Ogaom Chapter 9
Ogaom Chapter 9
Please Note:
This manual is written as a whole and provided to industry in sections to allow permit holders to access activity
chapters. It is prudent of the permit holder to review the manual in its entirety and be aware of the content in other
sections of the manual.
9.1.1 Wellheads
Wellheads are required to operate safely under the conditions anticipated during
the life of the well and the wellhead is not to be subjected to excessive force.
Review the ESC’s IRP Volume#5: Minimum Wellhead Requirements for more
information.
9.1.2 Tubing
Tubing is required for the production of gas containing greater than or equal to
five per cent H2S and for all injection and disposal except for the injection of fresh
water. This excludes initial completions and/or hydraulic fracturing.
Page: 88
9.1.3 Packers
Annual packer isolation testing is required for all regulated packer installations.
The report is to be submitted to the OGC within 30 days of the test. If a packer
test fails, the permit holder must complete the repairs without unreasonable
delay.
Operators of disposal wells, injection wells and sour gas production wells should
adhere to the requirements under the Drilling and Production Regulation Section
16(2) and Section 39(6):
Set a production packer in the well as near as is practical above the
injection interval or production formation, and fill the space between
tubing and casing with corrosion and frost inhibiting fluid. This prevents
production or injection fluids from contacting and potentially
compromising the integrity of the well casing.
Page: 89
As per section 16(1)(a) of the Drilling and Production Regulation, function testing
of the subsurface safety valve is to be done in accordance with the
manufacturer’s recommendation, or sound engineering practices. Function
testing, maintenance and inspection requirements may also be specified in an
Order approving a well for use as an acid gas disposal well. Guidance on
acceptable leak rates can be found in the American Petroleum Institute’s (API)
RP 14B: Design, Installation, Repair and Operation of Subsurface Safety Valve
Systems errata document.
In general, the distance from a city, town or village should be measured from the
corporate limits. In cases where the corporate limits do not reasonably
correspond with the boundaries of the community, the permit holder may take a
functional approach such as delineation of the extent of developed areas.
Oil wells completed after October 4, 2010 equipped with an artificial lift, if the H2S
content of the gas exceeds 100 ppm, must install the following:
Page: 90
9.1.6 Fencing
A Notice of Operation (NOO) must be submitted for all work being performed on a
well. This includes initial completions, completions workovers, abandonments and
maintenance. The complete list can be found in the Commission’s Notice of
Operations and Completion / Workover Report Reference Guide. The NOO is to be
submitted electronically through the eSubmission portal on the Commission’s website.
Page: 91
The Notice of Operations submission requires the well authorization number and is
submitted using eSubmission portal within at least 24 hours prior to the start of
completion operations. Notice of Operations submitted at least 7 days prior to the
start of abandonment operations.
If an activity at a well is expected to result in gas being flared, a Notice of Flare must be
submitted using the eSubmission Portal. This Notice may be submitted in conjunction with
a Notice of Operation if a well operation is taking place, or as a standalone submission.
To report actual flare volumes, ensure all volumes flared at a well are included in
production reporting via Petrinex.
Please Note:
Shallow Fracturing operations at a depth of 600 metres or less must be approved in the
well permit. Refer to the Commission’s Oil and Gas Activity Application Manual for more
information.
Subject well permit holders (the well undergoing hydraulic fracture stimulation) are
obligated to manage the risks of inter-wellbore communication between the subject
well and an offset well. The subject well permit holder must have a documented
hydraulic fracturing program that includes the following elements:
Identify all offset wells that could be affected.
Conduct a risk assessment of the identified offset wells.
Develop a well control plan for all offset wells that are at risk.
Modify the hydraulic fracturing program if risks cannot be mitigated.
The subject well permit holder must notify the permit holder of an at-risk offset well of
its planned hydraulic fracturing program and make all reasonable efforts to develop a
mutually-agreeable well control plan. The subject well permit holder must maintain a
copy of the at-risk well control plan for the duration of hydraulic fracturing operations.
The permit holder of an at-risk offset well, upon receiving notification of a planned
hydraulic fracturing program, is expected to engage and work cooperatively with the
subject well permit holder in development of well control plans.
Page: 92
During the design and execution of the fracturing program, the subject well permit
holder must ensure the fracture will not extend into any unintended formations. Any
communications with unintended formations are in conflict Section 22 of the Drilling
and Production Regulation.
Communication events should be reported even if contact did not reach the defined
“incident” level. A database of all communication events will further the understanding
of the resource and assist in the development of effective technology.
Permit holders are requested to report all fracture communication events using the
Inter-Wellbore Communication Report Form. Permit holders are also expected to
follow the ESC’s Industry Recommended Practice 24 for specific methodology and
procedures regarding the inter-wellbore communication management process.
All zones in a well must remain segregated unless permission has been granted for
commingled production. Permission may be granted in an individual well permit or by
a special project for commingling under Section 75 of OGAA.
Page: 93
Activity means:
Production, injection or disposal of fluids.
Drilling, completion or workover operations.
Inactive well means a well that has not been abandoned but:
Has not been active for 12 consecutive months.
If the well is classified as a special sour or an acid gas disposal and has not been
active for six consecutive months.
For active production, injection and disposal wells, the date of the last activity is defined as the
first day of the month following the last month for which production, injection and disposal
volumes were reported.
Observation wells are deemed to be active (see section 9.3.1 of this manual).
A permit holder may apply to the Commission to declassify a special sour well. The context
here is that as production rates fall, the H2S release rate may fall such that the well no longer
should be classified as a special sour well.
Page: 94
The Drilling and Production Regulation defines that a well or a portion of a well
may be designated as an observation well under Section 2(7). Reservoir
observation wells typically gather data on:
Formation pressure, fluid quality or fluid migration related to production,
injection or disposal.
Monitoring well completion operations (microseismic) or seismicity
observation.
A well permit holder must ensure that the static bottom hole pressure of each
observation well is measured at least once per calendar year, unless stated
otherwise in the approval. All static bottom hole pressure measurements and
resulting shut-in time must be reported to the Commission.
Observation wells are treated as active and do not require suspension unless
observation designation is withdrawn:
Observation well designation may be withdrawn if approval conditions
are not met.
Any well may be suspended to a higher standard than the minimum requirements
described in Tables 9A to 9D. Reporting requirements are described in Section
9.5.1.
Page: 95
Permit holders may apply to the Commission Drilling and Production department
for an extension of a deadline.
The following tables describe the Commission’s minimum requirements for each
category.
Pressure testing Low Risk and Medium Risk wells, do not require seals to be pressure
seals tested if integrity can be proven. Criteria for proving integrity are:
Page: 96
Lease Maintenance An area of 10 metres radius around the wellhead must be maintained to
prevent brush from growing and causing a fire hazard.
Noxious weeds must be controlled.
Hazards associated with, but not limited to, pits, rat hole and storage
materials, must be limited.
A visual inspection of the lease and wellhead must be conducted at least
yearly to observe for wellhead integrity, noxious weeds and other hazards.
Visual Inspection
For wells with helicopter access (limited year-round access), the visual
inspection frequency is the pressure testing / monitoring frequency.
Update the status of the well event in Petrinex.
Page: 97
1If applicable, install a bridge plug or packer and tubing plug within 100 metres of the liner top on uncompleted special sour
wells. If this option is used, ensure the plug is placed within zone or 15 meters or perforations. This Commission encourages
Permit Holders to review AER Directive 20 prior to suspending a Level-A well.
Page: 98
Pressure Testing /
At the time of suspension and At the time of suspension and then
Monitoring / Servicing
then annually. every 5 years.
Frequency
Wellbore must be filled with
Wellbore must be filled with non-
non-saline water or corrosion
saline water or corrosion inhibited
inhibited water. A minimum of
Wellbore Fluid water. A minimum of the top 2 m
the top 2 m must be freeze
must be freeze protected by the
protected by the use of a non-
use of a non-freezing fluid.
freezing fluid.
Type 1: Medium risk gas wells (see Appendix C for more information).
Type 2: Non-flowing oil wells ≥ 5% H2S.
Type 3: Flowing oil wells2.
Well Types Type 4: All injection and disposal wells except for acid gas disposal wells.
Type 6: Completed low risk wells that became inactive on or before 2009-05-30.
Type 7: All non-special sour cased wells that became inactive on or before 2009-
05-30.
2Flowing oil wells are oil wells with sufficient reservoir pressure to sustain flow against atmospheric pressure without artificial lift.
The flowing product is a fluid.
Page: 99
Type 1: All non-special sour cased wells (no perforations or open hole
sections).
Well Types Type 2: Low risk gas wells (see Appendix D of this manual).
Type 3: Water source wells.
Type 5: Non-flowing3 oil wells < 50 mol/kmol H2S.
3
Non-flowing oil wells are oil wells without sufficient reservoir pressure to sustain flow against atmospheric pressure without
artificial lift. The flowing product is a fluid. Removal of polish rods is not required to suspend low-risk oil wells as long as the
polish rod remains connected to the pump jack.
Page: 100
Service wellhead.
Wells requiring installation and yearly testing of a production packer are exempt
from the testing requirements if the well is suspended in accordance with the
Drilling and Production Regulation. Information on packer isolation testing
procedures is available in the Commission’s Water Service Wells Summary
Information document.
For information and requirements regarding long term inactive wells, refer to the
Dormancy and Shutdown Regulation and associated guidance.
Well Suspensions
A Well Suspension / Inspection Report must be submitted to the Commission’s,
Drilling and Production Department within 30 days of suspension of a well. The
completed suspension report must be submitted through the eSubmission portal.
All downhole activities to plug and suspend are considered Workover operations and
must be submitted to the Commission in a Completion/Workover Report. Suspensions
are to be reported as Workovers on report cover pages and in Notices of Operation.
Refer to the Well Data Submission Requirements Manual for further information.
Reactivations
Submission of a reactivation report is not required. Reactivations are identified by
alternate means (i.e. spud date, production reporting).
Page: 102
When submitting a suspended well pressure test report, the annual suspended well
inspection for that year must also be submitted through the eSubmission portal.
Drilling wells that are downhole, but not surface abandoned at the time of rig release, are not
considered abandoned. An abandonment notification and abandonment report must be
submitted to the Commission at the time of surface abandonment as outlined below for the well
status to be changed to abandoned.
For the wells only with conductor casing, permit holders are expected to conduct
abandonments and plugbacks in accordance with the Groundwater Protection Regulation
(Water Sustainability Act).
Page: 103
For water supply wells associated with oil and gas sites, permit holders are required to
conduct abandonments and plugbacks in accordance with the Groundwater Protection
Regulation (Water Sustainability Act).
For a well source well providing water for waterflood and fracturing, the permit holder:
For the wells drilled for oil and gas activities, permit holders are expected to conduct
abandonments and plugbacks in accordance with the AER Directive 20.
If there is any doubt about the adequacy of a plugging or abandonment program, discuss
the abandonment plans with the Commission. Failure to adequately plug or abandon a
well may result in an order for remedial work.
In cases where a well was cut and capped, but not reported to the Commission at the
time the work was completed, the Commission will accept the following as evidence of
cut and cap:
If the above materials are unavailable, excavate and photograph the casing stub.
Page: 104
The following section outlines blowout prevention standards that a permit holder
should follow to comply with the requirements of Part 4, Division 2 of the Drilling and
Production Regulation. It is the responsibility of the permit holder to ensure that
blowout prevention equipment and procedures are adequate.
A permit holder may use alternate blowout prevention equipment and techniques if
they can demonstrate by means of a detailed engineering analysis that the alternate
equipment or techniques are adequate as required by Section 16(1) of the Drilling and
Production Regulation.
For the purposes of well servicing, blowout prevention equipment classes are as
follows:
Class A equipment is required for a well where the minimum pressure rating
of the production casing flange is less than or equal to 21,000 kilopascals
(kPa) and the hydrogen sulphide content in a representative sample of the
gas is less than one mol per cent.
Class B equipment is required for a well where the minimum pressure rating
of the production casing flange is:
Greater than 21,000 kPa.
Less than or equal to 21,000 kPa and the hydrogen sulphide
content in a representative sample of the gas is one mol per cent or
greater.
Class C equipment is required for a special sour well (see IRP #2).
Minimum stack components shall conform to the BOP stack configuration as
shown in Appendix B of this manual.
Minimum manifold design shall conform to a Class B manifold.
Page: 105
9.6.3 General
At all times during well servicing, the well must be under control, adequate blowout
prevention equipment must be installed and must be able to shut off flow from the well
regardless of the type or diameter of tools or equipment in the well.
The blowout prevention equipment must have a pressure rating equal to or greater
than the pressure rating of the production casing flange or the formation pressure,
whichever is the lesser.
Hydraulic ram type blowout preventers which are not equipped with an automatic ram
locking device must have hand wheels available.
An accurate pressure gauge to determine the well annulus pressure during a well
shut-in must be either installed or readily accessible for installation.
A service rig used at the well site must have an operable horn on the drilling control
panel for sounding alerts.
A sour service separator and flare system, including appropriate manifolding, must be
used to process sour well effluent.
Page: 106
The accumulator system must be installed and operated in accordance with the
manufacturer's specifications. The system must be:
Connected to the blowout preventers with lines of working pressure equal to
the working pressure of the system, and within seven metres of the well, the
lines must be of steel construction unless completely sheathed with
adequate fire resistant sleeving.
Capable of providing, without recharging, fluid of sufficient volume and
pressure to effect full closure of all preventers, and to retain a pressure of
8,400 kPa on the accumulator system.
Recharged by a pressure controlled pump capable of recovering the
accumulator pressure drop resulting from full closure of all preventers within
5 minutes.
Capable of closing any ram type preventer within 30 seconds.
Capable of closing the annular preventer within 60 seconds.
Equipped with readily accessible fittings and gauges to determine the pre-
charge pressure.
Equipped with a check valve between the accumulator recharge pump and
the accumulator.
Connected to a nitrogen supply capable of closing all blowout preventers
installed on the well.
Page: 107
The following requirements do not apply to snubbing units and service rigs completing
rod jobs. A blowout prevention system must have two lines, one for bleeding off
pressure and one for killing the well, which must:
Be either steel or flexible sheathed hose to provide adequate fire resistant
rating.
Page: 108
Be valved and have a working pressure equal to or greater than that required
for the blowout prevention equipment.
Have one line connected to the rig pump and one line connected to the tank.
Be at least 50 mm nominal diameter.
Be securely tied down.
A full opening ball valve (stabbing valve) which can be attached to the tubing or other
pipe in the well must:
Be ready for use and located in a readily accessible location on the service
rig.
Be maintained in the open position.
Have an internal diameter equal to or greater than the smallest restriction
inside the tubing or casing.
Be kept clean and ice free.
Page: 109
All blowout prevention equipment, except for shear rams on special sour wells, must
be mechanically tested daily, if operationally safe to do so; any equipment found
defective must be made serviceable before operations are resumed.
A pressure test is considered a pass if the pressure decrease is less than 10% over
the 10 minute test.
All tests must be reported in the servicing log book and in the case of a pressure test,
the report must state the blowout preventer tested, the test duration and the test
pressure observed at the start and finish of each test.
At least once every three years, all blowout preventers must be shop serviced and
shop tested to their working pressure and the test data and the maintenance
performed must be recorded and made available to an official on request.
Refer to Energy Safe Canada (ESC)’s IRP Volume #2: Completing and Servicing
Critical Sour Wells for detailed information.
Page: 110
Hammer unions should not be used in the manifold shack or under the rig
substructure.
The following people must possess a valid Well Service Blowout Prevention certificate
issued by Energy Safe Canada (ESC), or a Well Intervention Pressure Control Level 4
certificate issued by IWCF, or a WellSharp Oil and Gas Operators Representative
certificate (WSOGOR) issued by IADC:
The driller on tour.
The rig manager (tool push).
The permit holder’s representative.
If gas containing H2S is expected, every crew member must be trained in H2S safety.
Blowout prevention drills should be performed by each rig crew every seven days or
once per well, whichever is more frequent. Blowout prevention drills should be
recorded in the servicing log book.
Evidence of the qualifications of any person referred to in this section must be made
available to an official on request.
Page: 111
The rig crew must have an adequate understanding of, and be able to operate, the
blowout prevention equipment and, when requested by an official and if it is safe to do
so, the contractor or rig crew must:
Test the operation and effectiveness of the blowout prevention equipment.
Perform a blowout prevention drill in accordance with the Well Control
Procedure placard issued by the Canadian Association of Oilwell Drilling
Contractors (CAODC) or as outlined by the ESC Blowout Prevention Manual.
Refer to the ESC’s IRP Volume #7: Standards for Wellsite Supervision of Drilling,
Completions and Workovers for more information.
Engines
Permit holders must ensure that, if engines are located at a wellsite, suitable
safeguards are installed and tested to prevent a fire or explosion in the event of a
release of flammable liquids or ignitable vapours.
For engines located within 25 metres of a well, petroleum storage tank or other
unprotected source of ignitable vapours, the Commission recommends that:
The engine exhaust pipe is insulated or cooled to prevent ignition in the
event that flammable material contacts the exhaust pipe.
The exhaust pipe is directed away from the well or source of ignitable
vapours.
The exhaust manifold is sufficiently shielded to prevent contact with
flammable materials.
For diesel engines located within 25 metres of a well, the Commission recommends
that one of the following devices be installed:
A positive air shutoff valve, equipped with a readily accessible control.
A system for injecting inert gas into the engine’s cylinders, equipped with a
readily accessible control.
Page: 112
A suitable duct so that air for the engine is obtained at least 25 metres from
the well.
Permit holders must also ensure compliance with the requirements in Work SafeBC’s
(Section 23.8) Occupational Health and Safety Regulation.
Fuel
Gasoline or liquid fuel, except for fuel in tanks that are connected to operating
equipment, must not be stored within 25 metres of a well and drainage must be away
from the wellhead.
Smoking
Smoking is prohibited within 25 metres of a well.
Flares and incinerators must be located at least 80 metres from any public road,
utility, building, installation, works, place of public concourse or reservation for
national defence.
Page: 113
Produced Water
Other Sources
& Condensate
Boiler, Steam
Flame Type
Of Ignitable
Generating
Flammable
Equipment
Incinerator
Separator
Produced
Wellhead
Vapours
Flare Or
Tanks
Tank
Wellhead 50 25 Ns Ns Ns 25* 50
Flare Or Incinerator 50 Ns 25 25 25 25 50
Boiler, Steam
Generating 25 Ns 25 25 25 25 25
Equipment, Teg*
Produced Water
Ns 25 25 Ns Ns 25* Ns
Tank
Other Sources Of
Ns 25 25 Ns Ns 25* Ns
Ignitable Vapours
Flame Type
25* 25 25 25* 25* 25* T 25*
Equipment
Produced
Flammable Liquids
50 50 25 Ns Ns Ns** 25*
Crude Oil &
Condensate Tanks
All distances are in metres (M). * 25 m without flame arrestors, not specified with flame arrestors. ** Separator cannot be in the same dyke.
T treaters should be at least 5 m (shell to shell) from other treaters.
Note: A) boilers etc. includes steam generating equipment, electric generators and teg units. B) Other sources of ignitable vapours include
compressors. C) Flame type equipment includes: treaters, reboilers and line heaters. D) All electrical installations must conform to the Canadian
Electrical Code.
Flare Stacks
A sufficient area beneath and around flare stacks must be cleared of flammable
materials and vegetation.
The recommended blackened area beneath a flare stack is 1.5 times the stack height
to a minimum of 10 metres in cultivated areas and 30 metres in forested areas, unless
conditions support a lesser distance.
Page: 114
The Commission recognizes that a lesser area may be justified depending on the
circumstances. It is the responsibility of the permit holder to maintain a sufficient area,
given the location and the conditions under which flaring will or may occur.
Flare blackened areas must be maintained within permissioned land area. If new
area is required to accommodate the blackened area, an amendment to the
well/facility area is required.
Explosives
Explosives must be stored in properly constructed magazines and be located a
minimum of 150 metres from any well servicing operation.
Subject well permit holder must notify a permit holder of an at-risk offset well of a
planned hydraulic fracturing program and make all reasonable efforts to develop a
Page: 115
mutually-agreeable well control plan. The subject well permit holder must maintain a
copy of the at-risk well control plan for the duration of hydraulic fracturing operations.
The permit holder of an at-risk offset well, upon receiving notification of a planned
hydraulic fracturing program, is expected to engage and work cooperatively with the
subject well permit holder in development of well control plans.
All fracture communication incidents must also be reported in accordance with the
Commission’s Incident Reporting Instructions and Guidelines.
The environmental considerations section outlines and explains the regulatory requirements for
testing, repairing and reporting environmental impacts: hydraulic fracturing, seismic activity,
surface case venting flows, gas migration, casing leaks and failures, noise, fluid storage and
spills.
In addition, refer to the Flaring and Venting Reduction Guideline for detailed guidance.
Section 37 of the Drilling and Production Regulation states that permit holders
carrying out hydraulic fracturing operations must maintain detailed records of fracture
fluid composition, and submit records to the Commission within 30 days of well
completion. Hydraulic fracture fluid reports are submitted to the Commission via
Kermit. More information on hydraulic fracture fluid reporting is available in the
Fracture Fluid Disclosure Manual.
Page: 116
In the event of a well pad is responsible for a seismic event, the permit holder will
suspend fracturing operations on the well immediately. The seismic event may be
identified by either the permit holder or the Commission as described above.
Suspended fracturing operations may be continued if: Permit holder presents to the
Commission a plan for mitigation aimed at reducing the seismicity or eliminating well
operations related to the induced seismicity.
Commission is satisfied with the plan.
Permit holder implements the plan.
The Commission tracks northeast B.C. seismic events and compares these seismic
events alongside the locations of oil and gas permit holders. Further information and
recommendations from the Commission’s investigation into seismic activity is detailed
in the Investigation of Observed Seismicity in the Montney Basin and the Investigation
of Observed Seismicity in the Horn River Basin.
Page: 117
Permit holders must carry out surface casing vent flow activities, checks and
tests, repairs where applicable and as detailed in this section and according to
Section 41 of the Drilling and Production Regulation.
Page: 118
Page: 119
Permit holders are encouraged to check for the presence of, and test, surface
casing vent flows only during non-freezing months to ensure that the buildup of
ice in the surface casing vent does not influence the results.
Page: 120
(a) from no vent flow to non-serious vent flow or serious vent flow,
(c) from non-serious vent flow or serious vent flow to no vent flow
Page: 121
All reporting of SCVF test results must be done via the Commission’s
eSubmission portal.
Measuring Flowrate
Once a positive vent flow is detected, the flow rate and stabilized shut in
pressures must be recorded. To measure venting gas volumes, a positive
displacement gas meter, turbine meter or an orifice well tester may be used.
Equipment selection should be based on previous observations indicating
what flow rate and pressure range can be expected. A positive displacement
meter will be necessary to measure low volumes accurately. An orifice well
tester, with proper orifice plate, may provide satisfactory measurements if the
24 hour shut in pressure is 200 kPa or greater and builds quickly.
Page: 122
Once the surface casing flow rate test has been completed, a buildup
pressure test must be conducted. The recommended buildup pressure test
procedure is as follows:
Install pressure recorder (or deadweight gauge) and pressure
relief valve.
Ensure that there are no leaking fittings, welds or connections.
Close the surface casing vent test assembly downstream of the
pressure recorder and pressure relief valve.
Monitor the buildup pressure as required until a stabilized
maximum pressure is reached, or the pressure relief valve opens.
If using a deadweight pressure gauge, record the buildup
pressure at appropriate intervals until a stabilized pressure is
reached or the pressure relief valve opens.
If a pen pressure recorder is being used, and the pressure does
not stabilize within 24 hours, change the chart as required to
obtain a full and complete record of the buildup pressure test.
The buildup pressure has reached a stabilized value if over the last 6 hours
of the test, the pressure changes at a rate of less than 2 kPa per hour - 12
kPa or less in a 6 hour period.
Non-Serious Repair
Remedial repair may be deferred until well abandonment for non-serious
surface casing vent flows.
Page: 123
Non-serious surface casing vent flows must be repaired at the time of well
abandonment.
If the permit holder wishes to explore the option of producing the surface
casing vent flow, an application must be made to the Drilling and Production
Department to obtain an exemption to Section 18(9)(a) of the Drilling and
Production Regulation. Requests will be considered if:
The source depth and formation of origin has been clearly identified.
The permit holder owns the mineral rights to produce the source
formation.
The cemented portion of the surface casing or the next casing string
covers the deepest known usable groundwater.
The flow has been analyzed and determined to be sweet (0 per cent
H2S).
The Commission may rescind the approval to produce from the surface
casing vent and may require the surface casing vent flow to be repaired at
any time if the Commission determines a safety or environmental hazard
exists.
“Gas migration” means a flow of gas outside of the surface casing of a well.
Page: 124
Notification is required:
if gas migration is visible as bubbles in water at the wellhead.
If gas migration is confirmed by any field testing.
Field testing at the ground surface outside the surface casing to confirm the presence
or absence of gas should be conducted if:
there is any visual, auditory, olfactory, or other evidence of possible gas
migration, or
issues with well drilling and completion, or with well condition, indicate the
potential for gas migration.
Page: 125
a copy of the GWRA output report shall be included with the Risk
Assessment Report. Additional land use information may be compiled
using iMapBC, Google Earth, and/or review of aerial photographs or
imagery where available.
Documentation of a “windshield” field reconnaissance, conducted where
practicable, to verify the desktop information related to land occupancy/use
and the locations of water supply wells.
Supporting maps as appropriate.
Assessment of Risk and Proposed Mitigation and Management Measures,
including:
Tabulated risks using the BC OGC Risk Assessment Framework for
Wellsites with Gas Migration (see Table 9F), which includes identification of
hazards and assessment of potential safety, health, and environmental risks
based on the compiled well, desktop, and field investigation information.
A fillable form version of Table 9F can be found on the Commission’s
website.
Proposed mitigation and management measures for identified risks. These
must include, where appropriate, gas migration repair measures, site
restoration measures, well abandonment plan, groundwater and/or soil
quality assessment (installation of monitoring wells), long term monitoring
of gas flow and extent of gas migration, air quality monitoring,
enhancements to site security (e.g., fencing), any or other appropriate
measures.
Page: 127
Table 9F: BC OGC Risk Assessment Framework for Wellsites with Gas Migration
1Risk rating must be supported by information documented in or appended to the Risk Assessment Report.
Risk rating may be updated following implementation of management, monitoring, mitigation, or further investigation.
Well Authorization Number: _____________ Risk Assessment Report Date: _______________
1Risk
Risk Potential Hazard Risk Rating Guidance Rating and
Category Description and Risk Low Moderate High Proposed Management, Monitoring,
Rationale Mitigation or Further Investigation
General Identify potential public safety No potential hazards One or more potential One or more
Public Safety hazards within the lease area identified site hazards identified potential site
(site), including general hazards AND low potential for hazards identified
associated with infrastructure public access to site AND reasonable
and potential confined space potential for public
hazards, with consideration of access to site
the potential for unintentional or
intentional public access.
Fire or Identify potential hazards based Gas Concentrations < Gas Concentrations > Gas Concentrations
Explosion on shallow gas survey results 100% LEL 100% LEL > 100% LEL
with consideration of potential OR AND low potential for AND potential for
ignition sources. >100% LEL and access is ignition source ignition source
restricted
Air Quality Identify potential concerns No odour observed AND Odour is apparent Gas contains H2S
related to air quality due to gas does not contain H2S AND members of the OR
odour and H2S based on field public are highly odour is apparent
observations or gas analysis, unlikely to be within and potential exists
with consideration of potential 100 m of the site for members of the
human receptors. public to be within
100 m of the site
Groundwate Identify potential hazards to Gas is not thermogenic Gas is thermogenic Gas is thermogenic
r groundwater quality based gas AND gas migration does OR gas is not AND water wells,
analysis and the shallow gas not extend off site thermogenic and water intakes, or
survey results, with shallow gas extends licensed springs are
consideration of the potential for off site within 600 m of the
groundwater to reach potential well
human receptors.
Surface Identify potential hazards based Gas is not thermogenic Gas is thermogenic Gas migration flow
Water and on the gas analysis with OR gas is thermogenic AND there is potential rates could result in
Riparian consideration of the potential for with low potential for for groundwater the accumulation of
Areas groundwater discharge to groundwater discharge to discharge to a riparian gas at surface water
surface water bodies/riparian a riparian area or surface area or surface water bodies or riparian
areas. water body body areas on or off site
A fillable version of Table 9-F is available on the Commission’s website.
Page: 128
Page: 129
Withdraw soil gas sample. The volume, rate, etc., will depend on the
instrumentation being used. Ensure that a sufficient sample is removed to
purge lines and instrumentation.
Purge instrument and lines prior to taking next measurement.
Document preparation, procedures and results.
A permit holder must notify the Commission of any casing leak or casing failure
as soon as possible. The leak or failure must be repaired within a reasonable time
frame, giving consideration to the accessibility of the site and the seriousness of
the leak or failure.
9.7.8 Noise
A permit holder must ensure operations at a well or facility for which the
permit holder is responsible does not cause excessive noise.
Review Section 40 of the DPR and the Commission’s British Columbia Noise Control
Best Practices Guideline for an understanding of noise levels, requirements and
suggested best practice standards. In addition, work with area residents to minimize
noise impacts when undertaking construction, drilling, completions, and operations
activities near populated areas.
Page: 130
The Completion / Workover / Abandonment Report is due within 30 days of the end of
main operations. Refer to the Notice of Operation and Completion Report Reference
Guide for a list of activities that require submission of a completion / Workover report.
For more information on operations not listed in the Notice of Operation and Completion
Report Reference Guide, contact Drilling and Production by email at
[email protected] or phone 250-794-5258.
Required Information/Attachments to
Completion/Workover Report
Page: 131
Page: 132
Results of work done and the outcome of the operation (such as,
successful completion of the Montney; well on production; productivity
increased; water flow successfully shut-off; well successfully suspended)
For the above example, the result would be, “Bluesky tested and
suspended with BP”.
Page: 133