particular
history and within its own context. Asking the visitors: "The mosaic as you see it today
conserves the signs of its history such as the Byzantine restorations and the indentation
caused by the fall of the ceiling", 77% think that "this is part of the history and therefore
must be conserved and presented to the public" and 23% think that: "these elements dis-
turb the legibility of the mosaic and must be removed in order to bring the surface to its
original level state.
4.3 To open the work site to the public and thus transform a technical intervention into a cul-
tural event
Thanks to the terrace built above the Nile mosaic, almost 10,000 visitors each month
were able to see work in progress live' (Fig. 7). This initiative was supplemented with in-
formation posters, updating briefings for tourist guides, lectures and guided tours. All this
contributed to open the technical intervention into a cultural event, creating greater sen-
sitivity among the public towards safeguarding the cultural heritage. Opening the con-
servation project to visitors does not means simply to allow the public physical access to
the site: the relationship with the public must be active, it must be managed rather than
endured. The public must be made to feel welcome by didactic aids or guided tours. In
Zippori the tourist guides were constantly brought up to date on the progress of the work,
and thus they functioned as a cushion between the public and the conservators. The re-
sponse of the children has been very positive, as has been shown by the large number of
guided tours requested by the schools. The initiative met with great public success and
achieved considerable media attention.
333
5. CONTINGENCIES
This item always appears in the balance of payments, but never in reports. The rea-
son probably is that the conservator is afraid of being accused of something going wrong.
We would instead like to comment upon an unplanned aspect of the programme since
analyzing contingencies is the best way to avoid similar errors in the future.
A series of organizational problems led to undertaking the second campaign while
the cover and new wall foundations were being built. This created a series of obstacles
that need no comment:
• the floors were not filled up to the outside edges;
• people not connected to the conservation project were continually moving
around consequently damaging the mosaics;
• the conservators were constantly distracted by so much extra activity;
• the newly restored floors had to be covered again with geo-textile and washed
tuff grains for their protection;
• organizing an official opening ceremony for public and media at the end of
the job was impossible.
6. CONCLUSIONS
It has again become evident that during a conservation process the mosaic is the
weakest element in the building and must be given absolute priority in terms of protec-
tion. This means that excellent working conditions must always be created, limiting in-
terference and the number of operations to be carried out. Every contact with the mosa-
ic (documentation, photos, visits, interviews, studies) is a source of potential damage in
spite of who may be responsible. Ironically, the more the person in charge feels part of
the process and expert in it, the more careless and possibly dangerous, he becomes. And
even if these damages, should they occur, be minor, their very number creates a problem.
The protective measures (temporary earth covering, covers of other kinds) are in any case
stress sources for the floor, straining one tessera against another. This allows us to define
a new threat: Excess Care.
The obvious conclusion: efforts must be concentrated on planning, even putting
off the starting date to ensure excellent working conditions.
At the end of this experience, we reaffirm the validity of the principles and tech-
niques such as: in situ conservation without detachment, preservation of historic 'traces',
techniques based on the use of traditional materials; and especially we would emphasize
the success we met in opening the work-site to the public. Visitors (and the media) re-
sponded enthusiastically, confirming the concept that investments in information have
high yielding results.
335
ACKNOWLEDGEMENTS
Yaacov Shaeffer from the Is-
The authors are grateful to Arch. Giora Solar and Eng.
ration programme with CCA for
rael Antiquities Authority for launching in 1990 a coope
n using traditional methods. We
the training of local technicians in on-site conservatio
Or and Zeev Margalit from the Na-
would also like to acknowledge Arch. Amnon Bar
Linder from Zippori National Park
tional Parks Authority and Benny Shalev and Zvica
to the Institute of Culture of the Ital-
for their constant assistance. Special thanks are due
d tours on site.
ian Embassy for having organized lectures and guide
DISCUSSION
Pique: I would like to know if you do reintegration of the losses. I always see very nice
neutral tones, so I wondered if you ever do something.
Costanzi Cobau: Yes. Where there is no risk, in the case of small lacunae, we think that
it is better to fill them with tesserae.
Fig. 4: Deep consolidation. This operation is carried out with grouting mortar. The infiltration is done
with catheter syringes starting from one side of the hollow and working progressively towards the other.
The process is slow and needs constant tapping up until the space is completely saturated.
339
Fig. 7: Thanks to a terrace built above the Nile mosaic, almost 10,000 visitors each
month were able to see work in progress live'. All this contributed to open the tech-
nical intervention into a cultural event, creating greater sensitivity among the pub-
lic towards safeguarding the cultural heritage.