Mizan Construction Work Method Statement
Mizan Construction Work Method Statement
SUB GROUP 5
NAME ID NO.
1-TIKO ABDI ETR/826/07
2- KIDIST DEMLA ETR/477/07
3- MEKLIT BEKELE ETR/548/07
4-KIDIST TAMRU ETR/482/07
5- YISEHAK TENKER ETR/890/07
ACKNOWLEDGEMENT
First of all we thank our GOD for everything that we had a strength and commitment to do this
project. Then we would like to thanks Mr. DAWIT BEZA who gives a brief instruction for the
Finally we would like to express our sincere appreciation for our group members
encouragement in this Project and to all our friends who have been very supportive in this
GROUP -5 Page 2
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Bulk Excavation works. The take-off sheet of this
activity shall immediately be signed upon completion.
Name Name
Signature Signature
Date Date:
GROUP -5 Page 3
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Bulk Excavation works. The take-off sheet of this activity
shall immediately be signed upon completion.
Name Name
Signature Signature
Date Date:
GROUP -5 Page 4
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Bulk Excavation works. The take-off sheet of this activity
shall immediately be signed upon completion.
.
For the Consultant: - For the Contractor:-
Name Name
Signature Signature
Date Date:
GROUP -5 Page 5
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Name Name
Signature Signature
Date Date:
GROUP -5 Page 6
CHECKLIST FOR WORK
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Trench Excavation works. The take-off sheet of this activity
shall immediately be signed upon completion
GROUP -5 Page 7
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Stone work
Hard coring makes a (√)
C NC NA
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Hard Coring works. The take-off sheet of this activity shall
immediately be signed upon completion.
.
GROUP -5 Page 8
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Stone Masonry works. The take-off sheet of this activity
shall immediately be signed upon completion.
GROUP -5 Page 9
CHECKLIST FOR WORK
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Stone Masonry works. The take-off sheet of this activity
shall immediately be signed upon completion.
GROUP -5 Page 10
CHECKLIST FOR WORK
Date Date:
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Element of Structure: Footing
Placing of Reinforcement Make a (√)
C NC NA
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Placing of Reinforcement. The take-off sheet of this activity
shall immediately be signed upon completion.
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Cement
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Placing of Concrete. The take-off sheet of this activity shall
immediately be signed upon completion.
GROUP -5 Page 13
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Element of Structure: - Column or Grade beam
Formwork Make a (√)
` C NC NA
Additional Remarks
GROUP -5 Page 14
CHECKLIST FOR WORK
Cement
GROUP -5 Page 15
CHECKLIST FOR WORK
GROUP -5 Page 16
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
GROUP -5 Page 17
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
GROUP -5 Page 19
CHECKLIST FOR WORK
Degree of dryness/seasoning
Degree of paleness
Visibility of cracks
Additional Remarks:
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Purling works. The take-off sheet of this activity shall
immediately be signed upon completion.
GROUP -5 Page 20
CHECKLIST FOR WORK
Name Name
Signature Signature
Date Date:
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Roof/cladding works. The take-off sheet of this activity shall
immediately be signed upon completion.
GROUP -5 Page 21
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Super Structure
Masonry for Elevation works Make a (√)
C NC NA
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Roof/cladding works. The take-off sheet of this activity shall
immediately be signed upon completion
GROUP -5 Page 22
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Qualification of plasterer
Max. allowable thickness of coats of plaster(1 st coat, 2nd coat, 3rd coat)
Additional Remarks
GROUP -5 Page 23
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Plastering work. The take-off sheet of this activity shall
immediately be signed upon completion.
Additional Remarks
GROUP -5 Page 24
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby allowed /refused
to proceed rendering work. The take-off sheet of this activity shall immediately be
signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
Location of door/block/floor/room
Size of door
a) Frame
- Raw material
- Thickness
- Width
- Homogeneity
b) Opening Leaf
- Thickness
- Height
- Width
- Elevation homogeneity
- Raw material (Facing, edges)
GROUP -5 Page 25
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed plumbing work. The take-off sheet of this activity shall
immediately be signed upon completion.
Name Name
Signature Signature
Date Date:
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Metal Work Fabrication and Fixing work. The take-off
sheet of this activity shall immediately be signed upon completion.
Signature Signature
Date Date:
Size of wire/Cable/Colour
Sizes of connectors
Nature of clamps
Size of connectors
Spacing of pins/bracket
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Pulling of wires/cables and related accessories work. The
take-off sheet of this activity shall immediately be signed upon completion.
Name Name
Signature Signature
GROUP -5 Page 27
CHECKLIST FOR WORK
Date Date:
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Ceiling/Cladding works. The take-off sheet of this activity
shall immediately be signed upon completion.
Signature Signature
Date Date:
GROUP -5 Page 28
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Cement Screed flooring Inspection works. The take-off
sheet of this activity shall immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 29
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Wall tile coverage inspection works. The take-off sheet of
this activity shall immediately be signed upon completion.
.
For the Consultant For the Contractor
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 30
CHECKLIST FOR WORK
Testing of material
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed floor tile. The take-off sheet of this activity shall
immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 31
CHECKLIST FOR WORK
Qualification of tiller
Readiness of floor W.R.T other works
Material approval slip and sample
Submittal of tiling module
Colour of selected material
Size of plastic tile (Length, width, thickness)
Checking physical properties of sample with site deliveries;
a) Product data of sample with deliveries
b) Flexibility of tile
c) Nature of underneath fiber of tile
d) Smooth/plane nature of surface
e) Nature of adhesive (approved with new deliveries)
Name : Name:
Signature: Signature:
GROUP -5 Page 32
CHECKLIST FOR WORK
Qualification of tiler
Designed pattern
Checking of specified rooms with quantity
Material approval slip number and sample
Size of marble checking
a. Length
b. Breadth
c. Thickness
Edge condition of delivered piees
Surface nature of delivered pieces (free from cracks, holes perforations)
Condition of floor to be covered
a. Adopted levelling course correction
b. State of chiselling of surface
c. Washed and free from dust grits etc
d. Checking application of designed mortar thickness
Type of mortar and mix ratio for laying
Grouting type (material)
Quality of fine aggregate, water etc..
Method of mixing of mortar
: Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed tile working. The take-off sheet of this activity shall
immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 33
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Stair tread and riser inspection . The take-off sheet of this
activity shall immediately be signed upon completion
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 34
CHECKLIST FOR WORK
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 35
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Steel Structure work. The take-off sheet of this activity shall
immediately be signed upon completion.
Signature: Signature:
Date: Date:
GROUP -5 Page 36
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Painting . The take-off sheet of this activity shall
immediately be signed upon completion.
Signature: Signature:
Date: Date:
GROUP -5 Page 37
CHECKLIST FOR WORK
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Glazing Work The take-off sheet of this activity shall
immediately be signed upon completion.
Signature: Signature:
Date: Date:
GROUP -5 Page 38
CHECKLIST FOR WORK
Project:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Plumbing and sanitary work inspection
Make a (√)
C NC NA
Qualification of plumber
Pipe position(Surface/embedded)
Fixtures
a. Colour appearance
b. Formation of threads
c. On site random manual thread formation against the approval
d. Checking of weight of specimen
e. Presence of cracks
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Painting . The take-off sheet of this activity shall
immediately be signed upon completion
Name: Name:
Signature: Signature:
Date: Date:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Down pipe Make a (√)
C NC NA
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Painting . The take-off sheet of this activity shall
immediately be signed upon completion
Signature: - Signature:-
Date: - Date:-
Project:
Employer: Block/Bill:
GROUP -5 Page 40
CHECKLIST FOR WORK
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Gutter Work Make a (√)
C NC NA
Submittal of detail shop drawing
Thickness, width and length of the brackets
Type of Gutter
Nature of the material (Its galvanization and the like)
Type of lead materials
No of joints; and type of connectors (for U PVC Down pipes)
Sufficiency of overlap length
Precedence of Fascia board/ final plastering
Slope of gutter
Spacing of the straps
Detailing of Roof treatment connection with the Down pips
Means of fixity
Qualification of work men
Sample Preparation
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Gutter work. The take-off sheet of this activity shall
immediately be signed upon completion.
For the Consultant For the Contractor
Name: Name:
Signature: Signature:
Date: Date:
Consultant: Floor:
Location:
Document Referred:
Plumbing and Sanitary work Inspection Make a (√)
Sanitary Fixtures C NC
NA
Presentation of Methodology
Qualification of Plumber
Location of fixture
Positioning of fixture
Material approval slip number (Date)
Checking physical properties of sample with deliveries
a. Colour
b. Shape
c. Flusher accessories
d. Shape of discharge outlet
e. Lid cover
f. Solidness of full set
g. Position of outlet of siphons
Fitting compliance with product data
Dimensional measurement for fixing
a. Horizontal
b. Vertical
c. With reference to floor/ceiling
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Electrical work. The take-off sheet of this activity shall
immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 42
CHECKLIST FOR WORK
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Electrical work Inspection
Fixing of Boards/Breakers/Bell Control Make a (√)
C NC NA
Qualification of electrician /Grade
Location of item wall/ceiling/floor
-Thermoplastic
-Thermosetting
Nature of fixing to proposed position product data/New idea
Clamp nature at joint of boards to cables
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Electrical work. The take-off sheet of this activity shall
immediately be signed upon completion.
Signature Signature
Date Date:
Project:
GROUP -5 Page 43
CHECKLIST FOR WORK
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Protection measure for incidental REDOX action at point of screws and slots;
. Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Electrical work. The take-off sheet of this activity shall
immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
Employer: Block/Bill:
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Length of plate
Width of plate
Thickness of plate
Length of plate
Width of plate
Thickness of plate
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Electrical work. The take-off sheet of this activity shall
immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 45
CHECKLIST FOR WORK
Contractor: Axes:
Consultant: Floor:
Location:
Document Referred:
Additional Remarks
For the above items are fulfilled /not fulfilled ,the Contractor is hereby
allowed /refused to proceed Electro mechanical work. The take-off sheet of this activity
shall immediately be signed upon completion.
Name: Name:
Signature: Signature:
Date: Date:
GROUP -5 Page 46