Sub:-I & CAD Dept, Finalization of issues related to GST and Works Contract
-Implementation of Goods and Services Tax (GST) for ongoing and
future Works Contractsw.e.f 01-07-2017- Guidelines on implementation of
Goods and Services Tax (GST) for regulating work bills for all Engineering
Departments - GO Ms No 67 I&CAD (Reforms) dept dated 04.07.2018
Quantification of Embedded Tax rates for the previous SoRs prior to 2017-18
Directed by the Government - Board of Chief Engineers meeting held on
23.03.2019- Minutes of BOCEs meeting held on 23.03.2019 -Embedded tax
rates of previous SoRsi.e,2008-09, 2014-15 to 2016-17on
implementation of GST for ongoing works as on 01.07.2017- Approval -
Communicated -Regarding.
&&&
Further, as per the plea of BAI, Telangana before the Board of Chief
Engineers meeting on 23.03.2019, the embedded tax rates of common materials like
Bricks, Fine & Coarse aggregate was also examined and discussed by the BOCEs.
Further, BOCEs also examined the embedded tax rates of common materials
like Fine & Coarse aggregate and Bricks etc., in pre-GST regime and after detailed
deliberations of BOCEs. It was recommended for exemption of bricks (except factory
made aerated bricks like Aerocon etc.,) and Coarse aggregate (crusher by product)
from the purview of embedded taxes and to retain the same rates in post-GST
regime as that of pre-GST regime for all the ongoing works as on 01.07.2017. This is
because most of the dealers/suppliers come under exempted category.”
1 2 3 4 5 6
(A) STONE AND ROAD MATERIALS
ROUGH STONE QUARRIED INCLUDING WEDGING,
BREAKING,BURNING, SPLITING AND STACKING
1 22.a For R.R Masonary Work (other than Granite, Dolomite and Trap 1 cum 133
4
2 b.I For SS Revetment work 225 mm 1 cum 71 4
3 b.ii For SS Revetment work 300 mm 1 cum 95 4
4 b.iii For SS Revetment work450 mm 1 cum 114 4
5 c Jeddy Stone above 450 mm to 600 mm 1 cum 156 4
6 d I. Laterite for revetment 225 mm 1 cum 98 4
7 d II. Laterite for revetment 300 mm 1 cum 114 4
8 d.iii Granite for SS revetment 225 mm 1 cum 117 4
9 d.iv Granite for SS revetment 300 mm 1 cum 136 4
Note:- Only when other than granite is not available
10 e Laterite for masonry 1 cum 114 4
11 f Cyclopean stones above 0.2 cum 1 cum 210 4
12 g For R.R.Masonry works ( granite, dolamite and trap variety 1 cum 155 4
NOTE:- For items 22(a) to 22© ,22d.iii,22d.iv 22(f) and 22(g) add 1 cum 67
extra Rs /cum, wherever quarrying is done by blasting
COURSED RUBBLE STONE QUARRYING WEDGING, BREAKING,
BURNING AND SPLITTING INCLUDING STACKING FOR SS
FIRST SORT WORKS
1 2 3 4 5 6
HARD BROKEN STONE OF GRANITE TRAP DOLERITE AND
DOLAMITE FREE FROM DUST OBTAINED BY QUARRYING
WEDGING, BREAKING, BURNING AND SPLITTING INCLUDING
STACKING (QUARTZITE AND BASALT WITH AGGREGATE
IMPACT OF LESS THAN 20)
70 z4 Soling stone of 150 mm size other than granite variety 1 Cum 57.5 4
71 z5 Soling Stone laterite, Kankar 150mm, surface stone 1 Cum 35 4
72 z6 Field picked metal unbroken 20 mm size 1 Cum 47.5 4
73 z7 - do - 25 mm size 1 Cum 37.5 0
74 z8 - do - 40 mm size 1 Cum 42 0
75 z9 - do - 50 mm size 1 Cum 37.5 4
76 z10 - do - 60 mm size 1 Cum 31 4
77 z11 - do - 80 mm size 1 Cum 22.5 4
NOTE:- Add Rs. /- Per Cum for selection of stone and boulders from 15.00
excavated spoil dumps for items 33 (Q) TO 33 Z , when this addition of Rs. 9.00
78 34 Gravel including stacking 1 Cum 56 -
79 35 a Quarry rubbish 1 Cum 25 4
b HBG Stone Chips 2.36mm and below 1 Cum 225 4
80 36.a Sand for mortar, ceiling coat including washing screening etc., 1 Cum 175 4
81 Sand for concrete
Sl. S.S. Description Unit Total
No Item SS Rate for embedded
No. 2008-09 Tax Rate (%)
1 2 3 4 5 6
82 b Sand for filling and blindage 1 Cum 60 4
83 37 Clay for puddle and masonry Items 38 (a) to 39 (h) As per local prevailing
1 rates
Cum based 28 on competitive quotations.
(C) LIME AND CEMENT
40 to As per local
41(c ) prevailing
84 42 Cement excluding cost of empty cement bags Metric The price of cement
will be reviewed
Tonne and fixed on
monthly basis as
per G.O.Ms.No.94
T,R&B Dept Dt16-4-
2008 and rates will
be communicated
separately.
NOTE:
(1) The rate is material at site ( No conveyance charges to be allowed) 2)As per
85 42.a
Labour for mixing cement mortar 1 Cum 28 0
86 b Mixing of cement mortar by machine 1 Cum 45 0
87 c Grinding lime mortar or Surkhi mortar 1 Cum 78 4
88 d Shell lime slaked and screened 1 Cum 780 4
(D) MORTARS
89 43 to Items 43 to 45 Rates have
45 to be worked
(E) METAL AND IRON WORKS out based on
(A) CLEARING SITE
90 1.a Clearing heavy Jungle 1 Sqm 2.2 0
91 b Clearing light Jungle 1 Sqm 2 0
92 c Clearing Scrub Jungle 1 Sqm 2 0
93 d Clearing Juliflora (Prosafis) jungle including up-rooting and removing of 1 Sqm 3.3
0
Juliflora stumps.
94 2.a.I Cutting and removing Palmyrah trees including stacking of girth 30 to Each 27
0
100 cm.
95 ii - do - 100 to 200 cm. Each 42.5 0
96 2.b.I Uprooting and removing Palmyrah stumps including stacking of girth Each 30
0
30 to 100 cm.
97 ii - do - 100 to 200 cm. Each 46 0
98 2.c.I Cutting and removing date trees including stacking of girth 30 to 100 Each 18
0
cm
99 ii - do - 100 to 200 cm Each 28 0
100 d.I Uprooting and removing stumps of date trees including stacking of Each 18
0
girth 30 to 100 cm.
101 ii - do - 100 to 200 cm Each 24 0
102 eI Cutting and removing other kind of trees including stacking of girth 30 Each 24
0
to 100 cm
103 ii - do - 100 to 200 cm Each 38 0
104 iii - do - above 200 cm Each 62 0
105 f.I Uprooting and removing stumps of other kind of trees including Each 18
0
stacking of girth 30 to 100 cm.
106 ii - do - 100 to 200 cm Each 26 0
107 iii - do - above 200 cm Each 35.5 0
108 3.a Uprooting and clearing prickly pear jungle 1 Sq.m 1.9
0
109 b - do - under 2.5 meters height including burning and burying as 1 Sq.m 2.4
0
directed.
110 c - do - over 2.5 meters height including burning and burying with an 1 Sq.m 2.9
0
initial lead of conveyance
111 4.a Removing of natchu, goobi, thooti etc., from drains, channels including 1 Sq.m 1.5
clearance if not more than 1 metre depth of water with an initial lead
0
of 10 metres and lift of 2 metres.
1 2 3 4 5 6
(C) QUARRYING AND BLASTING
119 6 Blasting and removing hard granite measured in solid 1 cum covered
under earth
7 Drilling holes in hard granite or sheet rock
a) Manually ( Hand)
120 I) 20 mm dia meter 1 RM 88 0
121 ii) 25 mm dia meter 1 RM 95.5 0
122 iii) 36 mm dia meter 1 RM 109 0
b) Pneumatic Compressor
123 I) 20 mm dia meter 1 RM 100 0
124 ii) 25 mm dia meter 1 RM 110 0
125 iii) 36 mm dia meter 1 RM 121 0
8 Grouting the holes with neat cement slurry excluding cost of
steel
126 I) 20 mm dia meter 1 RM 64.5 0
127 ii) 25 mm dia meter 1 RM 81 0
128 iii) 36 mm dia meter 1 RM 99.5 0
EARTH WORK EXCAVATION AND DEPOSITING ON BANK WITH
AN INITIAL LEAD OF 10 METRES AND AN INITIAL LIFT OF 2
METRES IN CASE OF HEAD LEAD ONLY.
Sand or loose soils wet sand not under water, silt in canals, channels
129 8.a 1 cum 27 0
and drains SS 20-A.
130 b - do - 20-B 1 cum 25 0
Loamy and Clayey soils like black cotton soils, red earth and ordinary
131 9.a 1 cum 41 0
gravel SS 20-A.
132 b - do - 20-B 1 cum 37.5 0
133 10.b Slushy soil and silt clearance up to 0.60 metres depth SS 20-B 1 cum 41 0
134 11.b Clayey Soil in wet and slushy condition SS 20-B 1 cum 43 0
139 14 Soft disintegrated rock ( removable by pick axes and crow bars) 1 cum 49 0
1 2 3 4 5 6
153 ii -do- from 4 th extra lead to 6 th extra lead 1 cum 2.7 0
Add to relevant SS 20-A rates for new tank bunds, closing breaches,
b(I) road formation and embankments for extra watering and consolidation 1 cum 5 0
by pneumatic tampers at 90% proctor's density.
Add to relevant SS 20-A rates for new tank bunds, closing breaches,
road formation and embankments for extra watering and consolidation
171 c 1 cum 28 0
of proctor's density with 8 to 10 tonne power roller including watering
and conveyance of water for initial lead of 1/2 Kilometer.
1 2 3 4 5 6
Turfing slopes including watering for 3 months with initial lead for
175 24 1 Sq.m 19 0
conveyance of water and grass for 1 hectometer.
Refilling with the excavated sand complying with the standard
176 25 1 cum 14 0
specifications for filling foundations
Refilling with the excavated soils ( other than sand) complying with
177 26.a 1 cum 14 0
the standard specifications for filling foundations.
50% of
earth work
Trimming of slopes of embankments and depositing the soils on the
178 b 1 cum excavation
top of the bank.
of similar
classification
3.Add where the power is available for operating the mixer, the rate is, 1 cum 27.5 0
White washing and colour banding for guard and guide stones
181 aI each 5.8 0
including cost of materials
182 bI Screening sand and gravel 1 cum 5.7 0
183 b2 Screening chips and metal 1 cum 11.8 0
184 c1 Removing and refixing Hectometer or Demarcation stones each 8.6 0
CENTERING CHARGES
Centering charges for culvert slabs and other structures of 3 mts.
185 L1 1 cum 950 0
span and above
Centering charges for bed blocks and culvert slabs and other
186 L2 1 cum 760 0
structures of less than 3 mts. span.
CENTERING CHARGES FOR MINOR AND MAJOR BRIDGE
WORKS
For mass concrete piers, abutments and steining well curbs, well caps
187 L3 1 cum 700 0
etc.,
For RCC piers, abutments, wing wall, steining, well curbs, well caps
188 L4 1 cum 850 0
etc.,
NOTE:- The rates under L3 and L 4 are applicable to Roads and
189
Buildings and Irrigation structures up to 2 metres width
190 L5 For RCC deck slabs 1 cum 1550 0
191 L6 For RCC beams 1 cum 2000 0
192 L7 For RCC hand rails 1 cum 2200 0
For CC pavements, wearing coats, approach, slabs, guide stone, J. M.
193 L8 1 cum 160 0
stone etc.,
Laying and fixing RCC Hume pipes in position including lifting,
aligning etc., complete with (fixing ) collars for the following
n
diametres of pipes but excluding cost of materials ( NP2 Class
)
194 n 1 250 mm diameter 1 Rm 17 0
195 n 2 300 mm diameter 1 Rm 23.5 0
196 n 3 450 mm diameter 1 Rm 30 0
197 n 4 600 mm diameter 1 Rm 49 0
198 n 5 750 mm diameter 1 Rm 60 0
199 n 6 800 mm diameter 1 Rm 73 0
200 n 7 1000 mm diameter 1 Rm 82 0
201 n 8 1220 mm diameter 1 Rm 100 0
Note:- For NP3 class 50% extra over the rates of NP2. Class may be
allowed.
(S ) ROAD WORK ITEMS
Sl. S.S. Description Unit Total
No Item SS Rate for embedded
No. 2008-09 Tax Rate (%)
1 2 3 4 5 6
PICKING OLD METALLED SURFACE TO DEPTH OF 40 TO 100
mm SPREADING OLD METAL AND NEW METAL SECTIONING
INCLUDING EDGEBUNDS AND SUBGRADE ROLLING,
SPREADING METAL INCLUDING BLINDAGE OFGRAVEL
WATERING WITH AN INITIAL LEAD OF 2 HECTOMETERS AND
HAND ROLLER ( 1.5 TO 2 TONNES) ROLLING ETC., INCLUDING
BARRICADING,DIVERSION OF TRAFFIC AND WETTING THE
NEW CONSOLIDATION FOR A FORTNIGHT COMPLETE.
210 3 Picking gravelled surface 25 mm deep and levelling and sectioning 10 sqm 6 0
211 4 Picking the existing B.T. surface and removal of chips 10 sqm 22 0
5 Picking old metalled surface to a depth of 40 to 100 mm and
spreading metal including watering with an initial lead of 2
Hectometers and rolling with power rollers watering and
spreading gravel for blindage and power roller rolling
including hire charges of power roller rolling including hire
charges of power roller ( 8 to 10 T) barricading and diversion
of traffic and wetting the new consolidation for a fortnight (
for compacted thickness of )
HARD METAL
212 5 (a) 40 mm thickness 10 sqm 137
0
213 (b) 50 mm thickness 10 sqm 155
0
214 (c ) 75 mm thickness 10 sqm 170
0
215 (d ) 100 mm thickness 10 sqm 185
0
216 (e) 150 mm thick excluding hire charges 10 sqm 330
0
Spreading gravel watering with an initial lead of 2
hectometers and power roller ( 8 to 10 T ) rolling excluding
hire charges of power roller and barricading etc., ( for a
compact thickness of )
217 6a 50 mm thickness 10 sqm 25 0
1 2 3 4 5 6
226 9a -do- 6mm to 20 mm thick 1 cum 38 0
1 2 3 4
(A) STONE AND ROAD MATERIALS
ROUGH STONE QUARRIED INCLUDING WEDGING,
BREAKING,BURNING, SPLITING AND STACKING
1 22.a For R.R Masonary Work (other than Granite, Dolomite and Trap 1 cum 160 5
2 b.I For SS Revetment work 225 mm 1 cum 160 5
3 b.ii For SS Revetment work 300 mm 1 cum 164 5
4 b.iii For SS Revetment work450 mm 1 cum 136 5
5 c Jeddy Stone above 450 mm to 600 mm 1 cum 188 5
6 d I. Laterite for revetment 225 mm 1 cum 118 5
7 d II. Laterite for revetment 300 mm 1 cum 138 5
8 d.iii Granite for SS revetment 225 mm 1 cum 154 5
9 d.iv Granite for SS revetment 300 mm 1 cum 156 5
Note:- Only when other than granite is not available
10 e Laterite for masonry 1 cum 136 5
11 f Cyclopean stones above 0.2 cum 1 cum 254 5
12 g For R.R.Masonry works ( granite, dolamite and trap variety 1 cum 252 5
13 NOTE:- For items 22(a) to 22© ,22d.iii,22d.iv 22(f) and 22(g) add extra Rs 1 cum
/cum, wherever quarrying is done by blasting 70
38 (3) Deduct Rs. /- per cum if the metal or rubble is obtained from surface
9.9
stone and boulders.
39 (4) Add Rs. /- per cum for selection of stones and boulders from excavated
spoil dumps for items 33 a to 33 k, when this addition of Rs. /- per Cum is
allowed deduction of Rs. /- per Cum mentioned under Note (3) above 17
should invariably be made.
HARD METAL
152 5 (a) 40 mm thickness 10 sqm
185 0
153 (b) 50 mm thickness 10 sqm
210 0
154 (c ) 75 mm thickness 10 sqm
231 0
155 (d ) 100 mm thickness 10 sqm
248.8 0
156 (e) 150 mm thick excluding hire charges 10 sqm
445.4 0
Structural steel/ Reinforcement steel (HYSD/TMT) Note:- As per monthly
157 16 1 tonne 18.12
rate fixed by the sub committee
Cement 43Gr/ 53 Gr Note:- As per monthly rate fixed by the sub
158 17 1 tonne 28.81
committee
Excise duty and
vat as provided
159 18 Bitumen 1 tonne in the sanctioned
estimate
SSR - 2016-17
Statement showing the Schedule of Rates with Revised embedded tax rates
for the material rates items of SoR 2016-17
Sl. S.S. Description Unit TS SSR Total
No Item 2016-17 embedded
No. Tax Rate (%)
1 2 3 4
(A) STONE AND ROAD MATERIALS
ROUGH STONE QUARRIED INCLUDING WEDGING,
BREAKING,BURNING, SPLITING AND STACKING
1 22.a For R.R Masonary Work (other than Granite, Dolomite and Trap 1 cum 160 5
2 b.I For SS Revetment work 225 mm 1 cum 160 5
3 b.ii For SS Revetment work 300 mm 1 cum 164 5
4 b.iii For SS Revetment work450 mm 1 cum 136 5
5 c Jeddy Stone above 450 mm to 600 mm 1 cum 188 5
6 d I. Laterite for revetment 225 mm 1 cum 118 5
7 d II. Laterite for revetment 300 mm 1 cum 138 5
8 d.iii Granite for SS revetment 225 mm 1 cum 154 5
9 d.iv Granite for SS revetment 300 mm 1 cum 156 5
Note:- Only when other than granite is not available
10 e Laterite for masonry 1 cum 136 5
11 f Cyclopean stones above 0.2 cum 1 cum 254 5
12 g For R.R.Masonry works ( granite, dolamite and trap variety 1 cum 252 5
13 NOTE:- For items 22(a) to 22© ,22d.iii,22d.iv 22(f) and 22(g) add extra Rs 1 cum
/cum, wherever quarrying is done by blasting 70
(3) Deduct Rs. /- per cum if the metal or rubble is obtained from surface stone
9.9
and boulders.
(4) Add Rs. /- per cum for selection of stones and boulders from excavated spoil
dumps for items 33 a to 33 k, when this addition of Rs. /- per Cum is allowed
17
deduction of Rs. /- per Cum mentioned under Note (3) above should
invariably be made.
SOFT BROKEN STONE SCREENED AND FREE FROM DUST INCLUDING
STACKING
38 33.l - do - 40 mm size ( IS383,1970 ) 1 Cum 123 0
39 33.m - do - 50 mm size ( IS383,1970 ) 1 Cum 111 5
40 33.n - do - 60 mm size ( IS383,1970 ) 1 Cum 87 5
41 33.o - do - 65 mm size ( IS383,1970 ) 1 Cum 78 5
42 33.p - do - 75 mm size ( IS383,1970 ) 1 Cum 73 5
HARD BROKEN STONE OF GRANITE TRAP DOLERITE AND DOLAMITE
FREE FROM DUST OBTAINED BY QUARRYING WEDGING, BREAKING,
BURNING AND SPLITTING INCLUDING STACKING (QUARTZITE AND
BASALT WITH AGGREGATE IMPACT OF LESS THAN 20)
HARD METAL
145 5 (a) 40 mm thickness 10 sqm 185 0
146 (b) 50 mm thickness 10 sqm 210 0
147 (c ) 75 mm thickness 10 sqm 231 0
148 (d ) 100 mm thickness 10 sqm 248.8 0
149 (e) 150 mm thick excluding hire charges 10 sqm 445.4 0
Structural steel/ Reinforcement steel (HYSD/TMT) Note:- As per monthly rate
150 16 1 tonne 18.12
fixed by the sub committee
151 17 Cement 43Gr/ 53 Gr Note:- As per monthly rate fixed by the sub committee 1 tonne 28.81
Initial cost less Embedded (1+(Tax Basic Rate Embedded tax (col
Sl.No Description of Metal Lead in Kms
stacking Tax Rate% Rate/100)) (Col 4/Col6) 4- Col 7)
1 2 3 4 5 6 7 9
A) FOR ROAD WORKS
60 to 63 mm IRC and MoRTH
1 HBG metal
10 419.00 5.00 1.05 399.05 19.95
50 to 55 mm IRC and MoRTH
2 HBG metal
10 456.00 5.00 1.05 434.29 21.71
Name of Work:-
Ref ::- For Emulsion (Bulk) :- HINCOL Price List With Effect From Dated:- 16.05.2017
For Bulk Bitumen VG-10, VG-30 :- HPCL Price List With Effect From
Lead from
0.00
610 0 0 0 0 0
Lead charges for Bulk
0.00 per KM
@
Rates of Bitumen / Emulsion including taxes 28926 28868 24600 24496 39007
Embedded tax amount - (a) + (b) = 4049.81 4041.67 3444.20 3429.54 5461.29
DATAS
89.10 cum 2.36mm to 75 micron @ 30% (2.36mm & below) 17.14 cum
1527.43
Total 1889.49
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 1889.49
(F) Add Contractors Profit at 10% on (E) 0% 0.00
Cost per 225 cum (E) + (F) 1889.49
Rate per 1 cum 8.40
Cum
3 Providing and applying tack coat with bitumenemulsion (Rapid settting) (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with
mechanical broom for finished item of work as per MoRT&H Specification 503 (5th revision) and as
directed by the Engineer-in-Charge.
unit = sqm Page 124 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos Mate day 0.00
2.00 nos Mazdoor day 0.00
Total 0.00
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250 sqm/hr. hr 0.00
2.80 hr Air compressor 250 cfm hr 0.00
2.00 hr Emulsion pressure distributor @1750 sqm/hr hr 0.00
Total 0.00
(C) Material
0.70 MT Bitumen emulsion @ 0.20 Kgs/sqm 3,444.20 MT 2410.94
Total 2410.94
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 2410.94
(F) Add Contractors Profit at 10% on (E) 0% 0.00
Cost per 3500 sqm (E) + (F) 2410.94
Rate per 1 sqm 0.69
1 Sqm
Page 2
Quantity Description of Item Rate per Amount
4 Providing and applying primer coat with Bitumen Emulsion (Slow Setting-1) on the prepared surface of
granular base including clearing of road surface and sparaying primer at the rate of 0.70kg/sqm using
mechanical means for finished item of work as per MoRT&H Specification 502 (5th revision) and as
directed by the Engineer-in-Charge.
unit = sqm Page 123 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos Mate day 0.00
2.00 nos Mazdoor day 0.00
Total 0.00
(B) Machinery
2.80 hr Mechanical broom Hydraulic @ 1250 sqm/hr. hr 0.00
2.80 hr Air compressor 250 cfm hr 0.00
2.00 hr Bitumen pressure distributor @1750 sqm/hr hr 0.00
1.00 hr Water tanker 6 KL capacity @ 1 trip per hour hr 0.00
Total 0.00
(C) Material
2.45 MT Bitumen Emulsion @ 0.70 Kgs/sqm 5461.29 MT 13380.16
6.00 KL Cost of water 0 0.00
Total 13380.16
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 13380.16
(F) Add Contractors Profit at 10% on (E) 0% 0.00
Cost per 3500 sqm (E) + (F) 13380.16
Rate per 1 sqm 3.82
1 Sqm
5 Providing and Laying 40/30mm thick Bituminous concrete with 100 to 120 TPH batch type hot mix
plant using HBG crushed aggregates of Grading-2 as per table 500-17 of Specification 507 of
MoRT&H (5th revesion), premixed with Bituminious binder VG-30 Grade @ 5.4% of mix and filler,
transporting the hot mix to work site, laying with Hydro static sensor paver finisher to the required
grade, level and alignment, rolling with smooth wheeled,vibratory and tandem rollers to achieve the
desired compaction as per MoRT&H Specification 507 (5th Revision) complete for finished item of
work in all respects excluding seiniorage charges and as directed by Engineer-in-charge.(Excluding
taxes Charges)
Unit = cum Page 138 of MoRT&H SDB
Taking output = 191 cum (450 tonnes.)
(A) Labour
0.84 nos. Mate day 0.00
14.00 nos. Mazdoor working with HMP, Mechanical broom, day 0.00
5.00 nos. paver,roller,asphalt
Skilled Mazdoor for cutter andline
checking assistance for setting
and levels. day 0.00
Total 0.00
(B) Machinary
6.00 hr Batch Mix HMP @ 100 to 120TPH hr 0.00
6.00 hr Hydero static sensor Paver finisher hr 0.00
6.00 hr Generator 250 KVA hr 0.00
6.00 hr Front end loader 1 cum capacity hr 0.00
3.90 hr Power road roller 8 tonne for initial break down rolling hr 0.00
3.90 hr Pneumatic road Roller hr 0.00
3.90 hr smooth wheeled roller 8 Ton hr 0.00
Total 0.00
(C) Material
24.30 M.T (I) Bitumen VG-30 @ 5.40% by weight of mix 4041.67 MT 98212.65
=191*2.356=450 ton
(ii) Aggregate
Quantity Description of Item Rate per Amount
total wt of mix 450T-24.30=425.70T
For Grading I
56.760 cum IRC &MORT&H HBG M/C chip Avg. of (14-12),(9.5-11.2) @ 20% 0 cum 0.00
70.950 cum IRC &MORT&H HBG M/C chipsAvg. of (9.5-11.2),( 5-7) 25% 0 cum 0.00
150.410 cum IRC &MORT&H HBG M/C chips2.36 to 5mm, 2.36 & 16.190 cum 2435.21
above 53%
2.838 cum Filler @ 1% of weight of aggregates. 17.14 cum 48.65
4.257 MT Filler (Cement) @ 1% of weight of aggregates. 1163.05 MT 4951.09
285.22 Total 105647.60
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
6 Providing and laying Dense graded bituminous macadam with 100-120 TPH batch type HMP using
HBG crushed aggregates of Grading-II as per table 500-10 of MoRT&H Specification 505 (5th
revision) premixed with bituminous binder of VG-30 grade @ 4.5% of weight of total mixture,
transporting the hot mix to work site, laid over a previously prepared surface with sensor paver finisher
to the required grade, level and alignment, rolled as per Clauses 501.6 and 501.7 to achive the
desired compaction for finished item of work as directed by the Engineer-In-Charge including hire and
operational charges all T&P and all other contingent charges necessary excluding cost of seiniorage
charges of all materials etc., completes and as per MoRT&H specification No.505 (5th revision)
(Excluding VAT charges)
85.95 cum IRC &MORT&H HBG M/C chips 25 to 10mm 0.00 cum 0.00
@ 30%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 25-27mm, 19-22mm, 12-
14mm, 9.5-11.2mm
80.22 cum IRC &MORT&H HBG M/C chips 10 to 5mm 0.00 cum 0.00
@ 40%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 9.5-11.2mm, 5 to 7mm
114.60 cum IRC &MORT&H HBG M/C chips 5mm and 16.19 cum 1855.43
below @ 20%
Average rate of IRC&MoRT&H HBG M/C
metal of sizes 2.36 to 5mm and 2.36mm&
below
5.73 cum Filler @ 2% of weight of aggregates 17.14 cum 98.23
Total 83797.53
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 83797.53
(F) Add Contractors Profit at 10% on (E) 0% 0.00
Cost per 195 cum (E) + (F) 83797.53
Rate per 1 cum 429.73
1 Cum
Data's with 100% Rock Sand
Quantity Description of Item Rate per Amount
7 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and
fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for base
coarse below CC Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate day 0.00
1.00 nos Mason day 0.00
15.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Stone dust 17.14 cum 57.86
3.375 cum Stone dust 17.14 cum 57.86
2.43 MT Cement at site 1163.05 MT 2826.20
Total 2941.92
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
2.00 hr Water tanker 6 KL hr 0.00
Total 0.00
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 2941.92
(F) Add Contractors Profit at 10% on (E) 0% 0.00
13.50 40mm SS-5 HBG M/C metal 0.00
3.38 Sand 0.00
Cost per 15 cum 2941.92
Rate for 1 cum 196.13
1 Cum
8 Vibrated cement concrete M 40 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Stone dust 17.14 cum 57.86
3.375 cum Stone dust 17.14 cum 57.86
6.45 MT Cement at site 1163.05 MT 7501.65
Total 7617.37
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
Quantity Description of Item Rate per Amount
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7617.37
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7617.37
Rate for 1 cum 507.82
1 Cum
9 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Stone dust 17.14 cum 57.86
3.375 cum Stone dust 17.14 cum 57.86
6.33 MT Cement at site 1163.05 MT 7362.08
Total 7477.8
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7477.80
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7477.80
Rate for 1 cum 498.52
1 Cum
10 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(5th revision) for footings and Raft foundation .
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
Quantity Description of Item Rate per Amount
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.38 cum Manufactured rock sand 17.14 cum 57.86
3.38 cum Manufactured rock sand 17.14 cum 57.86
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4919.10
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4919.10
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G)+(H) 4919.10
Rate for 1 cum 327.94
1 Cum
11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, and conveyance of all materials to site and all labour charges for machine
mixing, laying in position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200
(5th revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.38 cum Manufactured rock sand 17.14 cum 57.86
3.38 cum Manufactured rock sand 17.14 cum 57.86
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4919.10
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4919.10
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 4919.10
Rate for 1 cum 327.94
1 Cum
Quantity Description of Item Rate per Amount
23 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG
metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness
of not less than 600mm with smaller size towards the soil and bigger size towards the wall and
provided over the entire surface behind the abutment, wing wall and return wall to the full height
compacted to a firm condition including cost and conveyance of all metal seignorage charges ,and all
labour charges as directed by the departmental officers as per drawing and Technical specifications
as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th revision) for finished item of work.
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 4.52 cum 27.14
6.00 cum Cost of 40mm size IRC HBG metal 23.81 cum 142.86
Total 170.00
© Machinery
0.06 hr Water tanker 6 KL capacity hr 0.00
Total 0.00
(D) Over head charges @
Cost per 10 cum (E)+(F) 170.00
Rate for 1 cum 17.00
1 Cum
12 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour
charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing including all
other incidental and all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (5th Revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
5.40 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
2.70 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.38 cum Manufactured rock sand 17.14 cum 57.86
3.38 cum Manufactured rock sand 17.14 cum 57.86
5.16 MT Cement at site 1163.05 MT 6001.32
Total 6117.04
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
Quantity Description of Item Rate per Amount
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 6117.04
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 6117.04
Rate for 1 cum 407.80
1 Cum
Data's with 50% sand & 50% Rock Sand
Quantity Description of Item Rate per Amount
7 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and
fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for base
coarse below CC Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate day 0.00
1.00 nos Mason day 0.00
15.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90.00
2.43 MT Cement at site 1163.05 MT 2826.20
Total 2974.06
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
2.00 hr Water tanker 6 KL hr 0.00
Total 0.00
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 2974.06
(F) Add Contractors Profit at 10% on (E) 0% 0.00
13.50 40mm SS-5 HBG M/C metal 0.00
3.38 Sand 0.00
Cost per 15 cum 2974.06
Rate for 1 cum 198.27
1 Cum
8 Vibrated cement concrete M 40 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90
6.45 MT Cement at site 1163.05 MT 7501.65
Total 7649.51
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
Quantity Description of Item Rate per Amount
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7649.51
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7649.51
Rate for 1 cum 509.97
1 Cum
9 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90
6.33 MT Cement at site 1163.05 MT 7362.08
Total 7509.94
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7509.94
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7509.94
Rate for 1 cum 500.66
1 Cum
10 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(5th revision) for footings and Raft foundation .
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
Quantity Description of Item Rate per Amount
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90.00
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4951.24
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4951.24
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G)+(H) 4951.24
Rate for 1 cum 330.08
1 Cum
11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, and conveyance of all materials to site and all labour charges for machine
mixing, laying in position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200
(5th revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90.00
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4951.24
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4951.24
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 4951.24
Rate for 1 cum 330.08
1 Cum
Quantity Description of Item Rate per Amount
23 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG
metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness
of not less than 600mm with smaller size towards the soil and bigger size towards the wall and
provided over the entire surface behind the abutment, wing wall and return wall to the full height
compacted to a firm condition including cost and conveyance of all metal seignorage charges ,and all
labour charges as directed by the departmental officers as per drawing and Technical specifications
as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th revision) for finished item of work.
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 4.52 cum 27.14
6.00 cum Cost of 40mm size IRC HBG metal 23.81 cum 142.86
Total 170.00
© Machinery
0.06 hr Water tanker 6 KL capacity hr 0.00
Total 0.00
(D) Over head charges @
Cost per 10 cum (E)+(F) 170.00
Rate for 1 cum 17.00
1 Cum
12 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour
charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing including all
other incidental and all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (5th Revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
5.40 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
2.70 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Manufactured rock sand 17.14 cum 57.86
3.375 cum Sand for concrete 26.67 cum 90.00
5.16 MT Cement at site 1163.05 MT 6001.32
Total 6149.18
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
Quantity Description of Item Rate per Amount
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 6149.18
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 6149.18
Rate for 1 cum 409.95
1 Cum
Data's with 100% Sand
Quantity Description of Item Rate per Amount
7 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and
fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for base
coarse below CC Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate day 0.00
1.00 nos Mason day 0.00
15.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Sand for concrete 26.67 cum 90.00
3.375 cum Sand for concrete 26.67 cum 90.00
2.43 MT Cement at site 1163.05 MT 2826.20
Total 3006.20
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
2.00 hr Water tanker 6 KL hr 0.00
Total 0.00
(D) Over head charges @
0% Add for Over head charges on (A)+(B)+( C) 0.00
(E) Total of (A) + (B)+( C)+(D) 3006.20
(F) Add Contractors Profit at 10% on (E) 0% 0.00
13.50 40mm SS-5 HBG M/C metal 0.00
3.38 Sand 0.00
Cost per 15 cum 3006.20
Rate for 1 cum 200.41
1 Cum
8 Vibrated cement concrete M 40 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Sand for concrete 26.67 cum 90
3.375 cum Sand for concrete 26.67 cum 90
6.45 MT Cement at site 1163.05 MT 7501.65
Total 7681.65
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
Quantity Description of Item Rate per Amount
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7681.65
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7681.65
Rate for 1 cum 512.11
1 Cum
9 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished
item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th revision) and as directed
by the Engineer-in-Charge for C.C Pavement.
Unit = cum Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0
5.40 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0
3.375 cum Sand for concrete 26.67 cum 90
3.375 cum Sand for concrete 26.67 cum 90
6.33 MT Cement at site 1163.05 MT 7362.08
Total 7542.08
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 7542.08
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 7542.08
Rate for 1 cum 502.81
1 Cum
10 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(5th revision) for footings and Raft foundation .
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
Quantity Description of Item Rate per Amount
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Sand for concrete 26.67 cum 90.00
3.375 cum Sand for concrete 26.67 cum 90.00
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4983.38
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4983.38
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G)+(H) 4983.38
Rate for 1 cum 332.23
1 Cum
11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, and conveyance of all materials to site and all labour charges for machine
mixing, laying in position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200
(5th revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
4.05 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
1.35 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Sand for concrete 26.67 cum 90.00
3.375 cum Sand for concrete 26.67 cum 90.00
4.13 MT Cement at site 1163.05 MT 4803.38
Total 4983.38
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 4983.38
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 4983.38
Rate for 1 cum 332.23
1 Cum
Quantity Description of Item Rate per Amount
23 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG
metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness
of not less than 600mm with smaller size towards the soil and bigger size towards the wall and
provided over the entire surface behind the abutment, wing wall and return wall to the full height
compacted to a firm condition including cost and conveyance of all metal seignorage charges ,and all
labour charges as directed by the departmental officers as per drawing and Technical specifications
as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th revision) for finished item of work.
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 4.52 cum 27.14
6.00 cum Cost of 40mm size IRC HBG metal 23.81 cum 142.86
Total 170.00
© Machinery
0.06 hr Water tanker 6 KL capacity hr 0.00
Total 0.00
(D) Over head charges @
Cost per 10 cum (E)+(F) 170.00
Rate for 1 cum 17.00
1 Cum
12 Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour
charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing including all
other incidental and all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (5th Revision) for Sub structure .
Unit = cum Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 nos Mate day 0.00
1.50 nos Mason day 0.00
20.00 nos Mazdoor day 0.00
Total 0.00
(B) Material
5.40 cum Cost of 40mm SS-5 HBG M/C metal 0.00 cum 0.00
5.40 cum Cost of 20mm SS-5 HBG M/C metal 0.00 cum 0.00
2.70 cum Cost of 10mm SS-5 HBG M/C metal 0.00 cum 0.00
3.375 cum Sand for concrete 26.67 cum 90.00
3.375 cum Sand for concrete 26.67 cum 90.00
5.16 MT Cement at site 1163.05 MT 6001.32
Total 6181.32
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum hr 0.00
6.00 hr Generator set 35 KVA hr 0.00
0.00
(D) Form work
4.00 % Form work @ 10% on (A)+(B)+( C) Cum 0.00
Quantity Description of Item Rate per Amount
(E) Over head charges @
0% Add for Over head charges on (A)+(B)+( C)+(D) 0.00
(F) Total of (A) + (B)+( C)+(D)+(E) 6181.32
(G) Add Contractors Profit at 10% on (F) 0% 0.00
Cost per 15 cum (F)+(G) 6181.32
Rate for 1 cum 412.09
1 Cum
MINUTES OF 1st BOARD OF CHIEF ENGINEERS MEETING FOR THE
YEAR 2019 HELD ON 23.03.2019 @ 4.00PM IN THE BOCE CONFERENCE
HALL OF ENGINEER-IN-CHIEF (AW), I & CAD DEPARTMENT, ERRUM
MANZIL, HYDERABAD.
Agenda item No – 1:
I & CAD Department – Exemption of on hand works pending for want of
statutory clearances such as Forest clearance, Wild life clearance, Environmental
clearance and also Road permissions, Railway permissions, N.H Clearances while
calculating ‘B’ value in arriving Bid capacity of Bidders in Tenders Evaluation –
Placed before the Board of Chief Engineers - For discussion and necessary
recommendations - Regarding
Proposed by Engineer-in-Chief (AW), I&CAD Dept
and Commissioner, COT, Hyd
Certain instances have come up, wherein the bidders have represented that
some of their works are getting delayed because of delay in clearance of forest land
and LA of private land and other statutory Government clearances due to which such
works are delayed abnormally. This is affecting their Bid capacity criteria which is
one of the main eligibility criteria for tender qualification & requested to exempt all
pending projects (where the delay is not on account of contractor) in calculating
1
eligibility criteria like Bid capacity (B Value) to enable all the contractors to get the
required Bid Capacity.
“ The Board of Chief Engineers has discussed the issue and opined to recommend
the Government that it is not advisable to exempt some of the on hand works as this
will become precedence for other agencies to approach the Government. or to the
Court for such exemptions. As long as the agreement is in force, all those works shall
be considered as on hand works while calculating Bid Capacity of the bidder till the
agreement (i.e. balance works concerned) are closed by the Competent Authority.
However a procedure has to be evolved for solving the issue in case of the agencies
who are having a large number of non-started or standstill works which are not due to
the account of the agencies.”
The subject issue was once again placed for discussion before COT Committee
meeting held on 01.12.2018 and the members have opine to refer the matter to BOCEs
for its detailed discussion and necessary recommendations in the matter.
2
The Board of Chief Engineers has deliberated the issue in detail and
opined that on hand works pending due to delay in Forest clearance,
Environmental clearance and Interstate issues may be considered for exemption
in calculating ‘B’ Value for arriving Bid Capacity of Bidders based on the
specific reports by the concerned ENC/CE with detailed reasons thereof. In this
regard, the Government is to be addressed for issue of necessary GO in the
matter.
Action: Engineer-in-Chief (AW), I&CAD Dept
and Commissioner, COT, Hyd
Agenda Item No 2 :
The Government further directed that, the Board of Chief Engineers (BoCEs)
shall quantify the embedded taxes in various types/component of works, within a
fortnight of issue of the above order, so as to have uniformity across the state. The
Government in the above G.O. further stated that, the 5% additional amount paid
towards GST for the intervening period based on the instructions issued by the
Government vide Memo No. 33/WP/A2/2017, Dt: 08-08-2017 has to be taken in to
account while adjusting GST payable.
Accordingly, the BoCE has worked out the embedded taxes and published on
the irrigation department website. Aggrieved by the procedure adopted for calculating
embedded taxes, the BAI has approached the Chief Secretary to government with a
request to intervene in the matter and to instruct the concerned to consider the
exemptions, which were allowed under VAT regime, while calculating the embedded
taxes for all the ongoing works.
4
a. The Committee shall discuss with the concerned departments and various
agencies executing the works and list out the issues post implementation of
GST from 1st July-2017 with reference to the works commenced under
VAT and spill over under GST.
The BAI have further informed that their association members together with
engineering department officials have made calculations duly considering the above
provisions under VAT act to ascertain embedded taxes in the 2BHK housing project
work construction of 4428 2BHK houses at Ahmedguda of Medchal Constituency
taken up by GHMC, and the embedded taxes have been arrived at 3.95 % of value of
work. Therefore the BAI has requested that they are ready to accept reimbursement of
5
GST @ 5% to avoid further exact amount of Hypothetical values and to save valuable
Government time and Engineering hours.
In this regard the CE(H&A)/GHMC has submitted that the 2BHK housing
projects were sanctioned/tendered based on SSR 2016-17 (rates including taxes) with
5% provision towards VAT on value of work with the all applicable provisions and
exemptions available under VAT regime. Therefore accordingly the agencies have
quoted their tenders duly taking into considerations all provisions and existing rules
under VAT regime.
The embedded taxes are worked out for the above project of 2BHK scheme in
considering the allowable provisions of composition scheme under VAT act like Inter
State purchase of materials (CST), purchase of materials from unregistered/TOT
dealers and no input tax credit allowable on machinery in composition scheme under
VAT era etc., is found to be 3.95 % on value of work subject to legally eligible of
claims made by BAI. On the other hand the embedded tax component adopting BOCE
communicated rates is working out to be 8.61 %.
Therefore changes in the tax structure subsequently should neither provide any
undue advantage to the contractors nor punish them. Calculation of embedded taxes
without considering the provisions available at the time of sanction/tenders which are
working to 8.61% will result in recovery of 1.61% from contractors work bills and
therefore will affect the financial position and may lead to contractual litigations, legal
complications and stoppage of works.
On the other hand, considering the existing provisions under VAT regime, the
embedded taxes are working out to be 3.95% and therefore result in additional
financial burden of 3.05% on the Government due to release of GST @ 8.05% to the
agencies.
6
GST as final settlement for the works contracts of Building works, may be considered
for ongoing housing works of GHMC taken up with SSR prior to 2017-18 (i.e., rates
including taxes). The above proposals have been also submitted to Commissioner of
State Taxes for finalization of GST for the works contracts of Building works.
The Board of Chief Engineers has discussed the issue in detail and opined
that allowing of 5% or any other fixed percentage as Embedded Tax component
as final settlement for the ongoing Works Contracts of Building works is adhoc
and not justifiable as the same will vary from work to work depending on nature
& item of works in the Contract and advised to work out the same as per
embedded tax rates finalized by the concerned Depts., accordingly. This will be
one time exercise for each Agreement by the sanctioning authority and works can
be carried out and finalized accordingly. Otherwise there would be possibility of
Audit objections for the same as causing financial loss to Government and undue
benefit to the agencies.
Action: Chief Engineer (H&A) GHMC, Hyd
Agenda Item No 3 :
7
The Engineer-in-Chief (SR & CRN), R&B Dept., vide letter dated 18.03.2019 has
furnished the following as submitted by the BAI, Telangana vide their letter dated
28.02.2019 in the subject matter.
1) No input is allowed for the machinery in the VAT era in Composition Scheme.
The element of "Hire Charges of the machinery" was arrived at by dividing the
Capital Cost of the Machinery by the life-time working period of the machinery
and adding the salaries/wages of the crew and cost of Diesel. Hence, it is clear
that though the words "hire charges of the machinery" are used in the SoRs, in
fact, "depreciation of the machinery" is' taken into account for the calculation,
and the "hire charges" are nowhere taken into consideration. The correct
position is that there would be no embedded taxes in the value or depreciation
of the machinery OWNED by the contractor, and hence there should not be any
deduction on account of embedded taxes.
2) No changes have been made either in the ruling position pertaining to taxes like
VAT or in the procedure of preparation of SoRs existing in the combined state
of AP after bifurcation of the State. After introduction of GST w.e.f.
01-7-2017, the issue of deduction towards embedded taxes in the machinery is
being examined alike in both the States. The Government of AP have issued
orders vide GO Ms No.118, Dt:09.11.2018 to keep the same hire charges of
machinery adopted in the pre-GST regime even in the GST regime from
01-7-2017, for all the ongoing works as on 01-7-2017 (for which agreements
have been concluded before 01-7-2017) Suitable instructions have also been
issued by the Government of A.P. vide letter No Rev SoRs/
ENC(R&B)/DCE®/ EE(TEC) / DEE7 /AEE2 /2019, Dt:21.02.2019 to adopt
the SoRs and revised estimates as per the GO Ms No.118 Dt:09.11.2018 and
the datas with zero lead has been communicated.
3) Further, the BAI has requested to take similar action and issue necessary orders
as those of Government of AP so that no deduction towards embedded taxes is
made from the hire charges of the machinery, as the element of hire charges is
actually depreciation in the value of the machinery and as the machinery items
are owned by the contractors.
8
4) In this regard, the Engineer-in-Chief (SR & CRN), R&B Dept has requested to
put forth the above subject matter before Committee of Board of Chief
Engineers for its discussion and necessary recommendations.
While submitting their plea on this issue before BOCEs, the BAI has also
requested Board of Chief Engineers to examine the embedded taxes of common
materials like Fine & Coarse aggregate and Bricks.
The Board of Chief Engineers has deliberated the issue in detail and after
comprehensive discussions in the matter, the BOCEs has recommended to keep
the same hire charges of machinery as adopted in pre-GST regime in the
post-GST regime also for all the ongoing works as on 01.07.2017. In this regard,
BOCEs observed that by keeping the same machinery hire charges in post-GST
regime, the machinery lead/conveyance charges will not be affected and hence
recommended to keep the same machinery lead/conveyance charges in post-GST
regime for all the ongoing works as on 01.07.2017.
Further, BOCEs also examined the embedded tax rates of common
materials like Fine & Coarse aggregate and Bricks etc., in pre-GST regime and
after detailed deliberations BOCEs has recommended for exemption of bricks
(except factory made aerated bricks like Aerocon etc.,) and Coarse aggregate
(crusher by product) from the purview of embedded taxes and to retain the same
rates in post-GST regime as that of pre-GST regime for all the ongoing works as
on 01.07.2017. This is because most of the dealers/suppliers come under
exempted category.
Action: Engineer-in-Chief (SR & CRN), R & B Dept
10
Telangana State- Certain Instruction issued by Govt to place the matter before the
Board of Chief Engineers Meeting - Regarding
Proposed by Engineer-in-Chief (AW), I&CAD Dept
As per the request of the ICADR, the Government of Telangana have issued
the G.O.Rt.No. 597 Law (B) Department dated 31-10-2018 (copy enclosed) by raising
the ceiling of claim amount to Rs.10,00,000 to Rs.40,00,000/- for the purpose of the
arbitration disputes arising in the Government contracts and with a direction to get the
disputes arbitrated through the ICADR, Regional Centre, Hyderabad.
According to ICADR, the above direction by the Government will help to settle
disputes of all kinds arising out of Government contracts expeditiously, economically
and without the hassles involved in traditional court litigation within one-year period
as per the Arbitration and Conciliation (Amendment) Act, 2015.
In this regard, this office has requested the Government to issue necessary
orders for implementation of G.O.Rt.No. 597 Law (B) Department dated 31-10-2018
of Govt. of Telangana by all unit officers of I & CAD Department at their level to
settle disputes arbitrated through the ICADR, Regional Centre, Hyderabad.
In view of above, the Government has informed that at present in almost all
agreements in I&CAD Department, there is no provision for arbitration beyond
Rs.50,000/-. As per the existing instructions, the concerned CE or SE they can
arbitrate up to Rs.50,000/- claims only.
Further, the Government has informed that the Law Department has suggested
to incorporate alternative dispute resolutions and they have issued G.O.Rt.No. 597
Law (B) Department dated 31-10-2018 duly enhancing the limitation to
11