1. Compute the total effort, schedule and overall project productivity
associated with the development of organic-mode software products of
the following sizes: 5000 DSI, 20,000 DSI and 50,000 DSI.
Solution:
1. 5000 DSI
Effort:
MM = 2.4(5)1.05 = 13 Man-Months
Schedule:
TDEV= 2.5 (13)0.38 = 6.62 months
Productivity:
5000/13 = 384.6 DSI/MM
Or by roundoff productivity = 385 DSI/MM
2. 20,000 DSI
Effort:
MM = 2.4(20)1.05 = 55.75 = 56 Man-Months
Schedule:
TDEV= 2.5 (56)0.38 = 11.54 = 12 months
Productivity:
20000/56 = 357.14 DSI/MM
Or by roundoff productivity = 357 DSI/MM
3. 50,000 DSI
Effort:
MM = 2.4(50)1.05 = 145.92 = 146 Man-Months
Schedule:
TDEV= 2.5 (146)0.38 = 16.61= 17 months
Productivity:
50000/146 = 342.46 DSI/MM
Or by roundoff productivity = 342 DSI/MM
2. Suppose you are planning the maintenance of a 10-KDSI organic-mode
payroll processing software product, assuming that it will annually add
3000 DSI and modify 2000 DSI. How many man-months will be
required for annual maintenance and what FSP level of effort should be
anticipated?
Given:
Delivered source of Instructions = 10 KDSI
Annually addition = 3000 DSI
Modification = 2000 DSI
Basic Annual Maintenance effort (MM )AM = ?
Full Time Software Person ( FSP ) = ?
Solution:
1. Basic Annual Maintenance effort (MM )AM
(MM)AM = 1.0 (ACT) (MM)D
So, to find MM first we have to find ACT ;
Annual Change Traffic(ACT ) = ( 3000 + 2000 ) / 10,000
= 0.5
(MM )D = 2.4 (10 )1.05 = 26.92 = 27
Putting Values in Annual Maintenance Effort Formula;
(MM)AM = 1.0 (0.5 ) (27)D
= 13.5 MM
2. Full Time Software Person ( FSP )
(FSP)M = (MM)AM /12
= 13.5 / 12
= 1.125 FSP
3. Suppose you are developing a software product of organic type. You have
estimated the size of the product to be about 100,000 lines of code.
Compute the nominal effort and the development time.
Given:
Lines of codes = 100,000 DSI
= 100 KDSI
Mode = Organic mode
Solution:
1. Nominal Effort (MM )
MM = 2.4 (100 KDSI )1.05 = 302.14 Man-Months
2. Schedule (TDEV) =
TDEV = 2.5 (302.14 MM )0.38 = 21.89 months