JABATAN KERJA RAYA MALAYSIA
KERJA-KERJA PENGGANTIAN 29 UNIT LIF DAN LAIN-LAIN KERJA BERKAITAN
DI APARTMENT A,
PANGKALAN TLDM LUMUT, PERAK
NO. KONTRAK: JKR / IP / CKM / 192 / 2019
WORK METHOD STATEMENT
SLOPE CONSTRUCTION
KONTRAKTOR
FESMA SDN BHD
71-1, JALAN SBC 1,
TAMAN SRI BATU CAVES,
68100 BATU CAVES, SELANGOR
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: ii
WMS FRONT PAGE
PROJECT TLDM LUMUT Pack
WORK METHOD STATEMENT
SLOPE CONSTRUCTION
VER. 2020-03
12 NOVEMBER 2020
Prepared By Revised By
Revision Description Date
Name Date Name Date
1 Initial Release Mohd Hasif 11 Feb 2020 IR SM Salim Abu Yusof 13 Feb 2020
2 Revised Mohd Hasif 4 Aug 2020 IR SM Salim Abu Yusof 7 Aug 2020
3 Revised Mohd Hasif 12 Nov 2020 IR SM Salim Abu Yusof 13 Nov 2020
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: iii
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
TABLE OF CONTENTS
PAGE
COVER PAGE i
FRONT PAGE ii
TABLE OF CONTENTS iii
1.0 INTRODUCTION 1
2.0 MATERIALS 2
3.0 TOOL AND EQUIPMENT 2
4.0 HAZARD IDENTIFICATION AND SAFETY PRECAUTION 3
5.0 WORK METHODOLOGY 5
6.0 DETAIL DRAWING 6
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 1
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
1.0 INTRODUCTION
1.1 Project Description
This project involves the replacement works of twenty-nine (29) lift units and other
related works at Apartment A, Pangkalan TLDM Lumut, Perak. The blocks involved in
this project are A1, A3, A4, A5, A6, A7, A8, A9, A10, A11, A12, A13, A14, A25 and A26.
The lift installation process will be carried out in five phases to make sure that the
project is completed on time. For the first four phases, six (6) lift units will be installed
while the remaining five (5) lift units will be installed in the last phase.
Therefore, in order to avoid any delay in between the phase and all works in line
with Jabatan Kerja Raya requirement, a method statements was constructed. This section
will explain in detail the slope construction works that will be carried out at each block
stated above.
1.2 Objective
The purpose of this work method statement is to provide the personnel associated with the
works referred with appropriate work methodology and test procedures do that the Quality
requirements as defined can be accomplished when planning and executing the works
describe herein. This Work Method Statement covers the preparation and placement of a
concrete topping and sand-cement screed mix on structural slab surface in preparation for
final floor finish and to construct slope at landing door. The following table shall be used to
classify the material and method to be used:
Slop Requirement Type of Material
1:10 Sand-Cement Screed
*Note: Maximum topping to be poured is 100mm.
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 2
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
2.0 MATERIALS
1. Sand Cement Screed Mix with ratio of 6 parts sand to 1 parts cement
3.0 TOOLS AND EQUIPMENT
1. Screeding Tools
2. Cement Mixer
3. Hammer Drill
4. Digital Level
5. Spirit Level
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 3
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
4.0 HAZARD IDENTIFICATION AND SAFETY PRECAUTION
4.1 HIRARC FORM
HIRARC FORM
Company : Fesma Sdn Bhd
Conducted by :
Pengkalan Tentera Udara Di-Raja
Process / Location : (Name, Designation)
Malaysia (TLDM), Lumut
Approved by : Date: …. / …. / 2020 to …. / …. / 2020
Date : …. / …. / 2020 Review Date : …. / …. / 2020
1. Hazard Identification 2. Risk Analysis 3. Risk Control
Existing PIC
Work Which can Risk (Due
No. Hazard Likelihood Severity Risk Recommendation
Activities cause / effect Control Date /
(if any) Status)
Wear safety
Slip trip and shoes, safety
Physical injuries √
fall gloves, safety
helmet
Consider using
Hacking and
Overexertion trolley.
1. drill Works Back pain √
/ straining Correct lifting
heavy tool
Wear PPE such as
Exposures to
safety helmet,
sharp Tissues injuries √
safety glove,
material
goggles etc
Slip trip and
Physical injuries √ Wear PPE
fall
Screeding
2.
Works Wear PPE such as
Exposures to
safety helmet,
sharp Tissues Injuries √
safety glove,
material
goggles etc
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 4
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
4.2 Personal Protective Equipment
Heavy Duty Safety Equipment Goggles
Safety Jacket Nose Mask
Safety Shoes Safety Gloves
4.3 Safety Precaution
4.3.1 Emergency Arrangements
Emergency contact no. will be displayed at a prominent location and on the
back of workmen ID card.
Emergency assembly points will be demarcated at prominent locations.
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 5
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
4.3.2 Training
Maintains process for ensuring that personnel performing specific critical roles
competent on the basis of,
Awareness.
Experience & knowledge.
Skills.
Conduct daily pep talk.
Daily walk around on site for quality implements.
Awareness to site team about job cards.
Conduct to site team for method of work.
4.3.3 Other Information
• The workplace should be cleaned at the end of the day.
• Avoid direct contact with sand-cement screed material.
• Site safety sign and rules shall be strictly followed.
• Utilized the cement mixing, and vibrating equipment in accordance
With the manufactures instruction.
• Wear personal protective equipment & high visibility jackets at the site.
5.0 WORK METHODOLOGY
1. Site survey for dimension taking
2. Establish finish elevation markings as required.
3. Prepare guide on floor in accordance with the required topping elevation.
Make sure the thickness of finish is considered as required.
4. Randomly scratch upon Finish Floor Level surface approximately 1 – 10mm.
5. Construct slope at gradient 1:10 measuring from onsite landing door.
6. Apply the concrete topping or sand-cement screed to the required depth.
Make sure that the concrete topping or sand-cement screed is evenly
applied before finishing operation takes place.
7. Level the surface to the desired finish.
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 6
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
6.0 DETAIL DRAWING
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]
Rev: 2020-03
Slope Construction
SLOPE CONSTRUCTION
Date: 12 Nov 2020
Page: 7
WMS WORK METHOD STATEMENT
PROJECT TLDM LUMUT Pack
Area that need to be scratch
Typical Sectional Lift Entrance Plan
71-M, JALAN SBC 1, TAMAN SRI BATU CAVES, 68100 BATU CAVES, SELANGOR. TEL: 03-61774655 FAX : 03-61774135 EMAIL: [email protected]