Ruwanpura Expressway Project – Phase I (From Kahathuduwa to Ingiriya)
Rate Analysis for Basic Work Items
Item No:
Work Item: Mark-up:
Assumed Quantity for rate build-
Unit:
up:
HSR Items:
Price Code Labour Component Unit Quantity Rate Amount
Total Cost for Labour - A
Price Code Plant/ Equipment Component Unit Quantity Rate Amount
Total Cost for Plant/ Equipment - B
Price Code Material Component Unit Quantity Rate Amount
Total Cost for Material - C
Price Code Miscellaneous Cost Component Unit Quantity Rate Amount
Total Cost for Miscellaneous - D
Estimated Direct Cost - E (A+B+C+D)
Head Office Overhead - F 0%
Site Office Overhead - G 0%
Profit - H 0%
Total for Unit - I (E+F+G+H)
Rate per Unit
Ruwanpura Expressway Project – Phase I (From Kahathuduwa to Ingiriya)
Say Rate