RADIATOR INSTALLATION Checklist

The document provides a 17-step checklist for installing a transformer radiator. The checklist includes steps like raising the radiator safely, cleaning surfaces, removing blind lids and packing, aligning and tightening the radiator valve, torquing bolts, and installing supports. Once complete, the project quality assurance supervisor signs off on the checks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
949 views2 pages

RADIATOR INSTALLATION Checklist

The document provides a 17-step checklist for installing a transformer radiator. The checklist includes steps like raising the radiator safely, cleaning surfaces, removing blind lids and packing, aligning and tightening the radiator valve, torquing bolts, and installing supports. Once complete, the project quality assurance supervisor signs off on the checks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Doc.

No:

Review:01

Date: 25/02/2021

Page 1 of 1 TRANSFORMER RADIATOR INSTALLATION


CHECKLIST

No: TRANSFORMER
CHECKED WILKINS
RADIATOR INSTALLATION CHECKLIST
YES NO PERSONNEL”s
1 Raise the radiator from its storage position, and pay attention to avoid
damages to the other radiators with the tools used for hoisting.
2 Remove the blind lid and the packing from the radiator
3 Check visually the interior of the radiator.
4 Clean the surface of the assembly clamp of the radiator.
5 Remove the purge stopper (2) indicated below.
6 Remove the blind lid and the packing placed on the strangulation
valve of the transformer
7 Clean and if possible paint the surface of clamp of the valve from the
radiator.
8 Clean the groove for gasket of the valve. Apply a small amount of
adhesive in the groove and put the new specified gasket
9 Lift the radiator with a crane.
10 Move the radiator by hand, tilt it and drain any residual oil.
11 Align the radiator to the radiator valve
12 Align the radiator valve and the surface of the clamp of the radiator
and tight it with nuts.
13 Tight a pair of nuts located diagonally one after the other in order to
tight them evenly
14 Tight firmly until the radiator valve and the radiator clamp become
one whole unit.
15 Torque all the Eight(8) bolts 112 N/m
16 Install the purge stopper (2) indicated below. if the tank is filled with
nitrogen, if the tank is partially full with oil. See Fill up of radiators
17 Once finished with the assembly of the radiators, place the supports
symmetrically and the clamps of the radiator.

1
RADIATOR PARTS

WILKINS SITE SUPERVISOR - REMARKS

CHECKS ACCEPTED BY:


PROJECT QUALITY ASSURANCE WILKINS SITE SUPERVISOR
Name:
Signature:
Date: