0% found this document useful (1 vote)
315 views29 pages

Power Transformers Overview and Testing

The document provides an overview of pre-commissioning checks and tests that should be performed on power transformers before energization. It describes general checks that include inspecting the transformer arrangement and components, connections, earthing, controls, accessories and more. Functional checks of protective relays and instruments are also recommended, such as testing Buchholtz alarms, temperature indicators, tap changers and relays. Insulation resistance testing is highlighted as an important pre-commissioning test to check the soundness of the transformer insulation.

Uploaded by

mundra2010
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
315 views29 pages

Power Transformers Overview and Testing

The document provides an overview of pre-commissioning checks and tests that should be performed on power transformers before energization. It describes general checks that include inspecting the transformer arrangement and components, connections, earthing, controls, accessories and more. Functional checks of protective relays and instruments are also recommended, such as testing Buchholtz alarms, temperature indicators, tap changers and relays. Insulation resistance testing is highlighted as an important pre-commissioning test to check the soundness of the transformer insulation.

Uploaded by

mundra2010
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

POWER TRANSFORMERS – OVERVIEW –

Cover this document an important overview about Power


Transformers provides a main ideas of Power Transformers for
Distribution or Substations areas for instance. Lest go to play
information about it, we recommend to read this

2.1 Introduction
Transformer is the most important unit in an electrical
distribution network. All transformers are subjected to thorough
tests at the manufacturer’s works before despatch to the
destination of erection.Due to limitations in transport, large
capacity transformers are dis-assembled into various components
before despatch. At site, the transformers are re-assembled with
the various components like bushings, coolers, conservator etc.
and then the internal body is dried out to remove the surface
moisture sticking to the paper insulation during exposure at site.
As erection of transformers involve assembly of various
components, pre-test inspection of transformers have greater
importance than other parts of an electrical system. The following
paragraphs explain the pre-test inspections/pre-commission
checks and the pre-commission tests to be conducted on power
transformers prior to energisation of the unit.
2.2 Recording the salient parameters
As the service life of a transformer is expected to cover very many
years, it is necessary to record the salient parameters of the
transformer for future reference. Rated capacity, rated voltage
ratio,connection, make, maker’s serial number, year of
manufacture, date of completion of erection,insulation dry out
details at site etc. may be documented in a register as permanent
record. It is also necessary to record the serial number, rating and
make of various components like bushings, tap changer, tap
changer control cubicle, cooler control cubicle, cooling fans, oil
pumps, Buchholtz relay,temperature indicators, heat exchangers,
oil flow meter, water flow meter, pressure gauges, oil level gauge
etc. For easy reference, the details of the main body and various
components may be recorded in separate pages of a register. This
register will serve as a record of the service of the
transformer.Details of replacement of components may also be
recorded in the same register.
2.3 Pre-commission checks
Before commencing the pre-commission tests, it is necessary to
visually inspect various parts,components and accessories of the
transformer and also to conduct operational check for various
protective devices. Check lists may be followed for the visual
inspection and the operational checks so that the pre-commission
checks are conducted in a systematic manner and also that no
check/test is omitted. Model check lists for General checks and
Functional checks are given at the end of thischapter in Appendix
2.1 and 2.2 respectively.
2.3.1 General checks
(i) General arrangement
The General arrangement of the electrical installation shall be
checked for concurrence with the
scheme approved by the Department of Electrical Inspectorate.
Special emphasis may be given to the
following:
· size of cables
· size of bus bars
· size of bus trunking
· size of earthing conductors
· adequacy of various clearances
· spacing between supports
· ventilation
· oil drain facilities
· fire protection walls
· fire fighting arrangements
(ii) Terminations
The transformer terminal connections may be checked for the
following:
· flexibility and area of cross section of flexible connections at
bushings
· clearances of live jumper connections from transformer tank and
accessories
· socket size
· perfection of crimpings
· tinning of contact surfaces to prevent bimetalic action
· clearances inside cable end box
· clearances of bus bar trunking
· conformity of cable end box with the relevant IP( Ingress
Protection) classification
· correctness of cable glanding and adequacy of cable gland
earthing or pig tail
· support of cables at terminations and unsupported lengths
(iii) Perfection of connections
Connections to the following shall be checked for proper surface
contact, seating and tightness.
· to bushings
· to the tap changer
· to earth leads
· to control and protective cables
· to thermometers
(iv) Earthing

Check the size of earthing conductors, tinning of contact surfaces,


area of contact and seating,effectiveness of bolting, socketing,
riveting, welding etc.for the earthing of the following:

· Duplicate earthing for neutral and body

· Main tank and top cover


· Fan motors
· Pumps
· On Load Tap Changer (OLTC) chamber
· Tap changer driving gear
· Divertor switch
· Cable glands/termination
· Marshalling box
(v) Control cable connections
Check the control cable connections between the following
· transformer accessories and marshalling box
· marshalling box and sub-station panel
· tap changer control cubicle and sub-station panel
(vi) Radiator
Check the radiator for release of air and position of valves. The
valves shall be in open position.
(vii) Main conservator and OLTC conservator
Check the oil level in the main conservator and OLTC
conservator . The conservator shut off valve in the Buchholtz relay
pipe line shall be in open position.
(viii) Bushings
Check the oil level in the bushings if sealed bushings are used.
Release air from bushings if air release plugs are provided.
(ix) Breather
Check the oil level in the oil seal of the breather. Check the colour
of the silica gel in the breather .
(x) Cooler units, fans and pumps
Check fans and pumps for proper mounting. The number of fans
and their position on the radiators shall be in conformity with the
general arrangement drawings.
· Check the direction of rotation of cooling fans and pumps
· Check the direction of oil flow
· Check flow of water in heat -exchangers
· Measure the Insulation Resistance (IR) of fans and pumps
· Check the settings for operation of fan motors and oil pumps
· Check the cooler unit for correct indication of oil flow and setting
of the thermometer
(xi) Winding Temperature Indicator (WTI) and Oil Temperature
Indicator (OTI)
· Check whether thermometer pocket is filled with oil

· Check whether the connections of the CT for winding


temperature indicator to the thermometer pocket is properly
made as per the instructions given on the WTI terminal box.
· Check whether the contacts of WTI and OTI for alarm and trip
are set at required temperatures depending upon ambient
temperature and loading conditions. For oil filled transformers,
the maximum permissible temperature rise above the ambient
temperature is usually taken as 450C for oil and 550C for
winding. In the case of cast resin transformers, the alarm contact
of the winding temperature relay is usually designed to operate at
1400 C and trip contact at 1600 C for transformers upto 1000
kVA. For higher ratings, the temperatures are 1600 C and 1800C
respectively.
· Calibration of the WTI/OTI may be checked with hot oil.
Working of the WTI/RTD repeaters shall be checked at the
control room.
(xii) Buchholtz relays
· Check the angle of mounting of the Buchholtz relay using a spirit
level
· Check the floats for free movement
· Release air in the Buchholtz relay
· In the case of forced oil cooled transformers, make sure that the
Buchholtz relay does not operate when the pumps are switched on
xiii) Magnetic Oil Level Gauge
Move the float level of the oil level indicator up and down between
the end positions to ensure that the mechanism does not get stuck
at any point. The low oil level alarm of the gauge shall be checked.

(xiv) Arcing horn gap

Check arcing horn gaps of bushings for conformity with standard


values. The standard values are given below:

(xv) Tap changer


Check the sequence of operation of the tap changer for the
following:
· manual operation
· local electrical operation
· remote electrical operation
· parallel operation

(xvi) General inspection


i. Heaters in cubicles, conservator, etc. shall be checked
ii. Any other alarm/trip, contacts of flow meters, differential
pressure gauges, etc. shall be checked
iii. In the case of water cooled transformers, the pressure gauge
readings on water and oil sides shall be checked to ensure that the
water pressure is less than the oil pressure. The quantity of oil and
water flow shall not be less than what is specified
iv. The angle of protection of the lightning shield provided for
outdoor transformers shall be checked. The angle shall be less
than 30 degrees
v. Check whether roller blocks are provided for the rollers of the
transformer
2.3.2 Functional checks
After the visual inspection is complete, it is necessary to test
proper functioning of various protective
relays and instruments. The following functional checks may be
carried out.
1. Check the operation of the Buchholtz alarm and trip by
injecting air through the test pet cock.
2. Test the OTI for alarm and trip.
3. Test the WTI for alarm and trip.
4. Check the working of the WTI / RTD (Resistance Temperature
Device) repeaters at the
control room.
5. Test the OLTC – Oil surge relay for trip.
6. Check alarm for low oil level .
7. Check the REF relay for current setting
8. Check the differential relay for main and bias settings
9. Check the back up over current and earth fault relays for
current and time.
10. Check the over voltage relay for voltage and time.
11. Check the instantaneous over voltage relay for voltage.
12. Check the over fluxing relay for voltage, frequency and time.
13. Check the cooler unit for
· over current setting of fans
· over current setting of oil pumps
· cooler supply failure alarm

· fan/pump trip alarm

.any mal- operation of the transformer Buchholtz relay when all


the oil pumps are switched on simultaneously in forced oil cooled
transformers

2.4 Pre-commissioning tests


2.4.1 Insulation Resistance test
Insulation Resistance test is the simplest and most widely used
test to find out the soundness of insulation between two windings
or between windings and ground. Insulation resistance is
measured by means of insulation testers popularly known as
‘Megger’. The ‘Megger’ consists of a D.C power source (hand
operated or electrically driven D.C generator or a battery source
with electronic circuit ) and a measuring system. Microprocessor
based insulation testers are also now available. The insulation test
reveals the condition of the insulation inside the transformer. The
insulation resistance values are affected by temperature, humidity
and presence of dirt on insulators and bushings.
Selection of Insulation Testers
Insulation testers with test voltage of 500, 1000, 2500 and 5000
V are available. The recommended
ratings of the insulation testers are given below:

Factors influencing IR value


The IR value of transformers are influenced by
1. surface condition of the terminal bushing
2. quality of oil
3. quality of winding insulation
4. temperature of oil
5. duration of application and value of test voltage
Different IR values monitored in transformers
The following IR values are monitored in transformers
1. winding to ground. eg. HV to LV and earth connected together
LV to HV and earth.
2. winding to winding. eg. HV to LV
3. all windings to ground .eg. HV and LV to earth.

Steps for measuring the IR


1. Shut down the transformer and disconnect the jumpers and
lightning arrestors.
2. Discharge the winding capacitance.
3. Thoroughly clean all bushings
4. Short circuit the windings.
5. Guard the terminals to eliminate surface leakage over terminal
bushings.
6. Record the temperature.
7. Connect the test leads (avoid joints).
8. Apply the test voltage and note the reading. The IR. value at 60
seconds after application of the test voltage is referred to as the
Insulation Resistance of the transformer at the test temperature.
Minimum value of IR
The following values of IR at 30deg. C can be considered to be the
minimum requirement for new oil
filled transformers.

The transformer IR values in oil drained condition will be 15 to 20


times more than in oil filled condition.
Influence of temperature on IR
IR. values decrease sharply with the rise in temperature of the oil.
The following correction factors may be used for arriving at the IR
value with difference in temperature.
Interpretation of Insulation Resistance value.
While interpreting IR values, importance shall be given to the
variation of the values over a period of time rather than absolute
values. For conclusive analysis, use only results from tests
performed at identical conditions as IR values are affected by
value of test voltage, temperature of oil, duration of application of
voltage, humidity, extent of stress applied etc. IR values recorded
over a period of time may be plotted as a curve to study the
history of the insulation resistance. A curve showing a downward
trend indicates a loss of IR due to unfavourable conditions such as
oildeterioration, excessive moisture in paper,
deterioration/damage to terminal bushings etc. A very sharp drop
is a cause for concern and action shall be taken to ascertain the
exact cause of insulation failure and for corrective steps.
Points to note
1. Transformers with OLTC have lower IR values when compared
with transformers with off circuit tap changer.
2. Auto transformers have lower IR when compared to two
winding transformers.
3. Transformer windings with graded insulation have lower IR
when compared to fully
insulated windings.
4. If the non-measured winding terminals are not guarded, the
megger will give a low reading.
5. Avoid meggering when the transformer is under vacuum.
2.4.2 Dielectric absorption and polarisation index tests
Dielectric absorption and polarisation index tests give a good
indication of the condition of the insulation. This test is based on
the comparison of absorption characteristics of good insulation
versus absorption characteristics of humid or contaminated
insulation.
Instruments/materials required
Motorised or electronic insulation testers of appropriate voltage
Stop watch
Logarithmic paper
Procedure for test
In this test, a test voltage is applied for an extended period of
time, usually thirty minutes, using a megger of appropriate
voltage. The megger readings are taken every 10 seconds for the
first minute and thereafter every minute – upto 30 minutes. The
procedure for measurement of IR under para 2.4.1. is followed
here. Hand cranked instruments are not suitable as continuous
application of voltage is not possible with such instruments.
Motorised or battery operated insulation testers are used for the
test. A curve is drawn showing the variation in the value of IR.
against time on a logarithmic paper. The resultant curve is known
as dielectric absorption curve. A typical dielectric absorption
curve is shown in fig. 2.1.
Polarisation Index is the ratio of Insulation Resistance at 10
minutes to Insulation Resistance at 1 minute of application of test
voltage.
Polarisation Index =Insulation Resistance at 10
minutes/Insulation Resistance at 1 minute.
 

Interpretation of Polarisation Index and Dielectric Absorption


Curve
A steady increase in insulation resistance with continuous
application of test voltage indicates that the insulation is clean
and dry. Flat or ambulated curves demand reconditioning of the
insulation. Polarisation index is a good appraisal of the condition
of the insulation.

The following are the guidelines for evaluating the condition of


transformer insulation with respect to Polarisation Index values.
Polarisation indices with respect to insulation resistance between
HV and LV + earth , LV and HV+ earth , earth and HV+LV are
evaluated to ascertain the real condition of the transformer
insulation.
2.4.3 Two Voltage Test (Step Voltage Test)
This test is an extension of the dielectric absorption test. This has
been recommended as a more conclusive indication of presence of
moisture. Two separate dielectric absorption tests made at
different voltages help to detect moisture in the winding. The
higher test voltage should be about 4 to 5 times the lower one,
(eg.2500 V and 500 V) but should not be so high as to damage the
insulation. A wide spread between the two dielectric absorption
curves indicates presence of moisture. If the insulation resistance
value decreases substantially at a higher voltage, say more than 25
percent, it is a reasonable indication of presence of moisture in
the insulation system.
2.4.4 Measurement of Tan delta
Various insulation resistance tests explained above indicate
mainly the surface conditions and presence of moisture in the
insulation. Measurement of loss factor, commonly referred to as
tan delta reveals the internal condition of the insulation. With
alternating currents, the absorption of the dielectric is intimately
connected with the loss of power in the dielectric. This loss within
an insulation structure is associated with the oscillation of polar
molecules trying to orient themselves with the alternating electric
field. Hence current flowing through the insulation leads the
voltage by some angle which is slightly less than 90 degrees. This
small angle between pure capacitive current and actual current
represented by d (delta) is known as loss angle. The dielectric loss
in an insulation is given by V2 w C tan d and hence proportional
to tan d. If the insulation is perfect, the characteristic of tan delta
versus the applied voltage is almost a horizontal line. If voids have
crept in the insulation during manufacture or service, there will be
substantial increase in tan delta with the applied voltage. Hence
the absolute values of tan delta in a commercially manufactured
equipment have comparatively little practical significance. But the
variation in tan delta – ie. D tan delta – with respect to time is
very important. The values found during maintenance testing
should be compared with the initial values recorded before
commissioning the equipment. A stable value of tan delta is
indicative of insulation stability and small increase is indicative of
normal ageing. Tan delta is
measured using tan delta measuring equipment.
2.4.5 Transformer Ratio Test
Transformer ratio test is conducted to ensure that the turns ratio
tally with the name plate details and also that tap changer
connections are done correctly. Ratio test is done using a
transformer turns ratio tester or with voltmeters. With the turns
ratio tester, the turns ratio is directly read on the tester for each
tap and for each phase of the winding.The turns ratio can also be
tested by applying a single phase ac voltage (approximately 230V)
on the HV side and measuring the voltage on the low voltage side
at all tap positions.
The results of the voltage ratio test may be recorded in tabular
form as given below:

Voltage ratio test ( by voltmeter )

2.4.6 Short circuit current measurement


This test is carried out as a check for any loose contact in the tap
changer, lead connections etc. In this test, all the 3 windings in
the LV side of the transformer are short circuited. All contacts in
the tap changer, lead connections and terminals are checked for
proper contact. From a variable voltage source, a 3 phase
balanced low voltage a.c supply is applied to the HV winding at
rated tap and the current measured. The current measured at
rated tap should tally with the calculated value of HV current at
the applied voltage.
The value of HV current at the applied voltage is calculated as
follows:
Repeat the test at different tap positions by lowering and raising
taps. The current measured in the HV winding should tally with
the calculated value of HV short circuit current.

Wide difference between the measured and calculated values of


HV short circuit current is an indication of loose contact in tap
changer or lead connections.
2.4.7 Measurement of Magnetising current
The magnetising current is measured to test any fault in the
magnetic circuit and winding. The measured values are compared
with the factory test values. A balanced three phase 415V ac
supply is applied to the LV winding and the simultaneous current
readings of the three phases are taken using low range a.c
ammeters of the same accuracy class. For a core type transformer,
the middle phase magnetising current will be approximately half
that in other windings. In YyO, Dy1 and Dy11 connections, the
currents in ‘u’ and ‘w’ phases will be nearly double the current in
‘v’ phase. In a Yd1 connected transformer, currents in ‘v’ and ‘w’
phases will be nearly equal and the current in ‘u’ phase more than
that in ‘v’ and ‘w’ phases. In a Yd11 connection, currents in ‘u’ and
‘v’ phases will be nearly equal and the current in ‘w’ phase more
than that in ‘u’ and ‘v’ phases. If the measured values widely differ
from the above values or from the factory test values, there is
reason to suspect some defect in the transformer core and the
manufacturer may be consulted. The
measured values of magnetising current may be used as bench
marks for the service life of the transformer. Sample format for
recording the magnetising current is given below:

2.4.8 Test for magnetic balance


This test is done to find out the condition of stacking of core
laminations, tightness of core bolts and perfection of magnetic
circuit. The HV and LV sides are isolated by removing the bushing
connections. A single phase supply of nearly 230V is applied to
one phase of the star connected winding and the induced voltage
in othertwo phases are measured. The voltage may preferably be
applied on the HV winding, as applying voltage to LV winding
may induce very high voltage in the HV winding. If the HV
winding is connected in delta, the test may be conducted on the
LV side after taking necessary precautions against accidental
contact with the HV bushings.

When the voltage is applied to the middle phase, the induced


voltage measured on the two other phases should be
approximately equal. Where the voltage is applied to an extreme
phase, the induced voltage on the middle phase should be
substantially high when compared to the voltage induced in the
other extreme phase. In each test, the sum of the induced voltages
in two phases should be nearly equal to the applied voltage.
Tests may be carried out by connecting a series lamp (say 25
watts) at supply side to restrict higher current, if any. If the series
lamp glows brightly or the induced voltage readings in different
phases indicate zero or very low value or if the induced voltages
show abnormal variation from the expected values, fault in the
winding can be suspected.

For measuring the voltages, high impedance voltmeter like digital


multimeter should be used. The test may be repeated by applying
voltage to the second and third phases and measuring the induced
voltages in other phases. When the magnetic circuit is balanced,
there would be symmetry in the value of measured induced
voltages. The measured voltages may be recorded in the sample
format given below:

2.4.9 Phasor Group Test


Phasor relationship between HV and LV voltages is checked by
this test. Without earthing the winding neutral points,
interconnect one phase of HV winding – say 1U – to the
corresponding phase of LV winding -2U and apply a balanced 3
phase low voltage to the HV winding. The phase sequence of the
supply should be the same as the specified phase sequence of the
transformer winding. Connections for Dy 11 and Dy1 transformers
and the corrsponding vector groupings are given in figures 2.2
and 2.3. Measure the voltage between the primary and the
secondary terminals. The following requirements shall be fulfilled
depending on the vector group of the transformers.
If two transformers are available for test, the phasor groups can
be compared easily by applying voltage from same source to
identical bushings on the HV side and by measuring the voltage
between identically marked terminals on the LV sides with single
interconnection between either the neutrals or any one phase.
2.4.10 Test for Transformer Oil
Transformer oil is of petroleum origin and is used as a coolant and
dielectric in transformers. Transformer oil in good condition and
conforming to relevant standards will prevent deterioration of
transformer insulation. As the transformer oil is, to some extent,
exposed to air at site, it is always necessary to test the oil for
various characteristics before the transformer is put to service. As
the various tests for transformer oil are laboratory tests, details of
these tests are beyond the scope of this book. Test procedures for
various tests are given in the relevant standards of BIS, list of
which are given at the end of this chapter in para 2.6.
From the point of view of field tests, what is important is the
method of and precautions for collecting the transformer oil and
the limit values of various characteristics. However a rough test
on the moisture content of the oil can be made at site by
conducting a simple test, popularly called the crackle test. In this
test, a piece of steel tube of approximately 25 mm dia is closed at
one end and the closed end is heated to just under red hot . Now
the hot end is plunged into the oil sample with the ear close to the
open end. If the oil contains large quantity of moisture, a sharp
crackle will be heard.Dry oil will only sizzle.
Sampling of oil – General precautions
Since the results of the tests prescribed for transformer oil largely
depend on the impurities in the sample sent for testing, it is
essential to keep the oil free from any contamination. The
following precautions shall be taken while collecting samples of
transformer oil.
1. For collecting the sample, glass containers with glass stoppers
are preferred over metal type. Wax shall not be used for sealing
the containers. The stopper may be covered with a piece of cloth
packed with silica gel.
2. The container may be warmed to above the ambient air
temperature in order to avoid any condensation of moisture.
3. Before collecting the sample, all equipments used for handling
the oil must be washed with clean transformer oil. The oil used for
washing must be discarded.
4. Flexible steel hose may be used for handling the oil. Some kinds
of synthetic hoses are also suitable. Ordinary rubber hose should
not be used as oil dissolves the sulphur in the rubber and thereby
gets contaminated. The hose used must be clean and free from
dust, rust and scale.
5. The operator shall take special care to see that his hands do not
come in contact with the sample or the internal surface of the
container.
6. The transformer oil shall be protected against all kinds of light
radiation during transportation and storage.
Sampling procedure
1. Remove the valve shield if fitted.
2. Remove all visible dirt and dust from the valve with a lintfree
clean cloth.
3. Run off sufficient quantity of oil- say 1 litre – to eliminate any
contaminant that might have accumulated in the drain cock.
4. Rinse the container with the oil being sampled.
5. Fill the container by allowing the oil to flow against the side of
the containers to avoid air traps.

6. Close and seal the container and store the samples in a dark
place.
Evaluation of test results
Three samples of oil from the top and bottom of the tank are
tested for various characteristics. For transformers of capacity
below 1 MVA and where very high reliability is not expected the
five characteristics given in table 2.1 shall be invariably tested and
it shall be ensured that the test results are within the
minimum/maximum limits.
In the case of transformers where very high reliability is required
and in all cases where the capacity is 1 MVA or above, the
additional characteristics given in table 2.2 shall also be tested.
The test results shall be within the given limits.

2.4.11 Relay Tests


All protective relays , CTs, PTs and control wiring shall be tested
as explained under the chapter for protective relays. The relays
shall be set to suit the operating conditions and to coordinate with
other sections of the system. The relay test results shall be
documented for future reference.
2.5 Commissioning
After completing all the pre-commission tests given under section
2.4, the pre-test checks under section 2.3 are redone once again.
All the protective relays and circuit breakers are tested for proper
working. The relay settings are kept at a low value so that the
transformer will get isolated if there is any internal fault.Allow a
settling time of at least 24 hours for oil and then release air from
all points. Now the transformer may be test charged from the
incoming side on no-load and operated for about two hours.

Observe the transformer hum for any abnormality. Any vibration


or abnormal magnetising current may also be observed. After
continuous operation for about two hours, isolate the transformer
and check the gas operated Buchholtz relay for any gas collection.
Any dissolved air or air bubble that may be collected in the
Buchholtz relay may be released and the transformer charged
again on noload. All connected instruments may be checked for
any abnormal indication. Now gradually load the transformer to
full capacity and keep it under constant observation for at least 24
hours of operation. Check the oil and winding temperature at full
load and compare with factory test values. After four or five days
of service, test the oil for various characteristics, especially for
BDV. Any gas collection in the Buchholtz relay may also be
observed. If the test results and observations are found normal,
the transformer may be cleared for regular service. After the
transformer is put in service for some weeks with normal working
temperature, all sealed joints shall be re -tightened.
The results of the various tests shall be recorded and kept in the
station as a permanent record for future reference. Details such as
place of erection, date of commissioning, protection given to the
transformer etc. may be furnished to the manufacturer after
commissioning.

2.6 List of Indian Standards relevant to testing of Power


transformers

Appendix
 

You might also like