12/11/2018 Detail Information
Pakistan RF EHS Exam
Exam Detail Report
True or False Single Choice Multiple Choice Subtotal
Question Count 20 15 10 45
Score 40 30 30 100
Score 36 20 30 86
Personal Information
Account uniportal_hamza_muhammad
Full Name Muhammad Hamza
Department Temp
Job Temp
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 1/7
12/11/2018 Detail Information
True or False
1. Hazards identification in advance is a must even you are certified on EHS
True
False
My Answer: True
2. It can be allowed to access Rooftops during bad weather, Roof is “WET”,Exists Thunder or Lightening
True
False
My Answer: False
3. Drivers shall excise to be skilled enough to use a hand held phone when driving on the way
True
False
My Answer: False
4. In First Aid Kit Mandatory Items are 10.
True
False
My Answer: False
5. No need to fasten safety belt when sitting in the backseat
True
False
My Answer: False
6. You can perform working at height after sunset if its still enough light
True
False
My Answer: False
7. You can rub snow on frostbitten skin to treat it.
True
False
My Answer: False
8. It is still okay to use a hard hat with a minor crack in its shell.
True
False
My Answer: False
9. If you drive or operate machinery, work at heights, no need to tell your supervisor if you take medication that makes you dr
owsy or impairs you ability. Just to have a rest and restart your work when you feel better
True
False
My Answer: False
10. Step bolts that are bent at an angle greater than 15 degrees below horizontal should be removed and replaced.
True
False
My Answer: True
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 2/7
12/11/2018 Detail Information
11. Individual person is responsible for their own safety, no need to take care that of others
True
False
My Answer: False
12. Even when there are no signs of a fire, you should respond to every fire alarm as if it were real.
True
False
My Answer: True
13. An Emergency Action Plan (EAP) is designed to aid firefighters and other rescue personnel in case of emergencies
True
False
My Answer: True
14. Only qualified first aiders are allowed to use first aid to rescue casualties. This is to prevent further complication to the inju
red
True
False
My Answer: True
15. If fire fighting system is not available no site, we can still carry out our activities
True
False
My Answer: False
16. A portable fire extinguisher should only be used by trained employees.
True
False
My Answer: True
17. Activity can be registered in ISDP later, First priority is to complete customer task
True
False
My Answer: False
18. Purpose of deploying project EHS management is to ensure work safely, successful delivery of project and improve cust
omer satisfaction.
True
False
My Answer: True
19. The ladder used for safety work shall be without width limitation for overall ladder.
True
False
My Answer: False
20. If driver drives the car very slowly, no need to fasten the seatbelt
True
False
My Answer: False
Single Choice
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 3/7
12/11/2018 Detail Information
21. What type of protection is needed when you are exposed to hazards from flying particles?
A.Eye protection
B.Face protection
C.Head protection
D.Both a and b
My Answer: A
22. Who is responsible for training employees who perform work while on a scaffold?
A.The Competent Person
B.The Qualified Person
C.Either a or b
D.None of the above
My Answer: B
23. All PPE must be fit for ( ) and inspections carried out as per the manufacturer’s instructions and compliant with the loc
al applicable standards, if these are not known then European EN standards should be used
A.Purpose and maintenance
B.checking
C.working comfortably
D.None of above
My Answer: C
24. Vehicle speed limit in city is ( )
A.80
B.50
C.60
D.70
My Answer: C
25. A company should have at least ______ exit routes for proper evacuation during an emergency.
A.1
B.2
C.4
D.Not required
My Answer: B
26. Who is responsible for training employees on erecting, repairing, dismantling, and inspecting scaffolding equipment?
A.The Competent Person
B.The Qualified Person
C.The Authorized Employee
D.None of the above
My Answer: B
27. Which of the following is the most common symptom of a heart attack?
A.Nausea
B.Shortness of breath
C.Chest Pain
D.Cough
My Answer: C
28. Which lifeline allows the worker to move up and down the entire height of the line rather than having to disconnect and fin
d a new tie-off point on the tower or ladder he or she is climbing?
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 4/7
12/11/2018 Detail Information
A.Horizontal Lifeline
B.Vertical Lifeline
My Answer: B
29. For working at height need Ended Lanyard
A.One
B.Two
C.Zero
D.More Than Two
My Answer: B
30. For every 10 miles per hour speed on the highway, increase the flowing distance by
A.One car length
B.One-quarter mile
C.One block
D.Forty feet
My Answer: A
31. Who is primarily responsible for providing employees with a fall protection system?
A.The manufacturer of the fall protection system
B.The employer
C.The employee
D.The insurer
My Answer: B
32. Which of the following should you do if you are unable to evacuate a burning building?
A.Open the doors and windows to let the smoke out
B.Break windows
C.Breathe through your mouth
D.Stay low under the smoke
My Answer: A
33. CPR involves..
A.Chest compressions & rescue breaths
B.Rescue breaths & abdominal thrusts
C.Chest compression & abdominal thrusts
D.Abdominal thrusts & finger sweeps
My Answer: A
34. ( ) are needed for Special work(like working at height, manual soldering, etc)
A.Qualified by defined technical training, and get related certificate
B.Only get safety training is enough
C.If worker has enough experience, no need to take certificate
D.all of above are wrong
My Answer: A
35. When using a ladder to climb a roof, the ladder must extend at least___ above it.
A.18 inches
B.24 inches
C.30 inches
D.36 inches
My Answer: D
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 5/7
12/11/2018 Detail Information
Multiple Choice
36. Fitness to drive can be affected by a number of issues
A.illness
B.drug use
C.alcohol consumption
D.ages
My Answer: A,B,C,D
37. Safety area of engineering construction must have
A.alert signs and fence facilities
B.workers working in unsafe area need related protection (for instance, halmet, gloves, velt, eye protection glasses, and safety shoes, etc) and
take all necessary safety facilities and tools
C.dangerious operation much be equiped with emergency response and safe protection approaches for worker safety
D.None of above
My Answer: A,B,C
38. Before work, need to analyze the risk source and take necessary actions for prevention with PPE
A.for getting an electric shock
B.for dropping from height
C.hitting by dropping product
D.tranfic accidents
My Answer: A,B,C,D
39. Field working
A.need to prepare enough food as it is not convenient for good outside
B.normall need 2 or above workers to go to avoid being robbed or wild animal hurt, take protection facility when it is needed, not allow to work so
late
C.need to wear anti-skidding shoes and clothes fit to body
D.None of above
My Answer: A,B,C
40. All work at height requires planning. A risk assessment must be carried out to identify
A.The significant rated hazards
B.The medium rated hazards
C.The low rated hazards
D.No hazards
My Answer: A,B,C
41. RF safety need be minded following
A.All RF related working need competent and certified person
B.ensure to understand the safety area of antenna before approaching to antenna
C.Need to shut down power if must working in unsafe area of RF
D.Must not to remove RF cable and connectors when they are running in order to avoiding RF burt
My Answer: A,B,C,D
42. All work at height requires planning. A risk assessment must be carried out to identify ( )
A.The significant rated hazards
B.The medium rated hazards
C.The low rated hazards
D.No hazards
My Answer: A,B,C
http://en.huaweils.com/mgmt/Report/PreviewTestByPaper?displayscript=show&displayvalue=block&printLanguage=en-US&erId=1853546466777240… 6/7
12/11/2018 Detail Information
43. Working at tower safely
A.Not allow one rigger to work on tower, a watchman must standby
B.Must check PPE and wear PPE per requirements
C.ensure lanyard fixed at 2 different points
D.Carried tools shall be kept in back to avoid being dropped down
E.Now allow to climb tower in thunder and heavy wind
My Answer: A,B,C,D,E
44. The project EHS management requirement are from ( )
A.Local EHS-related laws and regulations, international standards
B.EHS-related clauses in the contract with the customer, customer‘s requirements and expectations for EHS management
C.Huawei minimum safety standards and EHS management absolute rules
D.None of above
My Answer: A,B,C
45. Safety Signs should include but not limited to the following;
A.No access to unauthorized persons
B.Safety Helmets must be worn
C.Working at height
D.None of above
My Answer: A,B,C