Plinth Area Rates For Rce 2017-18 PDF
Plinth Area Rates For Rce 2017-18 PDF
Building Schemes during the year 2O,7 -2018, worked out in line with the
impact of
adoption of Standard Schedule of Rates for the year 2OL7 -2018 are approved
and
furnished in Annexure I, II, III, IV & V' The Chief Engineers, the Superintending
Engineers and the Executive Engineers of Building organisation are requested
to adopt
the above rates in the preparation of the rough cost estimates for building schemes'
with effect from 01.O7.2O17, until further orders from thls office'
The receiPt of this circular memo along with its enclosures may b-"
acknowledged. \7
0
Enc!.: Annexures-I, II, III, IV &V.
for I ief (
Chief Engi ), Chennai
), PWD, Chennai-s
Framed 3760 9BBO t215 3950 10375 1285 4055 10605 1305
2. Non-Residentia I
2445 6010 1185 2565 6305 1250 2630 6460 1285
Load Bearinq
Framed 3760 7425 7215 3950 7795 1285 4055 7965 1305
3. Hospital
2445 6730 1185 2565 7505 1250 2630 7235 1285
Load Bearinq
Framed 3760 10350 t2t5 3950 10875 1285 4055 tLt40 1305
Note: -
(1) For the calculation of Foundation Cost, Plinth area at Ground level of the
building is to be taken.
(2) For the calculation of Super Structure cost, plinth area of respective floor
of the building is to be taken.
(3) For the calculation of Roof finishing cost, Plinth area at Ground level of
the building is to be taken.
(4) For School Buildings - the Super Structure cost will be 80o/o of Super
Structure cost of Non-Residential Buildings.
(5) For stilt floor towards Car parking, Garages, Cycle shed, Staircase Head
Rooms etc., - the plinth area rate will be 650lo of Super Structure cost of
Non-residential building.
(6) For basement floor, an extra 25olo over the super structure cost of
respective type of building is to be added.
(13) For works in coastar area, the folowing rates over the basic rate as
approved in the table above, (for the total plinth area) shall be added for
providing concrete of higher grade
a. Upto 10 km distance from Sea Water Front _ Rs. 200/m2
b. Beyond 10 km and upto 24 km distance from Sea Water Front _
Rs. 100/m2
(b) The height of each floor has been taken as 3.30m average.
(c) This rate is inclusive of provision for Anti skid ceramic tile flooring
and glazed tile dadooing in Toilets.
(d) This rate is inclusive of plasterlng with Cement Mortar 1:5, 12mm
thick, white washing two coats over one coat of white washing for
interior walls and colour washing two coats over one coat of white
washing for exterio r faces.
(a) IN FOUNDATION:-
Rate in
sl. Type of foundation Rupees per Area to which applicable
No.
one sq.m,
For stub column arrangements
(i) 960 Plinth area at ground level
for Load bearing structu re
( ii) For combined footing 625 Plinth area at ground level
( iii) For strip raft 2505 Plinth area at ground level
(iv) For raft ( Floating Raft) 3760 Plinth area at ground level
4
st. Rate in
No. Type of foundation Rupees per Area to which applicable
one sq.m.
For every additional floor over
(vii) initial Ground +3 Floors in 515 Respective floor area
case of Framed Structure
(viii) For Anti-Termite Treatment 95 Plinth area at ground level
(ix) Pile Foundation
(a) Upto 4 storeys for a depth of
15m
7375 Plinth area at ground level
(b)
More than 4 storeys but less
than 8 floors 9475 Plinth area at ground level
considered) Buildings
Build ings
5
(f) Marble (Adanga)
(not less than 600 x 600 x 18mm size) Rs.1375lm2 Rs.800/m'z
(t)
Double Charged Vitrified Tiles
600x600xBmm Rs.1310/m2 Rs.720/m2
[Link]
Chief Engineer (hd
-*..d-\f,
enier leufrain{s1.i
ngs), Chennai lRegion i
Chief Engineer (G eral), PWD, Chennai-5
G.;
6\$
6
ANNEXURE-II
OPTIONAL ITEMS
Rate in
sl. Description of work Rupees per
Area to which
No. applicable
one sq.m.
(b) False Ceiling with Perforated Gypsum Board using GI Channel Sections etc.,
( ii)
With Glass Wool 50mm thick below AC
1595 Ceiling area proposed
sheet rooflng
iii)
With Glass Wool 25mm thick below RCC
1460
( Ceiling area proposed
roofing
2
Wall Paneling using GI Channel Sections etc., (with cypsum Board)
if proposed:-
(a)
Wall Paneling with Perforated Gypsum
1325
Wall Paneling area
Board with Glass Wool of 25mm thick proposed
ro,.ns{X2
chief Engineer (dd
affi1,trI
GfGf (Buildinss!, I
ngs), Chennai nEgion a
/
Chief Engineer (Gc 3ral), PWD, Chefinai-5
d-
#\a
7
ANNEXURE-III
ELECTRICAL, WATER SUPPLY AND SANITARY ITEMS OF WORKS
s1, Rate in
Description of work Rupees per Area to which
No. applicable
one sq,m,
1
AC Provision for office Buildings and in Hospit"l..-
(if proposed):-
(a) Fornon-ductableACUnits ffi
(b) For ductable type AC Plants 5505 Floor area proposed
Note! The above rates are not inclusive of civil works such as aonstruction
of plant room, false ceiling, etc.
13 Persons capacity
( iii) Rs.19.30 lakhs Rs.20.20 Iakhs
(upto Ground + Three Floors)
iv)
20 Persons capacity
(
(upto Ground + Three Floors) Rs.24.00 lakhs Rs.25.50 lakhs
Bed-cum-Passenger Lift
(SS Body-304 Grade - Gearless) With Machine Without
(b) Machine Room
having speed 1m / second including Room (G+3)
(G+3)
power mains
20 Persons capacity
( ii) Rs.24.50 lakhs Rs.25.50 lakhs
(upto Ground + Three Floors)
26 Persons capacity
( iii) Rs.25.50 lakhs Rs.27.50 lakhs
(upto Ground + Three Floors)
a
Note:
1. Provision for civil works such as construction of Lift Pit, Shaft, Machine
Room, etc., are not included in the above rates.
2. For Passenger Lift and Bed-cum-Passenger Lift - For every
additional floor over the Ground + Three Floors an extra at
Rs.1,00,000/- shall be allowed for each floor.
3. For Dump Lift - For every additional floor over the Ground + Three
Floors an extra at Rs.44,970/- shall be allowed for each floor.
4. For Lift Pit an extra at Rs.12,840/- per sq.m. of lift well sectional
area shall be allowed.
5. Comprehensive servlcing and maintenance of lifts for further perlod of
2 years beyond free warranty period of one year from the date of
commissionlng of llfts will be paid at the rate of 5o/o of capital cost of
tift.
6. For Passenger Lift and Bed-cum-Passenger Lift - Add extra
Rs.50,000/- per Lift for Earthing, Shaft, Machine Power Mains as per
CEIG Norms shall be allowed.
7. Safety Certificate for Lift has to be obtalned by Supplier from CEIG.
9
sl. Description of work
No. Rate as
per SOR, AIlied works Total
High Tension SUPPIY
(3) (including Erection, Testing, 20L7-ta
Commissioning and Allied Works)
Rs.3.00
HT/LT Cable lakhs
Rs.5.00
MV Panel
lakhs
Rs.12.91 Safety Rs.0.30 Rs.23.21
( iii) With Transformer uPto 1000 KVA lakhs Accessories lakhs lakhs
Rs.2.00
APFC Pane|
lakhs
Rs.1O.3O
sub-Tota I
lakhs
Note:
1. Provision for civil works such as/ construction of Transformer Room, MV Panel
Room, etc., are not included in the above rates'
2. Add extra for Service Connection Charges payable to TNEB and approval
charges payable to CEIG.
3. If necessary, as per the approved design based on the site condition and CEIG
Norms, add extra for the provision of Vacuum Circuit Breaker Panel and Ring
Main Gear adopting Schedule of Rates, 2017-2018 shall be allowed.
10
7 Intercom with EPABX arrangements uPto 300 lines Rs.15.60 lakhs
Note:
Add extra for additional down conductor at Rs.140/- per RM for the
more than 5 storeYed buildings.
9
Civil Aviation Lights for buildings more than B
Rs.1.31 lakhs
storeys
11
External Water Supply, sanitary Arrangements &
11
Electrical Arrangements
Water SupplY Sanitary Electrical
Arrangements Arrangements Arrangements
Note:
1. The above rate is applicable only for ground and first floors on plinth area
basis.
2. For every upper floor over the basic ground and first floor, 50o/o of
respective floor area alone shall be taken into account for making
provision towards external water supply and sanitary arrangements'
3. For every upper floor over the basic ground and first floor, 2Oo/o of
respective floor area alone shall be taken into account, for making
provision towards external electrification arrangements. i I
P ..--."'- )
,"rffi,\
chief Ensineei1B
Chief Engineer (
ings), Chennai 'Region
reral), PWD, Chennai-5
&
L2
ANNEXURE - IV
OTHER PROVISIONS
st.
No, Description of work Rate
(b)
With load bearing foundation wlth brick work in
Rs.2840lRM
cement mortar 1 :5
2 Approach Road
Forming approach road in layers of 450mm thick sand
gravel mix of ratio 1:1 as base layer, WBM Laid in
(a) two layers of 75 mm thick each (total 150 mm thick) Rs.52O/sq m.
including cost of small culverts come across, forming
berms, etc.,
(b) For Prestigious / Heritage Buildings Not exceeding 21/zo/o of total value
of building
5 Soil Investigation (minimum) Rs.30,650/-
Note
1. If [he area is more, hlgher provision towards soil investigation may be allowed.
13
Provislon is to be made depending
6 Advertisement Charges on the norms prescribed by
Government time to time for
publication in Newspapers.
for Engin
chief Engineer
-A[\&
i:Chief ( Bdildi{r9s),'
dings), Chenndi Region
Enqinec (Geheral),
Chief Engineer neral ), PWD, Chennai-5
As
?\
L4
ANNEXURE-V
PLINTH AREA RATE FOR SUPER STRUCTURE
oF EARTH QUAKE RESISTANT STRUCTURES
TRICHY, SALEM, CH EN NAI,
ERODE, MADURAI, VELLORE,
sl. Type of building
MOFFUSIL TIRUNELVELI & COIMBATORE &
No. THOOTHUKUDI TIRUPPUR
DISTRICTS DISTRICTS
RATE IN RUPEES PER 1SQ.M. FOR EVERY FLOOR
I RESTDENTIAL
(a) Load bearing (upto G + 2) 7600 8000 8390
(b) Framed Structure
(i) Upto Two Floors 9880 10370 10860
( ii) 3 & 4tn Floors 9880 10370 10860
( iii) 5 & 6tn Floors 10870 11400 Lt940
( iv) 7 & 8tn Floors 10870 11400 11940
(v) Above Btn Floor 10870. 11400 t1940
(vi) Stilt Floor 6900 6960 7580
2 NON RESIDENTIAL
(a) Load bearlng (upto G + 2) 6460 6780 7100
(b) Framed Structure
(i) Upto Two Floors 7420 7780 8160
( ii) 3 & 4th Floors 7420 77aO 8160
( iii) 5 & 6th Floors 8140 8540 8970
(iv) 7 & 8th Floors 8140 8540 8970
(v) Above 8th Floor 8510 8930 9360
(vi) Stilt Floor 5120 5430 5680
3 HOSPITAL
(a) Load bearing (upto G + 2) 7230 7590 7950
(b) Framed Structure
(i) Upto Two Floors 10250 10370 11400
( ii) 3 & 4th Floors 11410 L7970 12550
( iii) 5 & 6th Floors 11410 rt970 12550
(iv) 7 & 8th Floors L2450 13060 13680
(v) Above Bth Floor t2450 13060 13680
(vi) Stilt Floor 7240 7600 7980
NOTE:
1. For calculating the rates, the respective floor area has to be considered.
2. For woks in special tracts like Jails, Reserve Forest, Hill Areas etc., the respective
extra percentage over the Moffusil rate is to be given. .'
for I
x-4;{$161
f-'fue{i"t ( eu itdi ngs l,
Chief Engi |tfliklings), Chennai Rdsion
Chief En! (Ger{eral), PWD, Chennai-5
15