Comparison of The Use of Traditional and Low Waste Formwork Systems in Hong Kong

This document compares the use of traditional timber formwork and integrated large panel steel formwork with pre-cast concrete for constructing school buildings in Hong Kong. It analyzes two identically designed school projects, one using traditional timber formwork and the other using the integrated system. The integrated system has environmental advantages in reducing waste but the traditional system was found to be more economically favorable for the projects studied. However, the recyclable steel formwork from the integrated system could provide economic benefits if reused for other standard school building projects.

Uploaded by

Mwesigwa Dani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
128 views8 pages

Comparison of The Use of Traditional and Low Waste Formwork Systems in Hong Kong

This document compares the use of traditional timber formwork and integrated large panel steel formwork with pre-cast concrete for constructing school buildings in Hong Kong. It analyzes two identically designed school projects, one using traditional timber formwork and the other using the integrated system. The integrated system has environmental advantages in reducing waste but the traditional system was found to be more economically favorable for the projects studied. However, the recyclable steel formwork from the integrated system could provide economic benefits if reused for other standard school building projects.

Uploaded by

Mwesigwa Dani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

The 2005 World Sustainable Building Conference,

09-032 Tokyo, 27-29 September 2005 (SB05Tokyo)

COMPARISON OF THE USE OF TRADITIONAL AND


LOW WASTE FORMWORK SYSTEMS IN HONG KONG

C.S. POON, Professor1


Robin C.P. YIP, Ph.D Candidate2
1
Department of Civil and Structural Engineering, The Hong Kong Polytechnic University, Hunghom,
Kowloon, Hong Kong, cecspoon@polyu.edu.hk
2
Department of Civil and Structural Engineering, The Hong Kong Polytechnic University, Hunghom,
Kowloon, Hong Kong, robin.yip@polyu.edu.hk

Keywords: Sustainable Development; Conventional Timber Formwork; Large Panel Steel Formwork;
Pre-cast Concrete Semi-slab

Summary
Formwork is one of the most important temporary works for construction of reinforced concrete
superstructure in building projects. The use of conventional timber formwork dominated the construction
market in Hong Kong for many years. Nowadays, low waste construction technologies for superstructure
construction are commonly adopted. The most commonly used low waste construction technology in Hong
Kong is large panel steel formwork integrated with pre-cast concrete units. Compared with the use of
conventional timber formwork system, the latter is considered a more sustainable construction method.

The selection of a formwork system and materials for the construction of superstructures would seriously
influence the cost, time, and quality of project delivery. Other than these issues, environmental objectives
and the associated waste generation during the course of construction are also of major concerns.
Stakeholders of the construction industry in Hong Kong are consistently exploring the use of innovative
construction technologies for various types of building projects in meeting both economic and environmental
requirements.

This paper aims to compare merits and demerits of the use of a conventional timber formwork system and an
integrated large panel steel formwork and pre-cast concrete semi-slab system in the construction of the
superstructure of two identically designed school projects in Hong Kong. The comparisons include costs,
time, quality and environmental issues of these two formwork systems. The study shows that despite the
quality and environmental advantages of the new formwork system, the conventional timber formwork
system is still more economically favorable in the projects studied. But if the recyclable metal formwork used
in the new system could be used in other standard school projects after the completion of the project,
economic advantage would be realized.

1. Introduction
The education reform proposal of Hong Kong was approved by the Government in 1999. The proposal
recommended a holistic reform approach to improve the quality of education. One of its key emphases was
to progressively replace all half-day primary school system by whole-day primary school system by 2007.
In meeting this reform objective, the government of HKSAR must build more new primary schools to meet
the demand of the new educational plan. Almost at the same time, the government of HKSAR promulgated
its sustainable development policy. The concept of sustainable development is used as guiding principle for
all government projects. The design and construction of new primary schools for education reform must
therefore contain elements of sustainability. In this connection, a School Building Committee was established.
The committee explored innovations of school building that provide both quality learning environment and
flexibility in use of space. The Architectural Services Department (ASD) of HKSAR government undertook
the task and supplied design solution.

1.1 Development Concept of New Primary School for the Education Reform
Elements of sustainable development are largely embraced in the new primary school design. Economic

- 2741 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

attribute focuses on value of land use and cost of construction. Social attribute concentrates on timely award
contracts to stimulate the declining construction market, enhance workers safety in construction site, swiftly
create adequate quality schools for the healthy development of school children. Environmental attribute
emphasizes waste reduction, using renewable raw materials, recycle waste materials and energy saving
during construction stage and when the schools are in use.
The design solutions consist of three different sizes of standard schools from 30-classroom, 24-classroom to
18-classroom respectively. The design of the school complex comprises two low rise buildings, the
Classroom Block and the Assembly Hall/Special Room Block interconnected by a common area at each floor
served as a lift lobby and a staircase lobby. The availability of three different designs was to provide
flexibility to accommodate the land use economy and demand of the local community.

1.1.1 Sustainable objectives in the Design of New Primary School


With respect to the promotion of the concept of sustainable development, all the government development
projects in Hong Kong are encouraged to follow most, if not all, sustainable construction criteria. These
criteria encompassed design and operation issues and the design of the new schools needed to address
the following requirements:
- Reduce energy consumption
To improve energy efficiency by reducing electricity demand through better overall thermal transfer value
(OTTV) which is a measurement of the energy consumption of a building envelope. The OTTV value of
ASD projects was set up at an average of 23W/m2. According to ASD’s Environmental Report (2000), the
new primary school design displayed an OTTV value of 11W/m2.

- Minimize Construction Waste


ASD encouraged reduction of construction waste by elimination of on site cutting, in-situ mixing of materials,
and using prefabricated components.

- Reduce the use of depletable materials


Use of system formwork in association with pre-cast concrete units to substitute traditional timber formwork
is highly recommended. Hui and Cheung (2000) suggested considerations are focused on various options
in structural design such as standardizing the dimension of structural members for repetitive use of system
formwork to avoid unnecessary cutting of depletable raw materials.

1.1.2 Selection of Construction Method


To attain the better environmental perfromance, Tang (2001) explained that it is important to adopt
sustainable development approaches during the project inception stage and the initial design stage. The
selection of construction methods are seriously influenced by the configuration of building and its structural
members. BEER (2000) described that standardizing the dimension of structural members facilitates the
use of reusable metal formworks pre-cast concrete elements which are believed to be able to generate less
waste during construction.

2. Comparison of Outcomes with Different Construction Methods by Case Studies


The aim of this research is to explore whether adoption of low waste construction technologies to construct
the superstructure of the new primary school is technically viable, financially beneficial, timely efficient and
environmentally sustainable. To facilitate the study, two separate school projects were selected as case
studies. Conventional timber formwork was used in the superstructure of the primary school in Lam Tin
District; and large panel steel formwork in association with pre-cast semi-slab units were applied at another
identically designed school project in Kowloon Bay. Both of the school projects were completed and put into
use in 2003.

2.1 Case Study I - Conventional Timber Formwork System used in Lam Tin School
The Lam Tin School was a standard design 30-classroom primary school. The project was consisted of two
reinforced concrete building complex, the Classroom Block and the Assembly Hall Block/special Room Block
interconnected perpendicularly to each other by a common area. The contractor of this project used
conventional timber formwork and cast in-situ concrete for the principal construct6ion method for the
superstructure.

- 2742 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

2.1.1 Conventional Timber Formwork System and Working Cycle


The timber formwork system for columns and walls used 18mm thick 6-ply Canadian Douglas Fir plywood as
the vertical shutter formface. The shutters were vertically stiffened with 50mm x 75mm softwood sawn
timber studs at an average of 180mm centre to centre. Concrete was placed between the shutters. The wall
and column formwork was removed the next day after completion of concreting of the entire floor. The
removed wall and column formwork was lifted to the upper floor level to repeat the working-cycle.

The beam and slab formwork system used 18mm thick 6-ply Canadian Douglas Fir plywood as beam & slab
soffit. The soffits and side shutters were strengthened by timber runners of 50mm x 100mm softwood-sawn
timber and propped by a propriety steel falsework system. According to the quantum of work of each floor,
the planned working cycle of the superstructure of these two blocks was 11 days per floor.

All the soffits of slab, beam and cantilever structure had to be propped for at least 7 days, 16days and 28
days respectively according to the General Specifications (2002) to allow the concrete strength development.
In order to achieve early removal of beam and slab formwork, individual dead propping supports were
installed at suitable positions to sustain the dead and live load. Thus the beam and slab timber formwork
system could be removed earlier and reused in upper floor to maintain its planned 11-day per floor working
cycle.

In total, one set each of wall and column formwork, two sets of beam and slab formwork and 3 sets of
cantilever beam and slab formwork were imperatively necessary. The breakdown of the 11-day per floor
working cycle for the whole timber formwork system is as follow:
- Fix wall & column reinforcement and formwork 3 days
- Erect L/D scaffolding system and fix beam & slab formwork 3 days
- Place concrete to wall & column 1 day
- Fixing beam & slab reinforcement and E/M conduit 3 days
- Place beam & slab concrete 1 day (Total: 11 days)

2.1.2 Quantity of Timber Material used


The amount timber formwork used was measured. The plywood was measured in m2, and the softwood
sawn timber stiffeners was measured in metre run according to the Standard Method of Measurement (2001).
As a common trade practice in Hong Kong, all soft wood sawn timber materials would be eventually
converted to cubic metre (m3). The amount of timber used for miscellaneous applications as side braces
throughout the entire formwork system were soft wood sawn timber of various cross-sections were estimated
by experience. The estimated quantity would be around 15% of the total timber studs and runners used in
the relevant portion of works. The estimated quantity of side braces of the entire superstructure was later
verified with material delivery record provided by the main contractor. The estimated figure was sufficiently
close to the material delivery record.
The percentages of cutting wastage of the plywood and the soft wood sawn timber stiffeners for wall and
column were estimated by experience (5% for plywood and 10% for softwood sawn timber stiffener). The
cutting wastage for the beam and the slab system for plywood and soft wood sawn timber materials were
estimated at 5% and 7% respectively.
The construction work for ground beam was carried out in sections according to the excavation progress.
Whenever excavation work and concrete blinding layer for a particular section was ready, erection of
formwork for the ground beam followed immediately. Therefore, cutting wastage was generally greater than
the typical floors (about 20% for each concrete placing cycle). The site record reflected that 6-cycles had
been done to complete all the ground beams.

To maintain the 11 days working cycle, the contractor worked out that one set of wall and column formwork
for the entire floor area, two sets of beam and slab formwork, and three sets of formwork for the cantilever
beam and slab portion were required. Table 1 shows the quantity of conventional timber formwork used in
various portion of the entire superstructure.

- 2743 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

Table 1 Calculation of Quantities of Conventional Timber Formwork for Various Elements of the Building
Items Area of Formwork for Set(s) of Area of
One Complete Floor Formwork Formwork
2 2
(m ) Provided Provided (m )
1 Column 450 1 450
2 Wall 3,009 1 3,009
3 Miscellaneous walls for roof stair house, 140 1 140
hose reel cabinets, dropper wall etc
4 Water tanks 123 1 123
5 Beam 502 2 1,004
6 Slab 1,168 2 2,336
7 Ground beam 185 0.5 92
8 Ground slab (suspension portion only) 42 Measured as required 42
9 Cantilever beam 129 3 387
10 Cantilever slab 154 3 462

The quantity of timber used for each portion of the entire conventional timber formwork system for Lam Tin
School is measured and tabulated as follow:

Table 2 Summation of Items 1, 2, 3 and 4 of Wall and Column Portions


2
Wall and Column Quantity (m ) Quantity (m) Allow for Cutting Wastage Total
2 2
18 mm thick plywood 3,722 3,722 x 0.05 = 186 m 3,908 m
50 x 75 mm softwood 21,700 21,700 x 0.1= 2,170 m 23,870 m
Miscellaneous softwood 21,700 x 0.15= 3,250 N/A 3,250 m

Table 3 Amount of Timber Formwork in Ground Beam and Ground Slab


2
Ground Beam and Quantity (m ) Quantity (m) Allow for Cutting Wastage Total
Ground Slab
2 2
18 mm thick plywood 190 190 x 0.2 x 6 cycles = 228 m 418 m
50 x 100 mm softwood 1,330 1,330 x 0.2 x 6 cycles= 1,596 m 2,926 m

Table 4 Amount of Timber Formwork for Superstructure Beam and Slab


2
Beam and Slab Quantity (m ) Quantity (m) Allow for Cutting Wastage Total
2 2
18 mm thick plywood 3,340 3,340 x 0.07 = 234 m 3,574 m
50 x 100 mm softwood 30,100 30,100 x 0.05= 1,505 m 31,605 m
Miscellaneous softwood 30,100 x 0.15= 4,515 N/A 4,515 m

Table 5 Amount of Timber Formwork for Cantilever Beam and Slab


2
Beam and Slab Quantity (m ) Quantity (m) Allow for Cutting Wastage Total
2 2
18 mm thick plywood 849 849 x 0.07 = 59 m 908 m
50 x 100 mm softwood 11,650 11,650 x 0.05= 582 m 12,232 m
Miscellaneous softwood 11,650 x 0.15= 1,747 N/A 1,747 m

The total quantity of timber materials used is summarized as follows:

- 18 mm thick plywood = (3,908 + 418 + 3,574 + 908) m2 = 8,808 m2


- 50 x 100mm softwood sawn timber = 53,025 m run, i.e. 265 m3
- 50 x 75mm softwood sawn timber = 27,120 m run, i.e. 102 m3
- Total volume of softwood sawn timber (265 + 102) = 367 m3

2.1.3 Financial Cost


It is a common practice in the construction industry of Hong Kong to sublet all major trades to subcontractors.
The formwork fixing trade for the superstructure of the Lam Tin School was subcontracted to a carpentry
subcontracting firm as a supply and fix subcontract. The rates for each type of carpentry works were
different in the bill of quantities. For simplicity, the following costs are categorized into three major groups –
wall & column, beams, and slabs (including ground beams, beams and slabs of cantilever portion).

- 2744 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

Table 6 Total Cost (Supply and Fix) of Conventional Timber Formwork for Lam Tin School
Category Contract Arrangement Material and Labour Cost
Column and Wall Supply labour and material HK$3,276,542
Beam Supply labour and material HK$1,060,731
Slab Supply labour and material HK$1,001,868
Total Variation Orders All changes in column, beam and slab (HK$70,521)
Total Amount HK$5,268,620

2.2 Case Study II - Large Panel Steel Formwork Integrated with Pre-cast Semi-Slab Unit used
Kowloon Bay School

2.2.1 The Project Design and Contract Arrangement


The school project in Kowloon Bay was a part of the new educational concept called “school village”. The
school village was made up by three schools built on a common site sharing a larger open space and
common facilities. The project comprised one 30-classroom secondary school, one 30-classroom primary
school and one 24-classroom primary school located adjacent to each others. The design of two primary
schools were similar to that used for the Lam Tin School and one contractor was responsible for constructing
both schools.

2.2.2 Selection of Formwork System for the School Village Project


Since the schools were of identical design, the formwork system could be interchangeably used. The
contractor chose the use of large panel steel formwork for wall and column and steel forms for beam. The
slab construction was by pre-cast concrete semi-slab panels placed between the edge of beams. Figure 1
shows a typical floor layout framing plan of the 30-classroom primary school.

Section 1-1

50 mm Topping of grade 30/20


Concrete
50 mm thick concrete topping

100 mm thick pre-cast concrete


Section 1-1

Figure 1: Typical Floor Layout and Semi Pre-cast Slab Arrangement

As shown in figure 1, (shaded colour portion) pre-cast concrete semi-slab panels were extensively used
covering most of the floor area. The remaining areas such as all the staircases, A/C platforms, and lift lobby,
where the beams were of longer span and for pre-cast concrete elements; slabs in these locations were cast
in-situ with conventional formwork. Section 1-1 of Figure 1 illustrates the placement of pre-cast semi-slab
units and the slab topping up concrete. The merit of choosing this formwork system was its interchangeable
nature serving both the 3-classroom and 24-classroom schools. Due to the magnitude of the work and the
time constrain, “one formwork two schools system” was adopted, i.e. one full set of large panel steel
formwork for 30-classroom school would be provided for alternative uses between the 30-classroom and
the 24-classroom school buildings.

- 2745 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

2.2.3 Working Cycle


The site condition of the Kowloon Bay school project enabled a full range operation of tower cranes and
crawler cranes so that lifting and shifting of the large panel steel formwork from one school building to
another could be effectively carried out. The formwork erection was sequenced into four consecutive
working portions operating in alternative manner between the two school buildings. Figure 2 shows the
formwork zoning layout and working cycle schedule.

Transportation of large panel formwork by Crane

Remove formwork
from zone B for
B D1 erection in zone B1
of other school
D C B A A1 B1 C1 D1
D C B A A1 B1 C1 D1

D C B D1 C1 B1

A A1

Plan of 30-Classrooms Primary School Plan of 24-Classrooms Primary School

Figure 2: 12-Day Working Cycle for 2 Primary Schools with one Full Set System Formwork

The merit of using one full set of system formwork for two buildings was operationally simple. However, its
demerit was self-restriction. The progress of one building would be delayed if there was delay in the progress
of the other building. Because the formwork components are used interchangeably between the two
buildings, the dismantling and lifting of the formwork component from one building to another had to
maintain a “dismantle-remove-transport-receive & install” synchronized operation. For instance, after
concrete was placed in the first portion of the column and wall of the 30-classroom primary school, the
formwork had to be removed, lifted and momentarily transported by crane to the correspondent portion of the
24-classroom primary school for installation.

2.2.4 Quantity of Material Used


Material used in the large panel steel formwork system was mainly 4 mm thick mild steel sheet. The quantity
of steel material and the associated cost was measured as follow:

Table 7 Quantity and Cost of Steel Formwork Material Used


Large Panel Steel Form Total Weight of Rate/Tonne Total Cost
Steel Material HK$ in HK$
2
Total area of column = 450 m 45 tonne 5,520 249,000
2
Total area of wall = 3,150 m 275 tonne 5,400 1,458,000
2
Total area of beam = 1,004 m 195 tonne 5,650 1,101,750
2
Total area of cantilever beam = 129 m 75 tonne 5,750 431,250
Total weight of mild steel used 590 tonne Total cost of material 3,240,000*
Note: *This figure is provided by the Kowloon Bay School main contractor which is rounded up to
HK$100,000 due to commercial reason.

Other than large panel steel formwork, some conventional timber formwork was also used in staircases and
areas where the structural members were of longer spans. To maintain the planned 12-day working cycle for
each typical floor, two sets of convention formwork covering the long span areas and staircases with dead
prop devices were required.

The quantity of timber used in the conventional formwork portion of the superstructure was measured as
follow:

Area of long span and staircases: Two sets of formwork for slab and beam similar to Lam Tin school.
18 mm thick plywood: 940m2
50 mm x 100mm soft wood swan timber: 7600 m run, i.e. 40m3

- 2746 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

2.2.5 Financial Cost


Similar to the conventional timber formwork subcontracting system, the main contractor of the Kowloon Bay
School project subleted the formwork subcontract to a system formwork subcontractor. The subcontract
work included the secondary school but cost of the secondary school was carefully taken out from this study.
The following figures covered only the 30-classroom and the 24-classroom primary schools. The material
used associated with the 24-classroom primary school was separated proportionally. This enables an direct
comparison between the conventional timber formwork system used in the Lam Tin School and the large
panel steel formwork and pre-cast semi-slab unit used in the Kowloon Bay School.
The cost information shown hereunder had been rounded up to HK$100,000

Table 8 Comparison of Total Cost of Formwork


Description 24-Classroom 30-Classroom Total
Primary School Primary School
1 Cost of material for system formwork HK$1,530,000 HK$1,710,000 HK$3,240,000
(one set of formwork for two schools)
2 Cost of pre-cast unit semi-slab HK$1,777,000 HK$2,638,000 HK$4,460,000
3 Cost of conventional timber formwork portion HK$340,000 HK$400,000 HK$740,000
4 Cost of installation of system formwork HK$4,590,000 HK$5,130,000 HK$9,720,000
5 Cost of installation of pre-cast unit HK$1,600,000 HK$2,020,000 HK$3,620,000
6 Total Cost HK$9,837,000 HK$11,943,000 HK$21,780,000

3. Comparison of Materials Used and Costs

3.1 Comparison of Material Used


The material used is compared between the two 30-classroom primary schools (the material used in the
24-classroom primary school in Kowloon Bay is excluded).

Material Lam Tin School Kowloon Bay School Difference


Plywood 8,808 m2 940 m2 7,868 m2
Softwood sawn timber 367 m3 40 m3 327 m3
Mild Steel N/A 590 tonnes 590 tonnes

3.2 Comparison of project duration


The time spent on both schools were similar. The working cycle per floor for the Lam Tin School was 11 days
and for the Kowloon Bay School was 12 days. Since the schools were of eight stories high, the total time
difference was 8 days. Taking into account of site cleanliness, the lesser amount of time spent on site
cleaning of the residue timber in the Kowloon Bay School overcompensated the 8 days difference.

3.3 Comparison of Cost


Nature of Subcontract Lam Tin School Kowloon Bay School
Supply of Labour & Material HK$5,268,620 HK$11,934,000

The cost attributed to the pre-cast concrete semi-slab should be deducted by the cost of equal volume of
equivalent grade (30/20) of ready mixed concrete.

Assembly Hall/Special Room Block (5 story) 30 m3


Class Room Block (8 story) 50 m3
Total: 80 m3 @ HK$450/m3

The cost of ready mixed concrete was HK$450x80=HK$36,000 for pre-cast semi-slab panels.
The salvage value of the steel formwork was considered as scrap steel for recycling. The cost of scrap steel
less transportation charge was HK$100/tonne. The salvage value was HK$100x590=HK$59,000.

Therefore the cost of using system formwork integrated with pre-cast semi-slab was HK$6,570,380
(11,934,000 – 5,268,620 – 36,000 – 59,000) higher than the conventional timber formwork.

- 2747 -
The 2005 World Sustainable Building Conference,
Tokyo, 27-29 September 2005 (SB05Tokyo)

3.4 Other Issues


According to the information given by the main contractor of the Kowloon Bay School, wastage of pre-cast
concrete semi-slab was over 20% of the total quantity delivered to the construction site. The cause of such
high wastage value was due to poor quality of supply and careless handling during the course of
transportation and installation. Labour resources required to remove and replace the damaged semi-slab
with new one was high. The total volume of damaged pre-cast semi-slab became C&D waste was estimated
to be 16 m3 (20% of 80 m3).

4. Conclusion
Based on the comparison of the cost and resources used for the two formwork systems, for the described
school projects, the conventional timber formwork system was more economical. However, timber material
consumption for the conventional timber formwork system was high and environmentally undesirable.

But large panel formwork can be repeatedly used for over 100 times. If the metal formwork could be used in
other standard primary school projects, an economic advantage would be realized. According to the
concreting cycle described in the case study, the formwork had been used for only 35 times. The formwork
can be extensively used for more school projects of the same design to increase its economic advantage. It
is suggested that in order to encourage the use of the low-waste construction method, priority for bidding
school construction contracts could be given to those contractors who owned or are willing to use second
hand large panel system formwork.
It is also noticed that environmental advantages warrant the use of system formwork over timber formwork.
The economic disadvantage would be overcome when the repetitive usage cycle is extended especially for
high-rise building construction.

Acknowledgements
The authors would like to express their sincere thanks to the following persons for providing valuable
information for this study.
Mr. Percy Lau and Mr. Sunny Chan of Chevalier (Construction) Co., Ltd.
Mr. Simon Lee and Mr. Andrew Ip of China Civil Engineering Construction Corp.
Mr. C. K. Chan of Loyal Eastern Ltd.
The financial support of the Hong Kong Polytechnic University is also acknowledged.

References:
Policy Address 1999, Hong Kong Special Administrative Region Government. Quality people, quality home,
Policy address by the Chief Executive, 1999. Hong Kong: HKSAR, 1999.

Environmental Report 2000, The Architectural Services Department: Environmental Report 2000. Hong Kong:
HKSAR, 2000.
BEER 2000, Building Energy Efficiency Research, http://arch.hku.hk/research.BEER/
Hui and Cheung 2000, Building energy efficiency research, Hong Kong: The University of Hong Kong, 2000.
Standard Method of Measurement 2001, Architectural Services Department. Standard method of
measurement for building element. Hong Kong: HKSAR, 2001.
Tang, H. 2001, Report of the Construction Industry Review Committee: construct for excellence. Hong Kong:
HKSAR, 2001.
General Specification 2002, Architectural Services Department. General Specification of Building Volume
1&2, 2002 (ed.), section 6.03 to 6.12. Hong Kong: HKSAR, 2002.