Fi - Punchlist

The document outlines a punch list for the FILINVEST AXIS TOWER 4, detailing specific issues on various floors including electrical box cover plates, thermostat wiring organization, and conflicts with sprinkler installations. It emphasizes the need to adjust ducting heights to meet ceiling requirements and addresses wire tapping for fan coil units. The punch list serves as a checklist for necessary corrections before project completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views6 pages

Fi - Punchlist

The document outlines a punch list for the FILINVEST AXIS TOWER 4, detailing specific issues on various floors including electrical box cover plates, thermostat wiring organization, and conflicts with sprinkler installations. It emphasizes the need to adjust ducting heights to meet ceiling requirements and addresses wire tapping for fan coil units. The punch list serves as a checklist for necessary corrections before project completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

FILINVEST AXIS TOWER 4 – RALGO PUNCHLIST

26th FLOOR

25th FLOOR

2ND FLOOR
14th FLOOR
15th FLOOR
11th FLOOR

- PULLBOX / ELECTRICAL BOX COVER PLATE - ORGANIZE / ARRANGE NEATLY ALL THERMOSTAT WIRING

- CONFLICT INSTALLATION SPRINKLER DROPPING AND DUMPER (DUCTING)


- ADJUST DUCTING HEIGHT NOT TO CONFLICT ON THE REQUIRED CEILING HEIGHT

- TAPPING OF WIRE TO FCU NEAR COMMON AREA