0% found this document useful (0 votes)
1K views8 pages

Individual Assignment #1 - Network Diagram Exercise

The document provides instructions for a project network exercise. It asks the student to: 1) Draw arrows to indicate the logical flow of the network 2) Fill in durations for each activity 3) Conduct forward and backward passes to calculate start/end dates 4) Identify the critical path It includes a work breakdown structure (WBS) with activities, predecessors, and durations.

Uploaded by

veenajkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views8 pages

Individual Assignment #1 - Network Diagram Exercise

The document provides instructions for a project network exercise. It asks the student to: 1) Draw arrows to indicate the logical flow of the network 2) Fill in durations for each activity 3) Conduct forward and backward passes to calculate start/end dates 4) Identify the critical path It includes a work breakdown structure (WBS) with activities, predecessors, and durations.

Uploaded by

veenajkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Project Network Exercise: Provides instructions for a project network exercise, including drawing flow arrows, calculating paths, and identifying critical path.
  • Project Network Diagram: Provides a blank network diagram layout for visual representation of project tasks and flow.
  • Project Network Exercise: Reiterates the project network exercise instructions for repeated practice.
  • Project Network Diagram: Repeated network diagram layout for multiple exercise attempts.
  • Project Network Exercise: Instructions repeated for continuous exercise practice.
  • Project Network Diagram: Continued blank diagram for visual task arrangement.
  • Project Network Exercise: Additional project network exercise details the same tasks for critical path learning.
  • Project Network Diagram: Another repeat of the diagram for practical working space.

Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 1
B Order parts A 6
C Produce parts A 4
D Design parts A 1
E Software Dev. A 3
F Manufacture parts B,C 6
G Assemble D,E 4
H Test F,G 9
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 2
B Order parts A 5
C Produce parts A 7
D Design parts A 9
E Software Dev. A 5
F Manufacture parts B 1
G Assemble C, D, E 3
H Test F,G 1
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 3
B Order parts A 4
C Produce parts A 8
D Design parts A 10
E Software Dev. A 6
F Manufacture parts B, C, D 2
G Assemble E 5
H Test F,G 3
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID
Project Network Exercise

Name:

Student ID:

Complete the exercise. You will need to:

1. Draw in the arrows that indicate the logical flow of the network.
2. Fill in the durations.
3. Conduct a forward pass of the network.
4. Conduct a backward pass of the network.
5. Clearly indicate the critical path.

WBS
ID Activity Predecessor Duration
A Order review 4
B Order parts A 3
C Produce parts A 2
D Design parts A 5
E Software Dev. A 4
F Manufacture parts B,C 7
G Assemble D,E 2
H Test F,G 4
B ES ID EF
SL
LS DUR LF

C F

A H

D G

E Name

Student ID