0% found this document useful (0 votes)
470 views6 pages

Construction Material Costs

The document provides a bill of materials for a 180 square meter construction project including cement, sand, gravel, rebar, concrete blocks, plywood, lumber, roofing materials and electrical components. It lists the quantity, unit, price and total cost for each material. The total material cost is PHP 607,302.08 which makes up 78.77% of the total project cost. The remaining 21.23% of the budget is allocated to equipment, labor and miscellaneous costs.

Uploaded by

Fritz Natividad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
470 views6 pages

Construction Material Costs

The document provides a bill of materials for a 180 square meter construction project including cement, sand, gravel, rebar, concrete blocks, plywood, lumber, roofing materials and electrical components. It lists the quantity, unit, price and total cost for each material. The total material cost is PHP 607,302.08 which makes up 78.77% of the total project cost. The remaining 21.23% of the budget is allocated to equipment, labor and miscellaneous costs.

Uploaded by

Fritz Natividad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Total Floor area Materials

180m2 Description Quantity Units Price Total


Cement 182 bag 210 38220
Sand 9.25 cu.m 800 7400
Gravel 8.41 cu.m 1300 10933
10mm(dia)x6m RSB 17 pc 118 2006
10mm(dia)x7.5m RSB 23 Pc 160 3680
12mm(dia)x6m RSB 4 Pc 175 700
#16 GI Tie Wire 4 kg 70 280
4” Thk. CHB 127 pc 13 1651
Grout (5 kg./pack) 90 kg 35 3150
Concrete Epoxy 1 gal 1400 1400
Red Lead (Read Oxide) 2 gal 380 760
QDE 2 gal 595 1190
Paint Thinner 2 gal 220 440
White Permacoat
7 gal 500 3500
Concrete Sealer
Semi-gloss Latex 15 gal 566 8490
Glazing Putty 10 gal 555 5550
Sand Paper (#120) 15 pc 10 150
Acri-color (brown) 4 pint 50 200
4” Paint Brush 7 pc 90 630
Solvent Cement (400 cc) 1 can 180 180
9” Paint Roller 2 pc 60 120
Nylon Bristled Brush 4 pc 0
Rubber Hand Gloves 10 pair 250 250
Masks 5 pc 25 125
1/2 thk. Ordinary
Plywood (8ftx4ft) 12 pc 650 7800

1/4 thk. Ordinary


Plywood (8ftx4ft) 32 pc 350 11200

2x2 Coco Lumber (8ft) 45 Pcs 85.333 3839.985

2x2 Coco Lumber (10ft) 30 Pcs 105.67 3170.1

2x3 Coco Lumber (10ft) 20 Pcs 160 3200

12'-0", # 26 corr. GI
12 pc 320 3840
Sheet
3" common nail 2 kg 70 140
2" common nail 2 kg 70 140
1"common nail 1 kg 70 70
2 1/2" roofing nails 4 kg 95 380
Concrete Wire Nail 15 kg 95 1425
3x3 butt hinge 9 pc 45 405
Door Lock 3 set 300 900
4" dia. porcelain
receptacle 4 pc 35 140

4x4 junction box (plastic) 4 pc 13 52

Duplex conv. outlet (surface 2 pc 70 140


mounted)

One gang switch (surface 4 pc 35 140


mounted)

Safety switch 1 pc 315 315


2.0 sq mm TW wire 40 mts 15 600
Hyrdogen Peroxide 100 kg 25 2500
Piedrra Pinoy 18"X24" 600 pc 600 360000
Piedrra Pinoy 20 x 60 145 pc 350 50750
Piedrra Pinoy 30 x 60 155 pc 280 43400
Adobe Crushed 150 sacks 145 21750

Total Material Cost 607302.085


Percent of Cost 78.77%
Remaining Cost 128902.085
Remaining Percent Cost 21.23%
Equipments Labor
Total Equipment Cost Total Labor Cost
Labor Miscellaneous
Total Miscellaneous Cost

You might also like