Teaa Case Study-Jz
Teaa Case Study-Jz
Submit one case study of 3000 words. The focus of the case study must be on a single
project or piece(s) of work undertaken in the last 24 months. The project you choose MUST
allow you to demonstrate technical competencies from your chosen pathway, and how you
used the competency skills. It must be written as a professional report.
Name of case study: Mitigation of Project Delays Caused by Design Issues at the
Estates at Acqualina
Date the project or piece(s) of work were carried out: October 2018-October 2020
Confidentiality statement
The following case study contains confidential information included for the purpose of the
Assessment of Professional Competence. (Suffolk Construction), hereinafter termed
(“the client/ Suffolk Construction/Board or Director”) and (Suffolk Construction) have
given their consent to disclose details for the case study on the basis that the information is
not to be used for any other purpose or by any person other than those authorised by the
Royal Institution of Chartered Surveyors (e.g. staff and assessors).
Contents:
1. Introduction
2. My Approach
3. My Achievements
4. Conclusion
Total Word Count: 2998 words (Not including content list or Appendices)
1|Page
1. Introduction
The Estates at Acqualina project (TEAA) is comprised of two 55-story high-rise luxury
condos with a five-story Villa in between. Villa serves as the amenities facility for the tower
residents, which includes Bowling Alley, Ice Skating Rink, Theatre, Children’s Room, Teen’s
Room on Level 1, a full service restaurant on Level 2, Wall Street Room and Residents Club
on Level 3, Lounge and Bar on Level 4, and Health Club on Level 5.
TEAA has two phases. South Tower and Villa are phase I and North Tower is Phase
II. Phase I started in October 2018 and is projecting to finish by August 2021. Phase II
started in April 2019 and is projecting to finish by March 2022.
I first started this project with Coastal Construction in October 2018 when Moss
Construction was terminated by Owner. When Coastal Construction took over this job, the
project just finished deep soil mix and no subcontractors had been signed up. My initial role
in the project was the project manager, responsible for the procurement of subcontracts for
the project, including drafting detailed scopes of work, preparing Request for Proposal (RFP)
packages, evaluating and levelling bids, conducting value engineering analysis, and issuing
final Recommendation to Award (RTA). As more subcontractors were on board, my
responsibilities evolved into managing coordination among subcontractors, design and
scope changes, reviewing and negotiating change orders, reviewing and processing
submittals, RFIs and managing procurement of deliverables, and issuing Monthly Project
Construction Report with my area focused on the Villa and Lobbies.
2. My Approach
Data from AT Kearney (2017)1 show that six out of ten projects run into over-budget
and behind-schedule. Project delays can be caused by a multitude of events, and the cost
2|Page
magnitude of project delays vary significantly on both budget and schedule. Thus, I am
committed to identify challenges and find the best methods for best practices and disciplined
execution for the project’s success.
With the privileges of working for both Coastal Construction and Suffolk Construction
for the same project, I experienced the uniqueness of this project and identified the following
key delay challenges for this project.
Budget allocated for Villa was $400/SF, which was before the drawings were
developed. After 75% construction drawings were issued, Coastal Construction sent the
drawings out for bid. When the bids came back, the total cost for Villa came to be double the
budget. Owner Representative expressed the budget concerns and made it clear to Coastal
Construction that it was imperative that we found pathways to meet the budget.
Towards the end of September 2020, the restaurant operator visited the jobsite and
initiated various design changes to the level 2 restaurant. Due to these design changes,
designers took much longer to approve millwork shop drawings. The Restaurant Operator,
STA architects and Owner Representative met multiple times to decide on the extent of the
changes, but it was not until beginning of November 2020, Owner Representative finally
informed Suffolk Construction of the discussions of the Restaurant changes.
3|Page
All these challenges put the project at the risk of either over-budget or behind
schedule. How to mitigate these delay risks caused by design is key to success.
3. My Achievements
The risk of project delays is always present regardless of project planning, but there
are strategies that can mitigate the likelihood of delays as well as the magnitude of the delay
if issues are identified prior to and during construction. Planning, communication and
assessment of the project and associated risks are the general principles behind the
strategies. While some causes of project delays are out of the control of both the Owner and
Contractor, proper project planning and execution can help mitigate these risks. Other
causes of project delays can be anticipated and mitigated from the very beginning of the
project, especially during the procurement process.
To mitigate the potential delay impact of design and budget issues during the
procurement process, the Owner, Designer, and General Contractor can and should
proactively work together during the needs assessment and design phase to flush out all
user needs and potential design and cost challenges related to the project. Further, the
General Contractor should review the proposals received from Subcontractors and
communicate openly with the Owner and Designer on areas that are unclear, impractical, or
unrealistic given the budget suggested. On the same note, the Owner should review prior
request for proposals for similar projects and use learned lessons of what was experienced
during the execution of those projects.
To help the design team to find potential pathways to meet the budget for the Villa, I
created a spreadsheet identifying the major features of the design by room and by level. For
each major feature, I identified the total construction cost based on the proposals received
from the market. Then, I added a column, identifying the credit required for each
feature/room to meet the budget.
1. Laser cut backlit swan panel walls at Grand Stair changed to Venetian plaster. The
cost for the swan pane wall finishes was over $500,000 per level, which is $2 million
4|Page
for all levels. Owner expressed that the Grand Stair would not be used as often as
most people would take the Grand Stair elevator to go up and down instead of the
stairs. As a result, the laser-cut backlit swan panel wall finishes were deleted and
replaced with Venetian plaster finishes.
2. 3Form resin wall finish changed to MDF with emulsion paint finish at the Bowling
Alley wall. Coastal expressed the concern that the ball might hit the Bowling Alley
walls and completely destroy the high-end 3Form resin wall finishes. In addition, no
one would notice that 3Form resin wall finish from far. This wall finish was then
agreed to downgrade to MDF wall with emulsion paint finish.
3. 3Form resin material for front desk finishes changed to MDF with emulsion paint
finish at front desk at Villa. Reddymade architects agreed to change it to a less
expensive material while still maintaining the look of the front desk.
4. Backlit Aktural panels changed to wall covering at the Galleries and Teen’s Room.
Based on proposals received from subcontractors, backlit Aktural panels were
approximately $300/SF installed. Most of the Aktural panels were inside the Teen’s
room and on one side of the corridor walls on Villa Level one. In the end, Reddymade
architects agreed to change them to wall covering finishes.
5. Underside of the Grand Stair stone finish changed to plaster finish. Originally, the
underside of the Grand Stair had the same stone finish as the walking side of the
Grand Stairs. As no one would ever walk the underside of the stairs, there was no
need to have a stone finish. This was then changed to a white plaster finish. The
linear light on the steps of the stairs was also deleted.
6. Curved metal inlay in Terrazzo changed to straight metal inlay. Originally the metal
inlay in Terrazzo was curved, which requires bending and therefore more costly.
Reddymade architects agreed to change it to straight metal inlay with the design
intent largely maintained.
7. Frameless glass enclosure with fire sprinkler system on both sides of Residents Club
perimeter walls changed to two-hour fire-rated drywall. Fire-rated 12’ high glazing
wall came back to be extremely costly with concealed fire sprinkler heads on both
sides of room. Reddymade architects agreed to downgrade it to two-hour fire-rated
drywall finishes.
8. Elevator Cab Interior Finishes Value Engineering. The allowance budget for cab
interior finishes was $75,000 per cab and $525,000 for seven cabs. The interior cab
wall finish was laminated glazing with woven fabric in between, which cost over $1
million with the initial feedback from the market. Reddymade architects agreed to
reduce this wall finish from four walls to two walls, and they also picked four different
types of metal woven fabric finishes.
5|Page
Another example of mitigating design and budget discrepancies is the buy-out of
elevator cab finishes. In August 2020, I followed up the pricing of the woven metal laminated
in glass interior cab finish with Otis, the Elevator Subcontractor. In September 2020, it came
back to be between $569,000 and $852,000, which was still higher than the budget
(Appendix D1). I requested price breakdown from Otis, but the cost did not come down as of
September 2020. I then requested Otis to price with three interior cab finish subcontractors.
This gave Owner twelve (12) options to pick from and greatly improved the cost
effectiveness. In addition, the ID drawing showed two Cab Operating Panel (COP) with the
second one being a redundant one. Avoidance of all non-essential cost, especially those for
which the client will not pay is important. I revised the bid tab and put the cost of supplying
and installing the second COP as an add alternate and requested Reddymade and Owner to
review for final deletion and it was agreed that the second COP was not needed at the cost
of $140,000. Furthermore, I removed Otis’ standby time from the base bid and directed them
to apply the run time included in 3.71.3 of their base contract to supervise interior cab
finishes installation.
As a result of these adjustments, the November 2020 bid tab showed many of the
options were under budget with minimum two subcontractors came under budget in each
material selection (Appendix D2). The success of this buy-out is measured by the success
of achieving the required deliverable through the approved budget and the approved date of
delivery. This is achieved by studying carefully the contractual documents, providing
effective cost management, conducting open communication with all parties, committing to
achieve the contractual demands and overcoming project constraints represented in any
deviation that affects scope, time or cost. This approach greatly improved the relationship
with Ownership.
Srdic & Selih (2015)2 stated that to avoid project delays “more attention should be
paid to … producing adequate design drawings and documents.” Among the most common
causes of delays that I have noticed during the construction phase of projects is
uncoordinated or incomplete design drawings. Several reasons can be attributed to design
drawings not being actually “ready for construction”: poor quality control from the designer of
record, pressure from owner for design drawings to be delivered on unrealistic timelines, and
lack of thorough review by the General Contractor during the bid phase. Other reasons can
6|Page
be that the design is one-of-a-kind or first-of-its-kind and unclear owner and user
requirements being relayed to the designer.
In order to get the uncoordinated Steidl design issue resolved, we had to receive
design drawings for Steidl panels due to it being one-of-a-kind artwork. First, I put this as an
issue in the Constraint Log, which was then discussed in the weekly Wednesday Owner
Architect Contractor (OAC) meeting. Meanwhile, I issued an RFI requesting this information.
In September 2020, Mayor of Munich had not received a contract for this scope of work.
However, in order to move forward, Owner’s representative immediately scheduled Zoom
calls with Mayor of Munich in Germany to discuss the information required. As weight
information was received for Steidl panels in the first Zoom meeting, I sent this information
to the drywall and framing subcontractor to start the calculations for structural supports of
the Steidl panels. However, lighting information was still pending after the first meeting. This
Zoom call with Mayor of Munich, Interior Designer, Lighting Designer, Low Voltage
Engineer, Electrical Engineer and Suffolk Construction continued for three weeks until we
received key electrical, lighting and low voltage information for field rough-in. I followed up
with each design team member for them to post official responses in Procore. This issue
was officially closed in November 2021 and by that time the drywall had been installed in the
lobby everywhere except the Steidl locations.
In November 2020, I heard that major changes were coming for Level 2 Restaurant
due to Operator changes. However, as nothing was officially transmitted to Suffolk
Construction advising Level 2 Restaurant design changes, I requested that Owner issue a
stop work order so we can officially stop Subcontractors from working on deleted items and
requested a subsequent meeting between Owner Representative, Suffolk Construction and
STA Architects to have a focused review for Villa Level 2 design revisions. This meeting was
7|Page
needed to be held immediately to review what approved submittals have been deleted and
stop work in these submittals. This meeting was also needed to review any/all disciplines
affected by these design revisions and determine any other items that were to be revised,
added or deleted as well. At the end of the meeting, we came up with a coloured drawing
showing the major design changes of Villa Level 2 and a Stop Work Order was received
shortly after (Appendix E).
The previous schedule developed with Coastal Construction was to release work into
fabrication in October 2020 and begin installation starting January 2021. Based on the
design changes on Villa level 2, a delay was experienced in millwork fabrication and framing
installation due to late design revisions. Therefore, Mortensen Millwork was unable to obtain
field dimensions in time to release this work as originally scheduled, which would push
TEAA millwork fabrication to the 1st quarter of 2021.
To mitigate the schedule delays, the framing installation and millwork fabrication
have to overlap to meet schedule. In these scenarios, I advised releasing work based on
Hold-to dimensions. This would allow Suffolk Construction to still maintain the fabrication
schedule in order to meet installation dates without waiting for framing work to be
completed. The add alternate for this service was $99,000.00 and I negotiated it down to
$64,680.00. As this service would provide a mutual benefit and help to maintain the original
schedule presented in the millwork package, I presented a change order to exercise this add
alternate in the subcontract, which was immediately approved by Owner. This change order
brought the required resources and provided an optimum work sequence in order to
maintain project schedule and achieve the project objectives. This is achieved by analysing
schedules, monitoring the project progress and performance, reporting the variances, and
recommending the required corrective actions.
4. Conclusion
In summary, design issues are a very common cause of project delays and project
delays are an inherent risk to both project budget and schedule. However, there are
strategies that help mitigate this risk and both the Owner and General Contractor can take
steps to mitigate the impact of delays during the procurement phases and construction
8|Page
phase of the project life cycle. These strategies include the importance of open
communication and establishing processes and priorities as a project team to ensure all the
parties’ interest are aligned. Planning for delays is the underlying theme of the risk mitigation
strategies. Project delivery teams have a responsibility to deliver their projects on-time and
under budget. Carefully assessing and preparing for potential project delays is part of that
responsibility.
Bibliography
Srdić, A & Selih, J. (2015). Delays in Construction Projects: Causes and Mitigation.
Organization, Technology and Management in Construction, Vol 7(3)2015. P.1383-1389.
9|Page
Case Study: Mitigation of Project Delays Caused by Design Issues at the Estates at Acqualina
Appendix A –
Competencies
Achieved
Appendix A - Competencies demonstrated in this case study
Please insert the mandatory, core technical and optional technical competencies
demonstrated in your case study. Please follow the format below and add more rows if
required, simply use copy and paste.
Project Finance
10 | P a g e
Case Study: Mitigation of Project Delays Caused by Design Issues at the Estates at Acqualina
Appendix B –
Steidl Renderings
27/04/20
Appendix B Steidl Renderings
Tale of
A
Fountains
Fire Engravings
by karl lagerfeld
The Estates at Acqualina
The Trump Group
n e A rt
Fi
d a t e d
t e s t up 2 0 20
La il 2 7 /
A p r
on
v e rs i
1
w: 1,83 m w: 1,83 m
h: 3,27 m h: 3,27 m
w: 6’ h: 9’ 10’’ w: 6’ h: 9’ 10’’
Panel C1 Panel C2
Panel E
North Lobby
w: 12’ 0” h: 9’ 10’’
Panel B w: 3,65 m h: 3,27 m
w: 38’ 9” h: 9’ 10’’
w: 11,81 m h: 3,27 m
w: 18,69 m h: 3,27 m
w: 61’ 4” h: 9’ 10’’
Panel A
Panel D
w: 24’ 0” h: 9’ 10’’
w: 7,31 m h: 3,27 m
South Lobby
15
27/04/20
27/04/20
Fountains
Fire Engravings
by karl lagerfeld
The Estates at Acqualina
The Trump Group
(ca. 3m)
9’ 10-1/8’’
61’ 0-1/4’’ (ca. 18,6 m)
2
27/04/20
Fountains
Fire Engravings
by karl lagerfeld
The Estates at Acqualina
The Trump Group
(ca. 3m)
9’ 10-1/8’’
23’ 11-13/16’’ (ca. 7,31 m)
3
27/04/20
(ca. 3m)
9’ 10-1/8’’
11’ 11-11/16’’ (ca. 3,65 m)
4
27/04/20
Fountains
Fire Engravings
by karl lagerfeld
The Estates at Acqualina
The Trump Group
(ca. 3m)
9’ 10-1/8’’
38’ 9’’ (ca. 11,81 m)
(ca. 3m)
9’ 10-1/8’’
5’ 12’’ (ca. 1,828 m)
6
27/04/20
(ca. 3m)
9’ 10-1/8’’
5’ 12’’ (ca. 1,828 m)
7
Case Study: Mitigation of Project Delays Caused by Design Issues at the Estates at Acqualina
Appendix C –
Key Materials/Design
Changes after Team
Meeting
Appendix C - Key Materials/Design Changes after the Value Engineering Process
8.Lobby Elevator Wall Finish Before 8.Lobby Elevator Wall Finish After
Laminated Glass with Metal Woven Fabric on all four walls Laminated Glass with Metal Woven Fabric on two walls
Case Study: Mitigation of Project Delays Caused by Design Issues at the Estates at Acqualina
Appendix D1 –
Elevator Cab Wall
Finishes Bid Tab
(Before)
Appendix D1 Cab Interior Finishes Bid Tab
PROJECT: The Estates at Acqualina XP = SUFFOLK PLUG BID DATE: 9/21/2020
LOCATION: Sunny Isles Beach, FL XS = PLUG FROM THIS SUB RECOMMENDED SUB:
TRADE: Elevator Cab Interior Finish XO = PLUG FROM OTHER SUB BUDGET AMOUNT:
Add Alternate
Touch Screen 5,000 5,000 5,000 5,000
BASE BID for Tower Cabs SUBTOTAL PER CAB 127,853.00 127,229.00 134,583.00 87,339.00
BOND AMOUNT ON BASE BID Excluded Excluded Excluded Excluded
TOTAL SOUTH TOWER AMOUNT BASE BID 511,412 508,916 538,332 349,356
TOTAL NORTH TOWER AMOUNT BASE BID 255,706 254,458 269,166 174,678
TOTAL VILLA AMOUNT BASE BID 45,297 45,297 45,297 45,297
TOTAL 812,415 808,671 852,795 569,331
PH1 Elevator Cab Finishes Allowances (375,000) (375,000) (375,000) (375,000)
PH2 Elevator Cab Finishes Allowances (150,000) (150,000) (150,000) (150,000)
EDM PH1 Cab Flooring 17,390 17,390 17,390 17,390
Brambier's Grand Stair Barrisol Ceiling 9,965 9,965 9,965 9,965
EDM PH2 Cab Flooring 8,961 8,961 8,961 8,961
Elevator Cab Finish Allowances Balance (488,684) (488,684) (488,684) (488,684)
Appendix D2 –
Elevator Cab Wall
Finishes Bid Tab
(After)
Appendix D2 Cab Interior Finishes Bid Tab
PROJECT: The Estates at Acqualina XP = SUFFOLK PLUG BID DATE: 11/12/2020
LOCATION: South Tower, North Tower & Villa XS = PLUG FROM THIS SUB RECOMMENDED SUB: Otis/MJ
TRADE: Interior Cab Finishes XO = PLUG FROM OTHER SUB BUDGET AMOUNT: $ 443,328.00
DETAIL SUB: OTIS/Vision OTIS/MJ OTIS/Retro OTIS/Vision OTIS/MJ OTIS/Retro OTIS/Vision OTIS/MJ OTIS/Retro OTIS/Vision OTIS/MJ OTIS/Retro
Sophie Mallebranche (P1-P6) Sophie Mallebranche (P1-P6) Sophie Mallebranche (P1-P6)
Cristina Turbo (P1-P6) & Cristina Turbo (P1-P6) & Cristina Turbo (P1-P6) & Cristina Hechizoo (P1-P6) Cristina Hechizoo (P1-P6) Cristina Hechizoo (P1-P6) ViviTela (P1-P6) & ViviTela (P1-P6) & ViviTela (P1-P6) &
& Venetian Plaster (P7) & Venetian Plaster (P7) & Venetian Plaster (P7)
Venetian Plaster (P7) Venetian Plaster (P7) Venetian Plaster (P7) & Venetian Plaster (P7) & Venetian Plaster (P7) & Venetian Plaster (P7) Venetian Plaster (P7) Venetian Plaster (P7) Venetian Plaster (P7)
SECTION DESCRIPTION
SPECIFIC TRADE SCOPE OF WORK REQUIREMENTS
Furnish and Install (2) Cab Side Panels, Handrail 80,829 41,804 50,203 80,262 41,054 34,993 86,947 49,320 42,565 43,998 27,141 32,531
Car front Handrails Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded
Markup 8,082.90 4,180.36 5,020 8,026.20 4,105.44 3,499.30 8,694.70 4,932.00 4,256.50 4,399.80 2,714.10 3,253.10
Otis Standby Install Labor Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded
Support Frames for Barrisol Ceiling Included Included Included Included Included Included Included Included Included Included Included Included
Lead Time 12-16 weeks 15-20 weeks 15-20 weeks 12-16 weeks 15-20 weeks 15-20 weeks 12-16 weeks 15-20 weeks 15-20 weeks 12-16 weeks 15-20 weeks 15-20 weeks
Flooring and Ceilings Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded
One 12"x12" sample Included Included Included Included Included Included Included Included Included Included Included Included
BASE BID for Tower Cabs SUBTOTAL PER CAB 88,912 45,984 55,223 88,288 45,160 38,492 95,642 54,252 46,822 48,398 29,855 35,784
BOND AMOUNT ON BASE BID Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded Excluded
TOTAL SOUTH TOWER AMOUNT BASE BID 355,648 183,936 220,892 353,152 180,640 153,968 382,568 217,008 187,288 193,592 119,420 143,136
TOTAL NORTH TOWER AMOUNT BASE BID 177,824 91,968 110,446 176,576 90,320 76,984 191,284 108,504 93,644 96,796 59,710 71,568
TOTAL VILLA AMOUNT BASE BID 26,397 14,212 19,752 26,397 14,212 19,752 26,397 14,212 19,752 26,397 14,212 19,752
TOTAL Cab Interior Wall Finishes 559,869 290,116 351,090 556,125 285,172 250,704 600,249 339,724 300,684 316,785 193,342 234,456
Phase 1 Elevator Cab Finishes Allowances (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000) (375,000)
Phase 2 Elevator Cab Finishes Allowances (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (150,000)
EDM PH1 Cab Flooring 17,390 17,390 17,390 17,390 17,390 17,390 17,390 17,390 17,390 17,390 17,390 17,390
Brambier's Grand Stair Barrisol Ceiling 9,965 9,965 9,965 9,965 9,965 9,965 9,965 9,965 9,965 9,965 9,965 9,965
EDM PH2 Cab Flooring 8,961 8,961 8,961 8,961 8,961 8,961 8,961 8,961 8,961 8,961 8,961 8,961
Non-committed Hold for Barrisol Ceiling Lighting (Phase 1) 30,888 30,888 30,888 30,888 30,888 30,888 30,888 30,888 30,888 30,888 30,888 30,888
Non-committed Hold for Barrisol Ceiling Hatch (Phase 1) 3,092 3,092 3,092 3,092 3,092 3,092 3,092 3,092 3,092 3,092 3,092 3,092
Non-committed Hold for Barrisol Ceiling Lighting (Phase 2) 10,066 10,066 10,066 10,066 10,066 10,066 10,066 10,066 10,066 10,066 10,066 10,066
Non-committed Hold for Barrisol Ceiling Hatch (Phase 2) 1,310 1,310 1,310 1,310 1,310 1,310 1,310 1,310 1,310 1,310 1,310 1,310
Elevator Cab Finish Allowances Balance (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328) (443,328)
Grand Total 116,541 (153,212) (92,238) 112,797 (158,156) (192,624) 156,921 (103,604) (142,644) (126,543) (249,986) (208,872)
Add Alternates
Auxiliary COP Per Cab 2,023 6,712 6,712 2,023 6,712 6,712 2,023 6,712 6,712 2,023 6,712 6,712
Tax for Aux COP 141.60 Included Included 141.60 Included Included 141.60 Included Included 141.60 Included Included
Shipping 1,200 Included Included 1,200 Included Included 1,200 Included Included 1,200 Included Included
Markup 336 Included Included 336 Included Included 336 Included Included 336 Included Included
Otis COP Install Labor Per Cab 11,340 11,340 11,340 11,340 11,340 11,340 11,340 11,340 11,340 11,340 11,340 11,340
Touch Screen 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000
COP/Touch Screen Phase 1 Total 80,164 92,208 92,208 80,164 92,208 92,208 80,164 92,208 92,208 80,164 92,208 92,208
COP/Touch Screen Phase 2 Total 40,082 46,104 46,104 40,082 46,104 46,104 40,082 46,104 46,104 40,082 46,104 46,104
Otis Standby Install Labor 132,300 132,300 132,300 132,300 132,300 132,300 132,300 132,300 132,300 132,300 132,300 132,300
Total with Added COPs/Touch Screen in P1 to P6 & Otis Standby Time 369,086 117,400 178,374 365,342 112,456 77,988 409,466 167,008 127,968 126,002 20,626 61,740
Otis Elevator Company
16200 NW 59th Avenue, Suite 109
Miami Lakes, FL 33014
Cell (786) 910-0940
Office: (305) 816-5740
Proposal #1-02: Custom Elevator Cabs for Elevators P1, P2, P3, P4, P5, P6, Sophie Mallebranche
and Cristina Grajales Wall Panels.
South Tower Elevators P1, P2, P3, P4, P5, P6 Custom Elevator Cab Interiors
1. Prepare the existing elevator cab to receive new custom interior.
2. Ceiling to be furnished and installed by-others. We will coordinate the installation and weld
any brackets to support the ceiling and will provide any type of ceiling lift to install the ceiling.
The ceiling will be mounted with threaded rod and if the ceiling will remain a 9’, steady
brackets be installed to keep the ceiling from swaying while the elevator is in travel.
3. Furnish and install 2” base board faced with 304-series #4 (brushed) stainless steel, per ID
drawing ID-L-220 Elevation 11.
4. Furnish and install 304-series #4 (brushed) stainless steel reveals between outer leading
edge of panels and cab fronts.
5. Furnish and install two panels (Sophie Mallebranche) or four panels (Cristina Grajales) to the
sidewalls faced with clear glass and the selected woven/mesh insert. The panels will be
captured in 1/8” aluminum angles. Please note: 1/8” aluminum captured along edges. A
backer material color will need to be selected due to this material being transparent.
6. Furnish and install one (1) 304-series #4 (brushed) stainless steel cylindrical handrail on each
side wall.
7. Elevator Front, Rear, Return and Transom will be Otis Brushed Stainless. One (1) Brushed
Stainless Steel Main Cab Operating Panel (COP) with MAD TTG 21” Touchscreen with
Keypad, and one (1) Brushed Stainless Steel auxiliary COP with MAD Auxiliary Touch screen
per elevator.
Panel Selections and Pricing, Including Installation, Materials and Partial Ceiling Installation.
1. Sophie Mallebranche Woven Metal. Lead time is 12-16 weeks.
Price per elevator cab………….…………………………………….….…….…….$ 127,853
Price for Six (6) elevator cabs……………………….………………..……...……$ 767,118
3. Cristina Grajales Hechizoo Turbo Mesh Textile. Lead time is 12-16 weeks.
Price per elevator cab, 7-8 month lead time….…………………..……….….….……….$ 134,583
Price for six (6) elevator cabs ………………………………….….…..………………….………$ 807,498
Page 2 of 2
Notes:
1. All previous submitted proposals for custom elevator finishes are void.
2. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of
Otis or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and
re-inspections.
3. Prices are based on elevators P1-P4 in the South Tower and P5-P6 in the North Tower
receiving identical finishes. Because of material quantity pricing, if there are changes to the
interior for one or more elevators, prices for all elevators will be adjusted.
4. If Otis Elevator is directed by Suffolk Construction to change the material supplier and/or
custom cab vendor, all items on this proposal will be requoted.
5. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
6. Flooring is by others. Flooring is to be installed prior to rebalancing.
7. (1) year standard manufacture warranty on installation and materials.
8. Detail breakdown of pricing is attached to this proposal.
9. (1) 12” x 12” sample is included. Mock-ups are not included in this proposal.
10. Offsite storage of material is not included in this proposal.
Terms:
1. 50% down payment, Balance, 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
3. Lead time for Wall Panels: Quoted lead times begin after submittals are approved and all
RFIs are answered. Metal Fabric will be shipping from overseas. Quoted lead time may be
affected by Customs processing and/or other delays that neither Otis nor Visions Elevator,
Inc can control.
4. Lead time for Cab Operating Panels (COPs) and Touch Screens: 12-14 weeks from signed
approvals.
5. Installation of side panels: 5 to 7 working days not including coordination of ceiling
installation.
6. Installation of P1, P2, P3, P4, P5, P6 COPs: 6 working days per elevator (2 COPs per
elevator).
Phil Mobilia
Otis Elevator Company
16200 NW 59th Avenue, Suite 109
Miami Lakes, FL 33014
Cell (786) 910-0940
Office: (305) 816-5740
Proposal#2-02: Custom Elevator Cabs for Elevators P1, P2, P3, P4, P5, P6 ViviTela
South Tower Elevators P1, P2, P3, P4, P5, P6 Custom Elevator Cab Interiors
1. Prepare the existing cab interior to receive a New Construction installation of customer
elevator cab interiors.
2. Ceiling to be furnished and installed by-others. We will coordinate the installation and weld
any brackets to support the ceiling and will provide any type of ceiling lift to install the ceiling.
The ceiling will be mounted with threaded rod and if the ceiling will remain a 9’, steady
brackets be installed to keep the ceiling from swaying while the elevator is in travel.
3. Furnish and install custom Forms & Surfaces Level E-105 vertical wall laminated glass
panels to the sidewalls only, inset with ViviTela Mesh Reflect. The panels will be captured in
custom aluminum framework, color to be white gold.
4. Furnish and install #4 satin finish stainless steel reveals to the vertical corners and horizontal
frieze area.
5. Furnish and install # 4 satin finish stainless steel baseboards to all three walls. The substrate
to be 1” fire rated MDF.
6. Furnish and install (2) #4 satin finish stainless steel Compass style handrails to each of the
sidewalls.
7. Elevator Front, Rear, Return and Transom will be Otis Brushed Stainless. One (1) Brushed
Stainless Steel Main Cab Operating Panel (COP) with MAD TTG 21” Touchscreen with
Keypad, and one (1) Brushed Stainless Steel auxiliary COP with MAD Auxiliary Touch screen
per elevator.
Notes:
1. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of
Otis or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and
re-inspections.
Page 2 of 2
2. Prices are based on elevators P1-P4 in the South Tower and P5-P6 in the North Tower
receiving identical finishes. Because of material quantity pricing, if there are changes to the
interior for one or more elevators, prices for all elevators will be adjusted.
3. If Otis Elevator is directed by Suffolk Construction to change the material supplier and/or
custom cab vendor, all items on this proposal will be requoted.
4. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
5. Flooring is by others. Flooring is to be installed prior to rebalancing.
6. (1) year standard manufacture warranty on installation and materials.
7. Detail breakdown of pricing is attached to this proposal.
8. (1) 12” x 12” sample is included. Mock-ups are not included in this proposal.
9. Offsite storage of material is not included in this proposal.
Terms:
1. 50% down payment, Balance, 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
3. Lead time for Wall Panels: 12-16 weeks from when submittals are approved and all RFIs are
answered.
4. Lead time for Cab Operating Panels (COPs) and Touch Screens: 12-14 weeks from signed
approvals.
5. Installation of side panels: 5 to 7 working days not including coordination of ceiling
installation.
6. Installation of P1, P2, P3, P4, P5, P6 COPs: 6 working days per elevator (2 COPs per
elevator).
Thank You,
Phil Mobilia
Project Manager
Otis Elevator Company
16200 NW 59th Avenue, Suite 109
Miami Lakes, FL 33014
Cell (786) 910-0940
Office: (305) 816-5740
Notes:
1. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of Otis
or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and re-
inspections.
Page 2 of 2
2. If Otis elevator is directed by Suffolk Construction to change the material supplier and.or custom
cab vendor, all items on this proposal will be requoted.
3. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
4. Flooring is by others. Flooring is to be installed prior to rebalancing.
5. (1) year standard manufacture warranty on installation and materials.
6. Samples or Mockups are not included in this proposal.
7. Offsite storage of material is not included in this proposal.
TERMS:
1. 50% down payment, Balance, 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
3. Lead time for Wall Panels: 6-8 weeks from when submittals are approved and all RFIs are
answered.
4. Installation of side panels: 5 to 7 working days not including coordination of ceiling installation.
Thank You,
Phil Mobilia
Project Manager
Estates at Acqualina Cab Finishes
Breakout of Cab Prices 9/15/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Sophie Mallenbranch Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Visions
Elevator, Inc. 80,829.00 80,829.00 80,829.00 80,829.00 23,998.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, MAD TTG 21" Elev P1-P4 (included in Contract) - - - - N/A
Auxilary COP 2,022.88 2,022.88 2,022.88 2,022.88 N/A
Tax Rate 0.07 0.07 0.07 0.07 N/A
Tax (for Aux COP) 141.60 141.60 141.60 141.60 N/A
Shipping and Handling 1,200.00 1,200.00 1,200.00 1,200.00 N/A
Sub Total 84,193.48 84,193.48 84,193.48 84,193.48 23,998.00
Markup 10% 8,419.35 8,419.35 8,419.35 8,419.35 2,399.80
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 127,852.83 127,852.83 127,852.83 127,852.83 45,297.80 556,709.12
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Sophie Mallenbranch Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Visions Elevator, Inc. 80,829.00 80,829.00
Main COP (included in Contract) - -
Touch Screen for Main COP, MAD TTG 21" (included in Contract) - -
Auxilary COP 2,022.88 2,022.88
Tax Rate 0.07 0.07
Tax (for Aux COP) 141.60 141.60
Shipping and Handling 1,200.00 1,200.00
Sub Total 84,193.48 84,193.48
Markup 10% 8,419.35 8,419.35
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00
Total 127,852.83 127,852.83 255,705.66
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes
Breakout of Cab Prices 9/15/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Visions Elevator,
Inc. 80,262.00 80,262.00 80,262.00 80,262.00 23,998.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, MAD TTG 21" Elev P1-P4 (included in Contract) - - - - N/A
Auxilary COP 2,022.88 2,022.88 2,022.88 2,022.88 N/A
Tax Rate 0.07 0.07 0.07 0.07 N/A
Tax (for Aux COP) 141.60 141.60 141.60 141.60 N/A
Shipping and Handling 1,200.00 1,200.00 1,200.00 1,200.00 N/A
Sub Total 83,626.48 83,626.48 83,626.48 83,626.48 23,998.00
Markup 10% 8,362.65 8,362.65 8,362.65 8,362.65 2,399.80
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 127,229.13 127,229.13 127,229.13 127,229.13 45,297.80 554,214.32
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Visions Elevator, Inc. 80,262.00 80,262.00
Main COP (included in Contract) - -
Touch Screen for Main COP, MAD TTG 21" (included in Contract) - -
Auxilary COP 2,022.88 2,022.88
Tax Rate 0.07 0.07
Tax (for Aux COP) 141.60 141.60
Shipping and Handling 1,200.00 1,200.00
Sub Total 83,626.48 83,626.48
Markup 10% 8,362.65 8,362.65
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00
Total 127,229.13 127,229.13 254,458.26
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes
Breakout of Cab Prices 9/15/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Cristina Grajales Hechizoo Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Visions Elevator,
Inc. 86,947.00 86,947.00 86,947.00 86,947.00 23,998.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, MAD TTG 21" Elev P1-P4 (included in Contract) - - - - N/A
Auxilary COP 2,022.88 2,022.88 2,022.88 2,022.88 N/A
Tax Rate 0.07 0.07 0.07 0.07 N/A
Tax (for Aux COP) 141.60 141.60 141.60 141.60 N/A
Shipping and Handling 1,200.00 1,200.00 1,200.00 1,200.00 N/A
Sub Total 90,311.48 90,311.48 90,311.48 90,311.48 23,998.00
Markup 10% 9,031.15 9,031.15 9,031.15 9,031.15 2,399.80
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 134,582.63 134,582.63 134,582.63 134,582.63 45,297.80 583,628.32
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Hechizoo Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, Handrail,Tax included. Visions Elevator, Inc. 86,947.00 86,947.00
Main COP (included in Contract) - -
Touch Screen for Main COP, MAD TTG 21" (included in Contract) - -
Auxilary COP 2,022.88 2,022.88
Tax Rate 0.07 0.07
Tax (for Aux COP) 141.60 141.60
Shipping and Handling 1,200.00 1,200.00
Sub Total 90,311.48 90,311.48
Markup 10% 9,031.15 9,031.15
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00
Total 134,582.63 134,582.63 269,165.26
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes
Breakout of Cab Prices 9/21/2020 South Tower
Item P1 P2 P3 P4 P7 Total
ViviTela P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Visions Elevator,
Inc. 43,998.00 43,998.00 43,998.00 43,998.00 23,998.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, MAD TTG 21" Elev P1-P4 (included in Contract) - - - - N/A
Auxilary COP 2,022.88 2,022.88 2,022.88 2,022.88 N/A
Tax Rate 0.07 0.07 0.07 0.07 N/A
Tax (for Aux COP) 141.60 141.60 141.60 141.60 N/A
Shipping and Handling 1,200.00 1,200.00 1,200.00 1,200.00 N/A
Sub Total 47,362.48 47,362.48 47,362.48 47,362.48 23,998.00
Markup 10% 4,736.25 4,736.25 4,736.25 4,736.25 2,399.80
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 87,338.73 87,338.73 87,338.73 87,338.73 45,297.80 394,652.72
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Vivitela Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, Handrail,Tax included. Visions Elevator, Inc. 43,998.00 43,998.00
Main COP (included in Contract) - -
Touch Screen for Main COP, MAD TTG 21" (included in Contract) - -
Auxilary COP 2,022.88 2,022.88
Tax Rate 0.07 0.07
Tax (for Aux COP) 141.60 141.60
Shipping and Handling 1,200.00 1,200.00
Sub Total 47,362.48 47,362.48
Markup 10% 4,736.25 4,736.25
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Touch Screen for Auxilary COP-MAD Fixtures (Contract Alternate) 5,000.00 5,000.00
Total 87,338.73 87,338.73 174,677.46
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
3125 John P. Curcie Drive Pembroke Park FL 33009 Suite #6| 954.589.2998 |www.VisionsElevator.com
Otis Elevator
16200 NW 59th Ave. Suite 109
Miami, FL 33014
We are pleased to submit the following proposal for the above referenced project.
Description: Six (6) Custom Elevator Cab Interiors | North & South Tower | Woven Metal
1. Prepare the existing elevator cab to receive new custom interior.
2. Ceiling to be furnished and installed by-others. We will coordinate the installation and weld
any brackets to support the ceiling and will provide any type of ceiling lift to install the
ceiling. The ceiling will be mounted with threaded rod and if the ceiling will remain a 9’,
steady brackets be installed to keep the ceiling from swaying while the elevator is in travel.
3. Furnish and install 2” base board faced with 304-series #4 (brushed) stainless steel, per ID
drawing ID-L-220 Elevation 11.
4. Furnish and install 304-series #4 (brushed) stainless steel reveals between outer leading
edge of panels and cab fronts.
5. Furnish and install two panels to the sidewalls faced with clear glass and the Sophie
Mallenbrach woven metal insert. The panels will be captured in 1/8” aluminum angles.
Please note: 1/8” aluminum captured along edges. A backer material color will need to be
selected due to this material being transparent.
6. Furnish and install one (1) 304-series #4 (brushed) stainless steel cylindrical handrail on each
side wall.
PRICE PER ELEVATOR CAB………………………………………………………………….….…………..$80,829.00
PRICE FOR ALL SIX ELEVATORS SOPHIE MALLEBRANCHE ELEVATOR CABS…………$484,974.00
Description: Cristina Grajales Turbo Mesh Textile | Installation & Materials | Partial Ceiling
Installation
1. Furnish and install (4) panels with Cristina Grajales Turbo Mesh Textile material to the
sidewalls only. The panels will be captured in brushed 1/8” architectural aluminum .
PRICE PER ELEVATOR CAB CRISTINA GRAJALES TURBO MESH TEXTILE……….........…80,262.00
PRICE FOR ALL (6) ELEVATOR CABS………………………………….…….…………………………$481,576.87
Description: Six (6) Custom Elevator Cab Interiors |Forms & Surface |Level- E-105
1. Prepare the existing cab interior to receive a New Construction installation of customer
elevator cab interiors.
2. Furnish and install custom Forms & Surfaces Level E-105 vertical wall laminated glass panels
to the sidewalls only, inset with Vivitela Mesh Reflect. The panels will be captured in custom
aluminum framework, color to be white gold.
3. Furnish and install 2” base board faced with 304-series #4 (brushed) stainless steel, per ID
drawing ID-V-250 Elevation.
4. Furnish and install rear wall as follows: Two (2) vertical raised panels faced with 304-series
#4 (brushed) stainless steel; these panels will be captured in 1/8” aluminum angles.
5. Furnish and install side walls as follows: Two (2) vertical raised panels faced with Venetian
Plaster - Exterior Rated – Color Silver, per customer approved specification and sample.
6. Panel will be constructed of ¾” fire-rated MDF and captured in 1/8” aluminum angles.
Please Note: Due to the nature of the finish material, variance should be expected.
7. Furnish and install one (1) Lustre 304-series #4 (brushed) stainless steel oval handrail or
comparable, on each rear and side walls.
PRICE FOR ONE (1) CAB INTERIOR…………………………………..……….….….…..………..…………$43,998.00
Notes:
1. Permit by others
2. Visions Elevator Incorporated is not responsible for any 3 rd party fees, such as balancing,
testing or adjusting and must be contracted directly through your elevator service company
and paid directly to the elevator service provider.
3. Door adjustments are done by others and must be contracted directly through your
elevator service company.
4. The above work is based on doing work during normal business hours Monday through
Friday 7:00 am to 6:00 pm.
5. Flooring is by others.
6. All taxes included.
7. (1) year standard manufacture warranty on installation and materials. We will provide this
in writing at the end of the project.
8. Any delays, due to COVID-19 from Italy is not the responsibility of Visions Elevator
Incorporated.
TERMS:
1. 50% down Balance | 25% Progress Payment at Installation | Balance Net 30 Days
2. Lead time: 12 weeks depending on shipments from Italy for metal fabric.
3. Project Duration: Installation 3 to 5 days depending on ceiling installer.
We thank you for the opportunity in submitting the above proposal and look forward to
working with you.
Best regards,
Bill LaFauci
Elevator Interior Specialist
Otis Elevator
16200 NW 59th Ave. Suite 109
Miami, FL 33014
Description: One (1) Custom Elevator Cab Interior | Podium | Venetian Plaster
1. Prepare the existing elevator cab to receive new custom interior.
2. Ceiling to be furnished and installed by-others. Please Note: Coordination with ceiling
contractor will be needed prior to any fabrication to prevent any dimensional or clearance
issues required for installation.
3. Furnish and install 2” base board faced with 304-series #4 (brushed) stainless steel, per ID
drawing ID-V-250 Elevation.
4. Furnish and install rear wall as follows: Two (2) vertical raised panels faced with 304-series
#4 (brushed) stainless steel; these panels will be captured in 1/8” aluminum angles.
5. Furnish and install side walls as follows: Two (2) vertical raised panels faced with Venetian
Plaster - Exterior Rated – Color Silver, per customer approved specification and sample.
6. Panel will be constructed of ¾” fire-rated MDF and captured in 1/8” aluminum angles.
Please Note: Due to the nature of the finish material, variance should be expected.
7. Furnish and install one (1) Lustre 304-series #4 (brushed) stainless steel oval handrail or
comparable, on each rear and side walls.
PRICE FOR ONE (1) CAB INTERIOR…………………………………..……….….….…..………..…………$23,998.00
Notes:
1. Permit by others
2. Visions Elevator Incorporated is not responsible for any 3 rd party fees, such as balancing,
testing or adjusting and must be contracted directly through your elevator service company
and paid directly to the elevator service provider.
3. Door adjustments are done by others and must be contracted directly through your
elevator service company.
4. The above work is based on doing work during normal business hours Monday through
Friday 7:00 am to 6:00 pm.
5. Flooring is by others.
6. All taxes included.
7. (1) year standard manufacture warranty on installation and materials. We will provide this
in writing at the end of the project.
8. Any delays, due to COVID-19 from Italy is not the responsibility of Visions Elevator
Incorporated.
TERMS:
1. 50% down Balance | 25% Progress Payment at Installation | Balance Net 30 Days
2. Material Lead time: 6-8 weeks.
3. Project Duration: Installation 3 to 5 days depending on ceiling installer.
We thank you for the opportunity in submitting the above proposal and look forward to
working with you.
Best regards,
Bill LaFauci
November 2, 2020
Estates at Acqualina
Suffolk Construction
17901 Collins Ave
Sunny Isles Beach, FL 33160
Proposal #5: Custom Elevator Cabs for Elevators P1, P2, P3, P4, P5 and P6 by Otis Elevator and
M&J Elevator Interiors
South and North Tower Elevators P1, P2, P3, P4, P5, P6 Custom Elevator Cab Interiors
1. Furnish and Install cab panels as per M&J Elevator Interiors proposals dated 10/30/20
(attached). All inclusions and exclusions in the M&J Elevator Interiors proposals are
incorporated in this proposal.
2. Elevator Front, Rear, Return and Transom will be Otis Brushed Stainless. One (1) Brushed
Stainless Steel Main Cab Operating Panel (COP) with Touchscreen with Keypad, and one (1)
Brushed Stainless Steel Auxiliary COP with Auxiliary Touch screen and Keypad per elevator.
Panel Selections and Pricing, Including Installation, Materials and Partial Ceiling Installation.
1. Sophie Mallebranche Woven Metal. Lead time is 15-20 weeks.
Price per elevator cab………….…………………………………….….…….…….$ 87,936
Price for Six (6) elevator cabs……………………….………………..……...……$ 527,616
3. Cristina Grajales Hechizoo Turbo Mesh Textile. Lead time is 15-20 weeks.
Price per elevator cab………………………………..….…………………..……….….….……….$ 96,204
Price for six (6) elevator cabs ………………………………….….…..…………$ 577,224
Notes:
1. This proposal replaces Otis proposal for cab finishes by M&J Elevator Interiors submitted on
10/28/20.
2. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of
Otis or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and
re-inspections.
Page 2 of 2
3. Prices are based on elevators P1-P4 in the South Tower and P5-P6 in the North Tower
receiving identical finishes. Because of material quantity pricing, if there are changes to the
interior for one or more elevators, prices for all elevators will be adjusted.
4. If Otis Elevator is directed by Suffolk Construction to change the material supplier and/or
custom cab vendor, all items on this proposal will be requoted.
5. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
6. Flooring is by others. Flooring is to be installed prior to rebalancing.
7. (1) year standard manufacture warranty on installation and materials.
8. Detail breakdown of pricing is attached to this proposal.
9. Mock-ups are not included in this proposal.
10. Offsite storage of material is not included in this proposal.
Terms:
1. 50% down payment, Balance, 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
3. Lead time for Wall Panels: Quoted lead times begin after submittals are approved and all
RFIs are answered. Quoted lead time may be affected by Customs processing and/or other
delays that neither Otis nor Visions Elevator, Inc can control.
4. Lead time for Cab Operating Panels (COPs) and Touch Screens: 12-14 weeks from signed
approvals.
5. Installation of side panels: 5 to 7 working days not including coordination of ceiling
installation.
6. Installation of P1, P2, P3, P4, P5, P6 COPs: 6 working days per elevator (2 COPs per
elevator).
Phil Mobilia
Estates at Acqualina Cab Finishes M&J Elevator Interiors, Inc.
Breakout of Cab Prices 11/2/2020 South Tower
Item P1 P2 P3 P4 Total
Sophie Mallenbranch Side Panels Elevators P1-P4
Furnish and Install 2 Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 41,803.63 41,803.63 41,803.63 41,803.63
Main COP (included in Contract) - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - -
Sub Total 41,803.63 41,803.63 41,803.63 41,803.63
Markup 10% 4,180.36 4,180.36 4,180.36 4,180.36
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00
Touch Screen for Auxilary COP Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00
Total 87,935.99 87,935.99 87,935.99 87,935.99 351,743.97
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Sophie Mallenbranch Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. M&J Elevator Interiors 41,803.63 41,803.63
Main COP (included in Contract) - -
Touch Screen for Main COP (included in Contract) - -
Sub Total 41,803.63 41,803.63
Markup 10% 4,180.36 4,180.36
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00
Total 87,935.99 87,935.99 175,871.99
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes M&J Elevator Interiors, Inc.
Breakout of Cab Prices 11/2/2020 South Tower
Item P1 P2 P3 P4 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P1-P4
Furnish and Install 2 Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 41,054.38 41,054.38 41,054.38 41,054.38
Main COP (included in Contract) - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - -
Sub Total 41,054.38 41,054.38 41,054.38 41,054.38
Markup 10% 4,105.44 4,105.44 4,105.44 4,105.44
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00
Touch Screen for Auxilary COP Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00
Total 87,111.82 87,111.82 87,111.82 87,111.82 348,447.27
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 41,054.38 41,054.38
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 41,054.38 41,054.38
Markup 10% 4,105.44 4,105.44
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00
Total 87,111.82 87,111.82 174,223.64
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes M&J Elevator Interiors, Inc.
Breakout of Cab Prices 11/2/2020 South Tower
Item P1 P2 P3 P4 Total
Cristina Grajales Hechizoo Side Panels Elevators P1-P4
Furnish and Install 2 Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 49,320.50 49,320.50 49,320.50 49,320.50
Main COP (included in Contract) - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - -
Sub Total 49,320.50 49,320.50 49,320.50 49,320.50
Markup 10% 4,932.05 4,932.05 4,932.05 4,932.05
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00
Total 96,204.55 96,204.55 96,204.55 96,204.55 384,818.20
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Hechizoo Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 49,320.50 49,320.50
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 49,320.50 49,320.50
Markup 10% 4,932.05 4,932.05
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP(Contract Alternate) 5,000.00 5,000.00
Total 96,204.55 96,204.55 192,409.10
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes M&J Elevator Interiors, Inc.
Breakout of Cab Prices 11/2/2020 South Tower
Item P1 P2 P3 P4 Total
ViviTela P1-P4
Furnish and Install 2 Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 27,141.00 27,141.00 27,141.00 27,141.00
Main COP (included in Contract) - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - -
Sub Total 27,141.00 27,141.00 27,141.00 27,141.00
Markup 10% 2,714.10 2,714.10 2,714.10 2,714.10
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00
Total 71,807.10 71,807.10 71,807.10 71,807.10 287,228.40
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Vivitela Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, Handrail,Tax included. M&J Elevator Interiors 27,141.00 27,141.00
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 27,141.00 27,141.00
Markup 10% 2,714.10 2,714.10
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP(Contract Alternate) 5,000.00 5,000.00
Total 71,807.10 71,807.10 143,614.20
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
M & J Elevator Interiors, Inc. QUOTE NO: 65071 R1 Sophie
3552 East 10th Court DATE: 10/30/2020
Hialeah, FL 33013
www.elevatorcabs.net QUOTE IS BASED ON OUR BEST INTERPRETATION OF THE INFO PROVIDED
CUSTOMER: Otis Elevator Company JOB NAME: Estates at Acqualina
OFFICE: Miami Lakes, FL LOCATION: 17885 Collina Avenue
ATTN: Phil Mobilia Sunny Isles Beach, FL 33160
EMAIL: [email protected] PHONE: 786-910-0940
CAB DESCRIPTION AND PRICING
PLATFORM: CAPACITY:
PRODUCT DESCRIPTION QTY PRICE PER TOTAL
Lead times have not been verified by M&J on materials specified. M&J was instructed by Otis to allocate 6-
LEAD TIMES 8 weeks of lead time for Metal mesh. M&J will require (2) additional lead times not accounted for by
customer. 1) To have said mesh laminated in glass. 2) To mount glass once arrived at M&J facility.
WEIGHT M&J has not preformed any weight calculation. M&J assumes weight calculations discussed with the
CALCULATION customer will be met however M&J cannot confirm at this point due to lack of time/material specifications.
CEILING M&J has concerns regarding the ceiling drop from canopy exceeding 3'. In our experience this has been a
HEIGHT code violation & will need to be adjusted.
M&J will require class A flame spread certificates & is not responsible for any flaws in design that will make
BARRISOL
the ceiling proposed non compliant.
M&J pricing based on estimated material cost spreadsheet provided by customer. Price subject to change
MESH
as no material specification or sample was provided for mesh at time of quote.
M & J Elevator Interiors, Inc. QUOTE NO: 65071 R1 CRISTINA 80/20
3552 East 10th Court DATE: 10/30/2020
Hialeah, FL 33013
www.elevatorcabs.net QUOTE IS BASED ON OUR BEST INTERPRETATION OF THE INFO PROVIDED
CUSTOMER: Otis Elevator Company JOB NAME: Estates at Acqualina
OFFICE: Miami Lakes, FL LOCATION: 17885 Collina Avenue
ATTN: Phil Mobilia Sunny Isles Beach, FL 33160
EMAIL: [email protected] PHONE: 786-910-0940
CAB DESCRIPTION AND PRICING
PLATFORM: CAPACITY:
PRODUCT DESCRIPTION QTY PRICE PER TOTAL
CRISTINA
Estimated freight for mesh material per customer sent
80/20 1 $6,626.25 $6,626.25
spread sheet.
FREIGHT
Lead times have not been verified by M&J on materials specified. M&J was instructed by Otis to allocate 6-
LEAD TIMES 8 weeks of lead time for Metal mesh. M&J will require (2) additional lead times not accounted for by
customer. 1) To have said mesh laminated in glass. 2) To mount glass once arrived at M&J facility.
WEIGHT M&J has not preformed any weight calculation. M&J assumes weight calculations discussed with the
CALCULATION customer will be met however M&J cannot confirm at this point due to lack of time/material specifications.
CEILING M&J has concerns regarding the ceiling drop from canopy exceeding 3'. In our experience this has been a
HEIGHT code violation & will need to be adjusted.
M&J will require class A flame spread certificates & is not responsible for any flaws in design that will make
BARRISOL
the ceiling proposed non compliant.
M&J pricing based on estimated material cost spreadsheet provided by customer. Price subject to change
MESH
as no material specification or sample was provided for mesh at time of quote.
M & J Elevator Interiors, Inc. QUOTE NO: 65071 R1 CRISTINA 50/50
3552 East 10th Court DATE: 10/30/2020
Hialeah, FL 33013
www.elevatorcabs.net QUOTE IS BASED ON OUR BEST INTERPRETATION OF THE INFO PROVIDED
CUSTOMER: Otis Elevator Company JOB NAME: Estates at Acqualina
OFFICE: Miami Lakes, FL LOCATION: 17885 Collina Avenue
ATTN: Phil Mobilia Sunny Isles Beach, FL 33160
EMAIL: [email protected] PHONE: 786-910-0940
CAB DESCRIPTION AND PRICING
PLATFORM: CAPACITY:
PRODUCT DESCRIPTION QTY PRICE PER TOTAL
CRISTINA
Estimated freight for mesh material per customer sent
50/50 1 $10,113.75 $10,113.75
spread sheet.
FREIGHT
Lead times have not been verified by M&J on materials specified. M&J was instructed by Otis to allocate 6-
LEAD TIMES 8 weeks of lead time for Metal mesh. M&J will require (2) additional lead times not accounted for by
customer. 1) To have said mesh laminated in glass. 2) To mount glass once arrived at M&J facility.
WEIGHT M&J has not preformed any weight calculation. M&J assumes weight calculations discussed with the
CALCULATION customer will be met however M&J cannot confirm at this point due to lack of time/material specifications.
CEILING M&J has concerns regarding the ceiling drop from canopy exceeding 3'. In our experience this has been a
HEIGHT code violation & will need to be adjusted.
M&J will require class A flame spread certificates & is not responsible for any flaws in design that will make
BARRISOL
the ceiling proposed non compliant.
M&J pricing based on estimated material cost spreadsheet provided by customer. Price subject to change
MESH
as no material specification or sample was provided for mesh at time of quote.
M & J Elevator Interiors, Inc. QUOTE NO: 65071 R1 Forms+Surfaces
3552 East 10th Court DATE: 10/30/2020
Hialeah, FL 33013
www.elevatorcabs.net QUOTE IS BASED ON OUR BEST INTERPRETATION OF THE INFO PROVIDED
CUSTOMER: Otis Elevator Company JOB NAME: Estates at Acqualina
OFFICE: Miami Lakes, FL LOCATION: 17885 Collina Avenue
ATTN: Phil Mobilia Sunny Isles Beach, FL 33160
EMAIL: [email protected] PHONE: 786-910-0940
CAB DESCRIPTION AND PRICING
PLATFORM: CAPACITY:
PRODUCT DESCRIPTION QTY PRICE PER TOTAL
Lead times have not been verified by M&J on materials specified. M&J was instructed by Otis to allocate 6-
LEAD TIMES 8 weeks of lead time for Metal mesh. M&J will require (2) additional lead times not accounted for by
customer. 1) To have said mesh laminated in glass. 2) To mount glass once arrived at M&J facility.
WEIGHT M&J has not preformed any weight calculation. M&J assumes weight calculations discussed with the
CALCULATION customer will be met however M&J cannot confirm at this point due to lack of time/material specifications.
CEILING M&J has concerns regarding the ceiling drop from canopy exceeding 3'. In our experience this has been a
HEIGHT code violation & will need to be adjusted.
M&J will require class A flame spread certificates & is not responsible for any flaws in design that will make
BARRISOL
the ceiling proposed non compliant.
HANDRAIL Forms+Surfaces Handrail can only be provided at 1.25" diameter per product availability.
Otis Elevator Company
16200 NW 59th Avenue, Suite 109
Miami Lakes, FL 33014
Cell (786) 910-0940
Office: (305) 816-5740
Estates at Acqualina
Suffolk Construction
17901 Collins Ave
Sunny Isles Beach, FL 33160
Proposal #6: Custom Elevator Cab for Elevator P7 by Otis Elevator and M&J Elevator Interiors
Notes:
1. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of
Otis or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and
re-inspections.
2. If Otis Elevator is directed by Suffolk Construction to change the material supplier and/or
custom cab vendor, all items on this proposal will be requoted.
3. Venetian Plaster Finish is provided and applied by others. Final acceptance of cab finishes
provided by Otis and M&J Elevator Interiors is not contingent on completed punchlist items
related to the Venetian Plaster Finish. If Venetian Plaster Finish is not installed prior to
elevator balancing, an additional rebalancing fee will be charged.
4. Flooring is by others. If flooring is not installed prior to elevator balancing, an additional
rebalancing fee will be charged.
5. Ceiling is by others. If the Ceiling not installed prior to elevator balancing an additional
rebalancing fee will be charged.
6. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
7. (1) year standard manufacture warranty on installation and materials.
8. Detail breakdown of pricing is attached to this proposal.
Page 2 of 2
Terms:
1. 50% initial down payment at acceptance, Final 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
Phil Mobilia
M & J Elevator Interiors, Inc. QUOTE NO: 65071 R1
3552 East 10th Court DATE: 11/18/2020
Hialeah, FL 33013
www.elevatorcabs.net QUOTE IS BASED ON OUR BEST INTERPRETATION OF THE INFO PROVIDED
CUSTOMER: Otis Elevator Company JOB NAME: Estates at Acqualina P7
OFFICE: Miami Lakes, FL LOCATION: 17885 Collina Avenue
ATTN: Phil Mobilia Sunny Isles Beach, FL 33160
EMAIL: [email protected] PHONE: 786-910-0940
CAB DESCRIPTION AND PRICING
PLATFORM: CAPACITY:
PRODUCT DESCRIPTION QTY PRICE PER TOTAL
Estates at Acqualina
Suffolk Construction
17901 Collins Ave
Sunny Isles Beach, FL 33160
Proposal #3: Custom Elevator Cabs for Elevators P1, P2, P3, P4, P5, P6 and P7 by Otis Elevator
and Retro Elevator
South and North Tower Elevators P1, P2, P3, P4, P5, P6 Custom Elevator Cab Interiors
1. Furnish and Install cab panels as per Retro Elevator proposal dated 10/22/20 (attached). All
inclusions and exclusions in the Retro Elevator proposal are incorporated in this proposal.
2. Elevator Front, Rear, Return and Transom will be Otis Brushed Stainless. One (1) Brushed
Stainless Steel Main Cab Operating Panel (COP) with Touchscreen with Keypad, and one (1)
Brushed Stainless Steel Auxiliary COP with Auxiliary Touch screen per elevator.
Panel Selections and Pricing, Including Installation, Materials and Partial Ceiling Installation.
1. Sophie Mallebranche Woven Metal. Lead time is 15-20 weeks.
Price per elevator cab………….…………………………………….….…….…….$ 97,175
Price for Six (6) elevator cabs……………………….………………..……...……$ 583,050
3. Cristina Grajales Hechizoo Turbo Mesh Textile. Lead time is 15-20 weeks.
Price per elevator cab………………………………..….…………………..……….….….……….$ 88,774
Price for six (6) elevator cabs ………………………………….….…..………………….………$ 532,644
1. Furnish and Install cab panels as per Retro Elevator proposal dated 10/22/20 (attached). All
inclusions and exclusions in the Retro Elevator proposal are incorporated in this proposal.
2. Otis brushed stainless steel car door, front transom and returns. Applied Cab operating
Panel (COP), Stainless Steel. As shown on Final Layout approved 3-17-2020.
Notes:
1. If custom elevator finishes are not installed prior to elevator final inspection due to no fault of
Otis or Otis subcontractor, additional fees will apply for elevator re-balancing, permitting and
re-inspections.
2. Prices are based on elevators P1-P4 in the South Tower and P5-P6 in the North Tower
receiving identical finishes. Because of material quantity pricing, if there are changes to the
interior for one or more elevators, prices for all elevators will be adjusted.
3. If Otis Elevator is directed by Suffolk Construction to change the material supplier and/or
custom cab vendor, all items on this proposal will be requoted.
4. Work to be performed during normal working hours of the elevator trade, Monday through
Thursday 6:00 am to 4:30 pm. Overtime is not included in this proposal.
5. Flooring is by others. Flooring is to be installed prior to rebalancing.
6. (1) year standard manufacture warranty on installation and materials.
7. Detail breakdown of pricing is attached to this proposal.
8. Mock-ups are not included in this proposal.
9. Offsite storage of material is not included in this proposal.
Terms:
1. 50% down payment, Balance, 50% Progress Payment at Installation.
2. A fully executed change order is required to indicate acceptance of this proposal.
3. Lead time for Wall Panels: Quoted lead times begin after submittals are approved and all
RFIs are answered. Quoted lead time may be affected by Customs processing and/or other
delays that neither Otis nor Visions Elevator, Inc can control.
4. Lead time for Cab Operating Panels (COPs) and Touch Screens: 12-14 weeks from signed
approvals.
5. Installation of side panels: 5 to 7 working days not including coordination of ceiling
installation.
6. Installation of P1, P2, P3, P4, P5, P6 COPs: 6 working days per elevator (2 COPs per
elevator).
Phil Mobilia
Estates at Acqualina Cab Finishes Retro Elevator
Breakout of Cab Prices 10/28/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Sophie Mallenbranch Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Retro
Elevator 50,203.00 50,203.00 50,203.00 50,203.00 17,957.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - - N/A
Sub Total 50,203.00 50,203.00 50,203.00 50,203.00 17,957.00
Markup 10% 5,020.30 5,020.30 5,020.30 5,020.30 1,795.70
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00 N/A
Touch Screen for Auxilary COP Fixtures (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 97,175.30 97,175.30 97,175.30 97,175.30 38,652.70 427,353.90
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Sophie Mallenbranch Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Retro Elevator 50,203.00 50,203.00
Main COP (included in Contract) - -
Touch Screen for Main COP (included in Contract) - -
Sub Total 50,203.00 50,203.00
Markup 10% 5,020.30 5,020.30
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00
Total 97,175.30 97,175.30 194,350.60
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes Retro Elevator
Breakout of Cab Prices 10/28/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Retro Elevator 34,993.00 34,993.00 34,993.00 34,993.00 17,957.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - - N/A
Sub Total 34,993.00 34,993.00 34,993.00 34,993.00 17,957.00
Markup 10% 3,499.30 3,499.30 3,499.30 3,499.30 1,795.70
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00 N/A
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 80,444.30 80,444.30 80,444.30 80,444.30 38,652.70 360,429.90
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Turbo Mesh Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Retro Elevator 34,993.00 34,993.00
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 34,993.00 34,993.00
Markup 10% 3,499.30 3,499.30
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00
Total 80,444.30 80,444.30 160,888.60
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes Retro Elevator
Breakout of Cab Prices 10/28/2020 South Tower
Item P1 P2 P3 P4 P7 Total
Cristina Grajales Hechizoo Side Panels Elevators P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Retro Elevator 42,565.00 42,565.00 42,565.00 42,565.00 17,957.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - - N/A
Sub Total 42,565.00 42,565.00 42,565.00 42,565.00 17,957.00
Markup 10% 4,256.50 4,256.50 4,256.50 4,256.50 1,795.70
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00 N/A
Touch Screen for Auxilary COP-MAD (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 88,773.50 88,773.50 88,773.50 88,773.50 38,652.70 393,746.70
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Cristina Grajales Hechizoo Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Retro Elevator 42,565.00 42,565.00
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 42,565.00 42,565.00
Markup 10% 4,256.50 4,256.50
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP(Contract Alternate) 5,000.00 5,000.00
Total 88,773.50 88,773.50 177,547.00
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Estates at Acqualina Cab Finishes Retro Elevator
Breakout of Cab Prices 10/28/2020 South Tower
Item P1 P2 P3 P4 P7 Total
ViviTela P1-P4, Venetian Plaster Elevator P7
Furnish and Install 2 Cab Side Panels, Rear Panel(P7), Handrail,Tax included. Retro Elevator 32,531.00 32,531.00 32,531.00 32,531.00 17,957.00
Main COP (included in Contract) - - - - -
Touch Screen for Main COP, Elev P1-P4 (included in Contract) - - - - N/A
Sub Total 32,531.00 32,531.00 32,531.00 32,531.00 17,957.00
Markup 10% 3,253.10 3,253.10 3,253.10 3,253.10 1,795.70
Standby Installation Labor (Otis)* 18,900.00 18,900.00 18,900.00 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00 11,340.00 11,340.00 N/A
Auxilary COP 6,712.00 6,712.00 6,712.00 6,712.00 N/A
Touch Screen for Auxilary COP (Contract Alternate) 5,000.00 5,000.00 5,000.00 5,000.00 N/A
Total 77,736.10 77,736.10 77,736.10 77,736.10 38,652.70 349,597.10
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
North Tower
Item P5 P6 Total
Vivitela Side Panels Elevators P5-P6
Furnish and Install Cab Side Panels, , Handrail,Tax included. Retro Elevator 32,531.00 32,531.00
Main COP (included in Contract) - -
Touch Screen for Main COP, (included in Contract) - -
Sub Total 32,531.00 32,531.00
Markup 10% 3,253.10 3,253.10
Standby Installation Labor (Otis)* 18,900.00 18,900.00
Labor (Otis) to Install Aux COP** 11,340.00 11,340.00
Auxilary COP 6,712.00 6,712.00
Touch Screen for Auxilary COP(Contract Alternate) 5,000.00 5,000.00
Total 77,736.10 77,736.10 155,472.20
*Union Requirement for Vendor Installed Cab Finishes. Calculated at 5 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
**3 days x 10 hours x 2 men x $189 regular rate. Mon-Thurs.
Page 1 of 5
3241 118TH Ave. N, St. Petersburg, FL 33716
Phone: (727) 895-8144
FAX: (727) 895-8213
Proposal
Submitted to: Job Name:
Phil Mobilia @ Otis Elevator Estates at Acqualina
16200 NW 59 Ave Ste 109 17895 Collins Avenue
Sunny Isles, FL 33160
Miami Lakes, FL 33014
Email: [email protected]
Mobile: 786-910-0904
Office : 305-816-5785
Ceiling:
We propose to furnish & install a new suspended support frame to support Brambiers provided ceiling. Support frame
to be fabricated out of Aluminum angle and weld. Edge of frame to be held approximately ¾” from face of walls and
transoms. We will also provide a means to access the escape hatch from the car top to meet code requirements.
Handrails:
We propose to furnish & install new 2” diameter satin finish stainless steel tubular handrails onto each side wall
with solid satin stainless steel standoffs to include concealed threaded set pins on underside. Handrail ends to be
returned. Handrails to be mounted at 32” above finish floor height to meet code requirements. Car front handrails
not included.
Option #1
Wall Finishes:
We propose to furnish & Install four (4) vertical raised panels. Each side wall to have two (2) panels. Panels to be
faced with laminated safety glass with a Christina Grajales (Turbo Mesh) wire mesh interlayer with a mirror
backer. Each piece of glass will have an etched ANSI logo (as required by code) in the lower corner. Glass panels
to be edged with 16ga Satin (#4) finish stainless steel (type 304) perimeter L-trim. All panels to be attached to cab
shell walls using z-clips to permit future removal. Panels separating each other to have a butt seam, reveals
separating panels from front/rear corners are 1” wide. 8” Frieze and reveals to be 20ga satin (#4) finish stainless
steel (Type 304) and will be on the same plane and are adhered to cab shell with industrial grade contact adhesive.
4” protruded base to be 20ga satin (#4) finish stainless steel and Code required lower ventilation to be
accomplished through punched ventilation slots in base.
Ceiling:
We propose to furnish & install a new suspended support frame to support provided Brambiers ceiling. Support frame
to be fabricated out of Aluminum angle and weld. Edge of frame to be held approximately ¾” from face of walls and
transoms. We will also provide a means to access the escape hatch from the car top to meet code requirements.
Handrails:
We propose to furnish & install new 2” diameter satin finish stainless steel tubular handrails onto each side wall
with solid satin stainless steel standoffs to include concealed threaded set pins on underside. Handrail ends to be
returned. Handrails to be mounted at 32” above finish floor height to meet code requirements. Car front handrails
not included.
Ceiling:
We propose to furnish & install a new suspended support frame to support provided Brambiers ceiling. Support frame
to be fabricated out of Aluminum angle and weld. Edge of frame to be held approximately ¾” from face of walls and
transoms. We will also provide a means to access the escape hatch from the car top to meet code requirements.
Handrails:
We propose to furnish & install new 2” diameter satin finish stainless steel tubular handrails onto each side wall
with solid satin stainless steel standoffs to include concealed threaded set pins on underside. Handrail ends to be
returned. Handrails to be mounted at 32” above finish floor height to meet code requirements. Car front handrails
not included.
Option #3
Forms & Surfaces Finishes:
We propose to furnish & install Forms & Surfaces interiors.
**TWO EQUAL WIDTH FULL HEIGHT PANELS ON SIDE WALLS**
PANEL ORIENTATION: VERTICAL
VIVITELA MESH, REFLECT
PART NUMBER:**TBD**
GLAZING THICKNESS: 9/32" (7.14mm) THICK LAMINATED GLASS
FINISH: PEARLEX+
PATTERN: FRAMEWORK
COLOR: WHITE GOLD
MINIMAL PANEL FRAME MATERIAL: EXTRUDED ALUMINUM
MINIMAL PANEL FRAME ANODIZED FINISH: CLEAR
BACKER: FR PARTICLEBOARD WITH 0.025" ALUMINUM SEALER SHEET OR
THERMAGLASS TWIN-WALL POLYCARBONATE AT MANUFACTURER`S
DISCRETION ONLY
BASE MATERIAL/FINISH: STAINLESS STEEL/SATIN
REVEAL STRIPS MATERIAL/FINISH: ALUMINUM BLACK ANODIZED
Price Includes two (2) Compass handrails and standoffs.
Ceiling:
We propose to furnish & install a new suspended support frame to support provided Brambiers ceiling. Support frame
to be fabricated out of Aluminum angle and weld. Edge of frame to be held approximately ¾” from face of walls and
transoms. We will also provide a means to access the escape hatch from the car top to meet code requirements.
We propose to furnish material and labor, complete with above specifications, for the sum of : $319,175.
Option #1: $227,915.
Option #2: $273,347.
Option #3 $213,143.
Payments to be made as follows:
20% Deposit of Total Contract Amount Due Upon acceptance of proposal.
50% Draw of Total Contract Amount Due Upon Receipt of Approved shop drawings.
30% Balance of Total Contract Amount Due Upon completion of work. (Progress billed if not completed in the same
month).
Appendix E –
Villa Level 2
Restaurant Stop
Work Order
Appendix E Level 2 Restaurant Stop Work Order
TEAA VILLA
LEVEL 2 RESTAURANT
OPERATOR CHANGES
NOVEMBER 13, 2020
Appendix F –
Mortensen Change
Order for Hold-to
Superintendent
Appendix F Mortensen Change Order for Hold to Superintendent
CHANGE ORDER #003
COMMITMENT #SC-220167-030
PROJECT #220167 - The Estates at Acqualina South Tower
and Villa
Description of Change
CE #67.1065.00 - ST - Mortensen Hold to Superintendent
This Change Order is for an on-site Mortensen superintendent to coordinate benchmarks with framers and other trades to create
"hold-to" dimensions in order to release Villa/Lobby millwork to fabrication to maintain the delivery/installation schedule. Duration
of on site coordination is 55 days, which starts 10/26/2020 and stops 1/17/2021.
Please refer to Mortensen COR #3 dated 10/7/20, for reference only.
Item Description Amount
PCO #003 CE #67.1065.00 - ST - Mortensen Hold to Superintendent
1: Mortensen COR - 3 $64,680.00
Total: $64,680.00
Grand Total: $64,680.00
The Original Contract Sum was.................................................................................................................. $ 8,600,000.00
Net Change by Previously Authorized Requests and Changes......................................................................... $ 0.00
The Contract Sum Prior to This Change Order was....................................................................................... $ 8,600,000.00
The Contract Sum would be changed by this Change Order in the amount of.................................................... $ 64,680.00
The New Contract Sum Including This Change Order.................................................................................... $ 8,664,680.00
Signature of the Subcontractor on this Change Order indicates the Subcontractor’s agreement that any terms, conditions or reservations of rights
included in any of the Subcontractor’s documentation, proposals or slips included in or supporting this Change Order are of no effect and are considered
to be null and void; and that this Change Order represents full and final settlement of all claims, amounts, damages, costs, fees, expenses, impacts and
adjustments to the Subcontract Amount and schedule arising out of or occurring in connection with the labor, equipment, material, work and/or services
that are the subject of this Change Order, including, without limitation, those arising out of or occurring in connection with delay, hindrance, disruption,
interference, re-sequencing and/or inefficiency.
ACCEPTED:
Mortensen Woodwork, Inc. Suffolk Construction Suffolk Construction Suffolk Construction
(UNION CITY)
By: By: By: By:
Brock Roark Joanne Zheng Andrew Frank Edward Janus
Date: Date: Date: Date:
11.5 in Exhibit A of Mortensen Subcontract Agreement
2|Page