Laguna Lake Water Treatment Plan

The document provides a 2-week look-ahead schedule for May 2020 for the Design and Build 150 MLD Laguna Lake Water Treatment Plant project located in Poblacion, Muntinlupa City. Key activities in the next two weeks include: finalizing the core design and developing detailed design drawings for the raw water intake, treated water reservoir, and flowmeter. General preliminaries will involve geotechnical surveys including offshore and onshore drilling, testing, and compliance activities. Civil and structural works will begin with earthworks such as excavation and backfilling.

Uploaded by

Ian Ventura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
210 views1 page

Laguna Lake Water Treatment Plan

The document provides a 2-week look-ahead schedule for May 2020 for the Design and Build 150 MLD Laguna Lake Water Treatment Plant project located in Poblacion, Muntinlupa City. Key activities in the next two weeks include: finalizing the core design and developing detailed design drawings for the raw water intake, treated water reservoir, and flowmeter. General preliminaries will involve geotechnical surveys including offshore and onshore drilling, testing, and compliance activities. Civil and structural works will begin with earthworks such as excavation and backfilling.

Uploaded by

Ian Ventura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Project Title: Design and Build 150 MLD Laguna Lake Water Treatment Plant

Location: Poblacion, Muntinlupa City


Contract No.: WS-19-WTP-01
Contractor: AA-DMCI Consortium

2 Weeks Look-ahead Schedule


May 2020
WEEK 01 WEEK 02
11 12 13 14 15 16 17 18 19 20 21 22 23 24
Schedule No. 3 Design Services
• Core Design
•Civil Works/ Building
•Civil / Structural Design Bases Final Revision/Review/Approval
• Process
• Tempfacil Design/Drawings (for permit)
• Developed (Detailed) Design
•Archi / Structural Design Drawings for Raw Water Intake
•Archi / Structural Design Drawings for Treated Water Reservoir
•Archi / Structural Design Drawings for Flowmeter
Schedule No. 4.1a General Preliminaries
• Geotechnical Survey
• Mobilization for On-Shore Drilling
• Set-up of Rig/Dismantling of Rig
• Drilling of Borehole
• Downhole Shear Test
• Mobilization for Off-Shore Drilling
• Set-up of Platform/Dismantling of Rig
• Drilling of Borehole
• Laboratory Testing
• Site Clearing
• Mobilization/Demobilization
• Cleaning and Grubbing
• Full Contractual Compliance (bonds and insurances, permits and
clearances)
• Regulatory, Implentation of Construction Safety, Health Programme, Quality and
Environmental, Management Systems
Schedule No. 4.2a Civil and Structural Works for 50 and 150 MLD
• Earthworks
• Excavation
• Backfilling

Prepared by: Certified Correct by: Noted By:

Javier Ruiz/ Noel Villanueva NEPTHALIE CELES CHESTER BONGAY


AA-DMCI, Contractor ARUP, Project Management Consultant Maynilad Construction Manager