Republic of Iraq Ministry of Electricity: Tender Documents NO: T.L 118/NT/2014
Republic of Iraq Ministry of Electricity: Tender Documents NO: T.L 118/NT/2014
MINISTRY OF ELECTRICITY
GENERAL DIRECTORATE OF
ELECTRICAL TRANSMISSION PROJECTS
TENDER DOCUMENTS
NO: T.L 118/NT/2014
VOLUME 2/3
PARTICULAR CONDITIONS
TABLE OF CONTENTS
PC 1: DEFINITIONS .....................................................................................................................3
PC 2: INTERPRETATION..............................................................................................................3
PC 3: LAW AND LANGUAGE........................................................................................................3
PC 4: FRAUD AND CORRUPTION................................................................................................4
PC 5: TIME FOR COMMENCEMENT AND COMPLETION...........................................................4
PC 6: CONTRACTOR’S RESPONSIBILITIES ..............................................................................4
PC 7: TERMS OF PAYMENT ........................................................................................................5
PC 8: SECURITIES........................................................................................................................6
PC 9: TAXES AND DUTIES ..........................................................................................................6
PC 10: LICENSE/USE OF TECHNICAL INFORMATION ...............................................................6
PC 11: CONFIDENTIAL INFORMATION ........................................................................................7
PC 12: REPRESENTATIVES ........................................................................................................9
PC 13: TEST AND INSPECTION ...................................................................................................9
PC 14: COMPLETION TIME GUARANTEE .................................................................................. 9
.
PC 15: DEFECT LIABILITY ...........................................................................................................9
PC 16: INDEMNITY .......................................................................................................................11
.
PC 17: LIMITATION OF LIABILITY ...............................................................................................11
PC 18: CARE OF FACILITIES.......................................................................................................12
PC 19: FORCE MAJEURE ............................................................................................................13
PARTICULAR CONDITIONS
PC 1: DEFINITIONS
Country of Origin: Major plant & equipment shall be from the countries given
in Clause 1.2.4.i (Tender Document).
“Time for Completion”: for the avoidance of doubt, Time for Completion as duly
amended in these PCs, includes also the time for Commissioning of Facilities
GCC: Iraqi General Conditions of Contract (civil, electrical, mechanical and chemical
engineering works with two parts)
PC 2: INTERPRETATION
PC 2.1
PC 3.1 The Contract shall be interpreted in accordance with the laws of the
Republic of Iraq.
PC 4.1
a. will reject a proposal for award if it determines that the tenderer recommended
for award has engaged in corrupt, collusive, obstructive, coercive or fraudulent
practices in competing for the contract in question; and
b. will declare a firm ineligible, either indefinitely or for a stated period of time, to be
awarded any contract within Iraq if it is at any time determined that the firm has
engaged in corrupt, collusive, obstructive, coercive or fraudulent practices in
competing for or in executing any contract in Iraq.
PC 4.2 Gratuities
The Contractor shall not provide any gratuities to Employer or its agents or employees.
The Contractor shall also comply with all provisions of law regarding prohibitions of
gifts or gratuities for the Iraqi Government and any foreign government or their agents
or employees. Violations of this provision shall constitute a material breach of this
Contract.
PC 5.1 The Contractor shall commence work on the Facilities from Effective Date
for determining Time for Completion as specified in the Contract Agreement.
PC 6: CONTRACTOR’S RESPONSIBILITIES
PC 6.1 The Contractor shall have the sole responsibility for satisfying itself
concerning the nature and location of the Facilities and the general and
local conditions, including, but not limited to, the following:
The Contractor shall give all notices and pay all fees required to be given or paid by
any such laws.
1. To the extent required for the performance of the Contract and not
locally available, the Contractor shall import into Iraq all equipment,
materials and services, not subject to all provisions of taxes, customs
duties, stamp fees and any other duties that are levied by the
government of Iraq .
Page | 4
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 6.4 Within fourteen (14) days of the signing of the Contract by both Parties, the
Contractor shall provide ten (10) hard copies and ten (10) soft copies (with
table of contents in a searchable pdf format) of the signed and
stamped Contract Documents (as per Article 1.1 of the Contract Agreement)
to the Employer.
PC 7: TERMS OF PAYMENT
Once the contract is signed, the Employer shall open an irrevocable, Letter of Credit (LC)
with (100%) of contract value. (Infavour to the Contractor through the Trade Bank of Iraq
(TBI).
- Ministry of Electricity (MOE) customs clearing office on the border shall be responsible
for collecting stamps from Iraqi customs on CMR documents when the goods enter the
Iraqi border.
- (60%) (sixty percent) of each shipment value of material value to be paid after arrival
of goods to the project sites warehouse in compliance with MOE specification and
requirements and received by employer committee approving receiving of material
mentioned in the above item
B - For activities
- (85%) (eighty five percent) to be paid upon presentation of the required documents and
approved by first party .
C - (15 %) (fifteen percent) of total contract price will be paid after execution all the
obligations of the Second party
Page | 5
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
- Partial shipment and partial payment is allowed in case of partial shipment the amount
equivalent to the portion amount that is partially shipped must be paid in the same
manner stipulated in the contract.
PC 8: BONDS
PC 8.1 The amount of performance bonds (in the form of a bank guaranty), as a
percentage of the Contract Price for the Facility or for the part of the Facility
for which a separate Time for Completion is provided, shall be: five percent
(5%) of the total Contract Price, which amount shall be maintained until the
end of the Defects Liability Period & warranty period.
PC 8.3 the performance bonds shall be through Trade bank of Iraq ( TBI )according to
Volume 1/1 Section 5 - Contract Forms
PC 9.1 The contract shall be subjected to the Iraqi law and the instruction of the
cabinet decree No.167 year 2010, after obtaining the necessary approval
from the Ministry of Planning, Republic of Iraq that this contract shall be one
of the development contracts in the country.
PC 9.2 The Contractor shall bear all charges and fees howsoever designated for
services rendered to the Contractor by establishments of the Government of
Iraq including, inter-alia, port or wharfage dues, pilotage charges, clearance
charges, demurrage, loading and unloading charges and public utilities
charges.
PC 9.3 Second party shall bear the administration charges at rate up to ( 20% )
twenty percent from the actual cost of not executed obligation which carry
out by the first party and through third party for executing that obligation.
a. Shall become the property of the Employer and may be used by the
Employer for the purposes of construction, commissioning, operation,
maintenance, modification, replacement and repair of the Facilities.
Page | 6
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 11.1 The Contractor agrees not to divulge to third parties, without the prior
written consent of the Employer, any information obtained from or through
the Project Manager or the Employer in connection with the performance of
the Contract, including the terms of the Contract, unless:
c. The information is obtained by the Contractor from a third party who did
not receive same, directly or indirectly from the Project Manager or the
Employer and who has no obligation of secrecy with respect thereto.
PC 11.2 The Contractor further agrees that it will not, without the prior written
consent of the Employer, disclose to any third party any information
obtained by the Contractor in the performance of this Contract except to the
extent that such information falls within one of the categories described in
clauses (a) through (c) above.
PC 11.4 Information that the Contractor provides to the Employer or the Project
Manager in connection with this Contract shall be regarded as “Contractor
Confidential Information” if it is (a) provided in writing and marked
confidential, (b) disclosed orally and identified at the time of disclosure as
being confidential and the information is summarized or described in a
writing marked confidential within thirty (30) days after disclosure, or (c)
provided on a computer disk, photographic, or other tangible media, which
is designated confidential (hereinafter referred to as the “Contractor
Confidential Information”).
Page | 7
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 11.5 The Project Manager’s or the Employer’s duty of confidentiality shall not
apply to the Contractor Confidential Information which can be shown is the
same as information which:
c. Is later received from an independent third party who is, as far as can
reasonably be determined, under no limitation or restriction with
respect to such information.
Notwithstanding the foregoing, this PC Sub-clause 11.5 shall only apply in the event that the
Project Manager and the Contractor desire to obtain confidential or proprietary information
from each other in connection with reviewing and responding to requests from the Employer or
other internal discussions between the parties in connection with the Project. This PC Sub- clause
11.5 shall not apply to any Contract deliverables or other work to be provided to the Employer by
the Contractor in performing its scope of work under this Contract. The Project Manager
shall maintain the confidential markings provided by the Contractor and use best efforts to
advise and require such third parties to maintain the confidentiality obligations.
PC 11.7 The above provisions of this PC Clause 11 shall not in any way modify any
undertaking of confidentiality given by either of the Parties hereto prior to the
date of this Contract in respect of the Facilities or any part thereof.
PC 11.9 The provisions of this PC Clause 11 shall survive termination, for whatever
reason, of this Contract.
Page | 8
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 12: REPRESENTATIVES
PC 13.2- Independent inspector should attend the test (FAT) & inspect all equipment of
the contract at the manufacturer factory according to MOE specification.
The Contractor shall commence work on the Facilities within Fourteen (14) days from the
Effective Date for determining Time for Completion as specified in the Contract Agreement
PC 14.1 : No bonus will be given for earlier Completion of the Facilities or part thereof
PC 14.2 : PENELTIES
PC 15.1 The Defect Liability Period shall be (365) days from the date of
Completion of the Facilities (or any part thereof) or (1) year from the date of
Operational Acceptance of the Facilities (or any part thereof), whichever first
occurs
a. The Contractor warrants to the Employer that each item of the
equipment and materials furnished under this Contract shall be (1)
new, of clear title and of the most suitable grade of their respective
kinds, (2) shall also conform to the requirements of this Contract and
(3) shall be free from defects in design, equipment, materials or
workmanship for the applicable period specified elsewhere in PC 15.
Page | 9
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
b. If at any time during the warranty period, the Employer, the Project
Manager or the Contractor discovers any defect in the design,
equipment, materials, or workmanship immediate written notice shall
be given to the other parties. The Contractor shall within a reasonable
time propose corrective actions to cure such defects to meet the
requirements of this Contract.
c. In the event the Contractor discovers or receives written notice from the
Employer or the Project Manager within the warranty period of any
failure of the equipment or materials to comply with the warranty, the
Contractor agrees to:
f. The Contractor shall obtain or provide, for the benefit of the Employer
and its successors-in-interest, warranties or guarantees for the
equipment, materials and work furnished by suppliers and
subcontractors of any tier. Such warranties or guarantees are to run
for the period set forth in the applicable specification of this Contract or,
when not specified, that period customarily provided by the supplier or
subcontractor. The Contractor shall use its best efforts to enforce such
lower-tier warranties or guarantees on its own behalf or, if requested by
the Employer, the Contractor shall provide warranty documentation by
Final Acceptance or as otherwise required by this Contract.
Page | 10
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 16: INDEMNITY
a. The Contractor shall indemnify, defend and hold harmless the Project
Manager, the Employer and their subsidiaries and affiliates and the
officers, agents, employees, successors and assigns and authorized
representatives of all the foregoing from and against any and all suits,
actions, legal or administrative proceedings, claims, demands,
damages, liabilities, interest, attorney’s fees, costs, expenses, and
losses for personal injury or death or damage or loss of third party
property, other than that of customers of the Project Manager, whether
arising before or after completion of the Facilities hereunder to the
extent caused, occasioned, or contributed to by reason of any
negligent act, omission or fault, whether active or passive, of the
Contractor, its Subcontractors, lower tier suppliers, contractor or of
anyone acting under its direction or control or on its behalf.
b. The foregoing shall include, but is not limited to, indemnity for property
damage and injury to or death of any person, including employees of
the Project Manager, the Employer or the Contractor.
e. To the extent consistent with the above, the Contractor is not waiving
any indemnification rights against the Project Manager, if any, to which
it may otherwise be entitled at law.
a. Notwithstanding any other provision of this Contract shall the Contractor or its
Subcontractors, be liable to the Employer or the Project Manager, whether in
contract, tort (including negligence), warranty, strict liability or any other legal
theory, for any special, incidental or consequential damages, such as, but not
limited to, cost of capital and loss of profits or revenues.
Page | 11
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
b. Notwithstanding any other provisions of this Contract, the total liability of the
Contractor and its Subcontractors, whether in contract, tort (including
negligence), warranty, strict liability or any other legal theory shall not exceed the
Contract Price, as amended; provided, however, that this total liability limit shall
in no event apply to the Contractor’s liability, and losses arising from wilful
misconduct or lack of good faith of the Contractor.
PC 18.2 The Employer may, upon written notice, occupy and use any portion of the
completed Facilities which is suitable for use; provided, however, that such
use shall not constitute acceptance by the Employer, relieve the Contractor
of its responsibilities, or act as a waiver by the Employer of any terms of this
Contract.
PC 18.3 If, as a result of the Contractor’s failure to comply with the provisions of this
Contract, such use proves to be unsatisfactory to the Employer, the
Employer shall have the right to continue such use until such portion of the
Facilities can, without injury to the Employer, be taken out of service for
correction of defects, errors, omissions or replacement of unsatisfactory
materials or equipment as necessary for such portion of the Facilities to
comply with this Contract; provided, that the period of such operation or use
pending completion of appropriate remedial action shall not exceed twelve
(12) months unless otherwise mutually agreed in writing between the
parties.
Page | 12
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 19.1 PC 19.1 Definition: “Force Majeure” shall be limited to the following events:
a. The nature and magnitude of the existing conflict in Iraq shall not be
considered as force majeure. Force majeure as used herein shall include
any circumstance beyond the control of parties that my results from
demonstrable escalation
b. Force majeure as used herein shall mean any circumstance beyond the
control of the parties according to international chamber of force majeure
clause 2003.
In case of force majeure either party shall take reasonable step to
minimize the consequence of such an event.
The party which to plead force majeure shall inform the other party on
the effect the case of majeure has on the fulfillment of the purchase or work
order concerned. Shipment cannot be postpone or cancelled by parties,
except force majeure,
If force majeure circumstance continues for accumulative period ninety
(90) days or more, either party shall have the right to terminate the contract,
upon such termination purchaser shall pay to the contractor all the
outstanding amount for the work carried out by the contractor until the
termination of the contract.
Notwithstanding any other provision of this clause, force majeure shall not
apply to obligation of either party to make payments to the other party under
the contract. Any period taking as a result of the event of force majeure must
be added to the delivery period stipulated in clause 9 for avoiding of double
clause (10) liquidated damage for delay will not apply to such extended
period
PC 19.2 Mitigation
The Contractor shall use its best efforts to mitigate and minimize the effects
of any Force Majeure event and to resume in full its performance under the
Contract Documents.
Upon the Contractor’s failure to take all necessary and appropriate steps to
remove the cause(s) and mitigate the direct and indirect effects of a Force
Majeure event, the Employer, in its sole discretion and upon written notice
to the Contractor, if practical, may initiate such measures to remove the
causes(s) or mitigate the direct and indirect effects of the Force Majeure
event. Such measures may include the hiring of Persons to take the actions
that the Employer deems appropriate or necessary. Upon the termination of
the Force Majeure event, the Employer may require the Contractor to
resume full or partial performance of the Facilities.
PC 19.5 Notwithstanding anything contained in this Contract, the Employer shall pay
the Contractor for any increased costs directly attributable to and resulting
solely from War Risks (to the extent not covered by insurance), provided
that the Contractor shall as soon as practicable notify the Employer in
writing of any such increased cost together with supporting documentation
therefore consistent with PC Clause 20; and provided, further, that the
Contractor shall notify the Employer immediately of the occurrence and
nature, and the Contractor shall use best efforts to mitigate the effects, of
such War Risks.
PC 20.1 The employer can add new items resulting from adding new requirements
which were not requested in contractual conditions when the tender was
announced.
These new requirements sums should be provided and included within
reserved sum of contract and from the total amount of project, or from the
abundant sums in schedule ( if any) and these schedules should be attached
with an addendum ( variation order)
PC 20.2 if the Employer and the Contractor cannot reach agreement on the price for
the Change, an equitable adjustment to the Time for Completion, or any
other matters identified in the Change Proposal, the Employer may
nevertheless instruct the Contractor to proceed with the Change by issue of
a “Pending Agreement Change Order.”
PC 20.3 The Contractor shall implement measures for tracking any additional
engineering, procurement and construction costs through the use of
periodic (weekly, unless otherwise agreed by the Employer) updates and
Page | 14
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
time impact analyses, whether due to Change, War Risks, Force Majeure or
otherwise. The Contractor shall establish and upon approval by the
Employer, shall adopt a baseline cpm schedule, which shall be updated
periodically with the Employer’s approval, and using such updated cpm
schedule and other appropriate procedures and practices, track labour
material and equipment costs as well as time schedule impacts associated
with any proposed Change. Using such data, and such other relevant
information available to it, the Contractor shall prepare and provide
reasonable calculations, supplier invoices, time sheets and other
documents to support any such costs. In addition, the Contractor must
demonstrate to the reasonable satisfaction of the Employer that the
proposed Change was beyond the minimum performance or design criteria
in the bid documents. The Project Manager reserves the right to contest the
validity and/or amount of any such costs.
Page | 15
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
PC 21.1 Any differences or disputes arising from the contract or from agreements
regarding its performance shall be settled by an amicable effort on the part of both
parties to the contract. An attempt to arrive at settlement shall be deemed to have failed
as soon as one of the parties to the contract so notifies the other party in writing. If an
attempt of settlement has failed, the subjects shall be finally settled under Iraqi rules and
regulation in Iraqi courts.
PC 21.2 APLICABLE LAW: All disputes shall be settled in accordance with the
provisions of the contract and the order agreements regarding its performance,
otherwise in accordance with the substantive law in force in the Republic of Iraq.
1. Identify and comply with all other applicable laws, regulations, ordinances,
statutes, rules, and codes governing environmental requirements and
conduct the Facilities based on the requirements of this Contract and the
requirements of the Equipment Supplier as set forth in the Equipment
Contract, including compliance with permit requirements and Project plans
and approvals. The Contractor shall have sole responsibility for compliance
of the Facilities with environmental requirements.
• Extraction/supply of water,
Page | 16
PARTICULAR CONDITIONS OF CONTRACT
TENDER NO:T.L 118 / NT/2014
GENERAL DIRECTORATE OF ELECTRICAL TRANSMISSION PROJECTS
MINISTRY OF ELECTRICITY, IRAQ
5. Require that its personnel do not hunt, fish, feed, capture, extract, or
otherwise disturb aquatic, animal, or vegetative species within the Project
boundary or while performing any tasks in performance of the Facilities
without prior approval from the Employer.
6. Not proceed with any renovation or demolition work until inspections and
notifications have been completed in accordance with the process outlined
in the Project’s Environmental requirements.
PC 23:
The contract subjected the rules of law that obtaining the government debts NO. ( 56 ) for year
1977.
Page | 17