PROJECT PLANNING USING NETWORK
TECHNIQUE
INTRODUCTION
Network planning technique is a very useful
tool in project management.
Two different types of networks are the Arrow
diagram and the Precedence diagram.
In principle, both techniques use the critical
path method to analyze the project time.
1
Historical Background
During world war 1, Henry [Link] develop a
graphical technique of displaying bar type line upon
specific time.
The technique was known as Bar Chart.
In 1956 E.I. du Pont de Nemours & Company
developed network concept known as Critical Path
Method
Booz Allen & Hamilton develop Project Evaluation
Review Technique (PERT)
Scheduling software application are Primavera,
Microsoft Project, Artemis, Timeline etc
2
Choice of Scheduling Method
Factors that governed the choice of the
technique are:
Familiarity on the technique to be used
Type and size of project
Purpose of scheduling
3
Familiarity on the technique to be used
A planner should not engaged any technique
which he has a limited knowledge on it’s
application
Main objective of the schedule as a
communication tool
Important to have a schedule technique
which is acceptable by all parties.
4
Type and Size of the Project
Project with few but repetitive tasks – Line of
Balance
Medium to Large Project – (Critical Path
Method) like Precedence Method or Arrow
Diagram
Small Project – Gantt Chart or Bar Chart
5
Purpose & Important of Schedule
Claim
Project time and cost control
Allocate project resources more efficiently
As a monitoring tool
Material delivery at site
Storage – all material cannot put in the site (confined space)
Avoid delay of the work and activity.
Minimize the cash flow – as min as possible such as order material
stage by stage depend on the work needed.
To guide fabricate (roofing, steel etc)
Control human resources and machinery
To give confidence to the client especially when bidding process.
To improve the efficiency of the operation through the efficient use of
resources and cost control.
Basic schedule for endorsement.
6
Basic Scheduling Technique
Gantt’s Chart or Bar Chart
Networking
Arrow diagram method
Precedence Diagram Method
Project Evaluation Review Technique (PERT)
Line of Balance
7
Bar Chart
Bar Chart is one of the oldest scheduling technique
Wide acceptance because it is readily understood
by almost every one
It is very easy to develop and used
Useful technique for a small project
Task schedule can be graphically presented on the
time-scale.
The main weakness is that relationship that exist
between the task cannot be shown.
8
Bar Chart
9
Network Method
Arrow Diagram
In arrow diagram project task or activities are represented by
the arrow and connected by the node to express their logical
relationship
Arrow – Activity
Node – Junction to the event
- Activity started or end
Arrow diagram for pad footing
10
Precedence Diagram Method
PDM activity is place on the node
The arrow used to connect between project task to show their
logical relationship
Arrow - Logical
Node - Activity
Logical – Show the relationship two activity
- Sequences of interrelated activity
PDM diagram for pad footing11
Line of Balance
Used to plan for construction of a number of
repetitive activities.
Concept of keeping all of resources in
balance, each following the other productivity
Main objective to optimum use of all
resources
Example for road construction, bridge, pipe
laying, housing and etc
12
Line of Balance Chart
13
Number of
product
week
Line of Balance for Housing Project
14
Basic Resources In Planning
Planner to establish the project objective and
purpose of the schedule to be developed
Planner must gather as much possible information
on the project resources like material, machine,
manpower money and time
Project resources and time available are critical
factors that determine the way that the project work
will be executed.
The availability of the material, the ordering time and
delivery material to site will have strong impact on
project time.
15
Basic Resources In Planning
Special long lead item may required several months
before actual delivery can be made to site.
The machine and technology to be used in the
project has strong influence on the productivity rate
at site also number of workers planned to be
employed.
Understanding of labor requirement for the
determination of performance time of the various
activities during the construction process.
16
Project task or Activity
Definition an Activity or task-
single work step that has a recognizable beginning
and end and requires time and resources for its
accomplishment .
Dummy Activity
- Have zero duration
- Do not require any resources
- Happen in both arrow diagram & precedence diagram
- Needed to have proper logic, maintain numbering, system or
milestone event.
17
Project Breakdown
Process of dividing it into smaller segments
Several criteria can be used to divide the project
such follows:
1. By area of responsibility
2. By structural elements
3. By category of works
4. By location of project
Planner must be able to identify all project activities
or task to executed.
18
Logical Relationship of Project
Activities
Understand the order of how the job to be
accomplished in the field.
The planner must understand how various
activities of the project related to each other
in term of their logical sequence.
Example preparing formwork before
reinforcement could be place & than pouring
concrete.
19
Strip top soil Cut and Fill
Figure-1 the logical relationship between the two activities shows
that the start of ‘cut & fill’ activity can only accomplished upon the
completion of the activity ‘strip top soil’.
Pour Concrete
Form work
Fixed rebar
Figure-2 indicate that activities ‘formwork’ and ‘rebar’ must be
accomplish before the start of activity ‘pour concrete’
20
ACTIVITY ON ARROW (AOA)
ES = Earliest Start (Masa Mula Awal)
LS = Latest Start ( Masa Mula Akhir)
EF = Earliest Finish ( Masa Tamat Awal)
LF = Latest Finish ( Masa Tamat Akhir)
TF = Total Float (Jumlah Apungan)
FF = Free Float (Apungan Bebas)
Duration = Time to complete an activity (D)
ES & LF – From arrrow diagram
EF = ES + Duration
LS = LF – Duration
TF = LF – EF
FF = Early start of succeeding - EF of activity
21
AOA
Forward pass - a process to find the earliest start time
for all activities
Backward - a process to find latest finish time for all
activities
Critical Path - the longest paths of the planning from start
to finish
Total Float (TF) - the maximum time available for an
activity that can be delay without
delaying the completion date
(TF = LF – ES)
Free float (FF) - the maximum time for an activity that can be
delayed without delayed the start of any
succeeding activity.
(FF = Early start of succeeding - EF of activity )
22
AOA
EXAMPLE ARROW DIAGRAM
Activity Duration Predecessor
A 5 -
B 2 -
C 1 -
D 4 A
E 3 B
F 6 C
G 2 C
H 5 D
I 1 E,F
J 6 G
23
\10
24
Result
Activity Duration ES EF LS LF TF FF
A 5 0 5 0 5 0 0
B 2 0 2 8 10 8 0
C 1 0 1 5 6 5 0
D 4 5 9 5 9 0 0
E 3 2 5 10 13 8 2
F 6 1 7 7 13 6 0
G 2 1 3 6 8 5 0
H 5 9 14 11 14 0 0
I 1 7 8 13 14 6 6
J 6 3 9 8 14 5 5
25