Task No. Task Description Precedes Duration

The document outlines a work breakdown structure for a construction project with 26 main tasks labeled A through ZZ. It shows the task name, duration in days, and which preceding tasks must be completed before each task can begin. The critical path runs through tasks B, C, G, H, I, J, K, L, M, P, Q, R, S, T, U, V, W, X, Y, Z, AA, BB, CC, DD, EE, FF, GG, HH, II, JJ, KK, LL, MM, NN, OO, PP, QQ, RR, SS, TT, UU, VV, WW, XX, YY, and ZZ.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
120 views3 pages

Task No. Task Description Precedes Duration

The document outlines a work breakdown structure for a construction project with 26 main tasks labeled A through ZZ. It shows the task name, duration in days, and which preceding tasks must be completed before each task can begin. The critical path runs through tasks B, C, G, H, I, J, K, L, M, P, Q, R, S, T, U, V, W, X, Y, Z, AA, BB, CC, DD, EE, FF, GG, HH, II, JJ, KK, LL, MM, NN, OO, PP, QQ, RR, SS, TT, UU, VV, WW, XX, YY, and ZZ.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Task No.

Task Description Precedes Duration


A Mobilization B 5
B Siteworks C,D 8
C Fabrication of Column, G 13
Footing, Footing Tie
Beam & Slab Rebars
D Fabrication of Septic E 2
Tank Rebars
E Installation of Septic F 2
Tank Rebars
F CHB Layouting & K 3
Mortaring of Septic
Tank
G Fabrication of Column, H 9
Footing & Footing Tie
Beam Forms
H Installation of Footing I 6
& Footing Tie Beam
Rebars
I Installation of Column J 6
& Slab Rebars
J Installation of Column , K 8
Footing, and Footing
Tie Beam Forms
K 1st Floor Roughing-in L,N 5
Plumbing & Electrical
Layout
L Concreting of Footing M 5
& Footing Tie Beam
M Concreting of Column P 5
& Slab
N Fabrication of 2nd Floor O 9
Column, Beam & Slab
Rebars
O Fabrication of 2nd Floor P 11
Column, Beam & Slab
Forms
P Installation of 2nd Floor Q 7
Column, Beam & Slab
Rebars
Q Installation of 2nd Floor R 10
Column, Beam & Slab
Forms
nd
R 2 Floor Roughing-in S,T 4
Plumbing & Electrical
Layout
S Concreting of 2nd Floor V 6
Column, Beam & Slab
T Fabrication of 3rd Floor U 9
Column, Beam & Slab
Rebars
U Dismantling of 2nd V 5
Floor Column, Beam &
Slab Forms
V Installation of 3rd Floor W 7
Column, Beam & Slab
Rebars
W Installation of 3rd Floor X 10
Column, Beam & Slab
Forms
rd
X 3 Floor Roughing-in Y,Z 4
Plumbing & Electrical
Layout
Y Concreting of 3rd Floor BB 6
Column, Beam & Slab
Z Fabrication of 4th Floor AA 9
Column, Beam & Slab
Rebars
AA Dismantling of 3rd BB 5
Floor Column, Beam
and Slab Forms
BB Installation of 4th Floor CC 7
Column, Beam and
Slab Rebars
CC Installation of 4th Floor DD 10
Column, Beam & Slab
Forms
th
DD 4 Floor Roughing-in EE,FF 4
Plumbing & Electrical
Layout
EE Concreting of 4th Floor HH 6
Column, Beam & Slab
FF Fabrication of 5th Floor GG 9
Column, Beam & Slab
Rebars
GG Dismantling of 4th HH 5
Floor Column, Beam &
Slab Forms
HH Installation of 5th Floor II 7
Column, Beam & Slab
Rebars
II Installation of 5th Floor JJ 10
Column, Beam & Slab
Forms
JJ 5th Floor Roughing-in KK,LL 4
Plumbing & Electrical
Layout
KK Concreting of 5th Floor NN 6
Column, Beam & Slab
LL Fabrication of Roof MM 7
Deck Column, Beam &
Slab Rebars
MM Dismantling of 5th NN 5
Floor Column, Beam &
Slab Forms
NN Installation of Roof OO 7
Deck Column, Beam &
Slab Rebars
OO Installation of Roof PP 10
Deck Column, Beam &
Slab Forms
PP Roof Deck Roughing-in QQ 4
Plumbing & Electrical
Layout
QQ Concreting of Roof RR,SS 6
Deck Column, Beam &
Slab
RR Dismantling of Roof TT 5
Deck Column, Beam &
Slab Forms
SS Stairs Construction TT 21
TT CHB Layout on All UU,VV 22
Floors
UU Fenestration WW 21
VV Installation of WW 19
Electrical & Plumbing
Fixtures
WW Plastering XX 36
XX Tile Setting YY 19
YY Painting ZZ 22
ZZ Demobilization 3