0% found this document useful (0 votes)
44 views2 pages

Payback Period 2

The document calculates the payback periods for projects E, F, G, and H. Project E has a payback period of 4 years, project F has a payback period of 2.45 years, project G has a payback period of 2.5 years, and project H has a payback period of 3.5 years. With a cutoff period of 3 years, projects F and G would be accepted since their payback periods are within 3 years, while projects E and H would be rejected since their payback periods exceed 3 years.

Uploaded by

Sharulatha S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views2 pages

Payback Period 2

The document calculates the payback periods for projects E, F, G, and H. Project E has a payback period of 4 years, project F has a payback period of 2.45 years, project G has a payback period of 2.5 years, and project H has a payback period of 3.5 years. With a cutoff period of 3 years, projects F and G would be accepted since their payback periods are within 3 years, while projects E and H would be rejected since their payback periods exceed 3 years.

Uploaded by

Sharulatha S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

2. Payback period. What are the payback periods of Projects E, F, G and H?

Assume all the


cash flows are evenly spread throughout the year. If the cutoff period is three years,
which projects do you accept?

ANSWER
Project E:
Year One: -$40,000 + $10,000 = $30,000 left to recover
Year Two: -$30,000 + $10,000 = $20,000 left to recover
Year Three: -$20,000 + $10,000 = $10,000 left to recover
Year Four: -$10,000 + $10,000 = fully recovered
Year Four: $10,000 / $10,000 = full year needed
Payback Period for Project E: 4 years
Project F:
Year One: -$250,000 + $40,000 = $210,000 left to recover
Year Two: -$210,000 + $120,000 = $90,000 left to recover
Year Three: -$90,000 + $200,000 = fully recovered
Year Three: $90,000 / $200,000 = 0.45 year needed
Payback Period for Project F: 2.45 years
Project G:
Year One: -$75,000 + $20,000 = $55,000 left to recover
Year Two: -$55,000 + $35,000 = $20,000 left to recover
Year Three: -$20,000 + $40,000 = fully recovered
Year Three: $20,000 / $40,000 = 0.5 year needed
Payback Period for Project G: 2.5 years
Project H:
Year One: -$100,000 + $30,000 = $70,000 left to recover
Year Two: -$70,000 + $30,000 = $40,000 left to recover
Year Three: -$40,000 + $30,000 = $10,000 left to recover
Year Four: -$10,000 + $20,000 = fully recovered
Year Four: $10,000 / $20,000 = 0.5 year needed
Payback Period for Project H: 3.5 years
With a three year cut-off period, ACCEPT F and G, REJECT E and H.