BUILDING WORKS AT HOUGANG TOWN
DAILY SITE RECORD Wednesday, March 18, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
FOUNDATION Bored Pile
Piling work in progress.
total completed to date: 128 nos.
total Number foundation Bored Piles 128 nos. 100.00%
Structural work
CONTIGUOUS Bored Pile ( CBP )
total completed to date: 141 nos.
Total number of contiguous Bored Piles 141 nos. 100.00%
GROUT PILES
PILE CAP CONSTRUCTION IN PROGRESS
total completed to date: 100 nos.
Total number of GROUT Piles 141 nos. 70.92%
Grout Pile " 8" PILE GROUT Today
Architectural
work
M & E Work
REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45
MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY
ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator BIG BREAKER 1
Site engineer 1 Safety office 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 grout machine 1
Weather
FAIR
Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 ON GOING EXCAVATION WORKS TO PLATFORM LEVEL
Housekeeping work inprogress,
REBAR WORKS AND FORWORKS IN PROGRESS ON FOUR PILE CAPS P41, P40, P39 AND P45
ON GOING EXCAVATION WORKS TO PLATFORM LEVEL
REMARKS :
8 CBP PILES HACKING DONE, 4 HACKED USING BIG MACHINE BREAKER PLUS 4 TRIMMING MANUAL HACKING
USING JACK HAMMER
noise level reading: AT 10:50AM TILL 10:55AM NOISE READING Exceeded, reading 92.3dB and 91.8dB 8 CBP PILES HACKING DONE, 4 HACKED USING
BIG MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER