Construction Project Timeline Breakdown

This document outlines the schedule for constructing a 12 storey building from 2017 to 2020. It details 83 tasks needed for the construction including activities like foundation work, concrete flooring, brickwork, and column construction for each level from the basement to the 11th floor. The schedule is broken down month by month to show the expected start and finish dates for each task over the 40 month construction period.

Uploaded by

phewphewphew200
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views4 pages

Construction Project Timeline Breakdown

This document outlines the schedule for constructing a 12 storey building from 2017 to 2020. It details 83 tasks needed for the construction including activities like foundation work, concrete flooring, brickwork, and column construction for each level from the basement to the 11th floor. The schedule is broken down month by month to show the expected start and finish dates for each task over the 40 month construction period.

Uploaded by

phewphewphew200
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID Task Name Duration 2016 2017 2018 2019 2020

H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
1 Pre-construction Activities 40.67 days
7 Construction of boundary wall 21.67 days
11 Construction of first 12 storey building 799.5 days
12 Foundation 56 days
13 Well boring 13.33 days 17-03 05-04
14 Well point dewatering 7.67 days 05-04 17-04
15 Sheet Piling 10.83 days 12-04 27-04
16 Excavation 4.17 days 27-04 03-05
17 Construction of raft foundation 23 days 03-05 05-06
18 Lower Basement construction 24.5 days
19 Concrete floor finishing 4.17 days 05-06 09-06
20 Firstclass brickwork for lower basement wall 14.83 days 09-06 30-06
21 Shuttering and centering and concreting for columns 20.33 days 09-06 07-07
22 RCC work for stairway and lintels 7.83 days 23-06 05-07
23 Upper Basement construction 41.17 days
24 Concrete flooring 23.33 days 07-07 10-08
25 Firstclass brickwork for upper basement wall 14.83 days 10-08 30-08
26 Shuttering and centering and concreting for columns 20.33 days 21-07 21-08
27 RCC work for stairway and lintels 7.83 days 24-08 02-09
28 Ground Floor Construction 30.33 days
29 Concrete flooring 24.17 days 04-09 06-10
30 Firstclass brickwork for superstructure wall 14.83 days 18-09 06-10
31 Shuttering and centering and concreting for columns 20.33 days 18-09 16-10
32 RCC work for stairway and lintels 7.83 days 02-10 11-10
33 First Floor Construction 30.33 days
34 Concrete flooring 23.5 days 16-10 16-11
35 Firstclass brickwork for superstructure wall 14.83 days 30-10 20-11
36 Shuttering and centering and concreting for columns 20.33 days 30-10 27-11
37 RCC work for stairway and lintels 7.83 days 13-11 23-11
38 Second Floor Construction 30.33 days
39 Concrete flooring 23.5 days 27-11 29-12
40 Firstclass brickwork for superstructure wall 14.83 days 11-12 01-01

Page 1
ID Task Name Duration 2016 2017 2018 2019 2020
H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
41 Shuttering and centering 20.33 days 11-12 08-01
42 RCC work for stairway and lintels 7.83 days 25-12 04-01
43 Third Floor Construction 30.33 days
44 Concrete flooring 23.5 days 09-01 09-02
45 Firstclass brickwork for superstructure wall 14.83 days 23-01 12-02
46 Shuttering and centering and concreting for columns 20.33 days 23-01 20-02
47 RCC work for stairway and lintels 7.83 days 06-02 15-02
48 Fourth Floor Construction 30.33 days
49 Concrete flooring 23.5 days 20-02 23-03
50 Firstclass brickwork for superstructure wall 14.83 days 06-03 27-03
51 Shuttering and centering and concreting for columns 20.33 days 06-03 03-04
52 RCC work for stairway and lintels 7.83 days 20-03 30-03
53 Fifth Floor Construction 30.33 days
54 concrete flooring 23.5 days 03-04 07-05
55 Firstclass brickwork for superstructure wall 14.83 days 17-04 08-05
56 Shuttering and centering and concreting for columns 20.33 days 17-04 15-05
57 RCC work for stairway and lintels 7.83 days 01-05 11-05
58 Sixth Floor Construction 30.33 days
59 Concrete flooring 23.5 days 16-05 18-06
60 Firstclass brickwork for superstructure wall 14.83 days 30-05 19-06
61 Shuttering and centering and concreting for columns 20.33 days 30-05 27-06
62 RCC work for stairway and lintels 7.83 days 13-06 22-06
63 Seventh Floor Construction 30.33 days
64 Concrete flooring 23.5 days 27-06 30-07
65 Firstclass brickwork for superstructure wall 14.83 days 11-07 01-08
66 Shuttering and centering and concreting for columns 20.33 days 11-07 08-08
67 RCC work for stairway and lintels 7.83 days 25-07 06-08
68 Eighth Floor Construction 30.33 days
69 Concrete flooring 23.5 days 08-08 11-09
70 Firstclass brickwork for superstructure wall 14.83 days 22-08 12-09
71 Shuttering and centering and concreting for columns 20.33 days 22-08 19-09
72 RCC work for stairway and lintels 7.83 days 05-09 17-09

Page 2
ID Task Name Duration 2016 2017 2018 2019 2020
H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
73 Ninth Floor Construction 30.33 days
74 Concrete flooring 23.5 days 20-09 23-10
75 Firstclass brickwork for superstructure wall 14.83 days 04-10 24-10
76 Shuttering and centering and concreting for columns 20.33 days 04-10 01-11
77 RCC work for stairway and lintels 7.83 days 18-10 29-10
78 Tenth Floor Construction 30.33 days
79 Concrete flooring 23.5 days 01-11 04-12
80 Firstclass brickwork for superstructure wall 14.83 days 15-11 06-12
81 Shuttering and centering and concreting for columns 20.33 days 15-11 13-12
82 RCC work for stairway and lintels 7.83 days 29-11 11-12
83 Eleventh Floor Construction 30.33 days
84 Concrete flooring 23.5 days 13-12 16-01
85 Firstclass brickwork for superstructure wall 14.83 days 27-12 17-01
86 Shuttering and centering and concreting for columns 20.33 days 27-12 24-01
87 RCC work for stairway and lintels 7.83 days 10-01 22-01
88 Twelfth Floor Construction 30.33 days
89 Concrete flooring 23.5 days 25-01 27-02
90 Firstclass brickwork for superstructure wall 14.83 days 08-02 28-02
91 Shuttering and centering and concreting for columns 20.33 days 08-02 08-03
92 RCC work for stairway and lintels 7.83 days 22-02 05-03
93 Terrace construction 24.83 days
94 Parapet wall construction 24.83 days 08-03 12-04
95 Waterproof course on terrace 14.83 days 08-03 29-03
96 Plastering Activites 71.67 days
97 Internal Plastering 61.67 days 30-04 24-07
98 External Plastering 61.67 days 14-05 07-08
99 Electrical Activities 87.83 days 22-03 24-07
100 Mechanical and Plumbing Activities 73 days 26-04 07-08
101 Painting Activities 109.67 days
102 White washing of interior walls and ceiling by plaster of paris 34.67 days 07-08 24-09
103 Painting of interior walls and ceiling 55.17 days 27-08 12-11
104 White washing of exterior walls and ceiling by plaster of paris 34.67 days 03-10 20-11

Page 3
ID Task Name Duration 2016 2017 2018 2019 2020
H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
105 Painting of exterior walls and ceiling 55.17 days 22-10 07-01
106 Flooring Activities 55.5 days
107 Laying of mortar 11 days 25-12 08-01
108 Laying of tiles 14.83 days 09-01 29-01
109 Grinding 14.83 days 29-01 19-02
110 Polishing 14.83 days 19-02 11-03
111 Installation of doors and windows 61.33 days 07-08 31-10
112 Finishing Activities 20.33 days 11-03 08-04
113 Construction of second 12 storey building 799.5 days
215 Construction of third 12 storey building 799.5 days
317 Construction of fourth 12 storey building 799.5 days
419 Construction of fifth 12 storey building 799.5 days
521 Construction of sixth 12 storey building 799.5 days
623 Construction of seventh 12 storey building 799.5 days
725 Construction of eighth 12 storey building 799.5 days

Page 4