METHOD OF STATEMENT - RAFT FOUNDATION
CONCRETE PORING
1. LOCATION & SCOPE
4.1 RAFT CONCRETE:
4.1.1 Tools & Equipment Required
Concrete Pump
Truck Mixer Concrete
Vibrator
Shovels
Floats
Survey Instruments Health & Safety Requirements :
4.1.2 Health & Safety Requirements :
‘* Safety of the personnel and properties is to be given prime importance and all the
works to be carried out without causing any accident or property damages
* Follow the Approved Project HSE Manual and Regulation.
4.1.3 Material :
Ready mix Concrete as per Specification & engineer approval.
4.1.4 Application:
Pre-Concreting
.In foundation, after fixing the reinforcements cleaning shall be carried out by blowing
‘compressed air through a nozzle to the bottom of rebar.
The surveyor shall check the line and levels after which, the QC inspector shall be conduct
inspection.
The QC inspection will ensure that no item such as rebar, spacer block, any embedded
item, has been disturbed or displaced by the cleaning operations,
fa water bar (Water stopper) is to be installed and required in the RCC.
or structural element, ensure the following: Water bar is
securely fixed
‘Water bar is placed in the correct level and alignment
Welded joint are correctly executed.
b. The Engineers inspection shall follow within 24 hour from the timing of Seapal submitted
WIR. If the Engineer finds the works satisfactory, he shall sign off the WIR and release the
work to continue. However, if the Engineer fined some items in the site work need corrective
action, he shall hold the release of work, until such time that deficient items are corrected by
stating the deficiencies on WIR. The release of work WIR with "Approved" status will
authorize to. be inspect by AlSuweidi resident engineer - before the commencement of
concrete placing.
Placing Concrete
* Ensure the concrete design mixed is approve.
* To check the allowed ambiance temperature for scheduled concrete
pouring
* To check before pouring for concrete temperature limits of 5 deg.
Celsius up to 30 deg. Celsius.
+ To ensure all type of newly casted concrete poured structure has cube
samples for monitoring of 7-28 days compressive strength.
* The contractor shall take (6) 150mm cube for every 100 m3
a. With the authorization release to start concrete pouring through Sepal -PM and
Engineer's approval, concrete of specified strength shall be requested from the approved
ready mix concrete supplier. Concrete of desired designed mix shall be delivered to the site
through transit mixers, each truck having a concrete Delivery Ticket / Receipt, bearing
relevant data of concrete load.
b. Slump and concrete temperature are to be check by Engineers and AlSuweidi
representative base on the designed slump and allowable concrete temperature.METHOD OF STATEMENT - RAFT FOUNDATION
CONCRETE PORING
‘Slump is to be taken by laboratory technician at site applying the required fresh concrete
tests as per required and requested by Engineer following the fresh code
d. Adding water to truck mixer is strictly not allowed at all time, Engineer has the right to reject,
cancel the delivered concrete, and recammend to replace with new and or stop the casting in this
reason and purposes.
. During hot weather, All concrete delivery should be with ice to maintain the temperature before
placing,
1, The concrete shall be deposited by a concrete pump starting from both ends of the formworks at
the typical practice rate 90 cu. m. per hour. Concrete shall be poured as closed as possible to
its final positions, in layers not exceeding 300mm of consolidated thickness. Layers
of concrete shall be carried out in good timing that the concrete in the previous layer has
not attained Its initial set before the succeeding layer is laid, and that compaction/vibration in
between layers shall be made good to prevent cold joint.
During the concrete pouring when only one (2) concrete pump is used two to four ~ inch
diameter vibrators shall be used for concrete consolidation, with an additional one(1) unit of
vibrator on standby.
h. The concrete shall be poured at a drop height of not more than 0.5 meters, A rope of
1.0 meters length shall be hanged from the open end of the flexible hose of the concrete
pump, to ensure that the hose operator can maintain within the required height.
Immediately after placing and compacting, the exposed concrete shall be graded to desired
level.
Also for concreting during hotweather at summer months, the
‘Temperature of concrete when deposited “does not” exceed 30 deg. Celsius.
m. General Foreman shall be responsible for routine inspection during concrete pouring to
ensure that all works are proceeding according to this method statement and the project
specification,
n. If there is problem or non-compliance to specifications for this method statement, The
Construction Manager shall be notified immediately in order to provide early remedial actions,
Concrete Delivery:
All concrete delivering truck mixer shall be accompanied each with a concrete batch
ticket or delivery receipt. With the site engineer or his representative shall check these
tickets against the concrete requisition form to ensure that the delivered concrete is
‘same as the requested one. He shall be also raceived the concrete load by signing the
ticket or delivery receipt.
1. QC Inspector shall check the type of delivered concrete and ensure the delivered concrete to site is
the define one, and ensure that any additive shall be added to the concrete on site under the
consultant approval additive material recommendation. (Refer to approved design mix)
2. QC Inspector shall write the time of arrival and departure of concrete truck mixer from site on the
ticket or delivery receipt.
3. Truck mixer shall return to the batching plant, after discharging its concrete load. Delivery ticket or
receipt, properly Signed from the pouring site shall be stamped by a time clock, marking the truck
arrival at the batching plant.
Concrete Curing:
The finished surface will be cleaned ensuring that it is free from contaminants.
Curing compound as per the Engineer's recommendation can be used, the
application of the curing compound shall be comply strictly with the manufacturer's
instruction.
From the above curing method, variation shall be adopted when concreting during
hot weather with the following:
In case of large area as in continuous pour, the curing operation shall commenceMETHOD OF STATEMENT - RAFT FOUNDATION
CONCRETE PORING
immediately on the completed and surface finished section without waiting for the whole
pouring to be finished.
‘When the concrete surface is hard enough to resist damage, the
exposed concrete surface shall be closely covered with polythene sheet,
properly secured to prevent removal by wind and development of air
spaces beneath it. This shall be stay in place and moist for seven 7
days
Post Concreting :
1. After completion of the curing period, as specified, a visual inspection shall be
carried out by QC inspector to verify and ascertain that there are no concrete
surface deficiencies.
2 In case of surface deficiencies spotted, appropriate corrective and remedial
repairs shall be initiated immediately, after curing in accordance with method
statement for concrete repairs. After satisfactory corrective repairs of the surface
deficiencies, WIR is raised to get the Engineers approval of works.RISK ASSESSMENT FOR CONCRETE POURING
c
PROJECT: Commercial Building Project # P2645 __[ RiskAssessment No: Revision : 00
PREPARED BY: Muhammad Umar Saeed DESIGNATION: HSE Officer Signature: __— te Date: 27/10/2020
t
i Evaluati = 7
Description Potentials | aed veers Actions required To reduce or control risks | Reeves | “a | Action
of Task Hazard side (ALARP) After CJ
Concrete Being hit or ¥ Implement Traffic management plan.
delivery run over By gygnag | {mM | ¥_ When delivering concrete, the following should be ensured, Hemet) gana | Oe
i : (a) Concrete delivery trucks should have clear and safe access to
(Concrete delivery truck. | consultant Shoes / /Forema
7 oe approach and leave the receiving hopper of the pump. Boots n
delivery Entrapment | ee (b) If more than one concrete delivery truck is required to approach the
involves the " receiving hopper at any one time, the person in control of the relevant | Hvis
between the | Delivery . Vest
delivery of delivery truck vehicles workplace area should ensure a spotter or traffic controller is on hand to
te f drivers, safely direct the movement of the trucks, considering the safety of each | safety
concrete trom | and hopper or Contractors worker in the area. Goggles
the delivery between | visitors, (c) Concrete delivery trucks should not reverse into the exclusion zone if
truck to the delivery ‘The Public they cannot see the nominated person for directing the truck (the Mock
concrete pump trucks. spotter). The vehicle should be stopped immediately when the driver
Entanglement loses sight of the nominated person directing the truck. Gloves HSE
hopper.) :
per. _ crushing and (d) If more than one concrete delivery truck is required to approach the Officer
amputation receiving hopper at any one time the person in control of the relevant M Me
from the workplace area should ensure: enor
(e) No person should stand between the reversing concrete delivery
concrete
truck and the hopper.
hopper.
(f) The concrete chute on concrete trucks should only be moved when
the truck is stationary. It is preferable for the truck driver to perform this
task. If another worker carries out the task the permission of the driver
should be obtained.
(g) The concrete receiving hopper should be at a height that allows a
gravity flow of concrete into the hopper.
(h) Additional ramping may be required for the concrete delivery truck
where low slump concrete is to be used.
Approved by: Name: Hussein Shdifat
Designation: Project Manager Date: 27/10/2020 Signature.