Chapter2-4 Project Management Framework
Chapter2-4 Project Management Framework
Project :
Temporary endeavor with a beginning and an end
Create a unique product ,service or result
Done for a purpose
Has interrelated activities
Is progressively elaborated
Portfolio is a collection of programs and/or projects and other work that are grouped together to meet strategic
objectives. These may not be interdependent or directly related.
Program is a group of related projects managed in coordinated way to obtain benefits and control not available from
managing them individually.
Forms Of Organization
Functional : (Power rests with the functional manager)
Matrix : (In strong matrix, power rests with the project manager . In week matrix, power rests with the functional
manager . In a balanced matrix, the power is shared between the functional manager and the project manager .
Projectized : All organization is by projects. The project manager has total control of projects. Personnel are assigned
and report to a project manager .
Matrix
Advantages Disadvantages
Highly visible project objectives Not cost effective because of extra administrative
personnel
Improved project manager control over resources More then one boss for project teams
More support from functional organizations More complex to monitor and control
Maximum utilization of scarce resources Tougher problems with resource allocation
Better coordination Need extensive policies and procedures
Better horizontal and vertical dissemination of Functional mangers may have different priorities than
information than functional project managers
Team members maintain a "home" Higher potential for conflict and duplication of effort
Functional
Advantages Disadvantages
Easier management of specialists People place more emphasis on their functional specialty
to the detriment of the project
Team members report to only one supervisor No career path in project management
Similar resources are centralized, companies are Project manager has no authority
grouped by specialties
Clearly defines career path in areas of work
specialization
Chapter5 Integration Management
Lessons learned: is a document that talks about what was done right, wrong and what be done differently if the project
could be redone. It should cover three areas :
Technical aspects of the project.
Project management (how did we do with WBS creation, risk etc.?)
Management (how did we do with communications and leadership as a project manager? )
Project management information system (PMIS) : is an all-encompassing phrase to mean the system set up in advance
that keep the project manager informed of the status of all project tasks. A PMIS is critical to now what is really happening on the
project and the real status of the project . it may contain manual and automated tools , techniques and procedures including
reporting ,meetings, management by walking around ,asking questions and using a Gantt chart.
Baseline : every time you see the word baseline, think of the original project plan with approved changes .
Kickoff meeting : a meeting of all parties to the project (customers, sellers, project team, senior management, agencies,
functional management, sponsor). It is held at the end of the planning phase just before beginning work on the project .
Work authorization system : a formal procedure for sanctioning project work to ensure that work is done at the right time
and in the proper sequence .
Change control board : is formed to review change requests to determine if additional analysis is warranted . they also
approve or reject project changes. the board may include the project manager, customer, experts, sponsor ad others .
Change control system : a collection of formal, documented procedures, paperwork, tracking systems and approval
levels for authorizing changes .
The exam has many situational questions, dealing with hw to make changes.
For example :
A functional manger wants to make a change to the project .what is the first thing a project manager should do? Or , a senior
manager wants to make a change to the scope of work . what is the best thing to do first?
The answers are the same in either case . generally, the team should follow these steps :
1. evaluate (assess) the impact of the changes to the project
2. create (compute) alternatives including cutting other tasks, crashing, fast tracking, etc .
3. meet with management ,sponsor and internal stakeholders
4. meet with customer as necessary
Chapter6 Scope Management
Scope Management: Includes the processes required to ensure that the project includes all the work and only the work
required to complete the project successfully .It is primarily concerned with what is ad what is not in the project.
Constraints : factors that limit the team's options such as resources , budget, schedule and scope .
Scope Statement : provides a basis for common understanding of the scope among the stakeholders and to determine if
the project phase has been completed .
Scope management Plan : a document that describe how scope and scope changes will be managed .
Management By Objectives (MBO) : A management philosophy that says an organization should be managed .It has
three steps :
1. Establish unambiguous and realistic objectives .
2. Periodically evaluate if objectives are being met
3. Take corrective action
Delphi technique : A method most commonly used to obtain expert opinions on technical issues, scope of work needed,
estimates or risks .
To use Delphi technique, a request for information is sent to experts, the responses they return are compiled, and the
results are sent back to them for further review. The Delphi technique has three rules :
1. Do not get the experts in the same room
2. keep the experts identifies anonymous
3. Try to build consensus
A WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the project
.
Scope Definition and Decomposition : is subdividing the major project deliverables into smaller, more manageable
components. The best way to handle these terms is to think of scope definition and decomposition as what you are doing, and the
WBS as the tool to do it .
Scope Verification : The process of formalizing acceptance of the project scope by the stakeholders .
Scope verification focus is on the acceptance of the scope of the work while quality control involves analysis of the
correctness of the work .
Chapter7 Time Management
Scheduling Tools :
1. Milestone Charts
2. Flowcharts
3. Bar(Gantt) Chart
4. Network Diagram
Under what circumstances would you use a network To show interdependencies between tasks
diagram instead of a Gantt chart ?
Under what circumstances would you want to use a To report to senior management
milestone chart instead of a Gantt chart ?
Under what circumstances would you want to use a To track progress
Gantt chart instead of a network diagram ? To report to the team
A network diagram is completed after the project charter ,project staffing and WBS .
Estimating Methods :
1. CPM ( Critical Path Method ) :
It refers to estimating based on one time estimate per activity
2. PERT (Program Evaluation and Review Technique )
PERT formula : (P+4M+O)/ 6
Standard Deviation of a task using PERT : P-O/6
Variance of a task using PERT : (P-O/6)2
# in order to find standard deviation of a series of items ,there is a rule . You cant add standard deviations ; you must convert
standard deviations into variances and then take the square root of the total to convert back into standard deviation .
3. Monte Carlo Simulation .
The critical path is the longest duration path through a network diagram and determines the shortest time to complete
the project .
SLACK ( FLOAT) : the a mount of time a task can be delayed without delaying the project .
Slack is found using either LS-ES or LF-EF . LS is the latest a task can start, ES is the earliest a task can start ,
LF is the latest a task can finish and EF is the earliest a task can finish .
The general definition of slack can be refined further to the following subcategories of slack :
1. Free Slack (float) : the a mount of time a task can be delayed without delaying the early start date of its successor .
2. Total Slack (float) : the amount of time a ask can be delayed without delaying the project completion date .
3. Project Slack(float) : the amount of time a project can be delayed without delaying the externally imposed project
completion date required by the customer or management , or previously committed to by project manager .
Resource Leveling : Leveling lets schedule and cost slip in favor of having a stable number of resources each month .
Inputs To Estimating : (or what do you need before you estimating cost or time ) :
1. WBS
2. Network Diagram
3. Schedule
4. Historical information
5. Resource pool
6. Risk management plan
7. Risks
Advantages of analogous estimating Disadvantages
Quick Less accurate
Tasks need not be identified Estimates prepared with a limited amount of detailed
information and understanding of the project
Less costly to create Requires considerable experience to do well
Gives the project manager an idea of the level of Infighting at the highest management levels to gain the
management's expectations biggest piece of the pie without knowing what the pie is
Overall project costs will be capped Extremely difficult for projects with uncertainty
Today
Original
Plan PV BAC
AC ETC EAC
Present Value : means the value today of future cash flows and can be found by the formula :
PV = FV / (1+r)n
FV : future value r: interest rate n : number of time periods
Net Present Value (NPV) :means the present value of the total benefits (income or revenue ) less the costs .
You have two projects to choose from .project A will take three years to complete and has an NPV of US $45000. project B will
take six years to complete and has an NPV of US $85000 which one would you prefer ?
The answer is project B
Benefit Cost Ratio (BCR) : compares the benefits to the costs of different projects where benefits are the same as
revenue, or sometimes referred to as "payback" . Remember that revenue is not the same as profit . a BCR of >1 means the
benefits are greater than the costs . a BCR of <1 means the costs are greater than the benefits . a BCR of 1 means the costs and
benefits are the same .
Opportunity Cost : The opportunity given up by selecting one project over another .
You have two projects to choose from : Project A with NPV of US$ 45,000 or Project B with an NPV of US$
85,000 what is the opportunity cost of selecting project B ?
The answer is $45,000
Cost Of Conformance Cost Of Non Conformance
Quality training Rework
Studies Scrap
Surveys Inventory costs
Warranty costs
Tricks for understanding the difference between quality planning ,assurance, and control
Quality Planning Quality Assurance Quality Control
Plan Implement ,check overall Measure details
What quality standards should What lessons can we find to Let's measure (test) the
we improve quality – quality number of errors in the
Tricks to use on the project ? audit ? program .
understand the
difference How will we meet those Let's take the outputs of quality Let's measure schedule
standards control measurement and see performance.
if we will meet the overall
quality standards. Did we meet the specific
quality standards ?
Are our quality standards still
appropriate ?
Mostly done
during Planning Executing controlling
Responsibility Chart :
1. Responsibility Matrix : this chart cross-reference team members with tasks they are to accomplish
2. Resource histogram :Is a graph that shows the number f resources used each month and is displayed in a bar chart
format.
3. Resource Gantt chart . : Shows WHEN staff is allocated to tasks
Halo Effect : The tendency to rate high or low on all factors due to impression of a high or low rating on some specific
factor. This can mean " you are a great programmer therefore we will make you a project manager and also expect you to be
great "
Leadership styles :
1. Directing : Telling others what to do
2. Facilitating : Coordinating the input of others
3. Coaching : Instructing others
4. Supporting : Providing assistance along the way
5. Autocratic making decisions without input
6. Consultative : Inviting ideas from others
7. Consensus Problem solving in a group with decision making based on group agreement >
Communications Method When used
Formal written Complex problems , project plans , project charter ,
communicating over long distances
Formal verbal Presentations , speeches
Informal written Memos , email , notes
Informal verbal Meetings , conversations
Communication Blockers :
1. Noise
2. Distance
3. Improper encoding of messages
4. Saying "that is a bad idea "
5. Hostility
6. Language
7. Culture
Communication Channels :
N x (N-1) /2 where N equals the number of people
Performance reporting :
1. Status report : describing where the project now stands .
2. Progress report : describing what has been accomplished .
3. Trend report : examining project results over time to see if performance is improving and deteriorating
4. forecasting report : predicting future project status and performance .
5. variance report : comparing actual results to planned .
6. earned value : integrating scope , cost and schedule measure to assess project performance .
All projects must be closed out no matter the circumstances under which they stop , are terminated or complete . if the
project involves contracts , contract close out should occur before administrative closure .
Definition of Risk or Risk event : a discrete occurrence that may affect the project for good or bad .
Risk Factors :
1. The probability that it will occur (what)
2. The range of possible outcomes (impact or amount at stake )
3. Expected timing (when) in the project life cycle
4. Anticipated frequency of risk events from that source (how often )
Risk averse - some one who does not want to take risks .
Risk Tolerances : The amount of risk that is acceptable ( tolerance level ) .for example " a risk that affects our reputation
will not be tolerated " or " a risk of two weeks delay is okay but nothing more .
Types Of Risk :
1. Business : Risk of a gain or loss
2. Pure ( Insurable ) risk : Only a risk of loss ( e.g. fire ,theft , personal injury )
Risk Triggers : (Symptoms) : A PM should determine what are the early warning signs for each risk on a project so that
they will understand when to take action .
Expected Monetary Value (or Expected Value ) : The product of two numbers , probability and consequences ( impact or
the amount at stake )
Contingency Plans - Planned response to risks or putting in place the contingency plans set up during risk response
planning
Workarounds : unplanned responses to risks or dealing with risks that you could not or did not anticipate .
Chapter13 Procurement Management
General Rules :
1. A contract is a formal agreement
2. All requirements should be specifically stated in the contract .
3. All contract requirements must be met
4. changes must be in writing and formally controlled
5. Most governments back all contracts by providing a court system for dispute resolution .