SL No Item Unit Labour Excavation Recommende D Constant in Days

This document lists 33 construction items along with the recommended number of labor days required to complete each item. For each item, it specifies the unit of measurement, required labor types including mason, mazdoor, carpenter, and their corresponding recommended constant labor days. Some examples include 0.06 labor days for a mason and 0.62 days for a mazdoor for general excavation work. It also provides labor estimates for tasks like concrete work, brick work, formwork, plastering, and painting.

Uploaded by

shyamsundar_ce
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
178 views4 pages

SL No Item Unit Labour Excavation Recommende D Constant in Days

This document lists 33 construction items along with the recommended number of labor days required to complete each item. For each item, it specifies the unit of measurement, required labor types including mason, mazdoor, carpenter, and their corresponding recommended constant labor days. Some examples include 0.06 labor days for a mason and 0.62 days for a mazdoor for general excavation work. It also provides labor estimates for tasks like concrete work, brick work, formwork, plastering, and painting.

Uploaded by

shyamsundar_ce
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

SL NO UNIT Recommende

ITEM Labour d Constant in


Days
EXCAVATION
1 General Excavation in Hard M3 Mate 0.06
Soil/Dense Soil depth upto 1.5m and
removal Mazdoor 0.62
2 Excavation in foundation depth upto M3 Mate 0.05
1.5m and removal Mazdoor 0.5
3 Extra over 1 & 2 for every additional M3 Mate 0.01
lead of 25.0 M beyond 1.0 M up to Mazdoor 0.12
250 M & deposit to a level of 1.5 M.

4 Filling Soil in Layers M3 Mate 0.02


Mazdoor 0.22
Waterman 0.02
5 Extra over item 1 for an additional M3 Mate 0.01
depth of 1.5 to 3.0 M. Mazdoor 0.11
6 Extra over item 2 for an additional M3 Mate 0.01
depth of 1.5 to 3.0 M. Mazdoor 0.08
CONCRETE
7 Mixer Mixed PCC under Floors M3 Mason 0.17
including mixing, pouring, Mazdoor 1.83
consolidating, Curing but excluding
Waterman 0.8
fair finish & Formwork.
Mixer - Operator 0.07
Mixer 0.07
Vibrator 0.07
8 Mixer Mixed RCC in Substructure M3 Mason 0.17
including mixing, pouring, Mazdoor 2
consolidating, Curing but excluding Bhisti 0.9
fair finish, Reinforcements & Mixer - Operator 0.07
Formwork.
Mixer 0.07
Vibrator 0.07
9 Mixer Mixed RCC in Superstructure M3 Mason 0.24
for slabs including mixing, pouring, Mazdoor 2.5
consolidating, Curing but excluding Waterman 0.9
fair finish, Reinforcements & Mixer - Operator 0.07
Formwork.
Mixer 0.07
Vibrator 0.07
10 Mixer Mixed RCC in Superstructure M3 Mason 0.2
for Beams including mixing, pouring, Mazdoor 3
consolidating, Curing but excluding Waterman 0.9
fair finish, Reinforcements & Mixer - Operator 0.07
Formwork.
11 Mixer Mixed RCC in Superstructure M3 Mason 0.3
for Chajjas including mixing, pouring, Mazdoor 3.5
consolidating, Curing but excluding Waterman 0.9
fair finish, Reinforcements & Mixer - Operator 0.09
Formwork.
12 Mixer Mixed RCC in Superstructure M3 Mason 0.23
for Columns including mixing, Mazdoor 3.5
pouring, consolidating, Curing but Waterman 0.9
excluding fair finish, Reinforcements Mixer - Operator 0.1
& Formwork.
MORTAR
13 Mixing by Hand Cement Mortar of any M3 Mazdoor 0.75
proportion. Waterman 0.07
14 Mixing by Hand Cement Lime Mortar M3 Mazdoor 1.33
of any proportion.
14 Mixing by Hand Cement Lime Mortar M3
of any proportion. Waterman 0.1
Bullock + Driver 0.33
BRICK WORK
15 Brick Work in Cement Mortar M3 Mason 0.94
Mazdoor 1.8
Waterman 0.2
16 Half Brick Thick with / without M2 Mason 0.12
reinforcements Mazdoor 0.2
Waterman 0.07
FORMWORK
17 Columns + Walls M2 Carpenter 0.25
Helper 0.2
18 Floors M2 Carpenter 0.23
Helper 0.2
19 Beams M2 Carpenter 0.3
Helper 0.2
REINFORCEMENTS
20 Cutting, Cranking, Bending Placing & Ton Fitter 10
Tying with Binding Wires. Helper 10
PLASTERING
21 15 mm thick Ceiling plaster in CM M2 Mason 0.08
including Mortar Mixing Mazdoor 0.1
Waterman 0.1
22 15 mm thick Exterior Masonry plaster M2 Mason 0.15
in CM in 2 Layers including Mortar Mazdoor 0.15
Mixing Waterman 0.15
23 15 mm thick Exterior Masonry plaster M2 Mason 0.06
in CM in Single Layer including Mortar Mazdoor 0.1
Mixing Waterman 0.1
24 15 mm thick Interior Masonry plaster M2 Mason 0.08
in CM in Single Layer including Mortar Mazdoor 0.1
Mixing Waterman 0.1
FLOORING
25 40 mm Thick IPS M2 Mason 0.08
Mazdoor 0.12
Waterman 0.1
26 Precast Terrazzo Tiles M2 Mason 0.12
Mazdoor 0.7
Waterman 0.1
27 40 mm Thick Damp Proof Course M2 Mason 0.1
Mazdoor 0.1
Waterman 0.01
JOINERY
28 Door & Window Frame M3 Carpenter 20
Helper 2
29 Paneled / Glazed Door with Frame M2 Carpenter 0.9
Helper 1
30 Fixing Ready Made Shutters to M2 Carpenter 0.25
Frames + Fittings Helper 0.25
PAINTING
31 3 coats of White / Color Wash with M2 Painter 0.02
lime Helper 0.01
32 3 Coats of Distempering M2 Painter 0.08
Helper 0.04
33 3 Coats of Cement Based Paint M2 Painter 0.15
Helper 0.02
Remarks

Labour
Required will be
same for
different mix
Proportion
Labour
Required will be
same for
different mix
Proportion