75% found this document useful (4 votes)
14K views3 pages

Boq For Tile Flooring and Wall

This document provides a bill of quantities (BOQ) for tile work on different floors of a building project. It includes rates for fixing tile flooring and dado from the ground floor to the 26th floor. The work involves laying tile floors over cement mortar beds and fixing tiles on walls using backing plaster or adhesive. Materials like tiles, cement, sand and protective sheets will be provided for the work.

Uploaded by

Harsh Sathvara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
75% found this document useful (4 votes)
14K views3 pages

Boq For Tile Flooring and Wall

This document provides a bill of quantities (BOQ) for tile work on different floors of a building project. It includes rates for fixing tile flooring and dado from the ground floor to the 26th floor. The work involves laying tile floors over cement mortar beds and fixing tiles on walls using backing plaster or adhesive. Materials like tiles, cement, sand and protective sheets will be provided for the work.

Uploaded by

Harsh Sathvara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

BOQ FOR TILE WORK

A Ground to 14th Floor


1 Tile Flooring
S. No. DESCRIPTION UNIT Rate
Labour charge for fixing of tiles of approved size, quality, type &
colour as per the approved sample in flooring at all leves (conforming
to IS 15622 & 13630 and ITP) in approved pattern as per
Architectural designs in true line and level to required slope over
average bedding 20-25mm thick of mechanically mixed cement
mortar 1:6 (1 cement : 6 sand) floated with neat cement slurry / paste
(3.3 kg/sqm) including fixing of 2mm thick spacers on joints and
chamfering of tiles wherever required. Surface preparation, hacking
,curing, cleaning and covering by approved protective sheet i.e
bubble guard or equivalent PVC sheets etc. Work to be executed and
accepted as per specifications, methodology, drawings and as
1.1 directed by Engineer In Charge. No hollowness will be permitted for Sqm. 230
tile flooring work.
Rate to include using diamond drill bit cutter for drilling holes in tiles,
round cutter for plumbing points cutting.
Location : At all location like drawing / dining, kitchen, balcony, toilet,
entrance lobby, lift lobby etc. Tiles, cement, sand, spacer, protection
material, cleaning cloth/dhoti, water, electricity will be provided free of
cost.
Material will be available within / near project area. Material loading &
unloading will be done by vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%
Same as above item but for 75/100 mm high skirting over 15 mm
thk. C.M. 1:4 backing or using approved adhesive or using cement
1.2 paste (3.3Kg/sqm) finish complete to the satisfaction of the Project Sqm. 360
manager. Location : same as above. To be fixed wall mounted.
2 Tile in Dado
Labour charge for fixing tiles of approved size, quality, type & colour
as per the approved sample in dado at all levels (conforming to IS
15622 & 13630 and ITP) in approved pattern as per Architectural
designs in true line & level as shown in drawing or as directed by the
Engineer-in-charge. At RCC shear wall / concrete portion hacking is
to be done by tile contractor before laying backing plaster. Tiles to be
fixed by adhesive with notch trowel or cement mortar backing plaster
1:4 (1 Cement:4 Sand) of thickness 12-15 mm & with neat cement
(3.3kg/sqm). Surface prepration, Curing, cleaning. complete all as
per specifications, methodology, drawings and as directed by
Engineer In Charge. Work to be executed and accepted as per
2 specifications, methodology, drawings and as directed by Engineer In Sqm. 301
Charge. No hollowness will be permited for tile dado work.
Rate to include using diamond drill bit cutter for drilling holes in tiles,
round cutter for plumbing points cutting.
Location : toilet & kitchen
Tiles, cement, sand, spacer, protection material, cleaning cloth/dhoti,
water, electricity will be provided free of cost. Material will be
available within / near project area. Material loading & unloading will
be done by vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%

1
B From 15th to 20th Floor
1 Tile Flooring
S. No. DESCRIPTION UNIT Rate
Labour charge for fixing of tiles of approved size, quality, type &
colour as per the approved sample in flooring at all leves (conforming
to IS 15622 & 13630 and ITP) in approved pattern as per
Architectural designs in true line and level to required slope over
average bedding 20-25mm thick of mechanicaly mixed cement
mortar 1:6 (1 cement : 6 sand) floated with neat cement slurry / paste
(3.3 kg/sqm) including fixing of 2mm thick spacers on joints and
chamfering of tiles wherever required. Surface prepration, hacking
,curing, cleaning and covering by approved protective sheet
i.e bubble guard or equivalent PVC sheets etc. Work to be executed
and accepted as per specifications, methodology, drawings and as
256
1.1 directed by Engineer In Charge. No hollowness will be permited for Sqm.
tile flooring work.
Rate to include using diamond drill bit cutter for drilling holes in tiles,
round cutter for plumbing points cutting.
Location : At all location like drawing / dining, kitchen, balcony, toilet,
entrance lobby, lift lobby etc. Tiles, cement, sand, spacer, protection
material, cleaning cloth/dhoti, water, electricity will be provided free of
cost.
Material will be available within / near project area. Material loading &
unloading will be done by vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%
Same as above item but for 75/100 mm high skirting over 15 mm
thk. C.M. 1:4 backing or using approved adhesive or using cement
1.2 paste (3.3Kg/sqm) finish complete to the satisfaction of the Project Sqm. 360
manager. Location : same as above. To be fixed wall mounted.
2 Tile in Dado
Labour charge for fixing tiles of approved size, quality, type & colour
as per the approved sample in dado at all levels (conforming to IS
15622 & 13630 and ITP) in approved pattern as per Architectural
designs in true line & level as shown in drawing or as directed by the
Engineer-in-charge. At RCC shear wall / concrete portion hacking is
to be done by tile contractor before laying backing plaster. Tiles to be
fixed by adhesive with notch trowel or cement mortar backing plaster
1:4 (1 Cement:4 Sand) of thickness 12-15 mm & with neat cement
(3.3kg/sqm). Surface prepration, Curing, cleaning. complete all as
per specifications, methodology, drawings and as directed by
Engineer In Charge. Work to be executed and accepted as per
2 specifications, methodology, drawings and as directed by Engineer In Sqm. 301
Charge. No hollowness will be permited for tile dado work.
Rate to include using diamond drill bit cutter for drilling holes in tiles,
round cutter for plumbing points cutting.
Location : toilet & kitchen
Tiles, cement, sand, spacer, protection material, cleaning cloth/dhoti,
water, electricity will be provided free of cost. Material will be
available within / near project area. Material loading & unloading will
be done by vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%

2
C From 21st to 26th Floor
1 Tile Flooring
S. DESCRIPTION UNIT Rate
No.
Labour charge for fixing of tiles of approved size, quality, type & colour
as per the approved sample in flooring at all leves (conforming to IS
15622 & 13630 and ITP) in approved pattern as per Architectural
designs in true line and level to required slope over average bedding
20-25mm thick of mechanicaly mixed cement mortar 1:6 (1 cement : 6
sand) floated with neat cement slurry / paste (3.3 kg/sqm) including
fixing of 2mm thick spacers on joints and chamfering of tiles wherever
required. Surface prepration, hacking ,curing, cleaning and covering
by approved protective sheet i.e bubble guard or equivalent PVC
sheets etc. Work to be executed and accepted as per specifications,
methodology, drawings and as directed by Engineer In Charge. No
1.1 hollowness will be permited for tile flooring work. Rate to include using Sqm. 279
diamond drill bit cutter for drilling holes in tiles, round cutter for
plumbing points cutting.
Location : At all location like drawing / dining, kitchen, balcony, toilet,
entrance lobby, lift lobby etc. Tiles, cement, sand, spacer, protection
material, cleaning cloth/dhoti, water, electricity will be provided free of
cost.
Material will be available within / near project area. Material loading &
unloading will be done by vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%
Same as above item but for 75/100 mm high skirting over 15 mm thk.
C.M. 1:4 backing or using approved adhesive or using cement paste
1.2 (3.3Kg/sqm) finish complete to the satisfaction of the Project manager. Sqm. 379
Location : same as above. To be fixed wall mounted.
2 Tile in Dado
Labour charge for fixing tiles of approved size, quality, type & colour
as per the approved sample in dado at all levels (conforming to IS
15622 & 13630 and ITP) in approved pattern as per Architectural
designs in true line & level as shown in drawing or as directed by the
Engineer-in-charge. At RCC shear wall / concrete portion hacking is to
be done by tile contractor before laying backing plaster. Tiles to be
fixed by adhesive with notch trowel or cement mortar backing plaster
1:4 (1 Cement:4 Sand) of thickness 12-15 mm & with neat cement
(3.3kg/sqm). Surface prepration, Curing, cleaning. complete all as per
specifications, methodology, drawings and as directed by Engineer In
2 Charge. Work to be executed and accepted as per specifications, Sqm. 320
methodology, drawings and as directed by Engineer In Charge. No
hollowness will be permited for tile dado work.
Rate to include using diamond drill bit cutter for drilling holes in tiles,
round cutter for plumbing points cutting.
Location : toilet & kitchen
Tiles, cement, sand, spacer, protection material, cleaning cloth/dhoti,
water, electricity will be provided free of cost. Material will be available
within / near project area. Material loading & unloading will be done by
vendor.
Allowable wastage : Cement – 3%, Tiles – (5%+5%), sand – 10%