Middleborough Road Rail Project Governance
Middleborough Road Rail Project Governance
Semester 2, 2017
In order to eliminate this railway crossing, this project was carried out by the Middleborough Road
Alliance, consisting of VicRoads, John Holland Pty Ltd, Connex, and the Director of Public
Transport. This report aims to provide some fundamental aspects in the Project Organization &
Governance Plan and its Stakeholder Management Plan.
Executive summary
This paper sets out a project plan for the organisation, governance and stakeholder management
elements of the Middleborough Road level crossing removal. Two organisation charts will
describe the alliance management structure for the advanced weekend works and major
shutdown period covering both on-site and off-site positions.
The geotechnical subcontractor’s organisational structure will also be outlined, including a list of
linkages between members of the major project organisation and the geotechnical subcontractor’s
paralleled positions.
Responsibilities for all major positions in the alliance team will be listed, as well as a schedule of
authorisation for the geotechnical subcontractor organization. It will lastly outline a stakeholder
management plan for a list of identified stakeholders, and map the stakeholders in terms of their
impact on, or impact from the project.
Project Organisation & Governance Plan
The Middleborough Road Rail Separation Project was an Alliance contract agreement chosen by
the Government Transport Department and was working with the winner for the project KBR and
John Holland. The Alliance Leadership Team consist of KBR as principal designer, Vicroad,
Connex and john holland, their main responsibility was providing corporate governance and
leadership to the Alliance Team members.
During the advance work (early works and weekend occupation), the jobs were divided by
geographic sections. The first section was the Laburnum section – the section manager of
Laburnum had responsibility to monitor the earthwork and preliminary excavation around the
railway, as well as the preparation for station reconstruction. The next section was Box
Hill/Blackburn – the section manager of this section focused on the preparatory works at both
stations and the railway signalling system at both ends of the forthcoming rail shutdown. The last
section was the Middleborough section – the manager of this section had a responsibility to
manage the ground levelling in the Middleborough Road level crossing.
During the Major Shutdown Period, the top of the structure remained the same as the advance
work. The main differences between the diagrams lies underneath the section managers, due to
the scope of the activities at site.
Task 1: Alliance structure organisation charts (Advanced work)
Alliance Team
Name Head Office
Owner Owner
Site Office
ABC Site
Procurement
Name
Project Name Name Civil Works
Name Civil Works
Name
Procurement
Project Surveyor Site Engineer
Site Engineer
Civil Work
Engineer
Site Safety
Manager
Manager
Surveyor Engineer
Engineer Officer
Name
HR/IR Manager Design TeamName Site SafetyName Site Engineer
Name
HR/IR Manager Design Team Site Safety
SiteName
Engineer
Site Engineer
Site Engineer
Leader Leader
Officer Officer
Site Safety
Name
Civil Work
Temp Name Civil WorksName Site Safety
Name OfficerEngineer
Works
Temporary Work Civil Work Site Safety
Designer
Designer Engineer
Engineer
Officer Officer
Programming
Name
Programming
Name
Traffic Mgmt
Traffic Programming
Name
Programming Programming
Name Engineer
Engineer
Management
EngineerEngineer Engineer
Engineer Programming
Engineer
Engineer
Rail Signalling
Name
Rail Signalling
Engineer Engineer
Task 1: Alliance structure organisation charts (Major Shutdown Period)
Name
Owner
Owner
Alliance Team
Head Office
Site Office
AllianceName ABC Site
Leadership
Alliance Leadership
Team
Team
LEGEND
Name
Temp Name Civil Works
Civil Work
Name
Works
Temporary Work Engineer Site Engineer
Site Engineer
Designer
Designer Engineer
Traffic Name
Traffic Mgmt
ElectricalName
Rail Trackwork
Electrical
Name
Electricity
Management
Engineer
Engineer Engineer
Engineer
Engineer
Engineer
Rail Signalling
Name
Rail trackwork
Name
Site Safety
Programming
Name
Programming
Rail Signalling
Engineer
Engineer Engineer Officer
Engineer
Engineer
Programming
Name
Programming
Engineer
Engineer
Task 2: Geotechnical subcontractor organisation charts
Construction
Name
Construction
Manager Manager
Section Section
NameManager, Name Programme
Name and Name NameContract Name
Manager, Programme and Cost HR/IR Manager Quality Manager
Section Manager Site Section Manager Plant Cost Engineer HR/IR Manager Manager
Contract Manager Quality Manager
Site Plant Engineer
Name
Site
Name Safety Maintenance
Maintenance
Cost
Name
Site Safety Officer Cost accountant
Officer Officer
Engineer Accountant
Name Plant
Name
Surveyor
Surveyor Plant Supervisor
Supervisor
Shift
Name
Shift Supervisor
Supervisor
Geotech
Name
Engineer
Geotech Engineer
Inspection
Name
and Test
Inspection & test
Engineer
Engineer
Major alliance position Geotechnical Description (The reason
Subcontractor position why the linkage exists)
Laburnum Section Manager Construction Manager The Construction Manager
gives all information and
reports about the
geotechnical works to the
Section Manager, and they
work together to coordinate
their activities and
programming
OH&S Manager Site Safety Officer They are both providing
safety policy. The site safety
officer should give a report
to OH&S Manager
Project Surveyor Surveyor Surveyor gives the levelling
report to the project surveyor
Quality Manager Inspection and test engineer Inspection and test engineer
reporting to quality manager
Project Programmer Programme and Cost The Programme and Cost
Engineer Engineer maintains the
scheduling and the cost of
the geotechnical works, and
gives a report to the Alliance
Project Programmer
HR/IR Manager HR/IR Manager Both managers have a
responsible to manage their
respective workforce, and
the subcontractor HR
manager should report to
the manager on Alliance
Contract Manager Contract Manager Both contract managers
reach an agreement about
the contract between the
alliance and the
subcontractor (with the
involvement of the project
managers)
Quality Manager Quality Manager The quality manager should
report the quality and the
specification used in
geotechnical section to the
Alliance
There are several reasons why some personnel in each subcontractor’s organization need to
work co-operatively with counterpart personnel in the alliance organization:
1. Preventing duplicate jobs occurring in some tasks due to unclear information or
miscommunication.
2. Ensuring the materials are within specification.
3. Preventing delays to the project
4. Preventing miscommunications between subcontractor and alliance
5. Minimizing the risks on project
○ Injury (Safety issues)
○ Budget overruns
○ Equipment and tools (depreciation or damaged items)
○ Communication problems
6. Maintaining a good relationship between them to avoid lack of trust.
7. Monitoring the subcontractor’s performance.
8. Avoiding unnecessary activities that delay the project.
The plan details the stakeholder engagement process during the project planning phase, when
input will be sought and information will be provided on project outcomes, proposed designs, and
the temporary changes to road and rail travel during construction. In addition, stakeholder
engagement will continue during the major shutdown as construction progresses.
Assumptions
The plan assumes that:
● A project design has been prepared;
● The project owner has provided channels of communication to key stakeholders, such
as the details of a relevant contact person within government body stakeholders;
● The project owner is supportive of a strategy that promotes public participation and is
prepared to make alterations to the project scope
Identifying Stakeholders
A number of organisations and groups have been identified as stakeholders in the Middleborough
Road Rail Separation Project. They have been categorised according to their level of interest in
the project (high or low) and the degree to which they have the power to significantly impact the
project (high or low). Figure 1 shows the stakeholder mapping during the planning phase of the
project, while Figure 2 displays the stakeholder mapping for the major construction
(implementation) phase.
Planning
High level of ● Utility service companies (with ● Railway operator (Connex)
influence/power assets in Middleborough Rd) ● Road operator (VicRoads)
● Municipal Government (City of
Whitehorse);
● Box Hill High School
● Box Hill Cemetery Trust
Low level of ● Emergency services (police, fire, ● Rail Users
influence/power ambulance) ● Labour organisations (various);
● Residents in the nearby community ● Road Users (community, bus
● Sporting teams using the adjacent companies, taxi companies);
sports ground ● Residents adjacent the site;
● Local Newspapers and RACV ● Local shopkeepers
Low Impact from, or Interest in the High Impact from, or Interest in the Project
Project
Figure 1
Implementation
High level of ● Utility service companies (with assets ● Railway operator (Connex)
influence/power in Middleborough Rd) ● Road operator (VicRoads)
● Emergency services (police, fire, ● Municipal Government (City of
ambulance) Whitehorse);
● Box Hill High School
● Box Hill Cemetery Trust
Low level of ● Residents in the nearby community ● Rail Users
influence/power ● Local Newspapers and RACV ● Labour organisations (various);
● Road Users (community, bus
companies, taxi companies);
● Residents adjacent the site;
● Local shopkeepers
● Sporting teams using the adjacent
sports ground
Low Impact from, or Interest in the High Impact from, or Interest in the Project
Project
Figure 2
Selecting an approach
The International Association for Public Participation (IAP2) has developed tools that help foster
public participation in a project. Alongside the IAP2 Core Values, which set out various goals that
public-facing projects should aspire to, a Public Participation Spectrum is provided, which sets
out different ways in which the public can be engaged with a project.
The Public Participation Spectrum features five levels of engagement (IAP2 2014):
1. Inform - where a one-way yet “objective and balanced” channel of communication exists
from the project team to the community (or other stakeholder).
2. Consult - where the community (or other stakeholder) has an opportunity to offer
feedback or comments on key project decisions.
3. Involve - where the community (or other stakeholder) is given numerous opportunities to
provide a range of input throughout the project.
4. Collaborate - where the project team works alongside the community (or other
stakeholder) at all phases to develop the project together.
5. Empower - where the community (or other stakeholder) is given complete decision-
making powers over some or all aspects of the project.
As noted in the list above, these levels of engagement are framed in terms of community
involvement, but they can apply equally to other stakeholders as well. For example, one could
decide to inform a local newspaper, but to collaborate with the High School next to the project
site.
Proposed approach
Monthly Newsletter for the stakeholders to be remain informed on the status of the project, it
should cover:
● Project deadlines and what to expect in the way of potential disruptions. Keep
stakeholders informed of when each stage is expected to be completed and what they
should expect from each stage, so they can manage their own timetables to avoid any
disruptions to their schedules.
● Project successes and a reminder of the eventual benefits of the realised project once it
is completed.
Liaison Officer to manage newsletter and directly respond to any concerns or questions which
members of this group may have.
Meeting at Each Phase. By meeting with these stakeholders at each phase of the project,
including sharing infrastructure designs and temporary works plans, the project team will ensure
that:
● Stakeholders are aware of the project scope and will be able to take action to work around
the disruptions the project will create.
● The project team is aware of any requirements of the stakeholders, such as preserving
emergency access and the locations of underground services. During the meetings, the
project team will have an opportunity to discuss how to address these requirements to the
stakeholder’s satisfaction.
● The project is not delayed by unexpected disruptions or previously unarticulated
stakeholder requirements.
Although these stakeholders have a low interest in the project, their involvement is crucial to
project success, so the benefits of these meetings to the stakeholders need to be made clear,
and they should only be held at times when a clear need is identified.
Frequent Updates - weekly during the advance works and daily during the major shutdown. The
stakeholders will be kept informed of any changes, such as unplanned closures
A Stakeholder Advisory Board will also be established. This will include all the stakeholders at
this level, including the local council, cemetery trust and high school. See Governance below.
Governance
This project will be managed by the project steering committee (PSC), and each stakeholder
group from the High Impact/High Influence grouping will be invited to the contribute one
representative to the PSC Stakeholder Advisory Board (SAB).
The SAB will meet with the PSC on a fortnightly basis, and will be responsible for making
recommendations on project proposals by the project manager from the context of stakeholder
impact minimisation. Minutes from the meeting will be made available to both the project manager
and all stakeholders in the High Interest grouping. All decisions will be made by popular vote by
the members who are present. Any member not in attendance for three consecutive meetings
without forward notification will be removed from the committee.
References
International Association for Public Participation (IAP2), 2014, IAP2’s Public Participation
Spectrum, Viewed 29 August 2017,
<[Link]
[Link]>