Net present value.
Lepton Industries has a project with the following projected cash
flows:
Initial Cost: $510,000
Cash flow year one: $135,000
Cash flow year two: $240,000
Cash flow year three: $185,000
Cash flow year four: $135,000
a. Using an 8% discount rate for this project and the NPV model, determine whether
this
project should be accepted or rejected.
b. Should it be accepted or rejected using a 14% discount rate?
c. Should it be accepted or rejected using a 20% discount rate?
ANSWER
(a)
NPV = - $510,000 + $135,000/1.08 + $240,000/1.082 + $185,000/1.083 + $135,000/1.084
NPV = - $510,000 + $125,000.00 + $205,761.32 + $146,858.96 + $99,229.03
NPV = $66,849.31, and accept the project.
(b)
NPV = - $510,000 + $135,000/1.14 + $240,000/1.142 + $185,000/1.143 + $135,000/1.144
NPV = - $510,000 + $118,421.05 + $184,672.21 + $124,869.73 + $79,930.84
NPV = - $2,106.17, and reject the project.
(c)
NPV = - $510,000 + $135,000/1.20 + $240,000/1.202 + $185,000/1.203 + $135,000/1.204
NPV = - $510,000 + $112,500.00 + $166,666.67 + $107,060.19 + $65,104.17
NPV = - $58,668.97, and reject the project