Please Select A SATIP From The Below Selection, Then Select An Item No.
Select
SATIP:
SATIP-T-911-01
Saudi Aramco Typical Inspection
Approved Date Discipline
Plan
UNDERGROUND CONDUIT SYSTEM
(DUCTBANK AND MANHOLE)
Inspection
Responsibility
Item No. Project Phase Task Activity Check List and / or Test Record Quality Record Risk Level Assignments Remarks
Cont Aramco
1.0 DOCUMENT REVIEW
MR/PR, IAP, ITP and other Vendor Inspection required
1.1 SAEP-1151 SAEP-1151 R RH
material documentations
Handling,Storage, and Preservation of Precast duct bank,
1.2 See Remarks See Remarks RH RH
Manhole and Handholes Procedure
Concrete Mix Design, Asphalt Mix Design, Road Subbase
1.3 See Remarks See Remarks RH RH
and Base Course Material Test Reports
OSP Pre-cast Fabrication Shop Drawings (Offsite
1.4 SAIC-T-5709 SAIC-T-5709 RH R
Fabrication) Ductbank Fabrication
OSP Pre-cast Fabrication Shop Drawings (Offsite
1.5 SAIC-T-5710 SAIC-T-5710 RH R
Fabrication) Manhole / Handhole Fabrication
OSP Ductbank-Manhole and Handhole Hardware-
1.6 SAIC-T-5702 SAIC-T-5702 W S
storage,Handling and Preservation
2.0 RECEIVING INSPECTION
Pre-Cast Concrete / Rebar Material Receiving Inspection
2.1 See Remarks See Remarks
and Testing
Cast-in-Place Portland Concrete Cement / Rebar Material
2.2 See Remarks See Remarks
Receiving Inspection and Testing
OSP Ductbank Bulk Material Storage, Handling, and
2.3 Preservation Visual Inspection (Onsite and Offsite SAIC-T-5701 SAIC-T-5701 W S
Fabrication) Plastic Conduit / Sleeves / Innerduct
OSP Ductbank Bulk Material Storage, Handling, and
Preservation Visual Inspection (Onsite and Offsite
2.4 SAIC-T-5703 SAIC-T-5703 W S
Fabrication) Conduit Plugs / Seal Fittings / Innerduct
Accessories
OSP Ductbank Bulk Material Receiving Visual Inspection
2.5 (Onsite and Offsite Fabrication) PVC Plastic Conduit / SAIC-T-5704 SAIC-T-5704 H H
Sleeves
OSP Ductbank Bulk Material Receiving Visual Inspection
2.6 (Onsite and Offsite Fabrication) Manhole and Handhole SAIC-T-5705 SAIC-T-5705 H H
Hardware
OSP Ductbank Bulk Material Receiving Visual Inspection
2.7 (Onsite and Offsite Fabrication) Plastic Innerduct / SAIC-T-5707 SAIC-T-5707 H H
Accessories
OSP Ductbank Bulk Material Receiving Visual Inspection
2.8 (Onsite and Offsite Fabrication) Conduit Fittings and SAIC-T-5708 SAIC-T-5708 H H
Accessories
Pre-cast Ductbanks, Manholes, and Handholes Concrete
2.9 See Remarks See Remarks
Strength Testing (Offsite Fabrication)
3.0 INSTALLATION
3.1 OSP Ductbank Excavation and Trenching Visual Inspection SAIC-T-5506 SAIC-T-5506 H W
3.10 OSP Ductbank Backfilling Testing and Visual Inspection SAIC-T-5506 SAIC-T-5506 H H
3.11 Innerduct Pulling Visual Inspection SAIC-T-5711 SAIC-T-5711 H W
Innerduct and Conduit Identification and Termination
3.12 SAIC-T-5712 SAIC-T-5712 H W
Visual Inspection
Saudi Aramco: Company General Use
Jobsite Fabricated Ductbanks, Manholes, and Handholes
3.2 Initial Mandrel Test and Visual Inspection Ductbank Initial SAIC-T-5709 SAIC-T-5709 H H
TandI
Jobsite Fabricated Ductbanks, Manholes, and Handholes
3.3 Initial Mandrel Test and Visual Inspection Manhole / SAIC-T-5710 SAIC-T-5710 H H
Handhole Initial TandI
Jobsite Fabricated and Pre-cast Ductbanks Final Mandrel
3.4 SAIC-T-5709 SAIC-T-5709 H H
Test and Visual Inspection Ductbank Final TandI
Jobsite Fabricated and Pre-cast Ductbanks and Manholes
3.5 Final Mandrel Test and Visual Inspection Manhole / SAIC-T-5710 SAIC-T-5710 H H
Handhole Final TandI
Jobsite Fabricated Ductbanks, Manholes, and Handholes
3.6 See Remarks See Remarks
Concrete Strength Testing
3.7 Manhole Frame and Cover Installation Visual Inspection
3.8 Warning Tape Installation Visual Inspection
3.9 Grounding System Installation See Remarks See Remarks
4.0 PRE-COMMISSIONING
4.1 Ground Resistance Testing See Remarks See Remarks
Saudi Aramco: Company General Use